This Invitation for Bid (IFB) 96256-261 is issued by the Wicomico County Public Schools (WCPS) in Maryland for moving services on an on-call, as-needed basis. The work encompasses relocation of furniture, files, and file cabinets within and between WCPS office and school sites located in Wicomico County. The contract is structured as a Job Order Contract (JOC) that will establish one or more Master Agreements with qualified contractors. Formal bids must be received by January 14, 2026, at 2:00 PM EST via the Euna/Bonfire Procurement Portal. No site visits or bidders conferences are specified in the documents. Upon award, the initial contract period extends through February 28, 2029, with the Board retaining the right to renew for two additional one-year periods. Individual projects will be assigned through Task Order Requests (TORs) issued to contract holders, with scope of work, pricing, and schedules to be negotiated and formalized in purchase orders prior to work commencement.
Pricing for this contract is based on billable hourly labor rates for self-performed work (Mover, Supervisor, and Van), plus separate markups for miscellaneous materials, subcontractor services, and rental equipment. Bidders must provide daytime, evening, weekend, and holiday rates, with all rates not to exceed 1.5 times the daytime rate. No travel time is permitted. Bidders must submit cost information for a pre-defined sample project to determine the award. There are no Minority Business Enterprise (MBE) goals or set-asides applicable to this bid; however, WCPS reserves the right to establish MBE goals for individual task orders if required by funding sources. All qualified contractors are encouraged to respond. The Board may award this contract to multiple contractors to ensure availability. Bidders must have at least five years of successful contracting experience in the industrial/commercial field and in moving services, provide evidence of three comparable projects completed in the past five years, maintain specified insurance coverage (Workers Compensation, Commercial General Liability, and Business Automobile Liability), hold all required Maryland contractor licenses, and provide a Certificate of Good Standing from the State of Maryland. The contract allows the Board to utilize weekend and evening work hours as needed to avoid interruption of normal school operations, without additional compensation adjustments for these scheduling restrictions.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BID
96256-261
CONDITIONS AND SPECIFICATIONS
for
MOVING SERVICES
Purchasing Division purchasing@mywcps.org
Release Date: 12/11/2025 mailto:purchasing@mywcps.org
IFB 96256-261 MOVING SERVICES TOC -1
TABLE OF CONTENTS
BIDDING DOCUMENTS: The Bid Documents consist of the following:
00030 – Notice to Bidders
00090 – Instruction to Bidders
00100 – General Conditions
00110 – Supplementary Conditions
00111 – Technical Form of Bid Instructions
00200 – Scope of Work
00301 – Bid Form – Pricing
00330 – Bid Affidavit
Exhibit A – Project References
IFB 96256-261 MOVING SERVICES 00030-1
Rick Konrad Purchasing Manager
Business Support Services
NOTICE TO BIDDERS
MOVING SERVICES
It is the intention of WCPS to establish one or more Master Agreements for On-Call MOVING SERVICES to qualified contractors for use by WCPS on an as needed basis.
Description of Work: Work consists of, but may not be limited to, moving furniture, files, and cabinets both within and between sites within the Wicomico County School Board offices and school sites located in Wicomico County, Maryland.
Formal Bids will be received by Wicomico County Public Schools (“WCPS”) no later than January 14, 2026, by 2:00 PM EST.
Bids are to be delivered via Euna/Bonfire Procurement Portal at https://wicomicoschools.bonfirehub.com/portal/?tab=openOpportunities.
Vendors must register on the Euna/Bonfire site at https://vendor.bonfirehub.com/sign-up.
No Bidder may withdraw their Bid within ninety (90) days after the date and time of IFB opening.
WCPS may extend the time and place for the opening of Bids by notification via addendum published on the Procurement Portal.
WCPS reserves the right to reject any or all Bids and waive formalities, informalities, and technicalities therein. The WCPS reserves the right to contact a Respondent for clarifications and may, at its sole discretion, allow a Respondent to correct any and all formalities, informalities, and technicalities in the best interest of the WCPS.
WCPS reserves the right to utilize existing WCPS or cooperative contracts in the best interest of the WCPS.
All addenda will be posted on the Euna/Bonfire portal.
Rick D Konrad Rick D. Konrad, CPP Procurement Manager https://wicomicoschools.bonfirehub.com/portal/?tab=openOpportunities https://vendor.bonfirehub.com/sign-up https://wicomicoschools.bonfirehub.com/portal/?tab=openOpportunities
IFB 96256-261 MOVING SERVICES 00090-1
INSTRUCTIONS TO BIDDERS
1. CLARIFICATIONS: If any person who contemplates submitting an offer is in doubt as to the true meaning of any part of the Terms and Conditions, Bid Documents, and/or Invitation For Bid (IFB), they MUST submit a written request for an interpretation thereof, delivered to purchasing@mywcps.org with a cc to glathbury@mywcps.org no fewer than seven (7) working days prior to the time and date the offers are due. Answers will be provided via Addendum within three (3) working days of the solicitation deadline. No phone calls please.
WCPS will not be responsible for any other interpretations or explanations of the
Specifications that are not provided in writing via addendum.
2. EXCEPTIONS: It shall be the responsibility of the Contractor to include with their Bid a list and clarification of any deviations from or qualifications of the Terms and Conditions and Specifications. The list must be attached to the Bid Form - Price. Failure to provide a list of exceptions may result in the withdrawal of the award.
3. INTERPRETATION OF THE TERM "EQUAL": The Board of Education of Wicomico
County (WCPS) reserves the right to evaluate the quality of articles offered as alternate or equal, and reserves the right to reject any or all articles judged not equal.
4. DETERMINATION OF GRADE OR QUALITY: WCPS reserves the right to award an item to other than the lowest Bid if, in its judgment, there is sufficient reason to believe that another item is a better grade, quality or that it will better serve the interests of the WCPS, whether based on product samples, objective test, subjective test, or experience.
5. EVALUATION OF BIDS: The Procurement Manager may request additional documentation during the evaluation of Bids. This additional information may include, but is not limited to, the following:
A. Schedule of Values
B. List of sub-contractors
C. Evidence of licensing of the Prime contractor and sub-contractors
D. Evidence of insurance, bonding (if applicable)
6. BID SUBMISSIONS: All Bids must include the Bid Form included in the Bid Documents signed by an official capable of committing the offeror to contractual relationships.
A. Any Bid may be withdrawn prior to the Bid’s due date and time; however, all Bids are considered final after the date and time for receipt of Bids.
B. Final Bids may not be altered, withdrawn, or canceled, for a period of 90 days after the time and date designated for receipt of Bids.
mailto:purchasing@mywcps.org mailto:glathbury@mywcps.org
IFB 96256-261 MOVING SERVICES 00090-2
C. Bids must be delivered to the Purchasing Department via the submission portal mentioned in the Notice to Bidders.
D. Bid submissions WILL NOT be accepted through eMaryland Marketplace, fax, email, or regular mail.
7. ANTI-COLLUSION: By signing the Bid Forms, the Bidder understands that, in accordance with the Annotated Code of Maryland Finance and Procurement Article 11-205; a person who, for the purpose of defrauding the WCPS, acts in collusion with another person in connection with the procurement process is liable for damages.
8. ANTI-BRIBERY/DEBARMENT: This procurement is subject to the Annotated Code of
Maryland Finance and Procurement Article 16 concerning Debarment of Contractors. By signing this Form of Bid, the offeror agrees that they understand and are in compliance with Article 16.
9. POLITICAL CONTRIBUTION DISCLOSURE: Election Law Article, §§14-101—14-108, Annotated Code of Maryland, requires that every person that enters into contracts, leases, or other agreements with the State of Maryland, including its agencies or a political subdivision of the State, during a calendar year in which the person receives in the aggregate $100,000 or more shall file with the State Board of Elections a statement disclosing contributions in excess of $500 made during the reporting period to a candidate for elective office in any primary or general election.
10. ASBESTOS CONTAINING BUILDING MATERIALS: By submitting a Bid for this project, the Contractor agrees that no asbestos containing building materials will be used in this project by any contractor, sub-contractor, or sub-sub-contractor.
11. TOBACCO-FREE SCHOOLS POLICY: All contractors, sub- contractors, and sub-sub-contractors must comply with the WCPS's tobacco-free schools policy "ADC".
The policy states that "the sale or use of tobacco in any form is prohibited in all buildings and all outside seating areas owned or leased by the Board of Education of Wicomico County, at all times (24 hours a day, every day), regardless of whether or not students are present." The policy also states that "the use of tobacco in any form is prohibited on school grounds during the official school day (7 a.m. to 5 p.m.)."
Any contractors, sub-contractors, or sub-sub-contractors "which do not enforce this tobacco-free policy may be ... declared in default of their contract."
12. CHILD SEX OFFENDER NOTIFICATION: Maryland law requires certain child sex offenders to register with the local law enforcement agency. One of the purposes of this law, found in Article 17.792, is to inform school systems when a child sex offender is residing or working in the area. When the child sex offender registers, the local police are required to notify the Superintendent of Schools, and the Superintendent, in turn, is required to send a notice to school principals.
As a Contractor working for WCPS, we require that you do not employ convicted child sex offenders to work on projects for our school system if they, as a result, are required to perform delivery, installation, repair, construction or any other kind of services on WCPS property.
IFB 96256-261 MOVING SERVICES 00090-3
13. CRIMINAL BACKGROUND CHECK AND WORKER ASSIGNMENT:
A. Effective July 1, 2015, amendments to 6-113 of the Education Article of the Maryland Code further require that a contractor or subcontractor for a local school system may not knowingly assign an employee to work on school premises with direct, unsupervised, and uncontrolled access to children, if the employee has been convicted of, or pled guilty or nolo contendere to, a crime involving:
1) A sexual offense in the third or fourth degree under 3-307 or 3-308 of the
Criminal Law Article of the Maryland Code or an offense under the laws of another state that would constitute an offense under 3-307 or 3-308 of the Criminal Law Article if committed in Maryland.
2) Child sexual abuse under 3-602 of the Criminal Law Article, or an offense under the laws of another state that would constitute child sexual abuse under 3-602 of the Criminal Law Article if committed in Maryland; or
3) A crime of violence as defined in 14-101 of the Criminal Law Article, or an offense under the laws of another state that would be a violation of 14-101 of the Criminal Law Article if committed Maryland, including: (1) abduction; (2) arson in the first degree; (3) kidnapping; (4) manslaughter, except involuntary manslaughter; (5) mayhem; (6) maiming; (7) murder; (8) rape; (9) robbery; (10) carjacking; (11) armed carjacking; (12) sexual offense in the first degree; (13) sexual offense in the second degree; (14) use of a handgun in the commission of a felony or other crime of violence; (15) child abuse in the first degree; (16) sexual abuse of a minor; (17) an attempt to commit any of the crimes described in items (1) through (16) of this list; (18) continuing course of conduct with a child under 3-315 of the Criminal Law Article; (19) assault in the first degree; (20) assault with intent to murder; (21) assault with intent to rape; (22) assault with intent to rob; (23) assault with intent to commit a sexual offense in the first degree; and (24) assault with intent to commit a sexual offense in the second degree.
B. Also, effective July 1, 2015, amendments to 5-561 of the Family Law Article of the
Maryland Code mandate that each contractor and subcontractor shall require that any individual in its workforce must undergo a criminal background check if the individuals have direct unsupervised, and uncontrolled access to children.
14. BID AFFIDAVIT: In accordance with the State Procurement Regulation Mandatory
Written Solicitation Requirements, CoMar 21.505.08.07, this Bid requires a signed Bid Affidavit. This affidavit is attached to the Form of Bid. Submissions without this document may be considered non-responsive.
15. TAXES:
A. Nothing in these Terms and Conditions and Specifications shall be construed as relieving the Contractor of their responsibility in paying all applicable taxes.
B. Sales of materials used to improve the realty of government entities are taxable. The
Maryland Sales and Use Tax Exemption Certificate of the Wicomico County Board of Education should not be used by contractors performing such work.
IFB 96256-261 MOVING SERVICES 00090-4
16. MATERIALS:
A. Unless explicitly stated otherwise, all specified equipment and material comprising the work of this Contract, as being provided, furnished, or installed, shall imply the inclusion of all components, hardware, and accessories, required for complete installation and satisfactory operation as intended by the manufacturer. Wherever the method installation of any material is not explicitly specified, the installation shall be as recommended by the manufacturer.
B. Wherever in the Contract Documents it is provided that the Contractor shall furnish materials or equipment for which no detailed specifications are set forth, such materials or equipment shall be new and of the best grade for the respective purpose for which they will be used when incorporated in the work. Materials specified by reference to a number or symbol of a specific standard, such as A.S.M., Federal Specification, State Standard, Trade Association, or similar standards, shall comply with requirements in the latest revision thereof and any amendment or supplement in effect on the date of Bid opening.
C. None of the materials to be provided, furnished or installed on this project shall contain asbestos or any other "hazardous substance" as that term is defined by Federal or State law.
17. NONDISCRIMINATION:
A. NONDISCRIMINATION CLAUSE: In accordance with the Annotated Code of Maryland, State Finance and Procurement Article 13-219, discrimination on the basis of sex, race, age, color, creed, or national origin is prohibited under the terms of this contract by any contractor, sub-contractor, or sub-sub-contractor.
B. Contractors and sub-contractors are required to include similar notification in all sub-contracts for other than standard commercial supplies or raw materials and are required to post notice of this provision so that the notice will be available to the Contractor's and/or sub- contractor's employees and applicants.
18. MINORITY BUSINESS ENTERPRISE PROCEDURES:
A. The Wicomico County Public Schools encourages all qualified Minority Business Enterprises (MBE) to apply for certification with the Maryland Department of Transportation (MDOT).
B. All qualified MDOT Certified MBE’s are encouraged to respond to this solicitation notice.
C. WCPS encourages prime contractors submitting an offer to this IFB to develop a plan to utilize qualified MDOT certified MBE’s as sub-contractors.
END INSTRUCTIONS TO BIDDERS
IFB 96256-261 MOVING SERVICES 00100 - 1
GENERAL CONDITIONS
TABLE OF CONTENTS
1. DEFINITIONS
2. PROJECT MANAGER
3. CONTRACT DOCUMENTS
4. PRE-CONSTRUCTION CONFERENCE/PROGRESS MEETINGS
5. MASTER MANDATORY PROVISIONS
6. RESPONSIBILTY OF GENERAL CONTRACTOR/CONTRACTOR
7. REPORTING TO SCHOOL ADMINISTRATION
8. USE OF BOARD FACILITIES
9. SUBCONTRACTORS
10. GOVERNING LAW AND VENUE
11. CLAIMS AND DISPUTES
12. INSURANCE
13. CODES AND REGULATIONS
14. PERMITS/PUBLIC UTILITIES
15. PATENTS AND ROYALTIES
16. SAFETY AND FIRE PREVENTION
17. HAZARDOUS MATERIALS
18. TEMPORARY FACILITIES
19. SIGNS
20. TIME
21. CONSTRUCTION SCHEDULE
22. DELAYS AND TIME EXTENSIONS
23. LIQUIDATED DAMAGES
24. BOARD'S RIGHT TO TERMINATE THE CONTRACT
25. COORDINATION WITH OTHER CONTRACTS
26. SUBMITTALS: SHOP DRAWINGS, CUTS AND SAMPLES
27. PAYMENTS
28. MODIFICATIONS OF CONTRACT
29. HOLD HARMLESS
30. WARRANTY
IFB 96256-261 MOVING SERVICES 00100 - 2
31. USE OF COMPLETED PARTS OF THE WORK BEFORE ACCEPTANCE
32. CONTRACTOR’S GUARANTEE
33. PROTECTION OF WORK AND PROPERTY
34. DAMAGE
35. USE OF ROADWAYS AND WALKWAYS
36. EQUIPMENT TAGGING
37. TESTING
38. INSPECTION
39. CLEANUP
40. OPERATION AND MAINTENANCE MANUALS
41. AS - BUILT DRAWINGS
42. PROJECT COMPLETION
43. TRENCHING OR OTHER EXCAVATIONS
44. MISS UTILITIES CONTACT “811”
45. NEW UNDERGROUND UTILITIES
IFB 96256-261 MOVING SERVICES 00100 - 3
1. DEFINITIONS:
Addendum: Written change or revision to the Bidding Documents issued to the prospective Bidders prior to the time of receiving bids.
Alternate: The sum to be added to, or deducted from, the Base Bid if the change in scope of work as described in Alternates is accepted by the Board.
Board: Wicomico County Board of Education also WCBE and WCPS.
Furnish: Purchase and deliver to the site of installation.
Holidays: The following days are recognized for Holiday Rates as appropriate: New Year’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day.
Install: Fix in place of materials; and fix in place and connect for equipment.
Owner: Wicomico County Board of Education (aka Wicomico County Public Schools).
Project: Collectively, future Work is to be accomplished by the Contractor in satisfaction with a requirement or group of related requirements pursuant to one or more purchase orders or other ordering instruments.
Project Manager: The Owner will designate a Project Manager for each approved Task Order. The Project Manager will serve as the Owners Representative and may make decisions related to the order work on behalf of the Owner.
Secure: Obtain.
Task Order Request (TOR): a request for a proposal for a specific project under this Job Order Contract issued to one or more contract holders to provide a proposal.
Work: The labor, material, equipment, and services necessary or convenient to the completion of future Task Orders.
2. PROJECT MANAGER: ARCHITECT (ENGINEER) AND/OR PROJECT MANAGER:
A. PROJECT MANAGER: On any project arising out of this Master Job Order Contract, all project correspondence, approvals, coordination, and contract administration shall be conducted through the Board's Project Manager. The Project Manager shall have authority, as outlined in the Bidding Documents, to act as agent for the Board.
B. The Architect (Engineer) and/or Project Manager is responsible for the overall design of the Projects arising from this contract and the final authority in judgments of aesthetic consideration. The working drawings, technical specifications, sketches, and other data necessary to define the work covered by these Contract Documents have been prepared by the Architect (Engineer) and/or Project Manager.
IFB 96256-261 MOVING SERVICES 00100 - 4
C. The Architect (Engineer) and/or Project Manager shall visit, inspect, and observe the construction to determine general compliance with the Bidding Documents, and interpret the drawings and specifications consistent with their intent. They shall evaluate the shop drawings, samples and other submittals required in the technical specifications, and maintain an up-to-date log of all such items processed. The Architect (Engineer) and/or Project Manager will consult with the Board, Contractors, and any state, county or city agency having jurisdiction over the work whenever necessary to further the best interests of the Project.
D. Should any dispute arise respecting the true value of any work done, or any work omitted, or of any extra work which said second party may be required to do, or respecting the size of any payment to said second party during the performance of this contract, said dispute shall be decided by the Architect (Engineer) and/or Project Manager, and the decision of the latter shall be final and conclusive.
E. WCPS will establish the Architect (Engineer) and/or Project Manager on the Purchase Order unless identified in the Bidding Documents.
F. The project manager shall conduct all project correspondence, approvals, coordination, and contract administration. The Board's Project Manager shall have the authority, as outlined in the Bidding Documents, to act as an agent for the Board.
3. CONTRACT DOCUMENTS:
A. The Bidding Documents as modified by any addenda shall become the Contract
Documents upon award by the Board.
B. JOB ORDER CONTRACTS: On projects arising out of this contract a Scope of Work (Technical Specifications) will be established, and a Task Order Request (TOR) will be issued to one or more contractors to provide a written proposal for a specific project.
The TOR response will become part of the original contract and all aspects of the original contract documents are in force for any Task Order project awarded under this JOC.
C. The Contract Documents shall include the following: Bid Addenda, the completed Bid
Form and Pricing Sheets, insurance forms, the Invitation to Bidders, Instructions to Bidders, General Conditions, Supplementary Conditions, Scope of Work (Technical Specifications), Bidder's Questionnaire and any additional information required with the Bid Form.
Any Task Order, modification, amending, or extension of the work shall be as binding as if originally included in the Contract Documents.
D. The Contract Documents are complementary, and anything required by one shall be as binding as if required by all. In case of conflicts within the Contract Documents, the order of precedence of interpretation shall be those established in the Supplementary Conditions having priority. In case of conflict within the drawings, IFB 96256-261 MOVING SERVICES 00100 - 5 larger-scale drawings shall govern smaller-scale drawings, and written dimensions shall govern over scaled dimensions.
E. Upon award notice the Contract is in place and no other documents are required unless requested by WCPS.
4. PRE-CONSTRUCTION CONFERENCE/PROGRESS MEETINGS:
A. Upon award of a future Task Order the Project Manager may require a pre-construction conference and request additional meetings, drawings, and details that are required to serve WCPS.
B. The following Project Management documentation shall be provided upon request:
1) Project Schedule per General Conditions.
2) Schedule of Values with MBE firms indicated (if applicable).
3) Sub-contractor list with MBE firms indicated (if applicable).
4) All required licenses, insurance, and bonds (if applicable).
C. The Prime Contractor and all Sub-contractors shall be represented by individuals that are authorized to commit the necessary resources to provide their portion of the project.
Attendance at all Pre-construction and progress meetings are mandatory unless prior approval is obtained from the Project Manager.
D. Upon the completion of any Task Order project the Project Manager may complete a
Contractor Performance Evaluation. This evaluation will be shared with the contractor. The evaluation may be used as evidence of the contractor’s ability to successfully perform future WCPS contracts.
5. MASTER MANDATORY PROVISIONS:
A. Any material, item, or piece of equipment mentioned, listed, or indicated without a definition of quality shall be consistent with the quality of adjacent or related materials, items, or equipment.
B. Any method of installation, finish, or workmanship of an operation called for, without definition of standard of workmanship, shall be followed or performed and finished in accordance with good practice and consistent with adjacent or related installations.
C. Any necessary material, item, piece of equipment, or operation not called for but reasonably implied as necessary for proper completion of the work shall be furnished, installed or performed and finished and shall be consistent with adjacent or related materials, items, or pieces of equipment, and following good practice.
D. Names or numbered products are to be used according to the manufacturers' specifications, directions, or recommendations unless otherwise specified.
IFB 96256-261 MOVING SERVICES 00100 - 6
6. RESPONSIBILITY OF THE CONTRACTOR:
A. It shall be the responsibility of the Contractor to notify their sub-bidders at the time of request for bids on all portions of the Bidding Documents (future TORs) and any parts of other sections of specifications or plans that the Contractor intends to include as part of the subcontract.
B. All contact with students should be avoided.
C. The Contractor shall submit verification of a company-wide substance abuse policy upon written request by WCPS.
D. The Contractor shall be held strictly responsible for the proper performance of all work covered by the Contract, including the work performed by them and all their subcontractors.
E. The Contractor shall provide resumes, as part of any TOR submission, of
Superintendents and Project Managers that the bidder intends to assign to work on WCPS projects. Any changes thereafter must be submitted to the WCPS Project Manager for review and approval.
F. The Contractor shall perform all the work required by the Contract Documents and furnish all labor, materials, plant, equipment, tools, and appurtenances necessary to perform said work and complete it within the time specified.
The Contractor shall at all times perform the work of this Contract in a competent and workmanlike manner and, if not specifically stated, accomplish the work according to the best standards of construction practice.
G. SUPERVISION: The Contractor shall employ a full-time competent, English speaking, superintendent and necessary assistants who shall have complete authority to act for the Contractor on all matters pertaining to the work. The superintendent shall be on-site at all times and remain on-site, through the duration of the project. The contractor’s Project Superintendent and Project Manager must be accessible to the WCPS Project Managers by cell phone.
The superintendent shall be on-site 100% of the time and remain on-site, through the duration of the project, unless prior authorization is obtained from the Owner. The superintendent shall be satisfactory to the Owner and, if not satisfactory, shall be replaced by the Contractor with one that is acceptable. Also, the superintendent shall not be changed without the consent of the Owner unless the superintendent ceases to be employed by the Contractor.
H. Contractor shall make their own layout of lines and elevations and shall be responsible for the accuracy of both their and the subcontractors' work resulting there from. All dimensions affecting proper fabrication and installation of all contract work must be verified prior to fabrication by taking field measurements of the true conditions. The Contractor shall take and assist subcontractors in taking all field dimensions required in the performance of the work and shall verify all dimensions
IFB 96256-261 MOVING SERVICES 00100 - 7
and conditions on the site. If there are any discrepancies between dimensions in drawings and existing conditions which will affect the work, the Contractor shall bring such discrepancies to the attention of the Project Manager for adjustment before proceeding with the work. The Contractor shall be responsible for the proper fitting of all work and for the coordination of all trades, subcontractors and persons engaged upon this Contract.
I. Contractor shall do all cutting, fitting, or patching of their work that may be required to make its several parts come together properly and fit it to receive or be received by work of other contractors as shown, or reasonably implied by, the Drawings and Specifications for the completed structure, and he shall make good after that as the Project Manager may direct. Any cost caused by defective or ill-timed work shall be borne by the party responsible.
J. DEMOLITION: When applicable, the Contractor shall remove and legally dispose of all items except those identified by the Owner to be reinstalled, salvaged, or to remain the Owner's property.
7. REPORTING TO SCHOOL ADMINISTRATION:
A. AT THE BEGINNING OF A TASK ORDER AWARD, THE CONTRACTOR MUST
NOTIFY THE BOARD'S PROJECT MANAGER AT LEAST 48-HOURS PRIOR TO
ARRIVAL AT THE BOARD'S FACILITY, AND SCHEDULE THE ACTIVITIES.
B. ALL CONTRACTORS, VENDORS and/or EMPLOYEES, shall upon entering any
WCPS facility show proof of identification, sign-in and obtain a WCPS numbered Contractor Security Badge and/or visitor’s badge.
C. Upon the completion of the project, ALL Contractor Security Badges must be returned before final payment can be made. Contractors that can provide their own verifiable, managed security identification program MAY be exempt from this requirement. PRIOR approval by the WCPS Project Manager is required.
D. If the Contractor considers it necessary or desirable to work on Saturday, Sunday or a holiday, they shall so notify the Board at least forty-eight (48) hours before the commencement of such work to provide the Project Manager the time necessary to make arrangements to allow Contractor access to the building.
8. USE OF BOARD FACILITIES:
A. The Contractor, sub-contractor, and sub-sub-contractor shall confine their operation to those areas permitted and authorized by the Project Manager. The use of Board's facilities (toilets, restrooms, lunchrooms, dumpsters, etc.) and utilities are strictly prohibited unless previously authorized and approved by the Project Manager.
B. The Contractor, sub-contractor, sub-sub-contractor may park only in those areas designated by the Project Manager.
9. SUBCONTRACTORS:
IFB 96256-261 MOVING SERVICES 00100 - 8
A. Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and the Board. The Board shall be deemed to be the third-party beneficiary of the contract between the contractor and the subcontractor. If the Contractor does not specify a Subcontractor for any portion of the work to be performed under this Contract, they agree to perform that portion of the work with their own forces.
B. The Contractor shall not substitute any other person or firm as a Subcontractor, other than those listed in the Task Order proposal submitted by them, without the written approval of the Board.
The Board reserves the right of approval of all subcontractors proposed for use on this Project, and to this end, may require financial, performance and additional information as is needed to secure this approval. If a Subcontractor is not approved, the Contractor shall promptly submit another of the same trade for approval.
C. The Contractor shall insert appropriate provisions in all subcontracts pertaining to work on this Project requiring the Subcontractors to be bound by all applicable terms of the Contract Documents. The Contractor shall be as fully responsible for the acts and omissions of their Subcontractors and of persons either directly or indirectly employed by them as they are for the acts and omissions of persons directly employed by them.
10 GOVERNING LAW AND VENUE:
A. The bid shall be construed in accordance with and interpreted under the Laws of the State of Maryland. Any lawsuit arising out of such a bid shall be filed in the appropriate State Court of competent jurisdiction located in Wicomico County, Maryland.
11. CLAIM AND DISPUTES:
A. The Owner shall in no way be obligated to enter into mediation proceedings with a Contractor for any purpose whatsoever. The Owner will reserve unto itself the right to determine what form of litigation, and its locations are appropriate at the time the dispute arises.
12. INSURANCE:
A. The Contractor shall not commence work under this contract until they have obtained all insurance required under this Article and such insurance has been approved by the Owner.
B. The Contractor shall provide to the Purchasing Manager a current Certificate of
Insurance indicating the coverages below with their bid and they agree to maintain such insurance until the completion of the contract.
C. The minimum insurance coverages shall be:
IFB 96256-261 MOVING SERVICES 00100 - 9
1) Workmen's Compensation: The Contractor shall maintain throughout the life of the contract statutory Workers' Compensation, including Maryland benefits and employer's liability with limits of $100,000/$100,000/$500,000 for all of the Contractor's and any sub-contractor's employees who will be engaged in the work at the sites of the project.
2) Commercial General Liability: The Contractor shall establish and maintain throughout the life of the contract Commercial General Liability Insurance - $2,000,000 each occurrence/general aggregate covering all premises and operations and including Personal Injury, Completed Operations, Contractual Liability and where applicable to the project as determined by the Purchasing Agent, Products and Independent Contractors. The general aggregate limit is to apply per project; and
3) Business Automobile Liability: $2,000,000 Combined Single Limit (Owned, non-owned, and hired).
D. The Board requires a forty-five (45) day notice, in writing, of cancellation, non-renewal or change in insurance coverage affecting this project. This written notice shall be furnished by the Contractor's insurance carrier(s) or insurance agent(s) to the Board's Purchasing Agent.
E. All bidders will have a current Certificate of Insurance (ACORD certificates) on file in the Purchasing Office at the time of the bid opening or included with the bid. Failure to provide the ACORD certificate may result in the bidder's offer being considered non-responsive.
F. The Board (including its elected or appointed officials, agents, and employees) is to be named as an additional insured in the Contractor's General Liability Policy.
Coverage must be primary with respect to the Board, its agents, and employees.
13. CODES AND REGULATIONS:
A. The Contractor shall be knowledgeable of and comply with all codes, ordinances, regulations, or orders of properly constituted authority having jurisdiction over the work of this project. The Contractor shall examine the Contract Documents for compliance with these codes and regulations, and he shall promptly notify the Project Manager of any discrepancies. Changes in the drawings and specifications shall be made only by means of change orders, or modifications approved by the Board. Change order procedures shall be as described elsewhere in these Contract Documents. The contractor shall keep a copy of all applicable Code of Regulations at the job site at all times.
B. All work and materials shall be in full accordance with the latest rules and regulations and other applicable State laws or regulations. Nothing in these plans or specifications is to be construed to permit work not conforming to these Codes.
1) Buildings and/or all other construction covered by this Contract shall meet all the regulations for access by physically handicapped.
IFB 96256-261 MOVING SERVICES 00100 - 10
14. PERMITS/PUBLIC UTILITIES:
A. The Contractor shall obtain and pay for all permits, fees, licenses, and inspections that are required in order to perform the work under this Contract. The Board shall pay connection charges and meter costs for new permanent utilities required by these Contract Documents.
B. The Contractor shall notify Board sufficiently in advance to submit requests for service to the appropriate utility companies so as to ensure connections or installation of utility services in accordance with the Project schedule.
15. PATENTS AND ROYALTIES: The Contractor shall pay for all royalties and patents and shall defend all suits or claims for infringement on any patent right and shall save the Board harmless from loss of account thereof.
16. SAFETY AND FIRE PREVENTION:
A. OCCUPATIONAL SAFETY AND HEALTH ACTS: Contractor(s) who perform any work under this contract shall fully comply with the provisions of the Federal Occupational Safety and Health Act of 1970 and any amendments thereto and regulations pursuant to the act, and also to the Maryland Occupational Safety and Health Act, Article 89, Sections 28 to 49A inclusive, Annotated Code of Maryland, as amended by Chapter 59, Laws of Maryland 1973 and any regulations pursuant thereto.
B. The Contractor shall provide proof of safety training programs for all employees to be used on any WCPS project and disclosure of the bidder’s safety EMR (Experience Modification Rate).
C. The Contractor shall take thorough precautions at all times for the protection of persons and property and shall be liable for all damages to persons or property, either on or off the site, which occur as a result of their prosecution of the work. The Contractor shall obtain permits for, install and maintain in safe condition barricades, walkways, fences, railings, and whatever other safeguards that may be necessary to protect persons and property from damage as a result of the construction under this Contract.
D. Contractor shall not endanger any work by cutting, excavating, or otherwise altering the work and shall not cut or alter the work of any other Contractor except with the consent of the Project Manager, nor overload any new or existing structures by the placing or storage of materials, equipment, or other items thereon, and if necessary, provide calculations proving the safety in so doing.
E. If it is necessary to work at night, or where daylight is obscured, the Contractor shall provide and maintain lighting of adequate level to properly prosecute the work and to permit thorough inspection of same.
F. Contractor shall take extraordinary care to prevent fires and keep all flammable materials and oily rags in tightly closed metal containers. Contractor should exercise
IFB 96256-261 MOVING SERVICES 00100 - 11
particular care when welding or cutting, and with regard to the disposition of waste materials, the nature and quantity of which might create or increase a fire hazard.
G. The Contractor and Subcontractors shall comply with Sections 6360, et. seq. of the Labor Code, together with Title 22 with regard to hazardous substances in the workplace. The Contractor and each Subcontractor shall supply to their employees and, where site is occupied, to Board, copies of Material Safety Data Sheets (MSDS) for hazardous substances that may be used in the course of the work, together with notice of actual hazardous substances to which employees may be exposed while performing work and appropriate protective measures.
17. HAZARDOUS MATERIALS:
A. This contract does not include the removal, handling, or disturbance of any hazardous substances or materials encountered in the new construction or on the project grounds. If such substances or materials are encountered, work shall cease in that area and the Board shall be notified to take appropriate action for removal or otherwise abating the condition in accordance with current regulations applicable to the Board.
B. All contractors performing work on Board of Education premises are required to make themselves aware of the locations of asbestos containing building materials that exist on the work site. Board personnel can supply such information prior to commencement of work.
1) General:
a) No asbestos, asbestos containing products or other hazardous materials shall be used in this construction or in any tools, devices, clothing, or equipment used to affect this construction.
b) Asbestos and/or asbestos containing products shall be defined as all items containing but not limited to chrysotile, crocidolite, amosite, anthophyllite, tremolite and actinolite.
c) Any or all material containing greater than one-tenth of one percent (> .1%) asbestos shall be defined as asbestos-containing material.
d) Any disputes involving the question of whether or not material contains asbestos shall be settled by electron microscopy; the costs of any such tests shall be paid by the contractor.
e) All work or materials found to contain asbestos, or work or material installed with asbestos containing equipment will be immediately rejected and this work will be removed at no additional cost to the Owner.
2) Decontamination and Removal of hazardous material from prior work:
a) Decontamination and removal of work found to contain asbestos, or work installed with asbestos containing equipment shall be done only under the supervision of a qualified consultant, knowledgeable in the field of asbestos abatement and accredited by the Environmental Protection Agency.
IFB 96256-261 MOVING SERVICES 00100 - 12
b) The asbestos removal contractor shall be an EPA accredited contractor qualified in the removal of asbestos and shall be chosen and approved by the asbestos consultant who shall have sole discretion and final determination in this matter.
c) The asbestos consultant shall be chosen and approved by the Board, which shall have sole discretion and final determination in this matter.
d) The work will not be accepted until asbestos contamination is reduced to levels deemed acceptable by the asbestos consultant.
e) Cost of all asbestos removal from prior work, including but not necessarily limited to the cost of the asbestos removal contractor, the cost of the asbestos consultant, analytical and laboratory fees, time delays, and additional costs as may be incurred by the Board and/or its agent(s) shall be borne entirely by the Board.
3) Hold Harmless:
a) Interface of work under this contract with work containing asbestos shall be executed by the Contractor at their risk and at their discretion with full knowledge of the currently accepted standards, hazards, risks, and liabilities associated with asbestos work and asbestos containing products. By execution of this contract the Contractor acknowledges the above and agrees to hold harmless the Owner, their employees, agents and assigns for all asbestos liability which may be associated with this work and agrees to instruct their employees with respect to the above mentioned standards, hazards, risks and liabilities.
b) The Contractor shall, prior to commencement of this work, provide a duly signed and notarized affidavit that they have instructed their employees with respect to the above-mentioned standards, hazards, risks and liabilities and the contents and requirements of this portion of the contract documents.
4) Certification:
The Contractor agrees that materials containing asbestos or other hazardous materials as defined in Federal and State law, shall not be used in construction and will provide prior to final payment a notarized affidavit stating that no asbestos containing building materials or other hazardous materials as defined in Federal and State law were installed during the project by themselves, their sub-contractors, or sub-sub-contractors.
18. TEMPORARY FACILITIES:
A. The Contractor shall obtain permits for, install and maintain in safe condition whatever scaffolds, hoisting equipment, barricades, walkways, or other temporary structures which may be required to accomplish the work. Such structures shall be adequate for the intended use and capable of safely accepting all loads that may be imposed upon them. They shall be installed and maintained in accordance with all applicable state and local codes and regulations.
IFB 96256-261 MOVING SERVICES 00100 - 13
B. The Contractor shall provide and maintain temporary heat from an approved source whenever in the course of the work it may become necessary for curing, drying, or warming spaces as may be required for the installation of materials or finishes. The Contractor shall provide and maintain any and all facilities that may be required for dewatering in order that work may proceed on the project. If it is necessary for dewatering to occur continually, the Contractor shall have on hand whatever spare parts or equipment that may be required to avoid interruption of service.
C. The Contractor shall promptly remove all such temporary facilities when they are no longer needed for the work or on completion of the project. The Contractor shall repair any damage to premises or property which resulted from the construction, use, or removal of temporary facilities and shall restore said premises and property to their original condition.
19. SIGNS: No signs may be displayed on or about the Board's property (except those which may be required by law) without the Board's specific approval of size, content, and location. Any signs required by the Board will be designated in the scope of work.
20. TIME:
A. It shall be understood that time is of the essence of the Contract, and the Contractor must prosecute the work diligently and regularly at such a rate of progress as to ensure completion of this Project within, or sooner than, the time specified. The Contractor shall commence the work on the date indicated in the Notice to Proceed, and he agrees to complete all work described by the Contract Documents within, or sooner than, the number of calendar days required in the Contract.
B. The Contractors and Subcontractors shall investigate and become aware of the amount of time required for the delivery of all equipment and materials required to perform the work under this Contract, and no extension of time shall be granted due to failure to order said equipment and materials sufficiently before their incorporation into the work so as to avoid delay to the Project.
C. The Contractors and Subcontractors shall provide and maintain enough workforce, materials, and equipment to ensure a rate of construction progress that will complete the Project within or sooner than the time specified and according to the schedule of work. If, in the Project Manager's opinion, the Contractor and/or their Subcontractors are not prosecuting the work at a sufficient rate of progress to meet the Project schedule, the Board may direct the Contractor to provide additional manpower, materials or equipment, or to work additional hours, holidays or weekends without additional cost to the Board until the work is progressing in a manner satisfactory to the Board. Failure to prosecute the work in a timely manner and according to the Project schedule is considered a breach of Contract and is cause for termination of the Contract according to the Article on "BOARD'S RIGHT TO TERMINATE
CONTRACT."
21. CONSTRUCTION/PROJECT SCHEDULE:
A. Within fifteen (15) calendar days after the Award of Contract, the Contractor shall
IFB 96256-261 MOVING SERVICES 00100 - 14
prepare and submit to the Project Manager, for approval, a construction schedule showing in detail how the Contractor plans to prosecute the work. The schedule shall include the work of all trades necessary for the construction of the Project, material delivery dates and shall be sufficiently complete and comprehensive to enable progress to be monitored on a day-by-day basis. The information for each activity shall include as a minimum the activity description, duration, start date and completion date.
B. The Contractor shall take care in the preparation of the schedule to ensure that it represents an accurate and efficient plan for accomplishing the work. If the Project is more than one week ahead of or behind schedule, it must be revised showing how the Contractor plans to complete the work, but in no case shall it show a completion date later than that required by the Contract, unless time extensions have been granted. The current schedule shall be kept posted in the Contractor's project office on site.
C. The Contractor shall be responsible for the coordination of all work necessary and pertaining to the construction whether actually a part of this Contract or attendant thereto. The Contractor shall notify the Owner and various utility companies, as far as possible in advance of their required work, in order that work schedules may be developed for all concerned, which will permit the most effective accomplishment of the entire project.
22. DELAYS AND TIME EXTENSIONS:
A. The Contractor may be granted a time extension if they encounter an unavoidable delay of the work due to causes completely beyond their control and which they could not have avoided by the exercise of more care, prudence, foresight, and diligence. Causes for which a claim for extension of time may be made are acts of the public enemy, acts of another Contractor in the performance of another contract with the Board, fire, flood, violent wind storm, epidemic, quarantine restriction, strike, freight embargo, or weather of an unusually severe nature. The Contractor will not be granted time extensions for weather conditions which are normal for the location of the Project, according to the U. S. Weather Bureau Records.
B. A request for extension of time shall be made in writing to the Project Manager within ten (10) calendar days of the date the delay is encountered and shall include a detailed description of the reasons for the delay and corrective measures by the Contractor. In order for the Project Manager to consider a request for time extension, the Contractor must prove that the reasons stated for a delay actually caused a delay in portions of the work which will result in completion beyond the date specified in the Contract. The Contractor may be granted a time extension for a significant change in the scope of work which request for extension of time shall be included in a Contract Modifications Proposal.
C. No damages or compensation or any kind shall be paid to a Contractor because of delays in the progress of work, whether such delays be avoidable or unavoidable that are not the responsibility of Board. Board's liability to Contractor for delays for which Board is responsible shall be limited to an extension of time for delays unless
IFB 96256-261 MOVING SERVICES 00100 - 15
such delays were unreasonable under the circumstances involved and were not within the contemplation of the parties when the contract was awarded. The Project Manager shall determine the actual costs to Contractor for which the Contractor may claim damages from Board. Such costs, if any, shall be directly related to the project, and shall not include costs that would be borne by the Contractor in the regular course of business, including, but not limited to, office overhead and ongoing insurance costs. The Board shall not be liable for any damages which the Contractor could have avoided by any reasonable means including, but not limited to, the judicious handling of forces, equipment, or plant.
D. The granting of an extension of time because of unavoidable delays shall in no way operate as a waiver on the part of the Board of the right to collect liquidated damages for other delays or of the right to collect other damages or of any other rights to which the Board is entitled.
23. LIQUIDATED DAMAGES:
A. When applicable the Daily Rate will be stated in the Section 00110 – Supplementary Conditions or in a future Task Order Request.
B. Should the Contractor fail to complete this Contract within the time fixed for completion, together with extensions granted by the Board for unavoidable delays, they shall become liable to the Board in the amount specified in the Contract per calendar day for each day said Contract remains uncompleted beyond the time for completion, as and for liquidated damages and not as a penalty. Contractor shall not be charged with liquidated damages when the delay in completion of the work beyond this time for completion is due to acts of the Board. It is expressly stipulated and agreed by Contractor and Board that it would be impractical and extremely difficult to fix the actual amount of damages.
C. Any money due or to become due the Contractor may be retained to cover said liquidated damages.