This is an Airport Capital Improvement Plan (ACIP) document for two airports operated by the Ventura County Department of Airports: Camarillo Airport (CMA) and Oxnard Airport (OXR). The document outlines capital improvement projects scheduled from Federal Fiscal Year 2026 through 2036. At Camarillo Airport, the primary near-term project is the Rehabilitation of Runway 8-26, budgeted at $37,977,298 total cost with construction anticipated to commence in 2027 following design completion in fiscal year 2026. Additional planned projects include design and reconstruction of taxiway connectors, PCC rehabilitation of taxiways and aprons, and various pavement rehabilitation initiatives. At Oxnard Airport, the FY 2026 project involves rehabilitation of the Air Traffic Control Tower (ATCT) at $2,700,000, with construction commencing in February 2027 following grant execution in November 2026. Subsequent projects include design and reconstruction of central apron and transient apron areas, terminal apron reconstruction, perimeter road rehabilitation, and west hangar apron area rehabilitation. The ACIP serves as the planning document for the referenced on-call engineering, design, and architectural consulting services solicitation posted May 13, 2026, with qualifications due June 18, 2026.

Camarillo Airport's total planned improvement investment across all fiscal years 2026–2036 is $79,734,380, funded through Federal shares of $73,659,805, State shares of $727,114, and Local shares of $5,347,462. Oxnard Airport's total planned investment is $14,220,425, with Federal shares of $12,798,382, State shares of $613,669, and Local shares of $808,374. Federal funding sources include FAA Airport Improvement Program (AIP) entitlements and Infrastructure Investment and Jobs Act (IIJA) grants; Camarillo received companion grants of $14.4 million and IIJA funding totaling $1,362,000 for FY 2026–2027, while Oxnard received IIJA funding of $285,000 for FY 2026. Land title for both airports is held by the County of Ventura. Environmental clearances through Categorical Exclusions (CatEx) have been obtained or are anticipated prior to design completion for most projects. The document identifies Keith Freitas, Director of Airports, and Danielle Tarr, Projects Administrator, as authorized contacts at (805) 388-4205.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3. NPIAS No.

06-0339

5. Project Description On ALP? Environmental NPR Code NPR PCI** PCR** Federal State Local Total $ (by funding year in priority order) Y/N Type (APCT) Rating Funds Funds Funds Description Amount Description Amount

Federal Fiscal Year 2026 Available 150,000$ Available 1,362,000$

1. Rehabilitation of Runway 8-26 (CMA FAA IIJA Funding from 2025 & 2026)*** Y CatEx A,RC,RW,IM 83 51-76 340/F/C/X/T 36,078,433$ 150,000$ 1,748,865$ 37,977,298$ Used -$ Used 1,362,000$

TOTAL 36,078,433$ 150,000$ 1,748,865$ 37,977,298$ Remaining 150,000$ Remaining -$

Federal Fiscal Year 2027 Available 300,000$

1. Design for Taxiway Connectors Reconstruction (Include. RIM Correction at Taxiway A) (2029 Construction) Y CatEx A,RC,RW,IM 78 57-65 340/F/C/X/T 1,830,218$ 91,511$ 111,847$ 2,033,576$ Used 300,000$

TOTAL 1,830,218$ 91,511$ 111,847$ 2,033,576$ Remaining -$

Federal Fiscal Year 2028 Available 150,000$

1. No Project: Roll Over Entitlements N/A N/A N/A N/A N/A N/A -$ -$ Used -$

TOTAL -$ -$ -$ -$ Remaining 150,000$

Federal Fiscal Year 2029 Available 300,000$

1. Reconstruction of Taxiway Connectors (Including RIM Correction at Taxiway A) Y CatEx A,RC,RW,IM 78 57-65 340/F/C/X/T 28,705,424$ 150,000$ 3,039,492$ 31,894,915$ Used 300,000$

28,705,424$ 150,000$ 3,039,492$ 31,894,915$ Remaining -$

Federal Fiscal Year 2030 Available 150,000$

1. Design for PCC Rehabilitation Taxiways F and G1 (2032 Construction) Y CatEx A,RC,RW,IM 78 40 320/R/C/W/T 186,659$ 9,333$ 11,407$ 207,399$ Used 150,000$ 2 Design for PCC Rehabilitation Main Apron and Key Hangar Area (2032 Construction) Y CatEx A,RC,RW,IM 69 40-55 320/R/C/W/T 186,659$ 9,333$ 11,407$ 207,399$ Used -$

TOTAL 373,318$ 18,666$ 22,814$ 414,798$ Remaining -$

Federal Fiscal Year 2031 Available 150,000$

1. No Project: Roll Over Entitlements N/A N/A N/A N/A N/A N/A Used -$

TOTAL -$ -$ -$ -$ Remaining 150,000$

Federal Fiscal Year 2032 Available 300,000$

1. PCC Rehabilitation Taxiways F and G1 Y CatEx A,RC,RW,IM 78 40 320/R/C/W/T 1,244,395$ 62,220$ 76,046$ 1,382,661$ Used 150,000$

2. PCC Rehabilitation Main Apron and Key Hangar Area Y CatEx A,RC,RW,IM 69 40-55 320/R/C/W/T 1,244,395$ 62,220$ 76,046$ 1,382,661$ Used 150,000$

TOTAL 2,488,790$ 124,439$ 152,093$ 2,765,322$ Remaining -$

Federal Fiscal Year 2033 Available 150,000$

1. Design for Rehabilitate Taxiways G, G2 & G3 & Rehabilitate NE Taxilane (2035 Construction) Y CatEx A,RE,TW,IM 68 59-78 115/F/D/X/T 500,051$ 25,003$ 30,559$ 555,613$ Used 150,000$

TOTAL 500,051$ 25,003$ 30,559$ 555,613$ Remaining -$

Federal Fiscal Year 2034 Available 150,000$

1. Design for Rehabilitation of Central Apron (2037 Construction) Y CatEx A,RE,AP,IM 81 53-72 315/F/D/X/T 349,895$ 17,495$ 21,383$ 388,773$ Used 150,000$

TOTAL 349,895$ 17,495$ 21,383$ 388,773$ Remaining -$

Federal Fiscal Year 2035 Available 150,000$

1. Rehabilitate Taxiways G, G2 & G3 & Rehabilitate NE Taxilane Y CatEx A,RE,TW,IM 68 59-78 115/F/D/X/T 3,333,676$ 150,000$ 220,409$ 3,704,085$ Used 150,000$

TOTAL 3,333,676$ 150,000$ 220,409$ 3,704,085$ Remaining -$

Federal Fiscal Year 2036 Available 150,000$

1. No Project: Roll Over Entitlements N/A N/A N/A N/A N/A N/A -$ -$ Used -$

TOTAL -$ -$ -$ -$ Remaining 150,000$

TOTAL 73,659,805$ 727,114$ 5,347,462$ 79,734,380$

3/19/2026

* Includes FAA IIJA funding for fiscal year 2025 ($687,000) and FAA IIJA funding of $675,000 for fiscal year 2026.

**A PMMP/APMS update is currently in progress. PCI/PCR values for near-term projects are updated based on geotechnical data as part of preliminary design.

***Master grant application submitted reflects full construction cost. Companion grant recently received for $14.4M not deducted.

1. Airport:

CAMARILLO AIRPORT

FAA Entitlements FAA IIJA*

AIRPORT CAPITAL IMPROVEMENT PLAN

Attachment A - ACIP

CMA ACIP DATA SHEET

Shown On

ALP

Project Type* Federal Share State Share Local Share Total

Y D $36,078,433 $150,000 $1,748,865 $37,977,298

$36,078,433 $150,000 $1,748,865 $37,977,298

Part 150 Noise Study (AIP 3-06-0339-043-2022) August 2026 CMA Final Design (AIP 03-06-0399-044-2024) December 2026 CMA Runway 8/26 Rehabilitation (AIP 03-06-0399-045-2025) December 2028

DateSignature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Open AIP Funded Projects Expected Close-out Date

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

County of Ventura holds title to Land.

Exhibit A, Property Map Approved, May 2025

1. CatEx with new floodplain requirements was approved on June 24, 2024.

Land Title Status & Date of Exhibit "A" Status Date

1. Rehabilitation of Runway 8-26 (CMA FAA IIJA Funding from 2025 & 2026)***

Runway 8-26 Rehabilitation consists of pavement removal, subgrade preparation and treatment, placement of aggregate base, asphalt paving, runway grooving, pavement marking, drainage improvements, and electrical improvements. The taxiway connectors transitions Rehabilitation consists of pavement removal, subgrade preparation and treatment, placement of aggregate base, asphalt paving, pavement marking, drainage improvements, and electrical improvements.

***Master grant application submitted reflects full construction cost. Companion grant recently received for $14.4M not deducted.

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. Design will be completed in fiscal year 2026 with construction in fiscal year 2027.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

Airport Name CAMARILLO AIRPORT Fiscal Year 2026

Project Description

1. Rehabilitation of Runway 8-26 (CMA FAA IIJA Funding from 2025 & 2026)***

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 1 OF 11

CAMARILLO AIRPORT

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2026

( IN FEET )

GRAPHIC SCALE

800400400

FY 2026 PROJECTS

1. REHABILITATION OF RUNWAY 8-26 (CMA FAA IIJA FUNDING FROM 2025 & 2026)

ALP

Project Type* Federal Share State Share Local Share Total

Y D $1,830,218 $91,511 $111,847 $2,033,576

$1,830,218 $91,511 $111,847 $2,033,576

Part 150 Noise Study (AIP 3-06-0339-043-2022) August 2026 CMA Final Design (AIP 03-06-0399-044-2024) December 2026 CMA Runway 8/26 Rehabilitation (AIP 03-06-0399-045-2025) December 2028

DateSignature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Open AIP Funded Projects Expected Close-out Date

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

County of Ventura holds title to Land.

Exhibit A, Property Map Approved, May 2025

1. Design will be completed during the 2027 Federal Fiscal Year. Bids are anticipated to be received by February 2028 with construction commencing in 2029. Construction length will be determined by the Engineer during design, the County is committed to project completion and grant sign off within FAA's grant closeout guidelines.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. CatEx with new floodplain requirements was approved on June 24, 2024.

Land Title Status & Date of Exhibit "A" Status Date

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

1. Design for Taxiway Connectors Reconstruction (Include. RIM Correction at Taxiway A) (2029 Construction)

The taxiway connectors were constructed in various phases, dating back to 1951. Other than seal coats and isolated repairs, no rehabilitation has been performed on the taxiways since the 1990s. A visual condition survey was performed in 2015 for an Airport Pavement Management System (APMS) prepared in 2016. At the time of the survey, the taxiways were found to be in Satisfactory condition (PCI of 70-85). Like the runway, this was shortly after a slurry seal had been applied in 2014. The PCN evaluation performed in 2017 has indicated that a majority of the taxiways are structurally insufficient, and a reconstruction is recommended. Taxiway A has also been identified as a runway incursion risk and the geometry will need to be corrected to mitigate this risk. The reconstruction consists of pavement removal, subgrade preparation and treatment, placement of aggregate base, asphalt paving, pavement marking, drainage improvements for MS4 compliance, and electrical improvements.

Airport Name CAMARILLO AIRPORT Fiscal Year 2027

Project Description

1. Design for Taxiway Connectors Reconstruction (Include. RIM Correction at Taxiway A) (2029 Construction)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 2 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2027

( IN FEET )

GRAPHIC SCALE

800400400

FY 2027 PROJECTS

1. DESIGN FOR TAXIWAY CONNECTORS RECONSTRUCTION (INCLUDE. RIM CORRECTION AT TAXIWAY A)

ALP

Project Type* Federal Share State Share Local Share Total

$0 $0 $0 $0

$0 $0 $0 $0

DateSignature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Open AIP Funded Projects Expected Close-out Date

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

1. Not Applicable

Land Title Status & Date of Exhibit "A" Status Date

1. No Project: Roll Over Entitlements

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. Not Applicable

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

Airport Name CAMARILLO AIRPORT Fiscal Year 2028

Project Description

1. No Project: Roll Over Entitlements

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 3 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2028

( IN FEET )

GRAPHIC SCALE

800400400

FY 2028 PROJECTS

1. NO PROJECT: ROLL OVER ENTITLEMENTS

ALP

Project Type* Federal Share State Share Local Share Total

Y D $28,705,424 $150,000 $3,039,492 $31,894,915

$28,705,424 $150,000 $3,039,492 $31,894,915

Part 150 Noise Study (AIP 3-06-0339-043-2022) August 2026 CMA Final Design (AIP 03-06-0399-044-2024) December 2026 CMA Runway 8/26 Rehabilitation (AIP 03-06-0399-045-2025) December 2028

Date

Danielle Tarr, Projects Administrator

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Keith Freitas, Director of Airports

County of Ventura holds title to Land.

Exhibit A, Property Map Approved, May 2025

Signature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. Design will be completed during the 2027 Federal Fiscal Year. Bids are anticipated to be received by February 2028 with construction commencing in 2029. Construction length will be determined by the Engineer during design, the County is committed to project completion and grant sign off within FAA's grant closeout guidelines.

1. CatEx with new floodplain requirements was approved on June 24, 2024.

Airport Name CAMARILLO AIRPORT Fiscal Year 2029

Project Description

1. Reconstruction of Taxiway Connectors (Including RIM Correction at Taxiway A)

Detail Project Description (Square/Lineal Footage or Length/Width)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

1. Reconstruction of Taxiway Connectors (Including RIM Correction at Taxiway A)

The taxiway connectors were constructed in various phases, dating back to 1951. Other than seal coats and isolated repairs, no rehabilitation has been performed on the taxiways since the 1990s. A visual condition survey was performed in 2015 for an Airport Pavement Management System (APMS) prepared in 2016. At the time of the survey, the taxiways were found to be in Satisfactory condition (PCI of 70-85). Like the runway, this was shortly after a slurry seal had been applied in 2014. The PCN evaluation performed in 2017 has indicated that a majority of the taxiways are structurally insufficient, and a reconstruction is recommended. Taxiway A has also been identified as a runway incursion risk and the geometry will need to be corrected to mitigate this risk. The reconstruction consists of pavement removal, subgrade preparation and treatment, placement of aggregate base, asphalt paving, pavement marking, drainage improvements for MS4 compliance, and electrical improvements.

Open AIP Funded Projects Expected Close-out Date

Land Title Status & Date of Exhibit "A" Status Date

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 4 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2029

( IN FEET )

GRAPHIC SCALE

800400400

FY 2029 PROJECTS

1. RECONSTRUCTION OF TAXIWAY CONNECTORS (INCLUDING RIM CORRECTION AT TAXIWAY A)

ALP

Project Type* Federal Share State Share Local Share Total

Y D $186,659 $9,333 $11,407 $207,399

Y D $186,659 $9,333 $11,407 $207,399

$373,318 $18,666 $22,814 $414,798

Part 150 Noise Study (AIP 3-06-0339-043-2022) August 2026 CMA Final Design (AIP 03-06-0399-044-2024) December 2026 CMA Runway 8/26 Rehabilitation (AIP 03-06-0399-045-2025) December 2028

Date

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. & 2. CatEx submittal planned prior to design completion.

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. & 2. Design will be complete during the 2030 Federal Fiscal Year.

Land Title Status & Date of Exhibit "A" Status Date

Airport Name CAMARILLO AIRPORT Fiscal Year 2030

Project Description

1. Design for PCC Rehabilitation Taxiways F and G1 (2032 Construction)

2 Design Grant for PCC Rehabilitation Main Apron and Key Hangar Area (2032 Construction)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

1. Design for PCC Rehabilitation Taxiways F and G1 (2032 Construction)

2. Design Grant for PCC Rehabilitation Main Apron and Key Hangar Area (2032 Construction)

Signature Contact Phone (Print or Type)

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

(805) 388-4205

Open AIP Funded Projects Expected Close-out Date

County of Ventura holds title to Land.

Exhibit A, Property Map Approved, May 2025

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 5 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2030

( IN FEET )

GRAPHIC SCALE

800400400

FY 2030 PROJECTS

1. DESIGN GRANT FOR PCC REHABILITATION TAXIWAY F, AND G1 (2032 CONSTRUCTION)

2. DESIGN GRANT FOR PCC REHABILITATION MAIN APRON, AND KEY HANGAR AREA (2032 CONSTRUCTION)

ALP

Project Type* Federal Share State Share Local Share Total

$0 $0 $0 $0

$0 $0 $0 $0

Date

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

Detail Project Description (Square/Lineal Footage or Length/Width)

Airport Name CAMARILLO AIRPORT Fiscal Year 2031

Project Description

1. No Project: Roll Over Entitlements

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

1. No Project: Roll Over Entitlements

1. Not Applicable

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. Not Applicable

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Open AIP Funded Projects Expected Close-out Date

(805) 388-4205 Signature Contact Phone (Print or Type)

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 6 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2031

( IN FEET )

GRAPHIC SCALE

800400400

FY 2031 PROJECTS

ALP

Project Type* Federal Share State Share Local Share Total

Y D $1,244,395 $62,220 $76,046 $1,382,661

Y D $1,244,395 $62,220 $76,046 $1,382,661

$2,488,790 $124,439 $152,093 $2,765,322

Part 150 Noise Study (AIP 3-06-0339-043-2022) August 2026 CMA Final Design (AIP 03-06-0399-044-2024) December 2026 CMA Runway 8/26 Rehabilitation (AIP 03-06-0399-045-2025) December 2028

Date

Detail Project Description (Square/Lineal Footage or Length/Width)

1. PCC Rehabilitation Taxiways F and G1

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

2. PCC Rehabilitation Main Apron and Key Hangar Area

Airport Name CAMARILLO AIRPORT Fiscal Year 2032

Project Description

1. PCC Rehabilitation Taxiways F and G1

Work is anticipated to include crack repair, resealing of joints, spall repair and select panel replacement. (160,000 SY)

Work is anticipated to include crack repair, resealing of joints, spall repair and select panel replacement.

Land Title Status & Date of Exhibit "A" Status Date

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. Design will be completed during the 2030 Federal Fiscal Year. Bids are anticipated to be received by February 2032 with construction commencing in 2032. Construction length will be determined by the Engineer during design, the County is committed to project completion and grant sign off within FAA's grant closeout guidelines.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. and 2. CatEx submittal planned prior to design completion.

2. PCC Rehabilitation Main Apron and Key Hangar Area

2. Design will be completed during the 2030 Federal Fiscal Year. Bids are anticipated to be received by February 2032 with construction commencing in 2032. Construction length will be determined by the Engineer during design, the County is committed to project completion and grant sign off within FAA's grant closeout guidelines.

County of Ventura holds title to Land.

Exhibit A, Property Map Approved, May 2025

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Open AIP Funded Projects Expected Close-out Date

(805) 388-4205 Signature Contact Phone (Print or Type)

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 7 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2032

( IN FEET )

GRAPHIC SCALE

800400400

FY 2032 PROJECTS

1. PCC REHABILITATION TAXIWAYS F AND G1

2. PCC REHABILITATION MAIN APRON AND KEY HANGAR AREA

ALP

Project Type* Federal Share State Share Local Share Total

Y D $500,051 $25,003 $30,559 $555,613

$500,051 $25,003 $30,559 $555,613

Part 150 Noise Study (AIP 3-06-0339-043-2022) August 2026 CMA Final Design (AIP 03-06-0399-044-2024) December 2026 CMA Runway 8/26 Rehabilitation (AIP 03-06-0399-045-2025) December 2028

DateSignature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Open AIP Funded Projects Expected Close-out Date

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

County of Ventura holds title to Land.

Exhibit A, Property Map Approved, May 2025

1. CatEx submittal planned prior to design completion.

Land Title Status & Date of Exhibit "A" Status Date

1. Design for Rehabilitate Taxiways G, G2 & G3 & Rehabilitate NE Taxilane (2035 Construction) Work is anticipated to include crack repair, seal coat application and new pavement markings.

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. Design will be completed during the 2033 Federal Fiscal Year. Bids are anticipated to be received by February 2035. Construction length will be determined by the Engineer during design, the County is committed to project completion and grant sign off within FAA's grant closeout guidelines.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

Airport Name CAMARILLO AIRPORT Fiscal Year 2033

Project Description

1. Design for Rehabilitate Taxiways G, G2 & G3 & Rehabilitate NE Taxilane (2035 Construction)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 8 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2033

( IN FEET )

GRAPHIC SCALE

800400400

FY 2033 PROJECTS

1. DESIGN FOR REHABILITATE TAXIWAYS G, G2 & G3 & REHABILITATE NE TAXILANE (2035 CONSTRUCTION)

ALP

Project Type* Federal Share State Share Local Share Total

Y D $349,895 $17,495 $21,383 $388,773

$349,895 $17,495 $21,383 $388,773

Part 150 Noise Study (AIP 3-06-0339-043-2022) August 2026 CMA Final Design (AIP 03-06-0399-044-2024) December 2026 CMA Runway 8/26 Rehabilitation (AIP 03-06-0399-045-2025) December 2028

Date

1. Design for Rehabilitation of Central Apron (2037 Construction)

Airport Name CAMARILLO AIRPORT Fiscal Year 2034

Project Description

1. Design for Rehabilitation of Central Apron (2037 Construction)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

Work is anticipated to include crack repair, seal coat application and new pavement markings (18,000 SY)

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

Design will be completed during the 2034 Federal Fiscal Year

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. CatEx submittal planned prior to design completion.

Land Title Status & Date of Exhibit "A" Status Date

Design for Rehabilitate Central Apron (2036 Construct) - County of Ventura holds title to Land.

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

Exhibit A, Property Map Approved, May 2025

Open AIP Funded Projects Expected Close-out Date

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

(805) 388-4205 Signature Contact Phone (Print or Type)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 9 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2034

( IN FEET )

GRAPHIC SCALE

800400400

FY 2034 PROJECTS

1. DESIGN FOR REHABILITATION OF CENTRAL APRON (2037 CONSTRUCTION)

ALP

Project Type* Federal Share State Share Local Share Total

Y D $3,333,676 $150,000 $220,409 $3,704,085

$3,333,676 $150,000 $220,409 $3,704,085

Part 150 Noise Study (AIP 3-06-0339-043-2022) August 2026 CMA Final Design (AIP 03-06-0399-044-2024) December 2026 CMA Runway 8/26 Rehabilitation (AIP 03-06-0399-045-2025) December 2028

Date

1. Rehabilitate Taxiways G, G2 & G3 & Rehabilitate NE Taxilane

Airport Name CAMARILLO AIRPORT Fiscal Year 2035

Project Description

1. Rehabilitate Taxiways G, G2 & G3 & Rehabilitate NE Taxilane

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

Work is anticipated to include crack repair, seal coat application and new pavement markings.

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. Design will be completed during the 2033 Federal Fiscal Year. Bids are anticipated to be received by February 2035. Construction length will be determined by the Engineer during design, the County is committed to project completion and grant sign off within FAA's grant closeout guidelines.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. CatEx submittal planned prior to design completion.

Land Title Status & Date of Exhibit "A" Status Date

County of Ventura holds title to Land.

Exhibit A, Property Map Approved, May 2025

Open AIP Funded Projects Expected Close-out Date

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

(805) 388-4205 Signature Contact Phone (Print or Type)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 10 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2035

( IN FEET )

GRAPHIC SCALE

800400400

FY 2035 PROJECTS

1. REHABILITATE TAXIWAYS G, G2 & G3 & REHABILITATE NE TAXILANE

ALP

Project Type* Federal Share State Share Local Share Total

$0 $0 $0 $0

$0 $0 $0 $0

Date

1. No Project: Roll Over Entitlements

Airport Name CAMARILLO AIRPORT Fiscal Year 2036

Project Description

1. No Project: Roll Over Entitlements

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. Not Applicable

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. Not Applicable

Land Title Status & Date of Exhibit "A" Status Date

1. Not Applicable

Open AIP Funded Projects Expected Close-out Date

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

(805) 388-4205 Signature Contact Phone (Print or Type)

P:\Capital Improvement Plan CIP\5 Year CIP 2026\CMA_ACIP 2026-2031 Summary and Data Sheets-Working 03.18.26 REV

DATE: JANUARY 14, 2026 SHEET 11 OF 11

CAMARILLO, CA

ACIP - FEDERAL FISCAL YEAR 2036

( IN FEET )

GRAPHIC SCALE

800400400

FY 2036 PROJECTS

3. NPIAS No.

06-0179

5. Project Description On ALP? Environmental NPR Code NPR PCI*** PCR*** Federal State Local Total $ (by funding year in priority order) Y/N Type (APCT) Rating Funds Funds Funds Description Amount Description Amount

Federal Fiscal Year 2026 Available 150,000$ Available 285,000$

1. Rehabilitate ATCT (ATP or FCT IIJA Grant) Y CatEx A,RE,BE,RT 69 N/A N/A 2,430,000$ 121,500$ 148,500$ 2,700,000$ Used 150,000$ Used 285,000$

TOTAL 2,430,000$ 121,500$ 148,500$ 2,700,000$ Remaining -$ Remaining -$

Federal Fiscal Year 2027 Available 150,000$

1. Design for Reconstruction of Central Apron and Portion of Transient Apron (2029 Construction) Y CatEx A,RE,AP,IM 69 AC 40-55 41/F/D/X/T 450,000$ 22,500$ 27,500$ 500,000$ Used 150,000$

TOTAL 450,000$ 22,500$ 27,500$ 500,000$ Remaining -$

Federal Fiscal Year 2028 Available 150,000$

1. No Project: Roll Over Entitlements N/A N/A N/A N/A N/A N/A -$ -$ -$ Used

TOTAL -$ -$ -$ -$ Remaining 150,000$

Federal Fiscal Year 2029 Available 300,000$

1. Reconstruction of Central Apron and Portion of Transient Apron Y CatEx A,RE,AP,IM 69 AC 40-55 41/F/D/X/T 3,262,500$ 150,000$ 212,500$ 3,625,000$ Used 300,000$

TOTAL 3,262,500$ 150,000$ 212,500$ 3,625,000$ Remaining -$

Federal Fiscal Year 2030 Available 150,000$

1. Design for Reconstruction of Terminal Apron PCC/AC & ARFF Apron (2032 Construction) Y CatEx A,RC,AP,IM 69 AC 55-70 110/F/D/X/T 489,375$ 24,469$ 29,906$ 543,750$ Used 150,000$

TOTAL 489,375$ 24,469$ 29,906$ 543,750$ Remaining -$

Federal Fiscal Year 2031 Available 150,000$

1. Design for Rehabilitate Perimeter & Terminal Loop Roads and ATCT & Operations & Central Hangar Parking (2033 Construction) Y CatEx A,ST,LA,SZ 68 N/A N/A 157,500$ 7,875$ 9,625$ 175,000$ Used 150,000$

2. Land Acquisitions - RPZ Property Purchases** N/A N/A N/A N/A 1,440,000$ 72,000$ 88,000$ 1,600,000$

TOTAL 1,597,500$ 79,875$ 97,625$ 1,775,000$ Remaining -$

Federal Fiscal Year 2032 Available 150,000$

1. Reconstruction of Terminal Apron PCC/AC & ARFF Apron Y CatEx A,RC,AP,IM 69 AC 55-70 110/F/D/X/T 3,262,500$ 150,000$ 212,500$ 3,625,000$ Used 150,000$

PCC 25-40 190/R/B/W/T TOTAL 3,262,500$ 150,000$ 212,500$ 3,625,000$ Remaining -$

Federal Fiscal Year 2033 Available 150,000$

1. Rehabilitate Perimeter & Terminal Loop Roads and ATCT & Operations & Central Hangar Parking Y CatEx A,ST,LA,SZ 68 AC 55-70 N/A 789,007$ 39,450$ 48,218$ 876,675$ Used 150,000$

TOTAL 789,007$ 39,450$ 48,218$ 876,675$ Remaining -$

Federal Fiscal Year 2034 Available 150,000$

1. Design for Rehabilitation of West Hangar Apron Area (2035 Construction) Y CatEx A,RE,AP,IM 62 AC 70-85 72/F/D/X/T 67,500$ 3,375$ 4,125$ 75,000$ Used 67,500$

TOTAL 67,500$ 3,375$ 4,125$ 75,000$ Remaining 82,500$

Federal Fiscal Year 2035 Available 232,500$

1. Rehabilitation of West Hangar Apron Area Y CatEx A,RE,AP,IM 62 AC 70-85 72/F/D/X/T 450,000$ 22,500$ 27,500$ 500,000$ Used 232,500$

TOTAL 450,000$ 22,500$ 27,500$ 500,000$ Remaining -$

Federal Fiscal Year 2036 Available 150,000$

1. No Project: Roll Over Entitlements N/A N/A N/A N/A N/A N/A Used

TOTAL -$ -$ -$ -$ Remaining 150,000$

TOTAL 12,798,382$ 613,669$ 808,374$ 14,220,425$

5/12/2026

* Includes FAA IIJA funding of $285,000 for fiscal year 2026.

** New Appraisal is being completed and costs are anticipated to be a smaller amount.

1. Airport:

OXNARD AIRPORT

FAA Entitlements FAA IIJA*

AIRPORT CAPITAL IMPROVEMENT PLAN

Attachment A - ACIPAttachment A - ACIP

OXR ACIP DATA SHEET

ALP

Project Type* Federal Share State Share Local Share Total

Y D $2,430,000 $121,500 $148,500 $2,700,000

$2,430,000 $121,500 $148,500 $2,700,000

OXR Reconstruct Taxiway F (AIP) Companion Grant (3-06-0179-045-2025) December 2026 OXR Reconstruct Taxiway F (AIP) (3-06-0179-044-2023) December 2026 OXR Reconstruction of Taxiway Connectors A-E (3-06-0179-042-2022) June 2026 OXR Part 150 Noise Compatibility Plan Study (3-06-0179-041-2022) December 2026

Date

Danielle Tarr, Projects Administrator

County of Ventura holds title to Land.

Exhibit A, Property Map ALP set updated 2/14/22.

(805) 388-4205 Signature Contact Phone (Print or Type)

Open AIP Funded Projects Expected Close-out Date

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Keith Freitas, Director of Airports

Date

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. CATEX was submitted for approval.

Land Title Status & Date of Exhibit "A" Status

1. Rehabilitate ATCT (ATP or FCT IIJA Grant)

OXR ATCT is a level 6 facility constructed in 1958. It has critical FAA equipment & infrastructure to support an airport with +39% growth in operations (TAF 2013-2023). A recent 2023 assessment found termite damage, asbestos/lead paint & the HVAC, fire rated doors, fire alarm system,electrical panels, windows & roof ladder beyond their life cycle.This project will reimburse assessment cost, remediate asbestos/lead paint & replace all of the above to improve energy efficiency & ADA compliance & provide redundant HVAC cooling to protect FAA equipment in the cab & equipment room.

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

Date Grant Fully Executed: 11/2026

Construction Start Date: 2/2027

Date Project Costs Known: 09/2026

Airport Name OXNARD AIRPORT Fiscal Year 2026

Project Description

1. Rehabilitate ATCT (ATP or FCT IIJA Grant)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

DATE: JANUARY 14, 2026 SHEET 1 OF 11

OXNARD AIRPORT

OXNARD, CA

ACIP - FEDERAL FISCAL YEAR 2026

1. REHABILITATE ATCT (ATP or FTC IIJA Grant)

( IN FEET )

GRAPHIC SCALE

500250250

FY 2026 PROJECTS

ALP

Project Type* Federal Share State Share Local Share Total

Y D $3,262,500 $150,000 $212,500 $3,625,000

$3,262,500 $150,000 $212,500 $3,625,000

OXR Reconstruct Taxiway F (AIP) Companion Grant (3-06-0179-045-2025) December 2026 OXR Reconstruct Taxiway F (AIP) (3-06-0179-044-2023) December 2026 OXR Reconstruction of Taxiway Connectors A-E (3-06-0179-042-2022) June 2026 OXR Part 150 Noise Compatibility Plan Study (3-06-0179-041-2022) December 2026

Date

Airport Name OXNARD AIRPORT Fiscal Year 2029

Project Description

1. Reconstruction of Central Apron and Portion of Transient Apron

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

1. Reconstruction of Central Apron and Portion of Transient Apron

A pavement condition survey was performed in 2025 for an Airport Pavement Management System (APMS) prepared in 2025/2026. At the time of the survey, the Central Hangar Area was found to have portions in Good Condition (PCI 85-100), in Satifactory Condition (PCI 70-85) and one small portion in Very Poor Condition (PCI 25-40).

The Transient Apron was found to have portions in Good Condition (PCI 85-100), in Satifactory Condition (PCI 70-85) and Poor Condition (PCI 40-55). Based on the conditions observed in the APMS, a pavement reconstruction recommended. Work would include full depth pavement removal, overexcavation, subgrade preparation, placing new base course material, placement of new asphalt pavement, and installation of new pavement markings.

1. Construction will be completed in fiscal year 2029.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. CatEx approval anticipated by early 2027.

Land Title Status & Date of Exhibit "A" Status Date

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

County of Ventura holds title to Land.

Exhibit A, Property Map ALP set updated 2/14/22.

Open AIP Funded Projects Expected Close-out Date

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Signature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Attachment A - ACIPAttachment A - ACIP

DATE: JANUARY 14, 2026 SHEET 2 OF 11

OXNARD, CA

ACIP - FEDERAL FISCAL YEAR 2027

( IN FEET )

GRAPHIC SCALE

500250250

FY 2027 PROJECTS

1. DESIGN FOR REHABILITATE CENTRAL APRON AND PORTION OF TRANSIENT APRON

(2029 CONSTRUCTION)

ALP

Project Type* Federal Share State Share Local Share Total

$0 $0 $0 $0

$0 $0 $0 $0

Date

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Signature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Open AIP Funded Projects Expected Close-out Date

1. Not applicable.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. Not applicable.

Land Title Status & Date of Exhibit "A" Status Date

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

1. No Project: Roll Over Entitlements

Airport Name OXNARD AIRPORT Fiscal Year 2028

Project Description

1. No Project: Roll Over Entitlements

DATE: JANUARY 14, 2026 SHEET 3 OF 11

OXNARD, CA

ACIP - FEDERAL FISCAL YEAR 2028

1. NO PROJECT: ROLL OVER ENTITLEMENTS

( IN FEET )

GRAPHIC SCALE

500250250

FY 2028 PROJECTS

ALP

Project Type* Federal Share State Share Local Share Total

Y D $3,262,500 $150,000 $212,500 $3,625,000

$3,262,500 $150,000 $212,500 $3,625,000

OXR Reconstruct Taxiway F (AIP) Companion Grant (3-06-0179-045-2025) December 2026 OXR Reconstruct Taxiway F (AIP) (3-06-0179-044-2023) December 2026 OXR Reconstruction of Taxiway Connectors A-E (3-06-0179-042-2022) June 2026 OXR Part 150 Noise Compatibility Plan Study (3-06-0179-041-2022) December 2026

Date

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Signature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

County of Ventura holds title to Land.

Exhibit A, Property Map ALP set updated 2/14/22.

Open AIP Funded Projects Expected Close-out Date

1. Construction will be completed in fiscal year 2029.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. CatEx approval anticipated by early 2027.

Land Title Status & Date of Exhibit "A" Status Date

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

1. Reconstruction of Central Apron and Portion of Transient Apron

The Terminal Apron was last reconstructed in 1992 while the ARFF Apron was last reconstructed in 1997. A visual condition survey was performed in 2015 for an Airport Pavement Management System (APMS) prepared in 2016. At the time of the survey, the PCC section on the Terminal Apron was found to be in Very Poor condition (PCI of 25-40) and the AC section in Fair condition (PCI of 55-70), while the ARFF Apron was found in Good Condition (PCI 85-100). Based on the conditions observed in the APMS and on the pavement strength analysis which showed the inadequacy of the pavement for the aircraft fleet mix at the time, a full reconstruction is recommended for the Terminal Apron and ARFF Apron. Work would include AC and PCC pavement removal, strengthening of the subgrade, placing new AB material, placing PCC and AC pavement, and application of pavement markings based on the most current Advisory Circular.

Airport Name OXNARD AIRPORT Fiscal Year 2029

Project Description

1. Reconstruction of Central Apron and Portion of Transient Apron

DATE: JANUARY 14, 2026 SHEET 4 OF 11

OXNARD, CA

ACIP - FEDERAL FISCAL YEAR 2029

( IN FEET )

GRAPHIC SCALE

500250250

FY 2029 PROJECTS

1. REHABILITATE CENTRAL APRON, EXECUTIVE HANGAR AREA AND PORTION OF

TRANSIENT APRON (CONSTRUCTION)

ALP

Project Type* Federal Share State Share Local Share Total

Y D $489,375 $24,469 $29,906 $543,750

$489,375 $24,469 $29,906 $543,750

OXR Reconstruct Taxiway F (AIP) Companion Grant (3-06-0179-045-2025) December 2026 OXR Reconstruct Taxiway F (AIP) (3-06-0179-044-2023) December 2026 OXR Reconstruction of Taxiway Connectors A-E (3-06-0179-042-2022) June 2026 OXR Part 150 Noise Compatibility Plan Study (3-06-0179-041-2022) December 2026

DateSignature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

(805) 388-4205

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Open AIP Funded Projects Expected Close-out Date

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

County of Ventura holds title to Land.

Exhibit A, Property Map ALP set updated 2/14/22.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. CatEx approval anticipated by early 2030.

Land Title Status & Date of Exhibit "A" Status Date

1. Design will be completed in 2030. Bids are anticipated to be received by February 2032 with construction in summer 2032. Construction length will be determined by the Engineer during design, the County is committed to project completion and grant sign off within FAA's grant closeout guidelines.

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

1. Design for Reconstruction of Terminal Apron PCC/AC & ARFF Apron (2032 Construction)

A visual condition survey was performed in 2015 for an Airport Pavement Management System (APMS) prepared in 2016. At the time of the survey, the Central Hangar Area was in Good Condition (PCI 85-100), the Transient Apron was found to be in Poor condition (PCI of 40-55), and the Executive Apron was found to be in Satisfactory condition (PCI of 70-85). Based on the conditions observed in the APMS, a seal coat is recommended for most of the area, with a reconstruction of a portion of the Transient apron (recommended in FY 2016 per APMS). Work would include crack seal, seal coat application, limited pavement removal, trimming of existing AB to meet grades, placing new AB material and AC pavement, and re-application of existing markings.

Airport Name OXNARD AIRPORT Fiscal Year 2030

Project Description

1. Design for Reconstruction of Terminal Apron PCC/AC & ARFF Apron (2032 Construction)

DATE: JANUARY 14, 2026 SHEET 5 OF 11

OXNARD, CA

ACIP - FEDERAL FISCAL YEAR 2030

1. DESIGN FOR RECONSTRUCTION OF TERMINAL APRON PCC/AC & ARFF APRON (2032 CONSTRUCTION)

( IN FEET )

GRAPHIC SCALE

500250250

FY 2030 PROJECTS

ALP

Project Type* Federal Share State Share Local Share Total

Y D $157,500 $7,875 $9,625 $175,000

$1,440,000 $72,000 $88,000 $1,600,000

$1,597,500 $79,875 $97,625 $1,775,000

OXR Reconstruct Taxiway F (AIP) Companion Grant (3-06-0179-045-2025) December 2026 OXR Reconstruct Taxiway F (AIP) (3-06-0179-044-2023) December 2026 OXR Reconstruction of Taxiway Connectors A-E (3-06-0179-042-2022) June 2026 OXR Part 150 Noise Compatibility Plan Study (3-06-0179-041-2022) December 2026

Date

2. Land Acquisitions - RPZ Property Purchases**

Airport Name OXNARD AIRPORT Fiscal Year 2031

Project Description

1. Design for Rehabilitate Perimeter & Terminal Loop Roads and ATCT & Operations & Central Hangar Parking (2033 Construction)

1. FFY 2031 Design for Rehabilitate Perimeter & Terminal Loop Roads and ATCT & Operations & Central Hangar Parking (2033 Construction) A visual condition survey was performed in 2015 for an Airport Pavement Management System (APMS) prepared in 2016. At the time of the survey, the Perimeter Road was in Fair (PCI 55-70) to Poor (PCI 40-55) Condition, the Terminal Loop was in Satisfactory Condition (PCI 70-85), the ATCT and Operations Parking was in Satisfactory Condition, and the Central Hangar Area Parking was in Poor Condition. The proposed improvements for the areas mentioned above consist of a rehabilitation for the section of the Perimeter Road in Poor condition and an emulsified asphalt seal coat for the other areas. The rehabilitation will consist of removing the existing pavement, trimming existing AB to meet design grades, placing new AB material over existing, and placing new AC pavement. The emulsified asphalt seal coat will include crack repair, seal coat application, and re-application of pavement markings.

2. Land Acquisitions - RPZ Property Purchases**

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

** New Appraisal is being completed and costs are anticipated to be a smaller amount.

Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process)

1. Design will be completed on 2031.

NEPA Environmental Status (Date of FONSI or submit CATEX Form for Approval)

1. CatEx approval anticipated by early 2031.

Land Title Status & Date of Exhibit "A" Status Date

County of Ventura holds title to Land.

Exhibit A, Property Map ALP set updated 2/14/22.

Open AIP Funded Projects Expected Close-out Date

Keith Freitas, Director of Airports Danielle Tarr, Projects Administrator

Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.

Signature Contact Phone (Print or Type)

Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)

DATE: JANUARY 14, 2026 SHEET 6 OF 11

OXNARD, CA

ACIP - FEDERAL FISCAL YEAR 2031

( IN FEET )

GRAPHIC SCALE

500250250

FY 2031 PROJECTS

1. DESIGN FOR REHABILITATE PERIMETER & TERMINAL LOOP ROADS AND ATCT &

OPERATIONS & CENTRAL HANGAR PARKING (2033 CONSTRUCTION)

2. LAND ACQUISITION - RPZ PROPERTY PURCHASES (NOT SHOWN)

ALP

Project Type* Federal Share State Share Local Share Total

Y D $3,262,500 $150,000 $212,500 $3,625,000

$3,262,500 $150,000 $212,500 $3,625,000

OXR Reconstruct Taxiway F (AIP) Companion Grant (3-06-0179-045-2025) December 2026 OXR Reconstruct Taxiway F (AIP) (3-06-0179-044-2023) December 2026 OXR Reconstruction of Taxiway Connectors A-E (3-06-0179-042-2022) June 2026 OXR Part 150 Noise Compatibility Plan Study (3-06-0179-041-2022) December 2026

Date

Airport Name OXNARD AIRPORT Fiscal Year 2032

Project Description

1. Reconstruction of Terminal Apron PCC/AC & ARFF Apron

Total

* D - Development; P - Planning; E - Environmental PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS

Detail Project Description (Square/Lineal Footage or Length/Width)

1. Construction will be completed in fiscal year 2032

1. Reconstruction of Terminal Apron PCC/AC & ARFF Apron

A visual condition survey was performed in 2015 for an Airport Pavement Management System (APMS) prepared in 2016.