1.02 38HZA53302R_00_A01.pdf
PDF 832 KB Posted
- Solicitation number
- N6264926Q0308
About this file
This is a Job Specification document for shipboard maintenance work on the USS NUECES (APL-40). The work involves replacing 2 feet of 2-1/2 inch IPS cold potable water piping located in AC Diesel Generator Room No. 2, Upper Level A-318-E (compartment 2-26-4). The piping is specified as CuNi90/10 (Copper-Nickel 90/10 alloy) and is currently leaking with a temporary patch in place. The anticipated award date is 06/30/2026, with production completion scheduled for 08/27/2026. The period of performance runs from 07/07/2026 through 09/28/2026, with work to be performed at Sasebo.
The work requirements include: obtaining and analyzing samples of existing insulation and lagging for asbestos-containing materials; removing and installing new cold potable water piping per Navy specifications S9AA0-AB-GOS-010 REV 11; performing chemical disinfection and bacteriological testing of affected piping; witnessing an operating pressure test with zero allowable leakage; accomplishing insulation and lagging per reference documents; and cleaning and preservation to match surrounding areas. Bacteriological testing must be performed by local government agencies or licensed Japanese laboratories. Government-furnished materials include pipe, fittings, insulation (NH-Armaflex foam), glass cloth, adhesives, welding electrodes, thermal insulation blocks, tape, and miscellaneous hardware. The document was prepared by T. Yoshinaga on 7/9/2025 and approved by S. Murakami with Job Order Number 38HZA53302R, Revision A01.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment N6264926Q03080001 SF 30.pdf | ||
| Solicitation - N6264926Q0308.pdf | ||
| 1.02 38HZA52101R_00_A01.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ShlDIHULL NO. I ShlDIHULL NAME
APL-40 I USS NUECES
ICN:
JON: 38HZA53302R
Rev: Key Op:
A01 fflLE:
Potable Water Piping In 2..28-ii replace
JOB SPECIFICATION
Anticipated Award Date Production Completion Date: PREPARING ACTMTY:
06/30/2026 08/27/2026
POP Start Date: POP End Date: SASEBO 07/07/2026 09/28/2026
PREPARED BY: CODE DATE
T.YOSHINAGA - PYO 7/912025
APPROVED BY: ~Jfvl CODE
S.MURAKAMI S225
CONCURRED BY: 7-7- CODE
T.TAKAMASU S234
ASSIST PLANNER'S NAME: CODE
ASSIST PLANNER'S NAME: CODE
ASSIST PLANNER'S NAME: CODE
DESCRIPTION:
JSN(S!: AP40-L381 CASREP#
SIF CONTACT: SCHUCHARD D. / PASCHKE, J. CWP# CCNS#
T. ESCRITOR-YAMAOA
Approved by S300/8900 ~ Date: 7/,~/uu,- Avl: &CM
LWC:
Work Completed
S/Force: Rate: Date:
SHIPSUPT: Date: SRF CONTROL NO.: 1301383234 wgs~ 5cl;8Tlfl~IIQN SIGNATURg
COMPLE110N OF WORK REVIEW BADGE NO.: SHOP/CODE: PHONE DATE:
Shl-'HULL NO. I Shl-'HULL NAME I ---....a~'----------+----=-"'----------: JON: ICN: I Rev:
I
Key Op:
APL-40 USS NUECES 38HZA53302 R
TITLE:
Potable Water Piping In 2·28-4; replace
1. SCOP&:
1.1 Title: Potable Water Piping in 2-26-4; replace
1. 2 Location of Work:
1.2.1 AC Diesel GEN Room No.2 Upper Level A-318-E (2-26-4)
1.3 Identification:
A01
1.3.1 Quantity (2 FT), 2-1/2 Inch IPS Cold Potable water Piping Located in 1.2.1, CuNi90/10 Piping, See ENCLOSURE (A)
1.3.1.1 Quantity (One EA), Sample of Insulation and Lagging
on 2-1/2 Inch IPS Cold Potable water Piping Located in 1.2.1, NH-Armaflex and Cloth MIL-C-20079
1.3.2 Quantity (One EA), Sample of Insulation and Lagging on
Overhead Located in 1.2.1, Around Cold Potable Water Piping Listed in 1.3.1, 2 Inch Thermal Insulation
2. RBl'l:UNCl:S:
2.1 Standard Items (FY26)
2.2 S9AA0-AB-GOS-010 REV 11, General Specifications for Overhaul of Surface Ships (GSO)
2.3 607-2281864 Rev A, Insulation & Sheathing Below Main Deck
2.4 S9086-VH-STM-010/CH-635/Rev 3, Thermal, Fire, Acoustic Insulation
3. RBQtl'IRBNINTS:
3.1 Obtain each sample listed in 1.3.1.l and 1.3.2 from existing insulation and lagging and analyze each sample for Asbestos-Containing Material.
(V) "RBP0R1'"
3.1.1 Submit One legible condition report listing results from a licensed laboratory to SUPERVISOR.
3.2 Remove existing and install new cold potable water piping to replace cold potable water piping listed in 1.3.1.
3.2.1 Accomplish the requirements of 009-12 of 2.1, including Table One Column A, Lines One through 10.
3.2.1.1 Fabricate each backing ring in accordance with Line
6.
Shi ULL NO. Shi HULL NAME i ICN:
JON: I 38HZA53302R
Rev: Key Op:
APL-40 USS NUECES
TITLE:
Potable Water Piping In 2-26◄; replace
3.3 Accomplish a chemical disinfection of each affected cold potable water piping listed in 1.3.1, in accordance with Section 532p of 2.2.
3.3.1 Accomplish a bacteriological test for each affected cold potable water piping.
A01
3.3.1.1 Bacteriological testing must be accomplished by local government agency or licensed Japanese laboratories.
(V) REPORT
3.3.1.2 Submit One legible condition report listing results
of the requirements of 3.3.1 with certification that water is safe for human consumption.
(V) (G) ~OPERATING PRESSURE TEST"
3.4 Witness operating pressure test to be conducted by ship's force to verify tightness of each weld joint and mechanical joint affected by this work item, until the specified criteria is verified. Allowable leakage: None. - S130
3.5 Accomplish the requirements of 009-11 of 2.1 for insulation and lagging affected by this work item, using 2.3 for guidance.
3.6 Accomplish the requirements of 009-32 of 2.1 for cleaning and preservation of each new and disturbed surface to match surrounding areas.
3.6.1 A brush or spray may be used as a paint application for acoustic insulation in 635-7.2.4 of 2.4 as applicable.
4. NO'l'ES:
4.1 Initial Condition - Potable water piping is leaking and temporary patch.
5. GOVERNMENT FURNISHED MATERIAL:
5.1 SRF will provide following material.
MATERIAL LIST
M QTY
ITEM PC REF I STOCK HAZ DOC REQD/ PARA
NO. NO. NO. C DESCRIPTION NUMBER MAT NO. UNIT NO.
001 M PIPE, 2-1/2"IPS, 2.875''0D X 0.083WT, 384710 N 5/FT 3.2
MIL-T-18420 CNA 90/10 002898007
002 C ELBOW, 2-1/2"IPS, 45 DEG, BW, 200#, 984730 N 1/EA 3.2
810-1385990 CNA 90/10 007254465
003 M PIPE COVERING, 2-1/2"IPS, 2.875"ID X 9Q 5840 N 2/EA 3.5
3/4"THK X 8FT, NH ARMAFLEX. NON- SM552493
HALOGEN RUBBER FOAM NHT21034
ShlDIHULL NO. ShlDIHULL NAME I ICN: I Rev: Key Op:
APL-40 USS NUECES JON: 1 38HZA53302 R I A01
TITLE:
Potable Water Piping In 2-28-t; replace
MATERIAL LIST - --M QTY
ITEM PC REF I STOCK HAZ DOC REQDI PARA
NO. NO. NO. C DESCRIPTION NUMBER ~ NO. UNIT NO.
004 - M INSULATION SHEET, 314"THK X 3FT W X 9B5970 N 12/SF 3.5
4FT L, NH ARMAFLEX, NON HALOGEN 015844038
RUBBER FOAM
005 M GLASS CLOTH, 5 FT W X 50 YD, MIL-C- 9B8305 N 1/RO 3.5
20079H TY.I CL.3 L/W 001487383
006 M ADHESIVE, NEOPRENE, MIL-A-2417QA 9B 8040 y 1/GL 3.5
TY.II CL.1 520 R-373 1 GL/UI 005508835
007 M ADHESIVE, WHITE, MIL-DTL-33160 CL.1 , 9B 8040 y 1/GL 3.5
GR.A 1GL/UI 002738708
008 C RUBBER SHEET, RUBBER, 1/6" X 38" X 9B 9320 N 11EA 3.5
36" MIL-G-1149 TY.I CL.1 HS 50 CPR 007295103
009 M WELDING ELECTRODE, 1/16" X 36", MIL- 9B3439 y 1/BX 3.2
RN67 MIL-E-21562 CL.2 GTAW 000868988
010 M INSULATION BLOCK, THERMAL, 2"THK X 9Q 5640 N 1/BX 3.5
38"L X 24-W, MIL-DTL-32585 TY-I FM-1 008096315
FC-B U/1 CONTAINS 10 EA/BX
011 M TAPE.TEXTILE, 2" WIDTH X 50 YD/RO, 9B 8315 N 2/RO 3.5
WHITE MIL-C-20079TY-II CL-1 002671632
012 M CAP.SNAP FASTENER, MIN 0.27" DIA 9B 5325 N 1/HD 3.5
CAP SHANK & 0.879" DIA CAP HEAD, 007377648
ALUMINUM
ShlDIHULL NO. Ship/HULL NAME 1 ICN: Rev:
APL-40 USS NUECES JON: l 38HZA53302R
TITLE:
Potable Water Piping In 2-26-4; replace
2-28-14
HW COV
2-28-10 cw cov
FR 28 1
f\C'C'l f'C'
2-28-12
HW COV
2-28-8 cw cov
ID:1.3 . 1, 2-1/2
2- 28- 4
FL COV
2-26-2 cw cov
2- 28- 2
FL COV
I I
SHIP'S OFFICE
2-24-2-Q ~ .J
FR 24
2- 19- 4
FL COV
2-24-2 cw cov
2-23-2 cw cov
OFFICE
2-22-2-Q
FR 22
AC Diesel GEN Room No . 2 Upper Level A-3 1 8- E (2 - 26 - 4)
ENCLOSURE (A) 1/1
Key Op:
A01
2-19
FL C:
5/s