1-Contract Documents and Specifications.pdf
PDF 35 MB Posted
- Attached to
- Borough Hall Memorial Park Phase II Improvements
- Solicitation number
- Not on record
- Issued by
- Monroe County, Pennsylvania
About this file
This is a Contract Documents and Specifications package for Mount Pocono Borough's Maintenance Building Expansion project, prepared by Barry Isett & Associates, Inc. The project scope includes demolition of an existing building and construction of a new 5,883 square foot maintenance facility with pavement, underground storm system, service utilities, and reinforced concrete apron located at 57 Knox Street, Mount Pocono, Pennsylvania. Sealed bids will be received online via the PennBid Program until 10:00 AM on April 22, 2026, with bidding documents available beginning April 1, 2026. A pre-bid meeting is scheduled for 10:00 AM on April 7, 2026 at the project site, and questions may be submitted through April 16, 2026 at 3:00 PM. The notice of award will be issued on April 29, 2026, with notice to proceed for Pre-Engineered Metal Building (PEMB) shop drawings also on April 29, 2026 and general project notice to proceed on May 13, 2026. The construction schedule establishes preconstruction meeting on May 14, 2026, construction commencement on May 26, 2026, substantial completion of maintenance and wash bays by November 30, 2026, full project substantial completion on February 3, 2027, and final completion on February 15, 2027.
Each bid must be accompanied by a bid bond in the amount of 10 percent of the total bid amount from a corporate surety authorized to do business in Pennsylvania, with the successful bidder required to furnish Performance and Payment Bonds in the amount of 100 percent of the contract value. A one-year maintenance bond in the amount of 10 percent of the awarded contract value is required after substantial completion. Prevailing wage rates apply to the project as established by the Pennsylvania Department of Labor & Industry. Liquidated damages are assessed at $750 per day if the contractor fails to achieve partial substantial completion by November 30, 2026, with partial substantial completion requiring the pre-engineered metal building to be erected with roof and siding complete, gas heating operational in three bays, electrical service installed with power available, and water service installed. The contract is a single-prime, stipulated sum agreement under AIA Document A104. All work must comply with the 2015 International Codes under Pennsylvania's Uniform Construction Code, Pennsylvania prevailing wage requirements, and the Public Works Employment Verification Act requiring E-Verify compliance for all new employees.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Contract Documents and Specifications-20260615.pdf | ||
| 2-Drawings-20260615.pdf | ||
| 2-Drawings-PEMB Maintenance Building.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contact Documents and Specifications
FOR
Mount Pocono Maintenance Building Expansion
Owner:
Mount Pocono Borough 1361 Pocono Blvd. Suite 100 Mount Pocono, PA 18344
Date: April 2026 Project #: 313625.006
Table of Contents
SECTION 000110 – TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT & CONTRACTING REQUIREMENTS
BIDDING INSTRUCTIONS
001116 Invitation to Bid
002113.31 Instruction to Bidders
BIDDING DOCUMENTS
004313.31 Bid Bond (Sample AIA-310)
004325 Substitution Request Form
004336 Proposed Subcontractors Form
004513.31 Contractor’s Qualifications (Sample AIA-305)
004515 Consent of Surety
004519 Non-Collusion Affidavit
004536 Equal Employment Opportunity Affidavit
004546 PA E-Verify
004560 Nondiscrimination Sexual Harassment Clause
004597 Bid Submittal Checklist
004600 Workmen’s Compensation Act Affidavit
CONTRACTING REQUIREMENTS
005213.31 Agreement Form (Stipulated Sum – Single-Prime Contract) – (Sample AIA-104)
006113.31 Performance Bond (Sample AIA-312)
006113.33 Payment Bond (Sample AIA-312)
006119 Maintenance Bond
006123 Warranty Bond (Sample AIA-A313)
006276.31 Application for Payment (Sample AIA-G702-703)
006346.31 Change Directive (Sample AIA-G714)
006363.31 Change Order (Sample AIA-A701)
007343 Prevailing Wage Rates
008600 PA Tax Exempt Disclosure
Mount Pocono Maintenance Building Expansion Project #313625.006
TECHNICAL SPECIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
011000 Summary
012200 Unit Prices
012500 Substitution Procedures
012600 Contract Modification Procedures
012900 Payment Procedures
013100 Project Management and Coordination
013300 Submittal Procedures
015000 Temporary Facilities and Controls
015000 Temporary Facilities and Controls - Site
015700 Maintenance and Protection of Traffic
017300 Execution
017700 Closeout Procedures
DIVISION 31 – EARTHWORK
311000 Site Clearing
312000 Earth Moving
DIVISION 33 – UTILITIES
330500 Common Work Results for Utilities
331415 Site Water Distribution Piping
333000 Sanitary Sewer Utilities
336100 Disinfecting Pipelines
DIVISION 50 – PENNDOT PUBLICATION COORDINATION
500000 PennDOT Technical Specifications Index
500001 PennDOT Publication Coordination
DRAWINGS
CS-1 Cover Sheet
SC-1 Civil Cover Sheet
EF-1 Existing Features & Demolition Plan
SP-1 Site Development Plan
GU-1 Grading & Utility Plan
LI-1 Lighting Plan
ES-1 Erosion & Sediment Control Plan
ESD-1 Erosion & Sediment Control Details – 1
ESD-2 Erosion & Sediment Control Details – 2
DE-1 Construction Details
PCD-1 Post Construction Stormwater Management Details
DRAWINGS (Cont.)
GA0.0 Code Plan
GA1.0 Floor Plans
GA1.1 Enlarged Plans
GA2.0 Elevations
GA3.0 Building Sections
GA3.1 Building Sections
GA4.0 Ceiling Plans and Finishes
S1.0 Foundation Plan
S1.1 Foundation Note
S1.2 Foundation Schedules and Details
S2.0 Mezzanine Framing Plan
S2.1 Steel Notes and Details
M0.0 Mechanical Information Sheet
M1.0 Mechanical Floor Plans
M2.0 Mechanical Schedules and Details
M3.0 Mechanical Specifications
P0.0 Plumbing Information Sheet
P1.0 Floor Plans-Domestic Water
P2.0 Floor Plans-Sanitary
P3.0 Plumbing Schedules and Details
P4.0 Plumbing Specifications
E0.0 Electrical Information Sheet
E1.0 Electrical Floor Plans-Lighting
E2.0 Electrical Floor Plans-Power
E3.0 Electrical Details and Riser Diagram
E3.1 Electrical Plan Schedules
E4.0 Electrical Specifications
E4.1 Electrical Specifications
Division 00
Procurement &
Contracting Requirements
Bidding Instructions
INVITATION TO BID 001116 - 1
SECTION 001116 – INVITATION TO BID
Notice is hereby given that Mount Pocono Borough will receive sealed bids online via the PennBid
Program (http://pennbid.bonfirehub.com) until 10:00 AM prevailing time on Wednesday, April 22, 2026 for the Mount Pocono Maintenance Building Expansion Project. The work includes but is not limited to all labor, materials, tools, oversight and permits required for existing building demolition and construction of new 5,883SF Maintenance Building, install pavement, underground storm system and service utilities, reinforced conc. apron and all other work shown or reasonably implied.
All bidding documents will be available online at no cost via the PennBid Program
(http://pennbid.bonfirehub.com) beginning at 12:00 PM on Wednesday, April 1, 2026.
Bids must be accompanied by a bid bond with a corporate surety authorized to do business in Pennsylvania, in accordance with the project specifications in the amount of 10% of the total bid amount. A Performance and Payment Bond in the amount of 100% of the contract shall be furnished by the successful bidder as detailed in the Instructions to Bidders. Prevailing Wage Rates shall apply.
Immediately following the due date and time, all bids received through PennBid will be opened online at the Engineer’s Office and referred to the Mount Pocono Borough for final award. An abstract of the bids received will be available to bidders on PennBid following the date and time that bids are due as indicated above.
A pre-bid meeting will be held at 10:00 AM on Tuesday, April 7, 2026 at the site weather permitting
57 Knox Street, Mount Pocono. All bidders are encouraged to attend. Questions may be submitted through
PennBid’s “Messages/Public Q&A” tab on or before 3:00 PM on Thursday, April 16, 2026. Responses will be provided via PennBid to all registered parties.
Special Instructions: Notice of award will be given on Wednesday, April 29th, 2026. Notice to proceed
PEMB shop drawings specific will be given Wednesday, April 29th, 2026.
The Mount Pocono Borough reserves the right to accept or reject any or all bids or portions or to waive any informalities in bidding and to withhold award for a period of sixty days.
On Behalf of Mount Pocono Borough
Barry Isett & Associates, Inc.
5420 Crackersport Road
Allentown, PA 18104
INSTRUCTION TO BIDDERS 002113.31 - 1
SECTION 002113.31 – INSTRUCTION TO BIDDERS
ARTICLE 1 - DEFINITIONS
1.1 Bidding Documents include the Bidding Requirements and the proposed Contract Documents.
The Bidding Requirements consist of the Advertisement or Invitation to Bid, Instructions to
Bidders, the bid form, and other sample bidding and contract forms. The proposed Contract
Documents consist of the form of Agreement between the Owner and Contractor, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications and all
Addenda issued prior to execution of the Contract.
1.2 Definitions set forth in the General Conditions of the Contract for Construction, AIA Document
A201, or in other Contract Documents are applicable to the Bidding Documents.
1.3 Addenda are written or graphic instruments issued by the Engineer prior to the execution of the
Contract which modify or interpret the Bidding Documents by additions, deletions, clarifications or corrections.
1.4 A Bid is a complete and properly executed proposal to do the Work for the sums stipulated therein, submitted in accordance with the Bidding Documents.
1.5 The Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents as the base, to which Work may be added or from which
Work may be deleted for sums stated in Alternate Bids.
1.6 An Allowance is a specified monetary amount identified in the Bidding Documents and stated in the Bid to cover the cost of particular items of Work, materials, equipment, or services.
Allowances are established to ensure that comparable costs are included by all Bidders for designated portions of the Work.
1.7 An Alternate Bid (or Alternate) is an amount stated in the Bid to be added to or deducted from the amount of the Base Bid if the corresponding change in the Work, as described in the Bidding
Documents, is accepted.
1.8 A Unit Price is an amount stated in the Bid as a price per unit of measurement for materials, equipment or services or a portion of the Work as described in the Bidding Documents.
1.9 A Bidder is a person or entity who submits a Bid and who meets the requirements set forth in the
Bidding Documents.
1.10 A Sub-bidder is a person or entity who submits a bid to a Bidder for materials, equipment or labor for a portion of the Work.
ARTICLE 2 - BIDDER'S REPRESENTATIONS
2.1 The Bidder by making a Bid represents that:
A. The Bidder has read and understands the Bidding Documents or Contract Documents, to the extent that such documentation relates to the Work for which the Bid is submitted, and for other portions of the Project, if any, being bid concurrently or presently under construction.
B. The Bid is made in compliance with the Bidding Documents.
INSTRUCTION TO BIDDERS 002113.31 - 2
C. The Bidder has visited the site, become familiar with local conditions under which the Work is to be performed and has correlated the Bidder's personal observations with the requirements of the proposed Contract Documents.
D. The Bid is based upon the materials, equipment and systems required by the Bidding Documents without exception.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.1 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall complete submit a properly executed AIA Document A305, Contractor's Qualification Statement.
3.2 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.3 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
3.4 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
ARTICLE 4 - BIDDING DOCUMENTS
4.1 COPIES
A. Bidders may obtain complete sets of the Bidding Documents at no cost, online via the PennBid
Program (https://pennbid.bonfirehub.com)
B. Bidders shall use complete sets of Bidding Documents in preparing Bids; neither the Owner nor
Engineer assumes responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
C. The Owner and Engineer may make copies of the Bidding Documents available on the above terms for the purpose of obtaining Bids on the Work. No license or grant of use is conferred by issuance of copies of the Bidding Documents.
4.2 INTERPRETATION OR CORRECTION OF BIDDING DOCUMENTS
A. The Bidder shall carefully study and compare the Bidding Documents with each other, and with other work being bid concurrently or presently under construction to the extent that it relates to the Work for which the Bid is submitted, shall examine the site and local conditions, and shall at once report to the Engineer errors, inconsistencies or ambiguities discovered.
B. Bidders and Sub-bidders requiring clarification or interpretation of the Bidding Documents shall make a written request via PennBid’s “Messages /Vendor Discussions” in accordance with the date referenced in the Invitation to Bidders.
C. Interpretations, corrections and changes of the Bidding Documents will be made by Addendum.
Interpretations, corrections and changes of the Bidding Documents made in any other manner will not be binding, and Bidders shall not rely upon them.
INSTRUCTION TO BIDDERS 002113.31 - 3
4.3 SUBSTITUTIONS
A. The materials, products and equipment described in the Bidding Documents establish a standard of required function, dimension, appearance and quality to be met by any proposed substitution.
Proprietary Items - Contractor may propose an “or equal” product for any item(s) specifically noted on the drawings or within the technical specifications. Contractor shall provide details and submit substitutions to the Engineer for review and approval as set forth in this section.
B. No substitution will be considered prior to receipt of Bids unless written request for approval has been received by the Engineer by 3:00 P.M. at least ten days prior to the date for receipt of Bids.
Such requests shall include the enclosed substitution request form, the name of the material or equipment for which it is to be substituted and a complete description of the proposed substitution including drawings, performance and test data, and other information necessary for an evaluation.
A statement setting forth changes in other materials, equipment or other portions of the Work, including changes in the work of other contracts that incorporation of the proposed substitution would require, shall be included. The burden of proof of the merit of the proposed substitution is upon the proposer. The Engineer's decision of approval or disapproval of a proposed substitution shall be final.
C. If the Engineer approves a proposed substitution prior to receipt of Bids, such approval will be set forth in an Addendum. Bidders shall not rely upon approvals made in any other manner.
D. No substitutions will be considered after the Contract award unless specifically provided for in the Contract Documents.
4.4 ADDENDA
A. Addenda will be posted online via PennBid’s “Files” tab and bidder will be notified via email.
B. Each Bidder shall ascertain prior to submitting a Bid that the Bidder has received all Addenda issued, and the Bidder shall acknowledge their receipt in the Bid.
ARTICLE 5 - BIDDING PROCEDURES
5.1 PREPARATION OF BIDS
A. The Bid Form may be included in the Bidding Documents for Reference. Bidders shall complete the electronic bid form within PennBid’s “Prepare Your Submission” tab.
B. Allowances shall be itemized separately from the Base Bid. Each allowance shall be clearly listed with its corresponding value in the Bid Form. The total of all allowances will be added to the
Base Bid to establish the Base Bid Amount. The Contractor shall not omit or conceal allowances within other line items of the bid. Failure to properly itemize allowances may render the bid nonresponsive.
C. All requested Alternates shall be bid. If no change in the Base Bid is required, enter “0.”
D. Where two or more Bids for designated portions of the Work have been requested, the Bidder may, without forfeiture of the bid security, state the Bidder's refusal to accept award of less than the combination of Bids stipulated by the Bidder. The Bidder shall make no additional stipulations on the bid form nor qualify the Bid in any other manner.
INSTRUCTION TO BIDDERS 002113.31 - 4
E. Each copy of the Bid shall state the legal name of the Bidder and the nature of legal form of the
Bidder. The Bidder shall provide evidence of legal authority to perform within the jurisdiction of the Work. Each copy shall be signed by the person or persons legally authorized to bind the
Bidder to a contract.
A Bid by a corporation shall further give the state of incorporation and have the corporate seal affixed. A Bid submitted by an agent shall have a current power of attorney attached certifying the agent's authority to bind the Bidder.
F. Each Bid shall be accompanied with a list of three closely-related past projects completed by the
Bidder within the last five years. This list shall include a description of the work included in the project, the Client, the Client’s contact information, time of completion, and a value of the total construction cost.
5.2 BID SECURITY
A. Each Bid shall be accompanied by a bid security in the form and the amount of 10% of the bid if so stipulated in the Instructions to Bidders. The Bidder pledges to enter into a Contract with the
Owner on the terms stated in the Bid and will, if required, furnish bonds covering the faithful performance of the Contract and payment of all obligations arising thereunder. Should the Bidder refuse to enter into such Contract or fail to furnish such bonds if required, the amount of the bid security shall be forfeited to the Owner as liquidated damages, not as a penalty. The amount of the bid security shall not be forfeited to the Owner in the event the Owner fails to comply with
Section 6.2.
B. If a surety bond is required, it shall be written on AIA Document A310, Bid Bond, unless otherwise provided in the Bidding Documents, and the attorney-in-fact who executes the bond on behalf of the surety shall affix to the bond a certified and current copy of the power of attorney.
C. The Owner will have the right to retain the bid security of Bidders to whom an award is being considered until either (a) the Contract has been executed and bonds, if required, have been furnished, or (b) the specified time has elapsed so that Bids may be withdrawn or (c) all Bids have been rejected.
5.3 CONTRACTOR'S QUALIFICATION STATEMENT
A. Bidders shall submit to the Engineer, upon request, a properly executed AIA Document A305, Contractor's Qualification Statement with attachments as required.
5.4 SUBMISSION OF BIDS
A. Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com).
Bidders shall complete the electronic bid form within PennBid’s “Prepare Your Submission” tab.
B. The bid security, if any, and any other documents required to be submitted with the Bid uploaded to the PennBid’s “Requested Information” tab.
C. The Bidder shall assume full responsibility for timely submission of Bids.
https://pennbid.bonfirehub.com/
INSTRUCTION TO BIDDERS 002113.31 - 5
5.5 MODIFICATION OR WITHDRAWAL OF BID
A. A Bid may not be modified, withdrawn or canceled by the Bidder during the stipulated time period following the time and date designated for the receipt of Bids, and each Bidder so agrees in submitting a Bid.
B. Prior to the time and date designated for receipt of Bids, a submitted Bid may be modified or withdrawn any time within the PennBid Program.
C. Withdrawn Bids may be resubmitted up to the date and time designated for the receipt of Bids provided that they are then fully in conformance with these Instructions to Bidders.
D. Bid security, if required, shall be in an amount sufficient for the Bid as resubmitted.
ARTICLE 6 - CONSIDERATION OF BIDS
6.1 OPENING OF BIDS
A. Upon receipt of the bids, the bids will be opened electronically. A public notice will be issued via
PennBid containing any available bid results. These results are subject to further review and should not be considered an issuance of an award.
B. At the discretion of the Owner and only if stipulated in the Invitation to Bid, the properly identified Bids received on time will be publicly opened and read aloud. Results will be issued per Article 6.1.A.
6.2 REJECTION OF BIDS
A. The Owner shall have the right to reject any or all Bids. A Bid not accompanied by a required bid security or by other data required by the Bidding Documents, or a Bid which is in any way incomplete or irregular is subject to rejection.
6.3 ACCEPTANCE OF BID (AWARD)
A. It is the intent of the Owner to award a Contract to the lowest qualified Bidder provided the Bid has been submitted in accordance with the requirements of the Bidding Documents and does not exceed the funds available.
B. The Owner shall have the right to waive informalities and irregularities in a Bid received and to accept the Bid which, in the Owner's judgment, is in the Owner's own best interests.
C. The Owner shall have the right to accept Alternates in any order or combination, unless otherwise specifically provided in the Bidding Documents, and to determine the low Bidder on the basis of the sum of the Base Bid and Alternates accepted.
ARTICLE 7 – CONTRACT TIMES
7.1 The number of days within which, or the dates by which, Milestones are to be achieved and the
Work is to be substantially completed, and completed and ready for final payment, are set forth in the Agreement.
INSTRUCTION TO BIDDERS 002113.31 - 6
ARTICLE 8 – LIQUIDATED DAMAGES
8.1 Provisions for liquidated damages, if any, for failure to timely attain the below Partial Substantial
Completion milestones in readiness for final payment, are set forth as follows:
If Contractor fails to achieve Partial Substantial Completion of the Work delineated below by
November 30, 2026, Owner shall be entitled to retain or recover from such Contractor as
Liquidated Damages, and not as a penalty, in the amount of $750.00 per day, commencing on the day after the Partial Substantial Completion date, and continuing until the actual date of loss of use of the facilities for the time associated with the delay.
Partial Substantial Completion shall include the following:
1. Pre-engineered metal building erection is complete, insulation complete, metal siding and roof complete, man and overhead doors complete. Both Maintenance Bays and the Wash
Bay must be available for Owner truck storage.
2. Gas service lines are installed and completed and gas unit heaters in both Maintenance
Bays and the Wash Bay are operational.
3. Electrical service lines are installed and completed. Power is made available for heating and general lighting in both Maintenance Bays and the Wash Bay.
4. Water service is installed and completed.
ARTICLE 9 - POST-BID INFORMATION
9.1 OWNER'S FINANCIAL CAPABILITY
A. The Owner shall, at the request of the Bidder to whom award of a Contract is under consideration and no later than seven days prior to the expiration of the time for withdrawal of Bids, furnish to the Bidder reasonable evidence that financial arrangements have been made to fulfill the Owner's obligations under the Contract. Unless such reasonable evidence is furnished, the Bidder will not be required to execute the Agreement between the Owner and Contractor.
9.2 SUBMITTALS
A. The Bidder shall, as soon as practicable or as stipulated in the Bidding Documents, after notification of selection for the award of a Contract, furnish to the Owner through the Engineer in writing:
1. a designation of the Work to be performed with the Bidder's own forces;
2. names of the manufacturers, products, and the suppliers of principal items or systems of materials and equipment proposed for the Work; and
3. names of persons or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for the principal portions of the Work.
B. The Bidder will be required to establish to the satisfaction of the Engineer and Owner the reliability and responsibility of the persons or entities proposed to furnish and perform the Work described in the Bidding Documents.
INSTRUCTION TO BIDDERS 002113.31 - 7
C. Prior to the execution of the Contract, the Engineer will notify the Bidder in writing if either the
Owner or Engineer, after due investigation, has reasonable objection to a person or entity proposed by the Bidder.
If the Owner or Engineer has reasonable objection to a proposed person or entity, the Bidder may, at the Bidder's option, (1) withdraw the Bid or (2) submit an acceptable substitute person or entity with no adjustment in the Base Bid or Alternate Bid occasioned by such substitution. The Owner may accept the adjusted bid or disqualify the Bidder. In the event of either withdrawal or disqualification, bid security will not be forfeited.
D. Persons and entities proposed by the Bidder and to whom the Owner and Engineer have made no reasonable objection must be used on the Work for which they were proposed and shall not be changed except with the written consent of the Owner and Engineer.
ARTICLE 10 - BONDING AND INSURANCE REQUIREMENTS
10.1 BOND REQUIREMENTS
A. The Bidder shall furnish bonds in 100% of the contract value covering the faithful performance of the Contract and payment of all obligations arising thereunder. Bonds may be secured through the
Bidder's usual sources.
B. The contractor shall be required to provide the Owner with a 1-year maintenance bond in the amount of 10% of the awarded contract value after achieving substantial completion.
C. If the furnishing of such bonds is stipulated in the Bidding Documents, the cost shall be included in the Bid. If the furnishing of such bonds is required after receipt of bids and before execution of the Contract, the cost of such bonds shall be added to the Bid in determining the Contract Sum.
D. If the Owner requires that bonds be secured from other than the Bidder's usual sources, changes in cost will be adjusted as provided in the Contract Documents.
10.2 TIME OF DELIVERY AND FORM OF BONDS
A. The Bidder shall deliver the required bonds to the Owner not later than three days following the date of execution of the Contract. If the Work is to be commenced prior thereto in response to a letter of intent, the Bidder shall, prior to commencement of the Work, submit evidence satisfactory to the Owner that such bonds will be furnished and delivered in accordance with this Section 10.2.
B. The bonds shall be dated on or after the date of the Contract.
C. The Bidder shall require the attorney-in-fact who executes the required bonds on behalf of the surety to affix thereto a certified and current copy of the power of attorney.
10.3 INSURANCE REQUIREMENTS
A. The successful bidder, prior to commencing work, shall provide at his own expense, the following insurance to the Owner, evidenced by certificates of insurance. Each certificate shall require that notice be given, thirty (30) days prior to cancellation or material change in the policies, to Owner and all additional insureds. Nothing contained in this section shall be construed as limiting the extent of the vendor’s responsibility for payment of damages resulting from his operations under the contract.
INSTRUCTION TO BIDDERS 002113.31 - 8
B. Workers’ Compensation including Occupational Disease and Employer’s Liability Insurance.
C. Statutory – Amounts and coverage as required by Pennsylvania Workmen’s Compensation and
Occupational Disease Laws.
D. Employer’s Liability – As listed in the AIA Standard Form of Agreement Between Owner and
Contractor included in the Contract Documents.
E. Liability – The vendor shall maintain a Commercial General Liability Insurance Policy, using an occurrence form of coverage. The required coverage forms are:
Comprehensive
Premises - Operation
Contractual Insurance
Independent Contractor
The General Liability Policy shall have a minimum limit of liability as listed in the AIA Standard Form of Agreement Between Owner and Contractor included in the Contract Documents.
Automobile Liability coverage with minimum combined single limits as listed in the AIA Standard
Form of Agreement Between Owner and Contractor included in the Contract Documents.
The Contractor shall obtain total minimum coverage limits as listed in the AIA Standard Form of
Agreement Between Owner and Contractor included in the Contract Documents.
10.5 ADDITIONALLY INSURED
A. The vendor, prior to commencing work, shall provide at his own expense, the required insurance to the Engineer and the Owner, evidenced by certificates of insurance. All policies shall name the
Owner, its officers, agents, employees and Barry Isett & Associates, Inc. as additional insured.
This coverage shall be reflected on the Certificates of Insurance.
ARTICLE 11 - PENNSYLVANIA CONSTRUCTION CODE ACT
11.1 Construction must comply with the Act of November 10, 1999 (P.L. 491, No. 45), known as the
Pennsylvania Construction Code Act (35 P.S. Sections 7210.101 et seq.), as implemented by
Department of Labor and Industry regulations, 34 Pa. Code Chapters 401, 403, and 405. Please note that, as of December 2006, Pennsylvania's statewide building code will be referred to as the
Uniform Construction Code (UCC). The codes currently in use under the UCC are the 2015
International Codes issued by the International Code Council.
ARTICLE 12 - STEEL PRODUCTS PROCUREMENT ACT
12.1 In accordance with Act No. 3 of the 1978 General Assembly of the Commonwealth of
Pennsylvania, approved March 3, 1978, and as currently amended, if any steel products are to be used or supplied in the performance of the contract, only steel products produced in the United
States as defined therein shall be used or supplied in the performance of the contract or any subcontracts thereunder.
Bidding Documents kthomas Text Box Mount Pocono Borough 1361 Pocono Blvd. Suite 100 Mount Pocono PA 18344 kthomas Text Box Mount Pocono Maintenance Building Expansion 57 Knox Street Mount Pocono PA 18344
SUBSTITUTION REQUEST FORM 004325 - 1
SECTION 004325 – SUBSTITUTION REQUEST FORM
CONTRACTOR:
Name: ______________________________________________________________
Address: ____________________________________________________________
SPECIFICATION SECTION NUMBER AND PARAGRAPH: ______________________________
DRAWING AND DETAILS AFFECTED: _______________________________________________
PROPOSED SUBSTITUTION:
Manufacturer: _______________________________________________________________________
Product (model, pattern, etc.): __________________________________________________________
WHY IS SUBSTITUTION BEING SUBMITTED? (Select 1 of the following):
[ ] Pre-Bid Substitution (Prior Approval) Bid Date
[ ] Specified product is not available. Explain
[ ] Cost saving to Owner. Indicate comparative cost analysis.
[ ] Other. Explain: _________________________________________________________________
EFFECTS OF PROPOSED SUBSTITUTION (Answer the following questions and attach explanations.)
Does substitution affect dimensions indicated on Drawings?
NO _____
YES _____, Explain: _______________________________________________________________
Does substitution affect Work of other Sections?
NO _____
YES _____, Explain: _______________________________________________________________
Does substitution require modifications to design, change to Drawings, or revisions to specifications to be incorporated into the Project?
NO _____
YES _____, Explain): ______________________________________________________________
Attach list of at least 3 projects where proposed substitution has been used within past 12 months include name, address, and telephone number of Owner and Architect/Engineer.
Mount Pocono Borough Mount Pocono Maintenance Building Expansion Project #313625.006 jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle
SUBSTITUTION REQUEST FORM 00 43 25 - 2
CONTRACTOR’S/BIDDERS REPRESENTATION
Reference Division 00 Section “Instructions to Bidders,” subsection 3.3.
Undersigned accepts responsibility for the coordination of proposed substitution and accepts all additional costs from the incorporation of proposed substitution into the Project per Division 01 Section “Substitution Procedures.”
SUBMITTED BY:
CONTRACTOR:
Name: _____________________________________________________________________________
Address: ___________________________________________________________________________
SUBCONTRACTOR:
Signature: __________________________________________________________________________
Date: ______________________________________________________________________________
CONTRACTOR:
Signature: __________________________________________________________________________
Date: ______________________________________________________________________________
FOR ENGINEER’S USE
[ ] ACCEPTED
[ ] NOT ACCEPTED
[ ] NO ACTION REQUIRED
[ ] SUBMISSION:
[ ] INCOMPLETE
[ ] TOO LATE
REVIEWED BY:
Name & Signature: __________________________________________________________________
Date: ______________________________________________________________________________
Mount Pocono Borough Mount Pocono Maintenance Building Expansion Project #313625.006 jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle
CONSENT OF SURETY 004515 - 1
SECTION 004515 – CONSENT OF SURETY
KNOW ALL MEN BY THESE PRESENTS, that we , as Surety, a corporation existing under the laws of the State/Commonwealth of , and authorized to transact business in the Commonwealth of Pennsylvania, hereby agree to execute within the time limit and in the forms and amounts specified in the Contract Documents, the Contract Bonds as required for the faithful performance and proper fulfillment of the Contract for
On behalf of hereinafter called the Bidder, provided that the above Contract be award to the Bidder within sixty (60) days after the date of opening of bids, or as otherwise set forth in the Instructions to Bidders and any amendments thereto; and the Surety further agrees that should the Surety, after notification of intent to make such award, refuse to execute and/or otherwise provide the required Bonds, then the Surety shall pay to the Owner of the Project, the amount of the Bid Security.
ATTEST SURETY
DATE SIGNATURE (AFFIX CORPORATE SEAL)
ATTORNEY IN FACT
* Attach an appropriate Power of Attorney, dated as of the same date as this Agreement, evidencing the authority of Attorney-in-Fact to act on behalf of the corporation.
NON-COLLUSION AFFIDAVIT 004519 - 1
SECTION 004519 – NON-COLLUSION AFFIDAVIT
State of _____________________________
County of ____________________________
I _______________________________________, being first duly sworn, deposes and says that:
(Print Name)
(1) I am __________________________________________________________ of (Title)
__________________________________________________, the Bidder that has submitted the (Name of Firm) attached bid;
(2) I am fully informed respecting the preparation and contents of the attached Bid and all pertinent circumstances respecting such Bid;
(3) Such Bid is genuine and is not a collusive or sham Bid;
(4) Neither the said Bidder nor any of its officers, partners, owners, agents, representatives, employees or parties in interest, including this affiant, has in any way colluded, conspired, connived or agreed, directly or indirectly with any other Bidder, firm or person to submit a collusive or sham Bid in connection with the Contract for which the attached Bid has been submitted or to refrain from bidding in connection with such Contract, or has in any manner, directly or indirectly, sought by agreement or collusion or communication or conference with any other Bidder, firm or person to fix the price or prices in the attached Bid or of any other Bidder, or to fix any overhead, profit or cost element of the Bid price or the Bid price of any Bidder, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantages against the Owner or any person interested in the proposed Contract; and
(5) The price or prices quoted in the attached Bid are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the Bidder or any of its agents, representatives, owners, employees, or parties in interest, including this affiant.
(Signed) ____________________________
(Title)
Subscribed and sworn to before me This ____ day of ______________, 20____.
(Title)
My Commission Expires ________________________________
Mount Pocono Borough Mount Pocono Maintenance Building Expansion Project #313625.006 jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle jharvey Rectangle
AMERICANS WITH DISABILITIES ACT 004537 - 1
SECTION 004537 – EQUAL EMPLOYMENT OPPORTUNITY AFFIDAVIT
EQUAL OPPORTUNITY FOR INDIVIDUALS WITH DISABILITIES:
The Contractor and the Owner do hereby agree that the provisions of Title II of the Americans With Disabilities Act of 1990 (the "Act") (42 U.S.C. S12101 et seq.), which prohibits discrimination on the basis of disability by public entities in all services, programs, and activities provided or made available by public entities, and the rules and regulations promulgated pursuant thereunto, are made a part of this Contract. In providing any aid, benefit, or service on behalf of the Owner pursuant to this Contract, the Contractor agrees that the performance shall be in strict compliance with the Act. In the event that the Contractor, it agents, servants, employees, or Subcontractors violate or are alleged to have violated the Act during the performance of this Contract, the Contractor shall defend the Owner in any action or administrative proceeding commenced pursuant to this Act. The Contractor shall indemnify, protect, and save harmless the Owner, its agents, servants, and employees from and against any and all suits, claims, losses, demands, or damages of whatever kind or nature arising out of or claimed to arise out of the alleged violation. The Contractor shall, at its own expense, appear, defend, and pay any and all charges for legal services and any and all costs and other expenses arising from such action or administrative proceeding or incurred in connection therewith. In any and all complaints brought pursuant to the Owner's grievance procedure, the Contractor agrees to abide by any decision of the Owner which is rendered pursuant to said grievance procedure. If any action or administrative proceeding results in an award of damages against the Owner or if the Owner incurs any expense to cure a violation of the ADA which has been brought pursuant to its grievance procedure, the Contractor shall satisfy and discharge the same at its own expense.
The Owner shall, as soon as practicable after a claim has been made against it, give written notice thereof to the Contractor along with full and complete particulars of the claim. If any action or administrative proceeding is brought against the Owner or any of its agents, servants, and employees, the Owner shall expeditiously forward or have forwarded to the Contractor every demand, complaint, notice, summons, pleading, or other process received by the Owner or its representatives.
It is expressly agreed and understood that any approval by the Owner of the services provided by the Contractor pursuant to this Contract will not relieve the Contractor of the obligation to comply with the Act and to defend, indemnify, protect, and save harmless the Owner pursuant to this Paragraph.
It is further agreed and understood that the Owner assumes no obligation to indemnify or save harmless the Contractor, its agents, servants, employees and Subcontractors for any claim which may arise out of their performance of the Agreement. Furthermore, the Contractor expressly understands and agrees that the provisions of this indemnification clause shall in no way limit the Contractor's obligations assumed in this Agreement, nor shall they be construed to relieve the Contractor from any liability, nor preclude the Owner from taking any other actions available to it under any other provisions of this Agreement or otherwise at law.
Contractor Signature: ________________________________________
Contractor Name: ___________________________________________
Date: _________________________
Mount Pocono Borough Mount Pocono Maintenance Building Expansion Project #313625.006 jharvey Rectangle jharvey Rectangle
COMMONWEALTH OF PENNSYLVANIA
PUBLIC WORKS EMPLOYMENT VERIFICATION FORM
Date _______________________
Business or Organization Name (Employer)_________________________________________________
Address _____________________________________________________________________________
City _____________________________________ State_____________ Zip Code ________________
Contractor {dzōŎƻƴǘNJŀŎǘƻNJ όŎƘŜŎƪ ƻƴŜύ
Contracting Public Body _______________________________________________________________
Contract/Project No ___________________________________________________________________
Project Description ____________________________________________________________________
Project Location ______________________________________________________________________
As a contractor/subcontractor for the above referenced public works contract, I hereby affirm that as of the above date, our company is in compliance with the Public Works Employment Verification Act
(‘the Act’) through utilization of the federal E‐Verify Program (EVP) operated by the United States
Department of Homeland Security. To the best of my/our knowledge, all employees hired post
January 1, 2013 are authorized to work in the United States.
It is also agreed to that all public works contractors/subcontractors will utilize the federal EVP to verify the employment eligibility of each new hire within five (5) business days of the employee start date throughout the duration of the public works contract. Documentation confirming the use of the federal EVP upon each new hire shall be maintained in the event of an investigation or audit.
I, _________________________, authorized representative of the company above, attest that the information contained in this verification form is true and correct and understand that the submission of false or misleading information in connection with the above verification shall be subject to sanctions provided by law.
Authorized Representative Signature
06 62 00 E-verify Act and Form
On July 5, 2012, Gov. Corbett signed into law the Public Works Employment Verification Act (S.B. 637) which takes effect January 1, 2013.
The Act requires all public works contractors and subcontractors in Pennsylvania to use E-Verify to verify the employment eligibility of new employees and applies to projects with an estimated cost in excess of $25,000 that are funded by the Commonwealth, or its political subdivisions, authorities, or agencies. E-Verify is an internet-based system that compares information from an employee’s Form I-9, Employment Eligibility Verification, to data from the U.S. Department of Homeland Security and Social Security Administration records to confirm employment eligibility.
(5) "Public work" means construction, reconstruction, demolition, alteration and/or repair work other than maintenance work, done under contract and paid for in whole or in part out of the funds of a public body where the estimated cost of the total project is in excess of twenty-five thousand dollars ($25,000), but shall not include work performed under a rehabilitation or manpower training program.
Under the Act, a contractor must submit a verification form signed under penalty of perjury and acknowledging its compliance with the Act as a precondition of being awarded a public works contract. Subcontractors must submit the form prior to commencing work on the public works project. In addition, contractors must include in their subcontracts information about the requirements of the Act. The Department of General Services (DGS) will create the verification form and is also charged with enforcement of the Act through complaint-based as well as random audits.
A contractor or subcontractor violates the Act by failing either to use E-Verify or to provide the verification form. Sanctions for failure to use E-Verify range from a warning letter (to be posted on the DGS website) for a first violation to a one year debarment for a third and subsequent violation. A willful violation of the Act will result in a 3-year debarment. Civil penalties for failure to use the form or for false statements on the form range from $250 to $1,000 for each violation.
The Act provides significant protection for whistleblowers. If an employee of a contractor or subcontractor is retaliated against for instigating or cooperating in an investigation, the employee can bring suit (which must be brought within 180 days from the date the employee knew of the retaliation) to obtain reinstatement of employment and to collect three times lost wages, along with an award of attorney’s fees and costs.
A contractor or subcontractor who relies in good faith on E-Verify has immunity from sanctions and shall have no liability to any individual who is not hired or is discharged from employment.
Good faith is shown by a federal agency’s written acknowledgment of the use of E-Verify.
Contractors are not liable for violations by subcontractors.
Information on E-Verify can be found:
http://www.uscis.gov/portal/site/uscis and searching for e-verify.
PA DGS regulations can be found:
http://www.pabulletin.com/secure/data/vol42/42-52/2525.html An electronic version of the verification form can be found at:
http://www.dgs.state.pa.us/portal/server.pt/community/construction_and_public_works/1235/pub lic_works_employment_verification/1357211
Mount Pocono Borough Mount Pocono Maintenance Building Expansion Project #313625.006 http://www.legis.state.pa.us/cfdocs/legis/PN/Public/btCheck.cfm?txtType=HTM&sessYr=2011&sessInd=0&billBody=S&billTyp=B&billNbr=0637&pn=2347 http://www.uscis.gov/portal/site/uscis/menuitem.eb1d4c2a3e5b9ac89243c6a7543f6d1a/?vgnextoid=75bce2e261405110VgnVCM1000004718190aRCRD&vgnextchannel=75bce2e261405110VgnVCM1000004718190aRCRD&gclid=CLKy7PD5lrECFcXe4Aodnm_Yew http://www.uscis.gov/portal/site/uscis http://www.pabulletin.com/secure/data/vol42/42-52/2525.html http://www.dgs.state.pa.us/portal/server.pt/community/construction_and_public_works/1235/public_works_employment_verification/1357211 http://www.dgs.state.pa.us/portal/server.pt/community/construction_and_public_works/1235/public_works_employment_verification/1357211 tsisock Rectangle cnewton Text Box PA E-Verify Form 004546-1
NONDISCRIMINATION/SEXUAL HARASSMENT CLAUSE 004560 - 1
NONDISCRIMINATION/SEXUAL HARASSMENT CLAUSE
1. Representations. The Grantee represents that it is presently in compliance with and will remain in compliance with all applicable federal, state, and local laws, regulations, and policies relating to nondiscrimination and sexual harassment for the term of the agreement.
The Grantee shall, upon request and within the time periods requested by the Commonwealth, furnish all necessary employment documents and records, including EEO-1 reports, and permit access to its books, records, and accounts by the Commonwealth for the purpose of ascertaining compliance with provisions of this Nondiscrimination/Sexual Harassment Clause.
2. Nondiscrimination/Sexual Harassment Obligations. The Grantee shall not:
a. in any manner discriminate in the hiring of any employee(s) for the performance of the activities required under this agreement or any subgrant agreement, contract, or subcontract, by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the Pennsylvania Human Relations Act (“PHRA”) and applicable federal laws, against any citizen of this Commonwealth who is qualified and available to perform the work to which the employment relates.
b. in any manner discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the PHRA and applicable federal laws, against or intimidate any of its employees.
c. in any manner discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the PHRA and applicable federal laws, in the provision of services under this agreement or any subgrant agreement, contract, or subcontract.
d. in any manner discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of PHRA and applicable federal laws, against any subgrantee, contractor, subcontractor, or supplier who is qualified to perform the work to which this agreement relates.
e. in any manner discriminate against employees by reason of participation in or decision to refrain from participating in labor activities protected under the Public Employee Relations Act, Pennsylvania Labor Relations Act, or National Labor Relations Act, as applicable, and to the extent determined by entities charged with the Acts’ enforcement and shall comply with any provision of law establishing organizations as employees’ exclusive representatives.
3. Establishment of Grantee Policy. The Grantee shall establish and maintain a written nondiscrimination and sexual harassment policy that complies with the applicable law and these Nondiscrimination/Sexual Harassment provisions and shall inform its employees in writing of the policy. The policy must contain a provision that states that sexual harassment will not be tolerated and employees who practice it will be disciplined. For the entire period of this agreement, the Grantee shall: (1) post its written nondiscrimination and sexual harassment policy or these Nondiscrimination/Sexual Harassment provisions conspicuously in easily accessible and well-lighted places customarily frequented by employees at or near
NONDISCRIMINATION/SEXUAL HARASSMENT CLAUSE 004560 - 2
where the grant activities are performed; or (2) provide electronic notice of the policy or this clause to its employees not less than annually.
4. Notification of Violations. The Grantee’s obligations pursuant to these provisions are ongoing from the effective date and through the termination date of the agreement.
Accordingly, the Grantee shall notify the Commonwealth if, at any time during the term of this agreement, it becomes aware of any actions or occurrences that would result in violation of these provisions.
5. Cancellation or Termination of Agreement. The Commonwealth may cancel or terminate this agreement and all money due or to become due under this agreement may be forfeited for a violation of the terms and conditions of these Nondiscrimination/Sexual Harassment provisions. In addition, the granting agency may proceed with debarment or suspension and may place the Grantee in the Contractor Responsibility File.
6. Subgrant Agreements, Contracts, and Subcontracts. The Grantee shall include these
Nondiscrimination/Sexual Harassment provisions in its subgrant agreements, contracts, and subcontracts with all subgrantees, contractors, and subcontractors providing goods or services under this agreement. The incorporation of these provisions in the Grantor’s subgrants, contracts, or subcontracts does not create privity of contract between the Commonwealth and any subgrantee, contractor, or subcontractor, and no third-party beneficiaries are created by those provisions. If the Grantee becomes aware of a subgrantee’s, contractor’s, or subcontractor’s violation of these provisions, the Grantee shall use its best efforts to ensure the subgrantee’s, contractor’s, or subcontractor’s compliance with these provisions.
Contractor Signature:…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .