This is an Advertisement for Bids issued by Holly Area School District for the Rose Pioneer Elementary Technology project in Holly, Michigan. The project has been designed by GMB Architecture + Engineering. Bidding documents are available for download via Pipeline Suites, with hard copies available for review at AUCH Construction's office located at 65 University Drive, Pontiac, Michigan, beginning May 10, 2021. A pre-bid meeting is scheduled for Monday, May 17, 2021, at 4:00 PM at Rose Pioneer Elementary, 7110 Milford Road, Holly, Michigan 48442. Sealed bids must be submitted to Mr. Scott Roper, Superintendent, Holly Area Schools, 920 Baird Street, Holly, Michigan 48442, with a deadline of 12:00 noon on Wednesday, June 2, 2021. Bids may also be delivered to AUCH Construction. Public bid opening will occur via Zoom at 1:30 PM on June 2, 2021, with meeting ID 2484590200. All proposals must be submitted on forms provided by the construction manager and remain firm for sixty days from submission.

Bids exceeding $25,288.00 must include a bid bond from a U.S. Treasury-listed surety company or a cashier's check equal to at least 5% of the proposal amount. Successful bidders with proposals of $50,000 or more must furnish a Performance and Payment Bond in the amount of 100% of their bid, with bond costs included in the proposal. Each bid must include a completed and notarized Familial Disclosure Statement and Affidavit of Compliance to the Iran Economic Sanctions Act. The Board of Education reserves the right to reject any or all bids and to accept the bid deemed in the best interest of the district.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADVERTISEMENT FOR BIDS

HOLLY AREA SCHOOLS

ROSE PIONEER ELEMENTARY TECHNOLOGY

Holly Area School District will receive firm prime contractor bids for the Rose Pioneer Elementary

Technology project located in Holly, Michigan.

The bidding documents consist of plans and specifications as prepared by GMB Architecture + Engineering, 85 East Eighth Street, Suite 200, Holland, MI 49423. Documents may be downloaded from Pipeline Suites.

Contact Veronica Passkiewicz or Shawn Debo at AUCH Construction, 248-334-2000, if you need assistance viewing or obtaining documents from Pipeline Suites. A copy of the documents will also be available for review at the offices of AUCH Construction., 65 University Drive, Pontiac, MI, 48342, 248-

334-2000, on or after May 10, 2021.

A Pre-Bid meeting will be held at Rose Pioneer Elementary, located at 7110 Milford Rd, Holly, MI 48442 on Monday, May 17th at 4:00 PM. The meeting will be held on-site at the main entrance.

An opaque envelope bearing your proposal must identify your company, the project being bid “Holly Area

Schools Rose Pioneer Elementary Technology” and “Sealed Bid, Do Not Open”. The proposal shall be addressed to the attention of Mr. Scott Roper, Superintendent, Holly Area Schools, 920 Baird Street, Holly, MI 48442.

Bids must be delivered no later than 12:00 noon, Wednesday June 2, 2021 to Holly Area School District at the address noted above or AUCH Construction. Each proposal must be submitted on the forms furnished by the Construction Manager and must be completed in full. Familial Disclosure Statement and the

Affidavit of Compliance to the Iran Economic Sanctions Act must both be completed and notarized. A bid bond executed by a U.S. Treasury Listed Surety Company acceptable to AUCH Construction or a cashier’s check in the amount of at least 5% of the sum of the proposal payable to Holly Area Schools shall be submitted with each proposal in excess of $25,288.00. All proposals shall be firm for a period of sixty (60) days.

Bids will be publicly opened and read via a public online Zoom meeting from the Holly Area Schools

Administration Building starting at 1:30 P.M. on WEDNESDAY JUNE 2, 2021. To access the Zoom meeting, go online to zoom.us or open the Zoom app and select the option to join meeting. Enter the meeting

ID 2484590200 when prompted. Please contact Veronica Passkiewicz at vpasskiewicz@auchconstruction.com or 248-334-2000 with any questions regarding this meeting.

Successful bidders whose proposals are $50,000 or more will be required to furnish a Satisfactory

Performance and Payment Bond in the amount of 100% of their bid. The cost of the Bond shall be included in each proposal.

The Board of Education reserves the right to reject any and/or all bids in whole or in part and to waive any informalities therein. The Board of Education reserves the right to accept that bid which in its opinion, is in the best interest of the Owner.

Linda Blair