1-B562-26-08 SWTP Sludge Grit Disposal.docx

DOCX document 509 KB Posted

Attached to
B562-26-08 Susquehanna Water Treatment Plant Sludge & Grit Disposal Service
Solicitation number
US.251507
Issued by
Lancaster County, Pennsylvania

About this file

This is a solicitation document for sludge and grit removal services issued by the City of Lancaster, Pennsylvania for the Susquehanna Water Treatment Plant (SWTP). The City seeks competitive bids to furnish and maintain three 30-cubic-yard containers at the SWTP located at 900 South 15th Street, Columbia, Pennsylvania, and one 30-cubic-yard container at the Low Service Pumping Station located at 10 Union Street, Columbia, Pennsylvania. The work involves regular removal and disposal of water treatment sludge generated from centrifuge dewatering and grit generated from incoming water screening. Bids were originally due September 30, 2026, at 11:00 AM but have been extended to October 14, 2026, at 11:00 AM. A non-mandatory pre-bid conference is scheduled for September 15, 2026, at 9:00 AM at the SWTP, with virtual attendance available via Microsoft Teams. Site visits during normal working hours are required; additional visits by appointment can be arranged by contacting Andres Pabon at 717-368-3941. The contract term is three years, with the City holding the option to extend for up to two additional one-year terms, with pricing adjusted according to the Consumer Price Index. The City will issue a notice of award within 60 days of bid opening (or 120 days if delayed by required governmental approvals or grants).

Pricing is structured as a unit price per ton for each of three material categories: Centrifuge Building Water Sludge (estimated 3,000 tons annually), Sludge Drying Bed Water Sludge (estimated 100 tons annually), and Low Service Pump Station Grit (estimated 50 tons annually). The unit price must be all-inclusive and cover all labor, equipment, utilities, facilities, overhead, profit, and incidental costs. Monthly invoices based on actual tons removed will be submitted with payment due within 30 days. Bid security equal to 10 percent of the maximum bid price must accompany each bid in the form of a bid bond. Successful bidders must provide a performance bond equal to 100 percent of the year-one contract price. Liquidated damages of four hours apply if material is not removed within four hours of the scheduled time; the City may transport and dispose of material itself and charge all additional transportation and disposal costs to the contractor. The successful bidder must comply with all applicable federal and state laws, including the Pennsylvania Public Works Employment Verification Act, and must maintain Workers' Compensation insurance (statutory), Employer's Liability coverage ($100,000 per accident/$500,000 disease limit), Commercial General Liability ($1,000,000 general aggregate), and Commercial Automobile Liability ($1,000,000 combined single limit). The City of Lancaster must be named as an additional insured. All bids must be submitted electronically through PennBid at http://pennbid.bonfirehub.com; hand-delivered, mailed, faxed, or emailed bids will not be accepted. No set-asides are identified in this solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contents

INTRODUCTION AND PROJECT DESCRIPTION2
PROJECT LOCATION2
INVITATION TO BIDDERS3
INSTRUCTIONS TO BIDDERS4
FORMS TO BE SUBMITTED WITH BID16
B1 - BID FORM17
B2 - IDENTIFICATION AND CERTIFICATION OF DISPOSAL SITES23
B3 - BID SECURITY25
B4 - NON-COLLUSION AFFIDAVIT OF PRIME BIDDER27
B5 - SELF-CERTIFICATION OF NO DEBARMENT, SUSPENSION, OR INELIGIBILITY28
B6 - EXPERIENCE QUESTIONNAIRE29
B7 - LIST OF PROPOSED SUCONTRACTORS37
B8 - MINORITY, WOMEN, AND DISADVANTAGED BUSINESS SUBCONTRACTOR’S COMPLIANCE38
B9 – SURETY’S CONSENT – PERFORMANCE BOND39
CONTRACT DOCUMENTS TO BE COMPLETED BY SUCCESSFUL BIDDER UPON AWARD40
A1 - AGREEMENT41
A2 - PERFORMANCE BOND49
A3 - CERTIFICATE OF INSURANCE52
A4 - AFFIDAVIT ACCEPTING PROVISIONS OF THE WORKERS COMPENSATION ACT53
A5 – WORKER PROTECTION AND INVESTMENT CERTIFICATION FORM54
A6 - SUB-CONTRACTING FORM55
A7 - SAM.GOV REGISTRATION DOCUMENTATION56
CONTRACT DOCUMENTS57
C1 –SPECIFICATIONS57
ADDENDUM(S)59
BID SUBMISSION CHECKLIST60
AWARD CHECKLIST61

INTRODUCTION AND PROJECT DESCRIPTION

The City of Lancaster, PA (“City”) is seeking competitive bids for Sludge and Grit Removal Services (“Project”) from the City’s Susquehanna Water Treatment Plant (“SWTP”) located at 900 South 15th Street, Columbia PA and the Low Service Pumping Station located at 10 Union Street, Columbia PA as specified herein. The sludge is generated from the water treatment process and dewatered using a centrifuge. The grit is generated through screening of the incoming water pumped from the Susquehanna River.

In general, the work under this contract consists of furnishing and maintaining three (3), 30 cubic yard containers at the City’s SWTP and one (1) 30 cubic yard container at the City’s Low Service Pumping Station with regular removal and disposal of waste material as specified herein.

The term of the Contract shall be for three (3) years beginning on the date listed in the Notice to Proceed issued by the City. The Contract will include an option of the City toto extend the term for up to two (2) additional one (1) year terms.

PROJECT LOCATION

A - Susquehanna Water Treatment Plant - 900 S 15th Street, Columbia PA, 17512 B - Low Service Pumping Station - 10 Union Street, Columbia PA, 17512

INVITATION TO BIDDERS

As set forth in the advertisement for bids, sealed bids will be received on the Pennsylvania Electronic Document and Bid Management Website known as PennBid at http://pennbid.bonfirehub.com by the City of Lancaster, Pennsylvania (City), 120 North Duke Street, Lancaster City, Lancaster County, Pennsylvania until 9/30/2026, at 11:00 AM, at which time bids will be opened on the website for Susquehanna Water Treatment Plant Sludge and Grit Disposal Service.

The terms of the introduction and project description are incorporated herein.

All bids shall be effective for sixty (60) calendar days from the date of the bid opening, unless an award of the contract is delayed by the required approval of another governmental agency, the sale of bonds or the award of a grant, in which case all bids will remain effective for one hundred twenty (120) calendar days from the date of the bid opening. The successful bidder will be required to provide a performance bond equal to one hundred (100%) percent of the year-one contract price with suitable, reasonable requirements guaranteeing the performance of the contract.

The successful bidder shall be required to comply with all applicable laws protecting individuals from discrimination.

The Project and contract are subject to applicable requirements of federal and state law as specifically set forth in Article 27 of the instructions to Bidders.

All bids shall be submitted exclusively in electronic format to City through PennBid at http://pennbid.bonfirehub.com. Bids provided by any other means will not be accepted. Incomplete bids and those received after the specified date and time will not be considered. Hand delivered, mailed, courier, faxed and/or e-mailed responses will not be accepted.

All bid clarification questions shall be submitted via PennBid as described within the bid documents.

Bids, after having been submitted, may be withdrawn by the Bidder prior to the time set for the opening of bids upon the written direction to City through PennBid at http://pennbid.bonfirehub.com and at such other times as set forth in Article 17 of the Instructions to Bidders. No withdrawal of bids will be allowed within sixty (60) calendar days after said time, even though bids may not yet have been opened.

The City will determine who is the lowest responsible bidder upon the basis of the bids submitted. The lowest responsible bidder need not be the bidder submitting the lowest dollar amount. The City may consider the quality of services supplied, responsiveness of the bidder, past performance of the bidder, compatibility of the bidder’s processes with other City services and the bidder’s ability to handle the volume of work proposed. Further, consideration will be given to such matters as contractor integrity, compliance with public policy, record of past performance, and financial and technical resources as specifically set forth in Article 3 of the Instructions to Bidders.

The City reserves the right to reject the bid of any bidder not possessing satisfactory qualifications.

The City reserves the right to reject any or all bids and re-advertise if the best interest of the City will thereby be promoted. The City also reserves the right to waive technical defects if in its judgment, the interest of the City shall so require. The City further reserves the right to waive any informalities in the bids received and reject any or all bids for any reason whatsoever. Included in its right to reject bids, is the right for the City, in its sole discretion, to reject bids which are deemed by the City to be incomplete, conditional, or obscure, or which contain additions, erasures, alterations, omissions or irregularities of any kind.

The City’s Contract Representative is Christine Volkay-Hilditch, P.E., BCEE, Deputy Director of Public Works – Utilities, 1220 New Danville Pike, Lancaster, PA 17603.

INSTRUCTIONS TO BIDDERS

DEFINED TERMS

Terms used in these Instructions to Bidders have the meanings indicated below:

BID - The sealed bid received on the Pennsylvania Electronic Document and Bid Management Website known as PennBid for Contract #B562-26-08.

BIDDER - any natural person or legally recognized entity which submits a bid.

BIDDING DOCUMENTS- The documents and forms required to be submitted with the Bid.

CITY – The City of Lancaster, Pennsylvania.

CONTRACT DOCUMENTS - All documents included in or supplied pursuant to the Bid Documents.

RESERVED

LOWEST RESPONSIBLE BIDDER or SUCCESSFUL BIDDER - the Bidder to whom the project is awarded.

PROJECT – all work associated with the Bid.

WORK– means the project described the Bid Documents to be performed or provided by the Successful Bidder.

SITE – means the location or locations of the Work.

BID DOCUMENTS

Complete sets of Bid Documents shall be used in preparing Bids; City does not assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bid Documents.

All bids shall be submitted exclusively in electronic format to City through PennBid at http://pennbid.bonfirehub.com. Bids provided by any other means will not be accepted. Incomplete bids and those received after the specified date and time will not be considered. Hand delivered, mailed, courier, faxed and/or emailed responses will not be accepted.

DEBARRMENT FROM BIDDING

Any person or entity (or enterprise) who has been convicted of, or been judged civilly to have committed, any offense indicating a lack of business integrity or honesty, shall be debarred from bidding on any contract which requires bidding and from participating in any City contract and should they bid shall not be deemed a responsible bidder.

The offenses shall include, but not be limited to, the following:

fraud or a criminal offense in connection with obtaining, attempting to obtain or performing a public or private contract or agreement or subcontract, or in the performance of the contract or subcontracts;

bribery, embezzlement, false claims, false statements, falsification or destruction of records, forgery, racketeering, mail fraud, receiving stolen property, obstruction of justice, theft, breach of duty to act disinterestedly, or another offense indicating a lack of business integrity or honesty;

unlawful price fixing between competitors, allocation of customers between competitors, bid rigging or any other violation of federal or state antitrust laws;

violations of a governing hour of labor, minimum wage standards or prevailing wage standards, or child labor law violations;

violation of any law, regulation or agreement related to conflict of interest;

loss or denial of the right to do business or practice a profession under a circumstance indicating a lack of business integrity or honesty;

failure to pay a debt, including any taxes, owed to the City, provided the debt is uncontested by the debtor or, if contested, provided that the debtor’s legal and administrative remedies have been exhausted;

subcontracting or otherwise doing business with a debarred person or enterprise, in connection with a contract with the City, where it is known or where it reasonably should have been known, that the person or entity is debarred;

willful or material failure to perform the terms of a contract or agreement with the City in accordance with its specifications or contractual time requirements;

providing false or misleading information as part of a prequalification statement, including but not limited to financial statements, affidavits of compliance with prevailing wage statutes and product descriptive literature;

debarment or equivalent exclusionary action by any public agency, government or government instrumentality; or other cause affecting responsibility as a City contractor or vendor as may be reasonably determined by the City.

QUALIFICATIONS OF BIDDERS

To demonstrate Bidder’s qualifications to perform the Project, Bidder shall submit with its Bid (a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) the Bidder’s Questionnaire and all documents required by it. In addition, Bidder shall submit with its Bid the following additional information:

Evidence of Bidder's qualification to do business in the Commonwealth of Pennsylvania or covenant to obtain such qualification prior to and as a condition for award of a contract (if Bidder is out of State).

Bidder’s state license number, or other contractor license number, if applicable.

Bidder’s SAM.gov Unique Entity Identification (UEI). For contracts over $25,000, Successful Bidder will also be required to be registered on SAM.gov and maintain a current SAM.gov registration until contract close-out.

Reserved Experience Documentation showing at minimum (using the Experience Questionnaire form included in the Bid Documents where appropriate):

A listing of contracts that the Bidder is performing or has performed during the last five (5) years similar to the service that is called for in this Bid Package, listing project name, location, contract value, and client contact.

At least three (3) customer references, including contact information (Company Name, Contact Name, Title, Email, Address, and Phone Number) for relevant projects and a brief explanation of the of the services provided for each. Government or Municipal references are preferred. Please include the nature and amount of residuals managed for each reference, the method of disposal and/or beneficial reuse, and how long you have been performing the service.

Attendance at pre-bid conference, if required by Article 7 of these Instruction to Bidders.

Any required sub-contractor and supplier qualification information as set forth herein.

A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the contract.

No requirement in this Article 4 to submit information will prejudice the right of City to seek additional pertinent information regarding Bidder’s qualifications.

SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; CITY’S SAFETY PROGRAM; OTHER WORK AT THE SITE Site and Other Areas The Site is more particularly described in the Bid Documents and includes rights-of-way, easements, and other lands furnished by City for the use of the Contractor. Any additional land required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

Existing Site Conditions Subsurface and Physical Conditions; Hazardous Environmental Conditions The Supplemental Conditions, if any, identify:

Those reports known to City of explorations and tests of subsurface conditions at or adjacent to the Site.

Those drawings known to City of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

Reports and drawings known to City relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

Technical Data contained in such reports and drawings.

To the extent the same exist, City will make copies of non-privileged reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Specifications contained therein upon whose accuracy Bidder is entitled to rely, as provided in the Standard General Conditions, has been identified and established in the Supplemental Conditions, if any. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings, if any. Nothing contained herein is intended to relieve Bidders of the responsibility to make their own determinations regarding construction costs, bid strategies, and bid prices, nor of the responsibility to select and be responsible for the means, methods, techniques, sequences, and procedures of construction, and for safety precautions and programs incident thereto.

Underground Facilities: Information and data shown or indicated in the Bid Documents, if any, with respect to existing Underground Facilities at or adjacent to the Site are set forth in the Contract Documents and are based upon information and data furnished to City by owners of such Underground Facilities, including City, or others.

Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bid Documents due to differing or unanticipated subsurface or physical conditions are set forth in Contract Documents. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications, if any, or identified in the Contract Documents to be within the Scope of the Work are set forth in the Contract Documents and in the Bid Form.

Site Visit and Testing by Bidders It is required that the Bidder conduct a pre-bid Site visit during normal working hours. The Site will be available on the day of the pre-bid conference. Access at other times by appointment by calling Andres Pabon at 717-368-3941.

Bidder is not required to conduct any subsurface testing or exhaustive investigations of Site Conditions.

Upon request, and to the extent City has control over the Site, and schedule permitting, the City will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies. City will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on City’s authority regarding the Site, however, the Site will be accessible at the scheduled pre-bid meeting (see Article 7).

Bidder shall comply with all applicable laws and regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by City or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

Bidder shall not disturb any ongoing operations at the Site.

Bidder shall fill all holes, clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests and studies.

City shall have the right to exclude any person from entering or remaining upon the Site which City in its sole discretion deems appropriate.

City’s Safety Program and/or Regulations Site visits and work at the Site may be governed by a City safety program and/or City regulations. If a City safety program exists, it will be noted in the Supplemental Conditions, if any.

Other Work at Site Reference is made to the Standard General Conditions, the Supplemental Conditions, if any, and the Specifications for the identification of the general nature of other work of which City is aware (if any) that is to be performed at the Site by City or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bid Documents. If City is party to a written contract for such other work, then on request, City will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

BIDDER’S REPRESENTATIONS

It is the responsibility of each Bidder before submitting a Bid to:

Examine and carefully study the Bid Documents, and any data and reference items identified in the Bid Documents (including the Scope of Work and all Appendices, if any).

Visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and/or become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

Become familiar with and satisfy itself as to all laws and regulations, including applicable City Ordinances and regulations that may affect cost, progress and performance of the Work.

Carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site, including all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplemental Conditions, if any, especially with respect to Technical Data in such reports and drawings, if any, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplemental Conditions, if any, especially with respect to Technical Data in such reports and drawings, if any.

Consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bid Documents; and the Site-related reports and drawings identified in the Bid Documents, if any, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs.

Assert all requests for examinations, investigations, explorations, tests, studies, or data are necessary for the preparation of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bid Documents. Notwithstanding the same, by submitting a Bid, Bidder does waive all objections and reservations that it was not provided the responses desired to overcome or resolve such objections and reservations.

Become aware of the general nature of the work to be performed by City and other municipalities as it relates to the Work indicated in the Bid Documents (including the Scope of Services and all Appendices, if any).

Promptly give City written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bid Documents (including the Specifications, plans, scope of work and all Appendices, if any) and confirm that the written resolution thereof by the City is acceptable to Bidder.

Determine that the Bid Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work.

Agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices and/or considerations in the Bid are premised upon performing and furnishing the Services required by the Bid Documents (including the Specifications, plans, scope of work and all Appendices, if any), and that Bidder has no claim for compensation, reimbursement for fee and costs, and/or any other benefit for having devoted time and materials in evaluating or submitting a Bid.

Assure that sufficiently qualified staff is available to do the work.

PRE-BID CONFERENCE

There will be a non-mandatory pre-bid conference held on Tuesday, September 15, 2026, at 9:00 AM at the Susquehanna Water Treatment Plant located at 900 S 15th St, Columbia, Pennsylvania 17512, then proceed to the Low Service Pumping Station at 10 Union Street, Columbia PA, 17512. Those that cannot attend in person, may virtually attend on Teams using the following log-in information:

Meeting ID: 256 046 497 795 140 Passcode: Co9VM7v5 City will transmit to all prospective Bidders of record such Addenda as City considers necessary in response to questions arising at the conference.

Oral statements may not be relied upon and will not be binding or legally effective.

INTERPRETATIONS AND ADDENDA

All questions about the meaning or intent of the Bid Documents are to be submitted through the “Public Q&A” feature on the PennBid website to City’s contract representative identified in the Invitation to Bidders in writing. Such questions shall be addressed prior to Bid opening or formal Addenda and shall be made available to all Bidders on the PennBid website for the Project. It is the responsibility of each potential Bidder to be continuously aware of any interpretations rendered by memoranda and/or Addenda made available on the PennBid website for the Project without notice from City. Questions received less than seven days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

Addenda may be issued to clarify, correct, supplement, or change the Bid Documents.

BID SECURITY

A bid must be accompanied by Bid security in an amount of 10% percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) in the form of a Bid bond (on the form included in the Bid Documents) meeting the surety requirements set forth herein. Electronic reproductions of the bid security shall be uploaded by Bidder to the PennBid as part of, and concurrent with the Bid. Within seventy-two (72) hours of bid opening, the original bid security shall be delivered to the City.

The Bid Security of the apparent Successful Bidder will be retained until City awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the notice of award, whereupon the Bid security will be released. Unless altered by the notice of award or by written consent of City, in the event the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required Bid security within 15 days after the notice of award, City may consider Bidder to be in default, annul the notice of award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be City’s exclusive remedy if Bidder defaults.

The Bid security of other Bidders that City believes to have a reasonable chance of receiving the award may be retained by City until the earlier of seven days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

Bid security of other Bidders that City believes, in its sound discretion, do not have a reasonable chance of receiving the award may be released within seven days after the Bid opening.

CONTRACT TIMES

The contract time shall commence ten days following issuance of the Notice to Proceed. The Contract shall be for the term of three (3) years.

The City may, by written notice to the Successful Bidder at least ninety (90) days prior to the expiration of the Contract, extend the terms of the Contract. Extension of the Contract shall be by mutual agreement between the City and successful Bidder. The City reserves the right to include two (2) one-year options to extend the Contract. If the City exercises the option to extend the contract (in one-year increments) the cost will be adjusted according to the Consumer Price Index (CPI). The CPI will be calculated using the CPI Inflation Calculator located on the U. S. Bureau of Labor Statistics website. The extension shall be under the same terms and conditions hereof.

LIQUIDATED DAMAGES

Continuous operation of the Susquehanna Water Treatment Plant requires that sludge and grit be removed from location listed within four (4) hours of the time scheduled by the city. If the Contractor does not remove the material within four (4) hours of the scheduled time, the City reserves the right to either; transport the material to the Contractor’s landfill, or transport and dispose of the material at another waste disposal facility using City vehicles or another company’s vehicles. The Contractor shall be responsible for paying all additional transportation and disposal charges, above the contract cost, as liquidated damages.

SUBSTITUTE AND “OR-EQUAL” ITEMS

All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the service and equipment specified or described in the Bid Documents, as supplemented by Addenda.

Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

SUBCONTRACTORS, SUPPLIERS, AND OTHERS

A Bidder shall be prepared to retain specific subcontractors, suppliers, or other individuals or entities identified by the City for the performance of the Work if required by the Successful Bidder to do so. If a prospective Bidder objects to retaining any such subcontractor, supplier, or other individual or entity identified by the City, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

Subsequent to the submittal of the Bid, City may waive its requirements for the Successful Bidder or Contractor to retain any subcontractor, supplier, or other individual or entity against which Contractor has a reasonable objection.

Each Bidder shall submit, with its bid, a list of proposed subcontractors meeting the requirements set forth in the Bid Documents. If required, they shall be submitted on the forms submitted therein.

Each subcontractor will be required to provide a confirmation of compliance with Act 127 of 2012 [footnoteRef:2], by submitting to the Successful Bidder, a Public Works Employment Verification Form as a pre-condition to being awarded a subcontract for this Work. [2: The Pennsylvania Public Works Employment Verification Act of July 5, 2012. P.L. 1086, No. 127, 43 P.S. 167-1 et seq. requires, as a precondition to the award of a contract for public work, a public works contractor to submit a completed E-Verify Program (EVP) Form to the public body that is bidding and awarding the public work contract. In relevant part, the form obligates public works contractors and every subcontractor performing work under a public works contract to utilize the United States Department of Homeland Security FVP system to verify the employment eligibility of each new employee hired after January 1, 2013. Afterwards, if a new employee hired by a public works contractor, regardless of whether he will be working onsite or offsite of a public work or otherwise, such employment eligibility shall be verified within 5 business days of his/her start date. Subcontracts between a public works contractor and its subcontractors are required to contain notification of the applicability of the act, information regarding the use of EVP and reference to the web site of the PA Department of General Services at www.dgs.state.pa.us to obtain a copy of the form.]

Each subcontractor will be required to provide a SAM.gov Unique Entity ID (UEI) by submitting it to the Successful Bidder.

Reserved If the apparent Successful Bidder declines to make any such substitution, City may award the Contract to the next lowest responsible Bidder that proposes to use acceptable subcontractors, suppliers, or other individuals or entities. Any subcontractor, supplier, individual, or entity so listed and against which City makes no written objection prior to the giving of the notice of award will be deemed acceptable to City and/or Engineer subject to subsequent revocation of such acceptance.

PREPARATION OF BID

A Bid Form is included with the Bidding Documents and is available via PennBid’s “Bid” tab.

All blanks on the Bid Form shall be completed and the Bid Form signed (Electronic signatures are acceptable).

A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation shall be shown. The corporate seal shall be affixed and attested by the corporate secretary or an assistant corporate secretary.

A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The partnership’s address for receiving notices shall be shown.

A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the firm’s address for receiving notices shall be shown.

A Bid by an individual shall show the Bidder’s name and address for receiving notices.

A Bid by a joint venture shall be executed by an authorized representative of each joint venture in the manner indicated on the Bid Form. The joint venture’s address for receiving notices shall be shown.

All names shall be printed below the signatures.

The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

Postal and e-mail address(es) and telephone number(s) for communications regarding the Bid shall be shown.

The Bid shall contain the information required by Article 4.

BASIS OF BID

Bidders shall use and complete the Bid Form included with the Bid Documents, including the Pricing Form for the Work (if one is provided) at the PennBid website, which form is incorporated herein by reference as though fully set forth at length.

A Bid price shall be indicated for each bid item listed therein.

The unit fee (fixed cost per ton) shall include all costs arising out of or related to the performance of the Contract and no additional compensation shall be expected by or paid to the successful Bidder.

Discrepancies between the multiplication of units of work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words.

SUBMITTAL OF BID

A Bid shall be received no later than the date and time prescribed and, in the manner, and at the place indicated in the Invitation to Bidders.

A Bid shall be deemed complete if it contains the following fully completed documents:

Bid Form Identification and Certification of Disposal Sites Required Bid Security (10% of Bid) in the form of a Bid Bond.

Non-Collusion Affidavit of Prime Bidder Self-Certification of No Debarment, Suspension, or Ineligibility (one for each agency and sub-agency) Experience Questionnaire and all documents in support thereof as set forth in Article 4 above.

List of Proposed Subcontractors (if none, write “none” on the form and submit with bid) Minority, Women, and Disadvantaged Business Subcontractor’s Compliance Form (if none, write “none” on the form and submit with bid) Surety Consent for Performance Bond Evidence of Bidder's qualification to do business in the Commonwealth of Pennsylvania or covenant to obtain such qualification prior to and as a condition for award of a Contract (if Bidder is out of State).

All other documents required to be submitted as set forth above.

Bids received after the date and time prescribed for the opening of bids or not submitted at the correct location or in the designated manner, will not be accepted.

By submitting a Bid, the Bidder acknowledges that they have:

Read and will comply with all of the Contract Documents found within the Bid Documents, including these Instructions to Bidders.

Thoroughly read and understood all of the Contract Documents found within the Bid Documents, including these Instructions to Bidders, so as to become familiar with all conditions that may affect cost, performance, and ability to provide the Work required.

Considered all Federal, state, and local laws and regulations that may affect cost, performance, and ability to provide the Work required, including but not limited to those set forth in the Federal Uniform Guidance for Procurement.

Found no errors, ambiguities, conflicts, or other matter in the Bid Documents and the remaining Contract Documents found within the Bid Documents, including these Instructions to Bidders, and other data and forms, and site conditions that may affect cost, performance, and ability to provide the Work required.

Acknowledges and understands that its Bid may be rejected for failure to submit the bid and other Bid Documents on the forms and/or in the manner included in the Bid Documents, failure to complete and/or sign any required documentation, failure to furnish the required bid security, failure to include a unit/lump sum price for each item on the Bid Form, including alternates, inclusion by Bidder of conditions or qualifications not provided for in the Bid Requirements and Bid Documents, submission of an incomplete Bid Form or other required documents, should the Bid Form contain any omissions, erasures, alterations, additions not called for, or irregularities of any kind, should any Bid prices be unbalanced, failure to attend the mandatory pre-bid conference (if required), or visit the Site (if required), debarment by a Commonwealth agency, political subdivision or federal agency, being declared in default on other prior projects, and generally not meeting the conditions for responsible low bidder set forth in the Bid Documents.

Acknowledges and understands that its Bid may be rejected should any conditions listed in Article 3 apply

MODIFICATION AND WITHDRAWAL OF BID

A Bid may be withdrawn from consideration on the PennBid website by the Bidder at any time prior to bid opening.

If a Bidder wishes to modify its Bid prior to Bid opening, Bidder may do so on the PennBid website prior to the time designated for opening Bids.

If within 24 hours after Bids are opened any Bidder files a duly signed written notice with City and promptly thereafter demonstrates to the reasonable satisfaction of City that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid.

OPENING OF BIDS

Bids will be opened at the PennBid website electronically by City at the time indicated in the Invitation to Bidders. Following the opening of bids, an abstract of the amounts of the base Bids and major alternates (if any) will be made publicly available on the PennBid website.

BIDS REMAIN SUBJECT TO ACCEPTANCE

Except as hereinafter provided, all Bids will remain subject to acceptance for a period of ninety (60) days after the date specified for the opening of bids or the issuance of a notice of award, whichever occurs first, unless stated otherwise on the Bid Form. In the event an award of the contract is delayed by the required approval of another government agency, the sale of bonds or the award of a grant, in which case all bids shall remain subject to acceptance for a period of one hundred twenty (120) calendar days from the date of the bid opening. City may, in its sole discretion, release any Bid prior to the issuance of a notice of award or the expiration of the applicable ninety (90) or one hundred twenty (120) day period.

EVALUATION OF BIDS AND AWARD OF CONTRACT

The City will determine who is the lowest responsible bidder upon the basis of the Bid Documents submitted. City reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. City will reject the Bid of any Bidder that City finds, after reasonable inquiry and evaluation, to not be responsible or not possessing satisfactory qualifications. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bid Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the City may reject the Bid as nonresponsive; provided that City also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.

If quantities are specified by City, both City and Bidder agree that the quantities specified are approximate only and are City’s estimates for the purposes of having uniform basis for comparison of bids or proposals submitted in response to City’s Invitation to Bidders. City shall have the right, in City’s sole discretion, to increase or decrease the quantities specified at the unit prices specified in the Bid.

Evaluation of Bids In evaluating Bids, City will consider whether or not Bids comply with the prescribed requirements, and such alternatives, unit prices, and other data, as may be requested in the Bid Form or prior notice of award.

The Lowest Responsible Bidder need not be the bidder submitting the lowest dollar amount.

The City may consider the quality of services supplied, responsiveness of the Bidder, past performance of the Bidder, compatibility of the Bidder’s processes with other City services and the Bidder’s ability to handle the volume of Work proposed.

The City may consider such matters as contractor integrity, compliance with public policy, record of past performance, and financial and technical resources.

City may consider the qualifications and experience of other persons and organizations proposed for those portions of the Project as to which the identity of other persons and organizations must be submitted as provided in the Bidding Documents. City also may consider the operating costs, maintenance requirements, performance data, and guarantee of major items of materials and equipment proposed for incorporation in the Project when such data is required to be submitted prior to the notice of award.

City may conduct such investigations as City deems necessary to assist in the evaluation of Bid and to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers and other persons and organizations to perform and furnish the Project in accordance with the Contract Documents to City‘s satisfaction within the prescribed time.

If a contract is to be awarded, City will give the Successful Bidder a notice of award within sixty (60) days after the date specified for the opening of bids. In the event an award of the contract is delayed by the required approval of another government agency, the sale of bonds or the award of a grant, in which case City will give the Successful Bidder a notice of award within one hundred twenty (120) calendar days from the date of the Bid opening. Such “notice of award” shall describe the nature, scope and facial amount stated in dollars of the Project awarded to Bidder and direct the Bidder submit the following truthful and accurate documents in the manner stated within a specified period of time:

Bidder-executed Agreement Performance Bond Certificate of Insurance with the prescribed minimum amounts set forth in Article 21 below and naming “City of Lancaster, PA” as additionally insured.

Affidavit Accepting Provisions of the Workers Compensation Act1 for Successful Bidder and all Subcontractors.

Worker Protection and Investment Certification Form Sub-Contracting Form for each Subcontractor, if any Sam.gov registration documentation, if contract is over $25,000.

All other documents required under and pursuant to the contract documents.

The City fully intends to perform the Work for which Bids are solicited.

INSURANCE

Successful Bidder will be required to provide insurance of the prescribed types and minimum amounts as set forth below.

All Insurance policies required shall be maintained in full force until all work under this Contract is completed, as evidenced by the formal acceptance thereof, in writing by the City. Each policy shall contain the provision that there will be 30 days prior written notice given to the City in the event of cancellation of or material change in the policy.

The insurance companies indicated in the certificates shall be authorized to do business in the Commonwealth of Pennsylvania and shall be acceptable to the City.

Neither approval by the City, nor a failure to disapprove insurance certificates by the Contractor shall release the Contractor of full responsibility for all liability as set forth in the indemnification clauses stated in the Contract Agreement.

The MINIMUM requirements of insurance to be carried by the Contractor shall be as follows:

Worker’s Compensation – Statutory

Employer’s Liability$100,000Each Accident
$500,000Disease – Policy Limit
$100,000Disease - Policy Limit Each Employee
Commercial General Liability$1,000,000
General Aggregate$1,000,000
Products and Completed Operations Aggregate$1,000,000
Personal and Advertising Aggregate$1,000,000
Each Occurrence$1,000,000
Fire Damage (Any One Time)$ 50,000
Medical payments$ 5,000

Other Conditions:

City of Lancaster, 120 North Duke Street, Lancaster, PA 17602, is to be named as an additional insured as its interests may appear, to the extent that Contractor is liable hereunder as set forth in the indemnification clauses stated in Contract Agreement.

Commercial Automobile Liability (“Commercial” defined to include any automobile used by Contractor, its agents, and employees, in the performance of the Contract) Combined Single Limit $1,000,000

OR

Bodily Injury – Per Person$1,000,000
Bodily Injury - Per Accident$1,000,000
Property Damage$1,000,000

Bidders are directed to review Article 6 of the General Conditions and Supplemental Conditions, if any, for information regarding insurance requirements of the Contractor.

Non-Appropriation.

The Parties agree that the awarding and/or continuation of this Agreement is dependent upon the lawful availability of funding. The City shall provide the Contractor written notice for any fiscal year of the failure of City Council to make an adequate appropriation or of the state or federal government’s failure to provide the required funding or reduction in the necessary grant funds necessary to permit the City to pay the amounts due under this Agreement. Upon notice that sufficient funds were not appropriated by City Council of the City of Lancaster, the state or the federal government sufficient to permit the City to pay for the continued performance of this Agreement, either Party may terminate the agreement without penalty

SIGNING OF AGREEMENT

When City issues a notice of award to a Successful Bidder it shall be accompanied by an unexecuted copy of the Agreement and all other applicable documents as per 20.04 of these Instructions to Bidders and the Agreement. Within 10 days thereafter, or as otherwise specified by City in the notice of award, the Successful Bidder shall execute and deliver the documents required.

RESERVED

SALES AND USE TAX

To the maximum extent permitted by Pennsylvania law, City is exempt from state sales and use taxes on materials and equipment to be incorporated in the Project. Said taxes shall not be included in the Bid to the extent of the exemption permitted by Pennsylvania law. Bidder is solely responsible for determining the applicability of such exemption to such materials and services to be provided when setting forth the prices or totals comprising its Bid. Bidder is not permitted to rely on any formal or informal or official or unofficial representation(s) by City or its representatives concerning the scope of materials and equipment which may or may not be exempt from sales or use taxes. No price adjustments or allowances will be made for Bidder’s pricing or overall Bid in the event Bidder failed to include, or properly calculate, sales or use taxes applicable to materials or equipment for which the exemption does not apply.

ASSIGNMENTS

Absent the written consent of City, the assignment of any Bid by any Bidder or any contract by a Successful Bidder is strictly prohibited and shall be grounds for declaring a breach of such Bidder’s obligations hereunder and/or the Agreement to perform the services required. In such an event, the City shall have recourse against bid security or Bidder’s performance and Payment bonds and/or such other remedies as may be allowed by the Bid Documents.

LAWS AND REGULATIONS

The Bidding Documents set forth responsibility or compliance with all applicable federal, state and local laws.

Bidders are required to comply with any law identified in the Technical Specifications and Bidding Documents, if any.

Bidders are directed to review the required compliance with the Public Works Employment Verification Act included in the Bid Documents.

Bidders shall be required to comply with all applicable laws protecting individuals from discrimination.

Bidders are required to comply with the Federal Occupational Safety and Health Act of 1970 (OSHA).

Bidders are required to comply with Pennsylvania Act 287, as amended by Act 181 of 2006 (also known as One Call or 811 Call before you dig!)

Bidders shall also refer to all local, Federal and State Statutes, Rules, and Regulations dealing with the prevention of environmental pollution and the preservation of public and natural resources pursuant to Pa. Act 1972-247.

END OF INSTRUCTIONS TO BIDDERS

FORMS TO BE SUBMITTED WITH BID

B1 - BID FORM

BIDDER (Name and Address):

UNIQUE ENTITY ID:

EXPIRATION DATE:

(available through SAM.gov)

PROJECT IDENTIFICATION
Susquehanna Water Treatment Plant Sludge and Grit Disposal Service

#B562-26-08

CONTRACT IDENTIFICATION:
GENERAL SERVICES
THIS BID IS SUBMITTED TO:
CITY OF LANCASTER

120 North Duke Street Lancaster, PA 17602

1.The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with City in the form included in the Bidding Documents to perform and furnish all Work as specified or indicated in the Bidding Documents for the Contract Price and within the Contract Time(s) and in accordance with the other terms and conditions of the Bidding Documents.
2.Bidder accepts all of the terms and conditions of the Invitation to Bidders and Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for a period of 60 days from the date of Bid opening unless award is delayed by a required approval from a governmental agency, the sale of bonds, or the award of a grant or grants, in which event the Bids shall remain open for a period of 120 days from the date of Bid opening. Thirty-day extensions of the date for the award may be made by the mutual written consent of the City and the apparent Successful Bidder. Bidder agrees, if required by City prior to and as a condition of Contract award, to execute and sign any documents related to financing of the Work. Bidder will sign and submit the Agreement with the Bonds and other documents required by the Bidding Documents within 10 days after the date of City's Notice of Intent to Award.
3.In submitting this Bid, Bidder represents, as more fully set forth in the Agreement, that:
3.1Bidder has examined copies of all the Bidding Documents and of the following Addenda, if any (receipt of all which is hereby acknowledged):
Date

Number

3.2Bidder has visited the site and/or become familiar with and is satisfied as to the general, local, and site conditions that may affect cost, equipment, performance, and furnishing of the Work.
Date of visitation to the Site:
3.3Bidder is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, equipment, performance, and furnishing of the Work.