1-Attachment B - Reconstruction Scope of Work.pdf

PDF 794 KB Posted

Attached to
Qualifications for a Contractor Pool for Residential Home Elevations and or Reconstruction for FEMA Harvey Disaster Funding Recipients
Solicitation number
25-59
Issued by
Brazoria County, Texas

About this file

This document is a Reconstruction Scope of Work from Brazoria County, Texas, utilizing FEMA Harvey Disaster Funding for residential reconstruction projects. The scope covers comprehensive home reconstruction services for flood-damaged properties that are deemed structurally unsound and incapable of elevation. Contractors will be responsible for complete demolition, debris removal, and reconstruction of elevated residential structures, with projects requiring compliance with local, state, and federal regulations including NFIP standards, floodplain requirements, and Texas Windstorm Insurance Association guidelines. The reconstruction process mandates building homes at least two feet above the Base Flood Elevation, with a total project completion timeline of 180 days from the Notice to Proceed.

Contractors must meet specific minimum qualifications, including three years of federally funded construction experience, ability to provide TWIA-certified engineering designs, and financial capability to manage multiple concurrent reconstructions. The compensation structure is milestone-based, with four payment draws ranging from 10% to 40% of the total contract amount, tied to specific construction phases and inspections. Each reconstruction project will require a separate written agreement with the homeowner, and contractors must provide a 10/2/1 third-party warranty covering structural foundation, mechanical systems, and workmanship. Funding for these reconstruction projects comes from FEMA Harvey Disaster Funding, with strict guidelines on eligible and ineligible work, and prohibitions on offering financial incentives to homeowners.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT B

RECONSTRUCTION SCOPE OF WORK

The scope of services within each individual project will vary, as the circumstances in each home to be reconstructed will be different. However, successful contractor services will include, but are not limited to, the following:

Contractors awarded for reconstruction services will need to comply with Brazoria County order applying Subchapter F, Chapter 233 of the Texas Local Government Code. The requirement can be found on the Brazoria County Floodplain website: https://www.brazoriacountytx.gov/departments/floodplain

1.1 Provide professional labor, equipment, and materials adequate to perform the work in accordance with the scope of work for each eligible applicant's residential structure while ensuring that all applicable housing standards and codes are met;

1.2 If the homeowner selects your company, you will meet with the individual property owner to review the scope of work to be performed, including establishing a work schedule acceptable to property owners and Brazoria County; Prepare plans and specifications and perform construction in compliance with applicable City and or County floodplain elevation requirements, code requirements, and the Texas Windstorm Insurance Association (TWIA) requirements;

1.4 Obtain all necessary state and local permits and approvals after permits are acquired. Prior to the commencement of the work for each home, copies of all permits not issued by the County shall be provided to the County;

1.5 Performing investigations for the presence of lead and/or asbestos containing materials and lead and asbestos abatement in compliance with applicable local, State, and Federal requirements;

1.6 Coordination with property owner; utility disconnection and deactivation; and, when applicable in reconstruction, demolition of existing structure;

1.7 Debris removal in accordance with all Federal, State, and local requirements, including the proper disposal and handling of potential asbestos containing materials;

1.8 Site preparation; and for reconstruction, the construction of new residential home in accordance with all applicable local and state codes and standards;

1.9 Compliance with applicable Americans with Disabilities Act requirements may be required if deemed necessary by the homeowner and Project Manager.

1.10 Pre-construction, construction, and post-construction photographs taken and provided to the County documenting services performed and compliance with permitting and building requirements;

1.11 If the successful contractor uses subcontractors, then prompt payment of all subcontractors for services rendered, and obtaining signed and notarized lien waivers from all subcontractors documenting proof of payment and providing copy of such lien waivers to the County with draw requests; and

1.12 Maintaining job sites in a neat and orderly manner.

1.13 Provide County all required residential inspection reports pursuant to Texas Local Government Code Chapter 233 Subchapter F

In accordance with FEMA guidance, mitigation reconstruction is the construction of an improved, elevated building on the same site where an existing building and/or foundation has been partially or completely demolished or destroyed.

The homes designated for mitigation reconstructions have been determined in the grant process to be eligible for mitigation reconstruction and thus mitigation reconstruction includes demolition and reconstruction. FEMA requires all mitigation reconstruction projects to be designed in accordance with American Society of Civil Engineers

(ASCE) 24-14.

Attachment B Reconstruction Scope of Work Page 1 of 4 https://www.brazoriacountytx.gov/departments/floodplain

All damages caused by the contractor during the mitigation reconstruction project shall be paid for by the contractor;

these damages are ineligible grant costs and the FEMA Grant Program does not cover such costs -these are the responsibility of the contractor.

Ineligible work shall not be allowed, with the sole exception of ineligible work necessarily incidental to the reconstruction project. Examples of ineligible work include, but are not limited to, building additions or auxiliary structures, additional landscaping for ornamentation beyond what existed at the site prior to the construction of the project, construction of new decks or porches, construction of expanded decks or porches, improvements for aesthetic reasons, or interior remodels. This list of examples is not exhaustive.

For contracted services from Brazoria County using FEMA Harvey Disaster Funding, a Contractor shall not hire a firm to perform engineering services on the same home if that firm also was contracted by the County to provide Structural Integrity and Inspection Services.

The awarded contractor or contractors will be required to sign an affidavit stating they will comply with the above statement.

Each home shall be subject to a separate written agreement that will be between the contractor and the respective Homeowner. Each Agreement will specify a term applicable to that FEMA project and specify draw requirements and other requirements associated with that given FEMA project.

Offering financial incentives of any kind such as: trips, meals, entertainment tickets, cash etc.is strictly prohibited

2.0 BACKGROUND INFORMATION

A residential reconstruction is when a house that is vulnerable to flooding and has been severely damaged – to where a structural engineer determines that the structure is not capable of being elevated – is reconstructed instead.

The reconstruction process includes demolishing the existing damaged dwelling, clearing the associated debris, and building an elevated house either on the same footprint or at another location on the same lot.

The construction is performed according to all applicable codes and standards, to include being elevated at least two

(2) feet above the Base Flood Elevation (BFE), as required by local code whichever is most stringent. The benefits of reconstructing a structure are to minimize the threat for future flood losses to property and personal belongings.

Many houses that are reconstructed are located in the Flood Insurance Rate Map’s designated Special Flood Hazard

Area (SFHA). However, homes located outside of the SFHA still flood and may need to be reconstructed as well.

`2.1 Type of Reconstruction

2.1.1 Houses reconstructed using piles, posts or piers

2.1.1.1 Reconstruction in a V zones (Velocity Zones in Coastal High Hazard Areas) are not permitted

2.1.2 Houses reconstructed with a closed foundation and placed on fill

2.1.3 Houses reconstructed on a closed foundation that meets the NFIP codes and standards.

`2.2 Reconstruction Requirements

2.2.1 Foundations must be designed to properly address all loads and be appropriately connected to the first floor structure above and utilities must also be properly elevated.

2.2.2 Reconstructions must comply with NFIP standards and building codes that exist in the State and County.

2.2.3 A building permit is required in order to reconstruct.

2.3 Structural Soundness

2.3.1 In order to participate in a reconstruction project, all structures must be deemed to NOT BE structurally sound and NOT CAPABLE of being elevated. Prior to participating in a FEMA Grant Program to reconstruct houses, homeowners will have a Structural Integrity Inspection by a licensed structural engineer that determines whether the house meets the requirements for being reconstructed.

Attachment B Reconstruction Scope of Work Page 2 of 4

`3.0 SPECIFICATION MILESTONES & COMPENSATION DRAWS

3.1 Inspections

The following milestone schedule will be followed for each house and engineers will inspect at the following construction phase milestones:

Milestone 1: 20% of the total contract amount in that FEMA project

3.1.1 Signed contract with performance & payment bonds, insurance

3.1.2 A&E drawings and plans, receipt of Notice to Proceed, mobilization of equipment to the construction site.

3.1.3 Acquisition of building permits

Milestone 2:40% of the total contract amount in that FEMA project

3.1.4 Complete demolition of building and removal of debris

3.1.5 Debris removal

3.1.6 INSPECTION

Milestone 3:30% of the total contract amount in that FEMA project

3.1.7 Build elevated structure, two (2) feet or more above the Base Flood Plain

3.1.8 INSPECTION

3.1.8.1 Provide all residential construction inspection reports as required by Texas Local Government Code Chapter 233 Subchapter F and County residential inspection requirements.

FINAL INSPECTION

Milestone 4: 10% of the total contract amount in that FEMA project

3.1.9 Completion of all work

3.1.10 All utilities are connected

3.1.11 Final site clean-up & removal of equipment

3.1.12 Homeowner concurrence with payment, signed and notarized lien waivers from subcontractors utilized (if any), interior & exterior photographs submitted, all grant requirements met

3.1.13 Certificate of Construction Completion

3.1.14 Final elevation certificate

3.1.15 Acquisition of Certificate of Occupancy & structure meets or exceeds the required height (BFE+2)

FINAL INSPECTION

3.2 Certificate of Occupancy

All permits have been successfully closed out and grant paperwork has been provided as necessary.

Communicate with the County to go ahead and issue a Certificate of Occupancy to the homeowner. A Certificate of Occupancy will not be issued until after the final inspection.

4.0 COMPLETION TIMELINE

Upon the contractor’s receipt of the Notice to Proceed, the contractor has one hundred and eighty days (180) to finalize the reconstruction.

Attachment B Reconstruction Scope of Work Page 3 of 4

5.0 MINIMUM QUALIFICATIONS

Respondents must meet or exceed the minimum qualifications listed herein.

5.1 Minimum of three (3) years of federally funded construction project experience.

5.2 Minimum of three (3) years company and company ownership / key staff experience in providing complete Home reconstruction services, or the principals must have had three (3) years ownership / management experience in a previous company that provided complete reconstruction services.

5.3 Contractor must demonstrate experience in providing complete home reconstruction services in the service listed in the Scope of Work/Specifications.

5.4 Contractor must be able to provide designs and specifications from a TWIA certified engineer who is a

Professional Engineer (P.E.) licensed by and in good standing with the State of Texas.

5.5 Contractor must provide a history of complete reconstruction services that they have completed for at least the last three (3) years or more.

5.6 Contractor shall be required to provide each homeowner for whom they complete a home reconstruction, a written minimum 10/2/1 warranty from a third-party warranty provider. The warranty will be a minimum ten

(10) years on the structural foundation system, a minimum 2 years on the mechanical, plumbing and new utility connections and equipment and a minimum one (1) year on workmanship. Contractors are to include the warranties they will provide.

5.7 Contractors must be authorized to conduct business in the State of Texas.

5.8 Contractors will or may be required to sustain multiple concurrent home reconstructions. Accordingly, contractors must demonstrate its financial fortitude by providing annual financial reports for at least its last two (2) fiscal years or income statements from such years.

5.9 Project completion bonding for the value of the project plus 10%.

Attachment B Reconstruction Scope of Work Page 4 of 4

File details come from the government source that posted it. Updated .