1-Contract Documents and Specifications.pdf

PDF 5 MB Posted

Attached to
Laurel Run DPW Pole Barn Concrete Floor
Solicitation number
Not on record
Issued by
Luzerne County, Wolfdale CDP, Pennsylvania

About this file

Contract Summary: Laurel Run DPW Pole Barn Concrete Floor Project

This is a construction contract document and invitation to bid issued by Laurel Run Borough, located in Luzerne County, Pennsylvania, for the installation of a reinforced concrete floor within an existing Department of Public Works pole barn and concrete apron. The project is identified as Serial Number 25-10069 and Project #382225.003. Sealed bids will be received online via the PennBid Program until 11:00 A.M. on January 16, 2025, with a pre-bid meeting scheduled for 10:00 A.M. on December 19, 2025, at the DPW Building, Dickerson Street, Laurel Run Borough. All bidding documents became available December 12, 2025, at no cost through PennBid. The work encompasses all labor, materials, tools, oversight, permits, and mobilization/demobilization required for the concrete installation. The anticipated notice to proceed is March 16, 2026, with substantial completion required within 30 days of the notice to proceed. Questions may be submitted through PennBid's messaging system on or before 3:00 P.M. on January 7, 2025. The contract award date is anticipated for January 20, 2026.

All prime contractor bidders must be PennDOT prequalified as a prime contractor for their assigned tasks, and all subcontractors must be PennDOT prequalified for their respective work. A bid bond with a corporate surety authorized to do business in Pennsylvania is required in the amount of 10 percent of the total bid amount. The successful bidder must furnish performance and payment bonds in the amount of 100 percent of the contract sum and a one-year maintenance bond in the amount of 10 percent of the awarded contract value after achieving substantial completion. Pennsylvania Prevailing Wage Rates apply to the project. The contract includes liquidated damages of $500 per day for failure to mobilize within 14 calendar days of notice to proceed, $750 per day for each day after substantial completion deadline, and $1,000 per day for failure to complete remaining work after substantial completion. Progress payments will be made at 90 percent of work completed with retainage, with the balance due upon substantial completion. No asphalt or diesel price adjustments for escalation costs are included in the contract.

View the file

Other files

File Type Posted
2-Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Documents and Specifications

FOR

Laurel Run DPW Pole Barn Concrete Floor Project

Laurel Run Borough 100 Dupont Road Laurel Run, PA 18706

Date: December 2025 Project #: 382225.003

Table of Contents

SECTION 000110 – Table of Contents

DIVISION 00 – PROCUREMENT & CONTRACTING REQUIREMENTS

BIDDING INSTRUCTIONS

001116.21 Invitation to Bid - PennBid

002113.21 Instruction to Bidders - PennBid

BIDDING DOCUMENTS

004313.31 Bid Bond EJCDC-C-430

004325 Substitution Request Form

004336 Proposed Subcontractors Form

004513.31 Bidders Qualifications EJCDC-C-451

004515 Consent of Surety

004519 Non-Collusion Affidavit

004537 Equal Employment Opportunity Affidavit

004546 PA E-Verify

004560 PA Nondiscrimination Clause

004597.21 Bid Submittal Checklist - PennBid

004600 Affidavit RE Accepting Provisions of the Workmen’s Compensation Act

CONTRACTING REQUIREMENTS

005213.13 Agreement by Owner EJCDC-C-520

006113.31 Performance Bond EJCDC-C-610

006113.33 Payment Bond EJCDC-C-615

006119 Maintenance Bond

006200 Application for Payments EJCDC-C-620

006250 Certificate of Substantial Completion

006500 Consent of Surety to Final Payment Form

007213.41 General Conditions EJCDC-C-700

007300.41 Supplementary Conditions 2013 EJCDC-C-800

007340 PA Prevailing Wage Rates

009400 Work Change Directive EJCDC-C-940

009410 Change Order EJCDC-C-941

009420 Field Order EJCDC-C-942

Table of Contents

TECHNICAL SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

011000 Summary

012200 Unit Prices

012500 Substitution Procedures

012600 Contract Modification Procedures

012900 Payment Procedures

013100 Project Management and Coordination

013300 Submittal Procedures

015000 Temporary Facilities and Controls

015700 Maintenance and Protection of Traffic

017300 Execution

017700 Closeout Procedures

DIVISION 50 – PENNDOT REQUIREMENTS

500000 PennDOT Specifications Index

500001 PennDOT Publication Coordination

DRAWINGS

SP-1 Floor Plan

CD-1 Construction Details

Division 00

Procurement &

Contracting Requirements

Bidding Instructions

INVITATION TO BID 001116.21 - 1

SECTION 001116.21 – INVITATION TO BID

Notice is hereby given that Laurel Run Borough will receive sealed bids online via the PennBid Program

(http://pennbid.bonfirehub.com) until 11:00 A.M, prevailing time on January 16, 2025 for the Laurel Run

DPW Pole Barn Concrete Floor Project, at which time the bids received will be opened via PennBid. The work includes but is not limited to all labor materials, tools, oversight, permits, and mobilization/demobilization required to install reinforced concrete floor within the existing DPW building and concrete apron.

All bidding documents will be available online at no cost via the PennBid Program

(http://pennbid.bonfirehub.com) beginning at 12:00 P.M. on December 12, 2025.

Bids must be accompanied by a bid bond with a corporate surety authorized to do business in

Pennsylvania, in accordance with the project specifications in the amount of 10% of the total bid amount.

A Performance and Payment Bond in the amount of 100% of the contract shall be furnished by the successful bidder as detailed in the Instructions to Bidders. PA Prevailing Wage Rates apply to the project.

All Prime Contractor Bidders must be PennDOT Prequalified as a Prime Contractor and for the tasks they complete, and all subcontractors must be PennDOT Prequalified as a Sub-Contractor for the tasks assigned.

Immediately following the due date and time, all bids received through PennBid will be opened online at the Engineer’s Office and referred to Laurel Run Borough for final award. An abstract of the bids received will be available to bidders on PennBid following the date and time that bids are due as indicated above.

A pre-bid meeting will be held at 10:00 AM on December 19, 2025 at DPW Building, Dickerson Street, Laurel Run Borough. All bidders are encouraged to attend. Questions may be submitted through

PennBid’s “Messages/Vendor Discussions” tab on or before 3:00 P.M. on January 7, 2025. Responses will be provided via PennBid to all registered parties.

Laurel Run Borough is an Equal Opportunity Employer. Minority and women owned businesses are encouraged to submit proposals. Laurel Run Borough reserves the right to accept or reject any or all bids or portions or to waive any informalities in bidding and to withhold award for a period of sixty days.

On Behalf of Laurel Run Borough

Barry Isett & Associates, Inc.

1170 Highway 315, Suite 3

Wilkes-Barre, PA 18702

INSTRUCTION TO BIDDERS 002113.21 - 1

SECTION 002113.21 – INSTRUCTION TO BIDDERS

ARTICLE 1 - DEFINITIONS

1.1 Bidding Documents include the Bidding Requirements and the proposed Contract Documents.

The Bidding Requirements consist of the Advertisement or Invitation to Bid, Instructions to Bidders, the bid form, and other sample bidding and contract forms. The proposed Contract Documents consist of the form of Agreement between the Owner and Contractor, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications and all Addenda issued prior to execution of the Contract.

1.2 Definitions set forth in the General Conditions of the Contract for Construction, EJCDC C-700 General Conditions, or in other Contract Documents are applicable to the Bidding Documents.

1.3 Addenda are written or graphic instruments issued by the Engineer prior to the execution of the Contract which modify or interpret the Bidding Documents by additions, deletions, clarifications or corrections.

1.4 A Bid is a complete and properly executed proposal to do the Work for the sums stipulated therein, submitted in accordance with the Bidding Documents.

1.5 The Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents as the base, to which Work may be added or from which Work may be deleted for sums stated in Alternate Bids.

1.6 An Alternate Bid (or Alternate) is an amount stated in the Bid to be added to or deducted from the amount of the Base Bid if the corresponding change in the Work, as described in the Bidding Documents, is accepted.

1.7 A Unit Price is an amount stated in the Bid as a price per unit of measurement for materials, equipment or services or a portion of the Work as described in the Bidding Documents.

1.8 A Bidder is a person or entity who submits a Bid and who meets the requirements set forth in the Bidding Documents.

1.9 A Sub-bidder is a person or entity who submits a bid to a Bidder for materials, equipment, or labor for a portion of the Work.

ARTICLE 2 - BIDDER'S REPRESENTATIONS

2.1 The Bidder by making a Bid represents that:

A. The Bidder has read and understands the Bidding Documents or Contract Documents, to the extent that such documentation relates to the Work for which the Bid is submitted, and for other portions of the Project, if any, being bid concurrently or presently under construction.

B. The Bid is made in compliance with the Bidding Documents.

C. The Bidder has visited the site, become familiar with local conditions under which the Work is to be performed and has correlated the Bidder's personal observations with the requirements of the proposed Contract Documents.

INSTRUCTION TO BIDDERS 002113.21 - 2

D. The Bid is based upon the materials, equipment and systems required by the Bidding Documents without exception.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.1 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall complete submit a properly executed EJCDC C-451, Contractor's Qualification Statement.

3.2 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.3 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.4 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

3.5 Prime bidder and any Subcontractors are required to be PennDOT prequalified for their roll and the work to be completed. Proof of PennDOT prequalification must be submitted as part of the bid.

ARTICLE 4 - BIDDING DOCUMENTS

4.1 COPIES

A. Bidders may obtain complete sets of the Bidding Documents at no cost, online via the PennBid Program (https://pennbid.bonfirehub.com)

B. Bidders shall use complete sets of Bidding Documents in preparing Bids; neither the Owner nor Engineer assumes responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

C. The Owner and Engineer may make copies of the Bidding Documents available on the above terms for the purpose of obtaining Bids on the Work. No license or grant of use is conferred by issuance of copies of the Bidding Documents.

4.2 INTERPRETATION OR CORRECTION OF BIDDING DOCUMENTS

A. The Bidder shall carefully study and compare the Bidding Documents with each other, and with other work being bid concurrently or presently under construction to the extent that it relates to the Work for which the Bid is submitted, shall examine the site and local conditions, and shall at once report to the Engineer errors, inconsistencies or ambiguities discovered.

B. Bidders and Sub-bidders requiring clarification or interpretation of the Bidding Documents shall make a written request via PennBid’s “Messages /Vendor Discussions” in accordance with the date referenced in the Invitation to Bidders.

C. Interpretations, corrections, and changes of the Bidding Documents will be made by Addendum.

Interpretations, corrections, and changes of the Bidding Documents made in any other manner will not be binding, and Bidders shall not rely upon them.

INSTRUCTION TO BIDDERS 002113.21 - 3

4.3 SUBSTITUTIONS

A. The materials, products and equipment described in the Bidding Documents establish a standard of required function, dimension, appearance, and quality to be met by any proposed substitution.

Proprietary Items - Contractor may propose an “or equal” product for any item(s) specifically noted on the drawings or within the technical specifications. Contractor shall provide details and submit substitutions to the Engineer for review and approval as set forth in this section.

B. No substitution will be considered prior to receipt of Bids unless written request for approval has been received by the Engineer by 3:00 P.M. at least ten days prior to the date for receipt of Bids.

Such requests shall include the enclosed substitution request form, the name of the material or equipment for which it is to be substituted and a complete description of the proposed substitution including drawings, performance and test data, and other information necessary for an evaluation.

A statement setting forth changes in other materials, equipment, or other portions of the Work, including changes in the work of other contracts that incorporation of the proposed substitution would require, shall be included. The burden of proof of the merit of the proposed substitution is upon the proposer. The Engineer's decision of approval or disapproval of a proposed substitution shall be final.

C. If the Engineer approves a proposed substitution prior to receipt of Bids, such approval will be set forth in an Addendum. Bidders shall not rely upon approvals made in any other manner.

D. No substitutions will be considered after the Contract award unless specifically provided for in the Contract Documents.

4.4 ADDENDA

A. Addenda will be posted online via PennBid’s “Files” tab and bidder will be notified via email.

B. Each Bidder shall ascertain prior to submitting a Bid that the Bidder has received all Addenda issued, and the Bidder shall acknowledge their receipt in the Bid.

ARTICLE 5 - BIDDING PROCEDURES

5.1 PREPARATION OF BIDS

A. The Bid Form may be included in the Bidding Documents for Reference. Bidders shall complete the electronic bid form within PennBid’s “Prepare Your Submission” tab.

B. All requested Alternates shall be bid. If no change in the Base Bid is required, enter “0.”

C. Where two or more Bids for designated portions of the Work have been requested, the Bidder may, without forfeiture of the bid security, state the Bidder's refusal to accept award of less than the combination of Bids stipulated by the Bidder. The Bidder shall make no additional stipulations on the bid form nor qualify the Bid in any other manner.

D. Each copy of the Bid shall state the legal name of the Bidder and the nature of legal form of the Bidder. The Bidder shall provide evidence of legal authority to perform within the jurisdiction of the Work. Each copy shall be signed by the person or persons legally authorized to bind the Bidder to a contract.

INSTRUCTION TO BIDDERS 002113.21 - 4

A Bid by a corporation shall further give the state of incorporation and have the corporate seal affixed. A Bid submitted by an agent shall have a current power of attorney attached certifying the agent's authority to bind the Bidder.

E. Each Bid shall be accompanied with a list of three closely-related past projects completed by the Bidder within the last five years. This list shall include a description of the work included in the project, the Client, the Client’s contact information, time of completion, and a value of the total construction cost.

5.2 BID SECURITY

A. Each Bid shall be accompanied by a bid security in the form and the amount of 10% of the bid if so stipulated in the Instructions to Bidders. The Bidder pledges to enter into a Contract with the Owner on the terms stated in the Bid and will, if required, furnish bonds covering the faithful performance of the Contract and payment of all obligations arising thereunder. Should the Bidder refuse to enter into such Contract or fail to furnish such bonds if required, the amount of the bid security shall be forfeited to the Owner as liquidated damages, not as a penalty. The amount of the bid security shall not be forfeited to the Owner in the event the Owner fails to comply with Section 6.2.

B. If a surety bond is required, it shall be written on EJCDC C-435, Bid Bond, unless otherwise provided in the Bidding Documents, and the attorney-in-fact who executes the bond on behalf of the surety shall affix to the bond a certified and current copy of the power of attorney.

C. The Owner will have the right to retain the bid security of Bidders to whom an award is being considered until either (a) the Contract has been executed and bonds, if required, have been furnished, or (b) the specified time has elapsed so that Bids may be withdrawn or (c) all Bids have been rejected.

5.3 CONTRACTOR'S QUALIFICATION STATEMENT

A. Bidders shall submit to the Engineer, upon request, a properly executed EJCDC C-451, Contractor's Qualification Statement.

5.4 SUBMISSION OF BIDS

A. Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com).

Bidders shall complete the electronic bid form within PennBid’s “Prepare Your Submission” tab.

B. The bid security, if any, and any other documents required to be submitted with the Bid uploaded to the PennBid’s “Requested Information” tab.

C. The Bidder shall assume full responsibility for timely submission of Bids.

5.5 MODIFICATION OR WITHDRAWAL OF BID

A. A Bid may not be modified, withdrawn or canceled by the Bidder during the stipulated time period following the time and date designated for the receipt of Bids, and each Bidder so agrees in submitting a Bid.

B. Prior to the time and date designated for receipt of Bids, a submitted Bid may be modified or withdrawn any time within the PennBid Program.

https://pennbid.bonfirehub.com/

INSTRUCTION TO BIDDERS 002113.21 - 5

C. Withdrawn Bids may be resubmitted up to the date and time designated for the receipt of Bids provided that they are then fully in conformance with these Instructions to Bidders.

D. Bid security, if required, shall be in an amount sufficient for the Bid as resubmitted.

ARTICLE 6 - CONSIDERATION OF BIDS

6.1 OPENING OF BIDS

A. Upon receipt of the bids, the bids will be opened electronically. A public notice will be issued via PennBid containing any available bid results. These results are subject to further review and should not be considered an issuance of an award.

B. At the discretion of the Owner and only if stipulated in the Invitation to Bid, the properly identified Bids received on time will be publicly opened and read aloud. Results will be issued per Article 6.1.A.

6.2 REJECTION OF BIDS

A. The Owner shall have the right to reject any or all Bids. A Bid not accompanied by a required bid security or by other data required by the Bidding Documents, or a Bid which is in any way incomplete or irregular is subject to rejection.

6.3 ACCEPTANCE OF BID (AWARD)

A. It is the intent of the Owner to award a Contract to the lowest qualified Bidder provided the Bid has been submitted in accordance with the requirements of the Bidding Documents and does not exceed the funds available.

The Owner shall have the right to waive informalities and irregularities in a Bid received and to accept the Bid which, in the Owner's judgment, is in the Owner's own best interests.

B. The Owner shall have the right to accept Alternates in any order or combination, unless otherwise specifically provided in the Bidding Documents, and to determine the low Bidder on the basis of the sum of the Base Bid and Alternates accepted.

ARTICLE 7 – CONTRACT TIMES

7.1 The number of days within which, or the dates by which, Milestones are to be achieved and the Work is to be substantially completed, and completed and ready for final payment, are set forth in the Agreement.

ARTICLE 8 – LIQUIDATED DAMAGES

8.1 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

INSTRUCTION TO BIDDERS 002113.21 - 6

ARTICLE 9 - POST-BID INFORMATION

9.1 OWNER'S FINANCIAL CAPABILITY

A. The Owner shall, at the request of the Bidder to whom award of a Contract is under consideration and no later than seven days prior to the expiration of the time for withdrawal of Bids, furnish to the Bidder reasonable evidence that financial arrangements have been made to fulfill the Owner's obligations under the Contract. Unless such reasonable evidence is furnished, the Bidder will not be required to execute the Agreement between the Owner and Contractor.

9.2 SUBMITTALS

A. The Bidder shall, as soon as practicable or as stipulated in the Bidding Documents, after notification of selection for the award of a Contract, furnish to the Owner through the Engineer in writing:

1. a designation of the Work to be performed with the Bidder's own forces;

2. names of the manufacturers, products, and the suppliers of principal items or systems of materials and equipment proposed for the Work; and

3. names of persons or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for the principal portions of the Work.

B. The Bidder will be required to establish to the satisfaction of the Engineer and Owner the reliability and responsibility of the persons or entities proposed to furnish and perform the Work described in the Bidding Documents.

C. Prior to the execution of the Contract, the Engineer will notify the Bidder in writing if either the Owner or Engineer, after due investigation, has reasonable objection to a person or entity proposed by the Bidder.

If the Owner or Engineer has reasonable objection to a proposed person or entity, the Bidder may, at the Bidder's option, (1) withdraw the Bid or (2) submit an acceptable substitute person or entity with no adjustment in the Base Bid or Alternate Bid occasioned by such substitution. The Owner may accept the adjusted bid or disqualify the Bidder. In the event of either withdrawal or disqualification, bid security will not be forfeited.

D. Persons and entities proposed by the Bidder and to whom the Owner and Engineer have made no reasonable objection must be used on the Work for which they were proposed and shall not be changed except with the written consent of the Owner and Engineer.

ARTICLE 10 - BONDING AND INSURANCE REQUIREMENTS

10.1 BOND REQUIREMENTS

A. The Bidder shall furnish bonds in 100% of the contract value covering the faithful performance of the Contract and payment of all obligations arising thereunder. Bonds may be secured through the Bidder's usual sources.

B. The contractor shall be required to provide the Owner with a 1-year maintenance bond in the amount of 10% of the awarded contract value after achieving substantial completion.

INSTRUCTION TO BIDDERS 002113.21 - 7

C. If the furnishing of such bonds is stipulated in the Bidding Documents, the cost shall be included in the Bid. If the furnishing of such bonds is required after receipt of bids and before execution of the Contract, the cost of such bonds shall be added to the Bid in determining the Contract Sum.

D. If the Owner requires that bonds be secured from other than the Bidder's usual sources, changes in cost will be adjusted as provided in the Contract Documents.

10.2 TIME OF DELIVERY AND FORM OF BONDS

A. The Bidder shall deliver the required bonds to the Owner not later than three days following the date of execution of the Contract. If the Work is to be commenced prior thereto in response to a letter of intent, the Bidder shall, prior to commencement of the Work, submit evidence satisfactory to the Owner that such bonds will be furnished and delivered in accordance with this Section 10.2.

B. The bonds shall be dated on or after the date of the Contract.

C. The Bidder shall require the attorney-in-fact who executes the required bonds on behalf of the surety to affix thereto a certified and current copy of the power of attorney.

10.3 INSURANCE REQUIREMENTS

A. The successful bidder, prior to commencing work, shall provide at his own expense, the following insurance to the Owner, evidenced by certificates of insurance. Each certificate shall require that notice be given, thirty (30) days prior to cancellation or material change in the policies, to Owner and all additional insureds. Nothing contained in this section shall be construed as limiting the extent of the vendor’s responsibility for payment of damages resulting from his operations under the contract.

B. Workers’ Compensation including Occupational Disease and Employer’s Liability Insurance.

C. Statutory – Amounts and coverage as required by Pennsylvania Workmen’s Compensation and Occupational Disease Laws.

D. Employer’s Liability – As listed in the EJCDC C-520 Standard Form of Agreement Between Owner and Contractor included in the Contract Documents.

E. Liability – The vendor shall maintain a Commercial General Liability Insurance Policy, using an occurrence form of coverage. The required coverage forms are:

Comprehensive Premises - Operation Contractual Insurance Independent Contractor

The General Liability Policy shall have a minimum limit of liability as listed in the EJCDC C-520, Standard Form of Agreement Between Owner and Contractor included in the Contract Documents.

Automobile Liability coverage with minimum combined single limits as listed in the EJCDC C- 520, Standard Form of Agreement Between Owner and Contractor included in the Contract Documents.

INSTRUCTION TO BIDDERS 002113.21 - 8

The Contractor shall obtain total minimum coverage limits as listed in the Standard Form of Agreement Between Owner and Contractor included in the Contract Documents.

10.5 ADDITIONALLY INSURED

A. The vendor, prior to commencing work, shall provide at his own expense, the required insurance to the Engineer and the Owner, evidenced by certificates of insurance. All policies shall name the Owner, its officers, agents, employees and Barry Isett & Associates, Inc. as additional insured.

This coverage shall be reflected on the Certificates of Insurance.

ARTICLE 11 - PENNSYLVANIA CONSTRUCTION CODE ACT

11.1 Construction must comply with the Act of November 10, 1999 (P.L. 491, No. 45), known as the Pennsylvania Construction Code Act (35 P.S. Sections 7210.101 et seq.), as implemented by Department of Labor and Industry regulations, 34 Pa. Code Chapters 401, 403, and 405. Please note that, as of December 2006, Pennsylvania's statewide building code will be referred to as the Uniform Construction Code (UCC). The codes currently in use under the UCC are the 2015 International Codes issued by the International Code Council.

ARTICLE 12 - STEEL PRODUCTS PROCUREMENT ACT

12.1 In accordance with Act No. 3 of the 1978 General Assembly of the Commonwealth of Pennsylvania, approved March 3, 1978, and as currently amended, if any steel products are to be used or supplied in the performance of the contract, only steel products produced in the United States as defined therein shall be used or supplied in the performance of the contract or any subcontracts thereunder.

Bidding Documents

PENAL SUM FORM

EJCDC® C-430, Bid Bond (Penal Sum Form). Published 2013.

Prepared by the Engineers Joint Contract Documents Committee.

BID BOND

Any singular reference to Bidder, Surety, Owner or other party shall be considered plural where applicable.

BIDDER (Name and Address):

SURETY (Name, and Address of Principal Place of Business):

OWNER (Name and Address):

BID

Bid Due Date:

Description (Project Name— Include Location):

BOND

Bond Number:

Date:

Penal sum $

(Words) (Figures) Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

BIDDER SURETY

(Seal) (Seal)

Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (Attach Power of Attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

Note: Addresses are to be used for giving any required notice.

Provide execution by any additional parties, such as joint venturers, if necessary.

PENAL SUM FORM

EJCDC® C-430, Bid Bond (Penal Sum Form). Published 2013.

Prepared by the Engineers Joint Contract Documents Committee.

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond shall be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation shall be null and void if:

3.1 Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2 All Bids are rejected by Owner, or

3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from the Bid due date without Surety’s written consent.

6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after the Bid due date.

7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect.

11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable.

SUBSTITUTION REQUEST FORM 004325 - 1

SECTION 004325 – SUBSTITUTION REQUEST FORM

CONTRACTOR:

Name: ______________________________________________________________

Address: ____________________________________________________________

SPECIFICATION SECTION NUMBER AND PARAGRAPH: ______________________________

DRAWING AND DETAILS AFFECTED: _______________________________________________

PROPOSED SUBSTITUTION:

Manufacturer: _______________________________________________________________________

Product (model, pattern, etc.): __________________________________________________________

WHY IS SUBSTITUTION BEING SUBMITTED? (Select 1 of the following):

[ ] Pre-Bid Substitution (Prior Approval) Bid Date

[ ] Specified product is not available. Explain

[ ] Cost saving to Owner. Indicate comparative cost analysis.

[ ] Other. Explain: _________________________________________________________________

EFFECTS OF PROPOSED SUBSTITUTION (Answer the following questions and attach explanations.)

Does substitution affect dimensions indicated on Drawings?

NO _____

YES _____, Explain: _______________________________________________________________

Does substitution affect Work of other Sections?

NO _____

YES _____, Explain: _______________________________________________________________

Does substitution require modifications to design, change to Drawings, or revisions to specifications to be incorporated into the Project?

NO _____

YES _____, Explain): ______________________________________________________________

Attach list of at least 3 projects where proposed substitution has been used within past 12 months include name, address, and telephone number of Owner and Architect/Engineer.

SUBSTITUTION REQUEST FORM 004325 - 2

CONTRACTOR’S/BIDDERS REPRESENTATION

Reference Section 002113.21 “Instructions to Bidders,” subsection 3.3.

Undersigned accepts responsibility for the coordination of proposed substitution and accepts all additional costs from the incorporation of proposed substitution into the Project per Section 012500 “Substitution Procedures.”

SUBMITTED BY:

CONTRACTOR:

Name: _____________________________________________________________________________

Address: ___________________________________________________________________________

SUBCONTRACTOR:

Signature: __________________________________________________________________________

Date: ______________________________________________________________________________

CONTRACTOR:

Signature: __________________________________________________________________________

Date: ______________________________________________________________________________

FOR ENGINEER’S USE

[ ] ACCEPTED

[ ] NOT ACCEPTED

[ ] NO ACTION REQUIRED

[ ] SUBMISSION:

[ ] INCOMPLETE

[ ] TOO LATE

REVIEWED BY:

Name & Signature: __________________________________________________________________

Date: ______________________________________________________________________________

PROPOSED SUBCONTRACTORS FORM 004336 - 1

SECTION 004336 – PROPOSED SUBCONTRACTORS FORM

Date ________________________________________

TO: _________________________________ Project No. __________________________________

_____________________________________ Project Name ________________________________

_____________________________________ Project Location ______________________________

In accordance with our prime contract for _____________________________________ of this project, we request acceptance of the following subcontractor to perform work or to supply material as indicated below:

1. ___________________________________________________________________________________

(Name)

(Street Address) (City) (State) (Zip)

2. Scope of Work (State kind of work, if for labor, or materials, or both, and give specification

Reference): ___________________________________________________________________________

3. The subcontractor’s non-collusive affidavit, and Insurance Certificate, is furnished herewith (original only), attached to the original of this request).

4. We warrant that the provisions required by our contract to be inserted in each subcontract, will be inserted in this subcontract.

5. We certify that this proposed subcontractor is not intelligible to receive awards of contracts from the

United States as evidenced by the list or lists of such contractors maintained by HUD.

6. There will be no assignment of interest in this subcontract except as follows (if none, so state):

7. Terms of payment: Price: $_______________________

8. Remarks: __________________________________________________________________________

(Prime Contractor)

By ___________________________

Title _________________________

If a sales agent, identify the manufacturer under (Remarks). If for a subcontract, identify principal subcontractor under (Remarks).

PROPOSED SUBCONTRACTORS FORM 004336 - 2

ACCEPTANCE OR REJECTION

The proposed subcontractor named above is _______________________________________________

If accepted, the contracting party giving such acceptance assumes no responsibility in connection with the form or terms of the subcontract, nor the performance of the subcontractor, and this form will not be returned.

If rejected, the reason (s) will be briefly stated herein, and this form will be returned within 10 days after receipt.

(Date) (Contracting Officer)

EJCDC® C-451, Qualifications Statement.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

QUALIFICATIONS STATEMENT

THE INFORMATION SUPPLIED IN THIS DOCUMENT IS CONFIDENTIAL TO THE EXTENT

PERMITTED BY LAWS AND REGULATIONS

1. SUBMITTED BY:

Official Name of Firm:

Address:

2. SUBMITTED TO:

3. SUBMITTED FOR:

Owner:

Project Name:

TYPE OF WORK:

4. CONTRACTOR'S CONTACT INFORMATION

Contact Person:

Title:

Phone:

Email:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies,

5. AFFILIATED COMPANIES:

Name:

6. TYPE OF ORGANIZATION:

SOLE PROPRIETORSHIP

Name of Owner:

Doing Business As:

Date of Organization:

PARTNERSHIP

Date of Organization:

Type of Partnership:

Name of General Partner(s):

CORPORATION

State of Organization:

Date of Organization:

Executive Officers:

- President:

- Vice President(s):

- Treasurer:

- Secretary:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, LIMITED LIABILITY COMPANY

State of Organization:

Date of Organization:

Members:

JOINT VENTURE

Sate of Organization:

Date of Organization:

Form of Organization:

Joint Venture Managing Partner

- Name:

- Address:

Joint Venture Managing Partner

Joint Venture Managing Partner

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies,

7. LICENSING

Jurisdiction:

Type of License:

License Number:

Jurisdiction:

Type of License:

License Number:

8. CERTIFICATIONS CERTIFIED BY:

Disadvantage Business Enterprise:

Minority Business Enterprise:

Woman Owned Enterprise:

Small Business Enterprise:

Other ( ):

9. BONDING INFORMATION

Bonding Company:

Bonding Agent:

Contact Name:

Aggregate Bonding Capacity:

Available Bonding Capacity as of date of this submittal:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies,

10. FINANCIAL INFORMATION

Financial Institution:

Account Manager:

INCLUDE AS AN ATTACHMENT AN AUDITED BALANCE SHEET FOR EACH OF THE

LAST 3 YEARS

11. CONSTRUCTION EXPERIENCE:

Current Experience:

List on Schedule A all uncompleted projects currently under contract (If Joint Venture list each participant's projects separately).

Previous Experience:

List on Schedule B all projects completed within the last 5 Years (If Joint Venture list each participant's projects separately).

Has firm listed in Section 1 ever failed to complete a construction contract awarded to it?

YES NO

If YES, attach as an Attachment details including Project Owner's contact information.

Has any Corporate Officer, Partner, Joint Venture participant or Proprietor ever failed to complete a construction contract awarded to them in their name or when acting as a principal of another entity?

YES NO

If YES, attach as an Attachment details including Project Owner's contact information.

Are there any judgments, claims, disputes or litigation pending or outstanding involving the firm listed in Section 1 or any of its officers (or any of its partners if a partnership or any of the individual entities if a joint venture)?

YES NO

If YES, attach as an Attachment details including Project Owner's contact information.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies,

12. SAFETY PROGRAM:

Name of Contractor's Safety Officer:

Include the following as attachments:

Provide as an Attachment Contractor's (and Contractor's proposed Subcontractors and Suppliers furnishing or performing Work having a value in excess of 10 percent of the total amount of the Bid) OSHA No. 500- Log & Summary of Occupational Injuries & Illnesses for the past 5 years.

Provide as an Attachment Contractor's (and Contractor's proposed Subcontractors and Suppliers furnishing or performing Work having a value in excess of 10 percent of the total amount of the Bid) list of all OSHA Citations & Notifications of Penalty (monetary or other) received within the last 5 years (indicate disposition as applicable) - IF NONE SO STATE.

Provide as an Attachment Contractor's (and Contractor's proposed Subcontractors and Suppliers furnishing or performing Work having a value in excess of 10 percent of the total amount of the Bid) list of all safety citations or violations under any state all received within the last 5 years (indicate disposition as applicable) - IF NONE SO STATE.

Provide the following for the firm listed in Section V (and for each proposed Subcontractor furnishing or performing Work having a value in excess of 10 percent of the total amount of the Bid) the following (attach additional sheets as necessary):

Workers' compensation Experience Modification Rate (EMR) for the last 5 years:

YEAR EMR

YEAR EMR

YEAR EMR

YEAR EMR

YEAR EMR

Total Recordable Frequency Rate (TRFR) for the last 5 years:

YEAR TRFR

YEAR TRFR

YEAR TRFR

YEAR TRFR

YEAR TRFR

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, Total number of man-hours worked for the last 5 Years:

YEAR TOTAL NUMBER OF MAN-HOURS

YEAR TOTAL NUMBER OF MAN-HOURS

YEAR TOTAL NUMBER OF MAN-HOURS

Provide Contractor's (and Contractor's proposed Subcontractors and Suppliers furnishing or performing Work having a value in excess of 10 percent of the total amount of the Bid) Days Away From Work, Days of Restricted Work Activity or Job Transfer (DART) incidence rate for the particular industry or type of Work to be performed by Contractor and each of Contractor's proposed Subcontractors and Suppliers) for the last 5 years:

YEAR DART

YEAR DART

YEAR DART

YEAR DART

YEAR DART

13. EQUIPMENT:

MAJOR EQUIPMENT:

List on Schedule C all pieces of major equipment available for use on Owner's Project.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, I HEREBY CERTIFY THAT THE INFORMATION SUBMITTED HEREWITH, INCLUDING ANY ATTACHMENTS, IS

TRUE TO THE BEST OF MY KNOWLEDGE AND BELIEF.

NAME OF ORGANIZATION:

BY:

TITLE:

DATED:

NOTARY ATTEST:

SUBSCRIBED AND SWORN TO BEFORE ME

THIS DAY OF , 20___

NOTARY PUBLIC - STATE OF

MY COMMISSION EXPIRES:

REQUIRED ATTACHMENTS

1. Schedule A (Current Experience).

2. Schedule B (Previous Experience).

3. Schedule C (Major Equipment).

4. Audited balance sheet for each of the last 3 years for firm named in Section 1.

5. Evidence of authority for individuals listed in Section 7 to bind organization to an agreement.

6. Resumes of officers and key individuals (including Safety Officer) of firm named in Section 1.

7. Required safety program submittals listed in Section 13.

8. Additional items as pertinent.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, SCHEDULE A

CURRENT EXPERIENCE

Project Name Owner's Contact Person Design Engineer Contract Date Type of Work Status Cost of Work

Telephone:

Name:

Company:

Telephone:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, SCHEDULE B

PREVIOUS EXPERIENCE (Include ALL Projects Completed within last 5 years)

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, SCHEDULE B

PREVIOUS EXPERIENCE (Include ALL Projects Completed within last 5 years)

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, SCHEDULE C - LIST OF MAJOR EQUIPMENT AVAILABLE

ITEM PURCHASE DATE CONDITION ACQUIRED VALUE

CONSENT OF SURETY 004515 - 1

SECTION 004515 – CONSENT OF SURETY

KNOW ALL MEN BY THESE PRESENTS, that we

, as Surety, a corporation existing under the laws of the State/Commonwealth of

, and authorized to transact business in the Commonwealth of Pennsylvania, hereby agree to execute within the time limit and in the forms and amounts specified in the Contract

Documents, the Contract Bonds as required for the faithful performance and proper fulfillment of the

Contract for

On behalf of hereinafter called the Bidder, provided that the above Contract be award to the Bidder within sixty (60) days after the date of opening of bids, or as otherwise set forth in the Instructions to Bidders and any amendments thereto; and the Surety further agrees that should the Surety, after notification of intent to make such award, refuse to execute and/or otherwise provide the required Bonds, then the Surety shall pay to the Owner of the Project, the amount of the Bid Security.

ATTEST SURETY

DATE SIGNATURE (AFFIX CORPORATE SEAL)

ATTORNEY IN FACT

NON-COLLUSION AFFIDAVIT 004519 - 1

SECTION 004519 – NON-COLLUSION AFFIDAVIT

State of _____________________________

County of ____________________________

I _______________________________________, being first duly sworn, deposes and says that:

(Print Name)

(1) I am __________________________________________________________ of

(Title)

__________________________________________________, the Bidder that has submitted the

(Name of Firm) attached bid;

(2) I am fully informed respecting the preparation and contents of the attached Bid and all pertinent circumstances respecting such Bid;

(3) Such Bid is genuine and is not a collusive or sham Bid;

(4) Neither the said Bidder nor any of its officers, partners, owners, agents, representatives, employees or parties in interest, including this affiant, has in any way colluded, conspired, connived or agreed, directly or indirectly with any other Bidder, firm or person to submit a collusive or sham Bid in connection with the Contract for which the attached Bid has been submitted or to refrain from bidding in connection with such Contract, or has in any manner, directly or indirectly, sought by agreement or collusion or communication or conference with any other Bidder, firm or person to fix the price or prices in the attached Bid or of any other Bidder, or to fix any overhead, profit or cost element of the Bid price or the Bid price of any Bidder, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantages against the Owner or any person interested in the proposed Contract; and

(5) The price or prices quoted in the attached Bid are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the Bidder or any of its agents, representatives, owners, employees, or parties in interest, including this affiant.

(Signed) ____________________________

Subscribed and sworn to before me

This ____ day of ______________, 20____.

My Commission Expires ________________________________

AMERICANS WITH DISABILITIES ACT 004537 - 1

SECTION 004537 – EQUAL EMPLOYMENT OPPORTUNITY AFFIDAVIT

EQUAL OPPORTUNITY FOR INDIVIDUALS WITH DISABILITIES:

The Contractor and the Owner do hereby agree that the provisions of Title II of the Americans With Disabilities Act of 1990 (the "Act") (42 U.S.C. S12101 et seq.), which prohibits discrimination on the basis of disability by public entities in all services, programs, and activities provided or made available by public entities, and the rules and regulations promulgated pursuant thereunto, are made a part of this Contract. In providing any aid, benefit, or service on behalf of the Owner pursuant to this Contract, the Contractor agrees that the performance shall be in strict compliance with the Act. In the event that the Contractor, it agents, servants, employees, or Subcontractors violate or are alleged to have violated the Act during the performance of this Contract, the Contractor shall defend the Owner in any action or administrative proceeding commenced pursuant to this Act. The Contractor shall indemnify, protect, and save harmless the Owner, its agents, servants, and employees from and against any and all suits, claims, losses, demands, or damages of whatever kind or nature arising out of or claimed to arise out of the alleged violation. The Contractor shall, at its own expense, appear, defend, and pay any and all charges for legal services and any and all costs and other expenses arising from such action or administrative proceeding or incurred in connection therewith. In any and all complaints brought pursuant to the Owner's grievance procedure, the Contractor agrees to abide by any decision of the Owner which is rendered pursuant to said grievance procedure. If any action or administrative proceeding results in an award of damages against the Owner or if the Owner incurs any expense to cure a violation of the ADA which has been brought pursuant to its grievance procedure, the Contractor shall satisfy and discharge the same at its own expense.

The Owner shall, as soon as practicable after a claim has been made against it, give written notice thereof to the Contractor along with full and complete particulars of the claim. If any action or administrative proceeding is brought against the Owner or any of its agents, servants, and employees, the Owner shall expeditiously forward or have forwarded to the Contractor every demand, complaint, notice, summons, pleading, or other process received by the Owner or its representatives.

It is expressly agreed and understood that any approval by the Owner of the services provided by the Contractor pursuant to this Contract will not relieve the Contractor of the obligation to comply with the Act and to defend, indemnify, protect, and save harmless the Owner pursuant to this Paragraph.

It is further agreed and understood that the Owner assumes no obligation to indemnify or save harmless the Contractor, its agents, servants, employees and Subcontractors for any claim which may arise out of their performance of the Agreement. Furthermore, the Contractor expressly understands and agrees that the provisions of this indemnification clause shall in no way limit the Contractor's obligations assumed in this Agreement, nor shall they be construed to relieve the Contractor from any liability, nor preclude the Owner from taking any other actions available to it under any other provisions of this Agreement or otherwise at law.

Contractor Signature: ________________________________________

Contractor Name: ___________________________________________

Date: _________________________ jharvey Rectangle jharvey Rectangle jharvey Rectangle

COMMONWEALTH OF PENNSYLVANIA

PUBLIC WORKS EMPLOYMENT VERIFICATION FORM

Date _______________________

Business or Organization Name (Employer)_________________________________________________

Address _____________________________________________________________________________

City _____________________________________ State_____________ Zip Code ________________

Contractor {dzōŎƻƴǘNJŀŎǘƻNJ όŎƘŜŎƪ ƻƴŜύ

Contracting Public Body _______________________________________________________________

Contract/Project No ___________________________________________________________________

Project Description ____________________________________________________________________

Project Location ______________________________________________________________________

As a contractor/subcontractor for the above referenced public works contract, I hereby affirm that as of the above date, our company is in compliance with the Public Works…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .