This is a Contract Data Requirements List (DD Form 1423) for Refurbishment Instruction No. 3140-012-0711 Rev C Chg 3, establishing documentation and certification requirements for a 70 KW MG (Motor Generator) submetering equipment and process (SUBMEPP) refurbishment contract.

The contract specifies seven data items required from the contractor, all of which must be submitted via WAWF (Wide Area Work Flow) to the maximum extent possible. These include: (A001) Submepp Receipt Inspection; (A002) Submepp Condition Report; (A003) Submepp Welding Procedures (with acceptance required prior to welding, must meet NAVSEA S9074-AR-GIB-010/278 requirements); (A004) Submepp Reassembly Quality Assurance Report; (A005) Submepp Test Procedure (acceptance required prior to NDT, must meet NAVSEA T9074-AS-GIB-010/271 requirements); (A006) Submepp Test Inspection Report (required prior to shipment of each unit); and (A007) Submepp Certification of Compliance (required prior to shipment of each unit, with one copy placed in crate). All documentation must be distributed to SUBMEPP Code 1831, NAVSUP WSS N9751, and NAVSUP WSS N742, with contractor-developed formats acceptable where specified. The contract references Statement of Work paragraphs 7.1 through 7.7 for specific requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REFURBISHMENT INSTRUCTION

No. 3140-012-0711 Rev C Chg 3

Enclosure (1)

CONTRACT DATA REQUIREMENTS LIST

A. CONTR. LINE ITEM NO. B. EXHIBIT C. CATEGORY:

XX TDP TM OTHER

D. SYSTEM/ITEM

70 KW MG

E. CONTRACT/PR NO.

NO. 3140-012-0711 Rev C Chg 3

F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUHORITY

(Data Item Descript)

5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ. 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF

FIRST

SUBMISSION

14. DISTRIBUTION

DR - DRAFT RG

- REGULAR RP

- REPRO

8. APP CODE 11. AS OF

DATE

13. SUBSEQUENT

SUBMISSION

15. REMARKS

1. A001 2. SUBMEPP RECEIPT INSPECTION 3. N/A

4. DI-MGMT-80389C (SUBRIR) 5. CSD REF. IN PARA. 7.1 6. SUBMEPP

7. LT 9. Dist 10. 12. AS REQ 14. DISTRIBUTION Statement required AS REQ a. ADDRESSEE b. Copies

8. N/A D 11. N/A 13. AS REQ D

R

R G

R P

16. REMARKS SUBMEPP CODE 1831 1

Certification documentation must be submitted via WAWF (Wide Area NAVSUP WSS N9751 1

Work Flow) to the maximum extent possible. See Enclosure 1. NAVSUP WSS N742 1

15. TOTAL 3

1. A002 2. SUBMEPP CONDITION REPORT 3. N/A

4. DI-MGMT-82048 (SUBCR) 5. CSD REF. IN PARA. 7.2 6. SUBMEPP

7. LT 9. Dist 10. 12. AS REQ 14. DISTRIBUTION Statement

Required AS REQ a. ADDRESSEE b. Copies

8. N/A

D 11. N/A 13. AS REQ D

R

R G

R P

16. REMARKS SUBMEPP CODE 1831 1

Certification documentation must be submitted via WAWF (Wide Area NAVSUP WSS N9751 1 Work Flow) to the maximum extent possible. Contractor own format is NAVSUP WSS N742 1 acceptable. 15. TOTAL 3

1. A003 2. SUBMEPP WELDING PROCEDURES 3. N/A

4. DI-MISC-80875A (SUBWP) 5. CSD REF. IN PARA. 7.3 6. SUBMEPP

7. DD 9. Dist 10. 12. Acceptance required prior 14. DISTRIBUTION Statement

Required AS REQ to welding. a. ADDRESSEE b. Copies

8. N/A

D 11. N/A 13. AS REQ D

R

R G

R P

16. REMARKS

Certification documentation must be submitted via WAWF (Wide Area NAVSUP WSS N9751 1 Work Flow) to maximum extent possible. Weld procedures are required NAVSUP WSS N742 1 to meet the requirements within NAVSEA S9074-AR-GIB-010/278. 15. TOTAL 3

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423, JUN 90 Previous editions are obsolete Page 1 of 3 Pages

Enclosure (1)

DD Form 1423, JUN 90 Previous editions are obsolete Page 2 of 3 Pages

CONTRACT DATA REQUIREMENTS LIST

A. CONTR. LINE ITEM NO. B. EXHIBIT C. CATEGORY:

XX TDP TM OTHER

D. SYSTEM/ITEM

70 KW MG

E. CONTRACT/PR NO.

NO. 3140-012-0711 Rev C Chg 3

F. CONTRACTOR

1. A004 2. SUBMEPP REASSEMBLY QUALITY

ASSURANCE REPORT

3. N/A

4. DI-QCIC-81890 (SUBRQAR) 5. CSD REF. IN PARA. 7.4 6. SUBMEPP

7. DD 9. Dist 10. 12. 14. DISTRIBUTION Statement

Required AS REQ AS REQ a. ADDRESSEE b. Copies

8. N/A D 11. N/A 13. AS REQ D

R

R G

R P

16. REMARKS SUBMEPP Code 1831 1

Certification documentation must be submitted via WAWF (Wide NAVSUP WSS N9751 1 Work Flow) to the maximum extent possible. NAVSUP WSS N742 1 Contractor’s own format is acceptable. 15. TOTAL 3

1. A005 2. SUBMEPP TEST PROCEDURE 3. N/A

4. DI-MISC-82386 (SUBNDT) 5. CSD REF. IN PARA. 7.5 6. SUBMEPP

7. LT 9. Dist 10. 12. Acceptance req’d 14. DISTRIBUTION Statement Required

AS REQ prior to NDT. a. ADDRESSEE b. Copies

8. N/A D 11.

N/A

13. AS REQ D

R

R G

R P

16. REMARKS SUBMEPP CODE 1831 1

Certification documentation must be submitted via WAWF (Wide Area NAVSUP WSS N9751 1

Work Flow) to the maximum extent possible. NDT procedures are NAVSUP WSS N742 1 required to meet requirements within NAVSEA T9074-AS-GIB-010/271. 15.TOTAL 3

1. A006 2. SUBMEPP TEST INSPECTION REPORT 3. N/A

4. DI-NDTI-80809B (SUBNDTR) 5. CSD REF. IN PARA. 7.6 6. SUBMEPP

7. DD 9. Dist 10. 12. Prior to shipment of 14. DISTRIBUTION Statement Required

AS REQ each unit. a. ADDRESSEE b. Copies

8. N/A D 11. N/A 13. AS REQ D

R

R G

R P

16. REMARKS SUBMEPP CODE 1831 1

Certification documentation must be submitted via WAWF (Wide NAVSUP WSS N9751 1 Area Work Flow) to the maximum extent possible. NAVSUP WSS N742 1

15. TOTAL 3

G. PREPARED BY

H. DATE

I. APPROVED BY

J. DATE

Enclosure (1)

CONTRACT DATA REQUIREMENTS LIST

A. CONTR. LINE ITEM NO. B. EXHIBIT C. CATEGORY:

XX TDP TM OTHER

D. SYSTEM/ITEM

70 KW MG

E. CONTRACT/PR NO.

NO. 3140-012-0711 Rev C Chg 3

F. CONTRACTOR

1. A007 2. SUBMEPP CERTIFICATION OF

COMPLIANCE

3. N/A

4. DI-MISC-82386 (SUBCC) 5. CSD REF. IN PARA. 7.7 6. SUBMEPP

7. DD 9. Dist 10. 12. Prior to shipment of 14. DISTRIBUTION Statement

Required AS REQ each unit. a. ADDRESSEE b. Copies

8.

N/A

D 11. N/A 13. AS REQ D

R

R G

R P

16. REMARKS SUBMEPP Code 1831 1 Certification documentation must be submitted via WAWF (Wide NAVSUP WSS N9751 1

Area Work Flow) to the maximum extent possible. NAVSUP WSS N742 1 Contractor’s own format is acceptable. Copy in Crate 1

15. TOTAL 4

1. 2. 3.

4. 5. 6.

7. 9. 10. 12. 14. DISTRIBUTION

b. Copies

8. 11. 13. D R

R G

R P

15. REMARKS

TOTAL

1. 2. 3.

4. 5. 6.

7. 9. 10. 12. 14.

8. 11. 13.

15. REMARKS

G. PREPARED BY

H. DATE

I. APPROVED BY J. DATE

DD Form 1423, JUN 90 Previous editions are obsolete Page 3 of 3 Pages