This document is a mechanical systems design specification and bidding package for the Clinical Laboratory and Pharmacy Building (Project 13-127) located in Prescott, Arizona, prepared for the Department of Veterans Affairs.

The specifications establish comprehensive requirements for the mechanical contractor to furnish and install complete HVAC, piping, and control systems. Key deliverables include air handling units (AHU-1 through AHU-4), variable air volume (VAV) boxes, exhaust fans, humidification systems, steam pressure reducing stations, chilled water and hot water distribution piping, condensate pumps, glycol makeup units, and building automation controls. Design conditions specify indoor temperatures of 73°F with 25% relative humidity for winter operation and 73°F with 30% relative humidity for summer operation, with outdoor design based on Prescott, Arizona weather data. The contractor must perform system balancing through an independent AABC/NEBB-certified balancing contractor, submit shop drawings for approval prior to installation, provide as-built drawings in reproducible form, conduct equipment startup and operator training, and guarantee all work and materials per specification requirements. All work must comply with current federal building codes, ASHRAE standards, local utility requirements, and OSHA safety provisions. The contractor bears responsibility for all permit fees, plan review fees, licenses, inspections, and taxes. Ductwork must meet SMACNA construction standards with specified leakage rates based on system pressure classifications. The project includes future provisions for expanded cytology and histology laboratories with capped ductwork and piping stub-outs. Bid submission deadline was December 3, 2015, with the project designated as 100% bid document revision 1.

View the file

Other files

File Type Posted
10-B162 Controls3.pdf PDF
7- Chiller Plant System Drawing.pdf PDF
6-B162 Controls1.pdf PDF
8-B158 Mechanical Schedules.pdf PDF
2- 70-M-601.pdf PDF
5-B158 HVAC Layout.pdf PDF
4-2016_649-409_162_Mechanical.pdf PDF
3- 70-M-602.pdf PDF
9-B162 Controls2.pdf PDF
CS RFQ- Delta BAS Enteliweb- 36C26226Q1025- Unrestricted.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LEGEND MECHANICAL GENERAL NOTES

A. READING AND TESTS OF ALL AIR DEVICES SHALL INCLUDE REQUIRED

VELOCITIES (FPM), TEST RESULTANT VELOCITIES, REQUIRED

CAPACITIES (CFM) AND TEST RESULTANT CAPACITIES AFTER

ADJUSTMENTS.

B. IDENTIFY EACH AIR DEVICE BY LOCATION. TYPE AND SIZE.

C. TEST AND ADJUST EACH AIR DEVICE TO WITHIN 10% OF DESIGN.

MECHANICAL CONTRACTOR SHALL FURNISH AND INSTALL A COMPLETE

TEMPERATURE CONTROL SYSTEM.

ALL THERMOSTATS SHALL BE MOUNTED AT +54" ABOVE FINISHED

FLOOR (UNLESS OTHERWISE SPECIFIED). THERMOSTATS SHALL NOT

INTERFERE WITH SHELVING, VENDING MACHINES, OTHER FIXTURES OR

CONTROLS.

ALL WORK SHALL BE DONE IN ACCORDANCE WITH ALL CURRENT

FEDERAL BUILDING CODES, REGULATIONS, AND REQUIREMENTS, LOCAL

UTILITY COMPANY REQUIREMENTS, AND ASHRAE STANDARDS.

THIS CONTRACTOR SHALL PAY ALL PERMIT FEES, PLAN REVIEW FEES,

LICENSE FEES, INSPECTIONS, AND TAXES APPLICABLE TO THEIR DIVISION

AND SHALL BE INCLUDED IN THE BASE BID AS PART OF THEIR CONTRACT.

THIS CONTRACTOR SHALL BE LICENSED, BONDED, INSURED, AND CAPABLE

OF PERFORMING QUALITY WORKMANSHIP. THIS CONTRACTOR GUARANTEES

ALL OF HIS WORK AND MATERIALS FOR THE PERIOD AS REQUIRED IN THE

SPECIFICATIONS. FROM FINAL ACCEPTANCE BY THE OWNER/COR.

THIS CONTRACTOR SHALL ESTABLISH SAFE WORKING PROCEDURES FOR

THE PROTECTION OF THE WORKMEN IN ALL PHASES OF WORK, COMPLYING

WITH ALL APPLICABLE PROVISIONS OF CITY, STATE, AND FEDERAL SAFETY

LAWS (OSHA) AND AS RECOMMENDED IN THE "MANUAL OF ACCIDENT

PREVENTION IN CONSTRUCTION" AS ISSUED BY THE ASSOCIATION OF

GENERAL CONTRACTORS OF AMERICA, IN., 20TH AND E. STREETS, N.W.

WASHINGTON, D.C.

THIS CONTRACTOR IS RESPONSIBLE FOR SCHEDULING THE PURCHASE,

DELIVERY, RECEIVING, UNLOADING, UNCRATING, STORING, SETTING IN

PLACE, AND PROTECTING ALL NEW EQUIPMENT FURNISHED BY THIS

CONTRACTOR AND EQUIPMENT FURNISHED BY OWNER FROM DAMAGE BY

VANDALISM AND WEATHER DURING CONSTRUCTION.

THIS CONTRACTOR SHALL SUBMIT SHOP DRAWINGS AS REQUIRED IN THE

SPECIFICATIONS PRIOR TO THE START OF INSTALLATION FOR OWNER /

COR APPROVAL AND THE SUCCESSFUL REVIEW BY THE ARCHITECT

***ENGINEER***.

THIS CONTRACTOR SHALL FURNISH AS-BUILT DRAWINGS TO THE

OWNER BEFORE FINAL PAYMENT WILL BE ISSUED. THE AS-BUILT

DRAWINGS SHALL BE SUBMITTED IN REPRODUCIBLE FORM.

THIS CONTRACTOR SHALL BE RESPONSIBLE FOR THE STARTUP OF

ALL HEATING, VENTING, AND AIR-CONDITIONING EQUIPMENT.

THIS CONTRACTOR SHALL PROVIDE A COMPETENT OPERATING

TECHNICIAN TO INSTRUCT THE OWNER IN THE OPERATION AND

MAINTENANCE OF THE NEW EQUIPMENT.

UPON COMPLETION OF THE WORK, THIS CONTRACTOR SHALL

REVIEW AND CHECK THE ENTIRE PORTION OF WORK, CLEAN

EQUIPMENT AND DEVICES. REMOVE SURPLUS MATERIALS AND

RUBBISH FROM THE PROPERTY AND LEAVE THE WORK IN NEAT AND

CLEAN ORDER AND IN COMPLETE WORKING CONDITION. EACH

RESPECTIVE CONTRACTOR SHALL BE RESPONSIBLE FOR THE

REMOVAL OF ANY CARTONS, DEBRIS, EQUIPMENT, ETC. INSTALLED

BY THIS CONTRACTOR INCLUDING EQUIPMENT FURNISHED BY

OTHERS AND UNPACKED OR REMOVED FROM CARTONS BY THIS

CONTRACTOR.

THIS CONTRACTOR SHALL REVIEW ENTIRE SET OF CONTRACT DOCUMENTS: INCLUDING BUT

NOT NECESSARILY LIMITED TO ALL ARCHITECTURAL, ALL STRUCTURAL, ALL MECHANICAL,

ALL PLUMBING, ALL FIRE PROTECTION, ALL ELECTRICAL DRAWINGS AND ENTIRE PROJECT

MANUAL. THIS CONTRACTOR SHALL ACKNOWLEDGE AND INCLUDE IN THE SCOPE OF WORK

(CONTRACT) ALL CONDITIONS PERTINENT TO THE COMPLETION OF HIS WORK. THIS

CONTRACTOR SHALL FULLY COORDINATE HIS WORK WITH THE INSTALLATION OF WORK BY

OTHER TRADES AND MAKE NECESSARY FIELD ADJUSTMENTS AS REQUIRED TO

ACCOMODATE THE INSTALLATION. ALL OF THE ABOVE SHALL BE INCLUDED IN THE SCOPE

OF WORK AT NO ADDITIONAL CHARGE TO THE OWNER.

THIS CONTRACTOR SHALL CAREFULLY EXAMINE THE DRAWINGS AND SPECIFICATIONS,

VISIT THE SITE OF THE WORK AND FULLY INFORM THEMSELVES AS TO ALL CONDITIONS

AND MATTERS THAT CAN, IN ANY WAY, AFFECT THE WORK OR THE COST THEREOF.

SHOULD THIS CONTRACTOR FIND DISCREPANCIES IN, OR OMISSIONS FROM THE

DRAWINGS, SPECIFICATIONS OR OTHER DOCUMENTS, OR BE IN DOUBT AS TO THEIR

MEANING, NOTIFY THE OWNER AND THE ARCHITECT AT ONCE, IN WRITING, OF ANY

DISCREPANCIES BETWEEN EXISTING CONDITIONS AND NEW WORK, OR BETWEEN THEIR

WORK AND THE WORK OF THEIR TRADES AND OBTAIN CLARIFICATION PRIOR TO

SUBMITTING ANY BID. LACK OF SUCH NOTIFICATION SHALL BE CONSTRUED AS TO

INDICATE NO DISCREPANCIES WILL NOT BE GRANTED AFTER THE AWARD OF CONTRACT

FOR ANY WORK REQUIRED TO COMPLY WITH THESE REQUIREMENTS.

THE DRAWINGS INDICATE DIAGRAMMATICALLY THE INTENT, GENERAL CHARACTER,

REQUIREMENTS AND LOCATION OF THE WORK SHOWN AND INCLUDED. THE

WORK INDICATED BUT HAVING MINOR DETAILS OBVIOUSLY OMITTED SHALL BE

PROVIDED AT NO ADDITIONAL COST TO THE OWNER.

THIS CONTRACTOR IS REQUIRED TO BID, AS SPECIFIED, ON THE DRAWINGS

WITHOUT DEVIATION. THIS CONTRACTOR IS INVITED TO SUBMIT SUBSTITUTIONS

FROM THE BASE BID, ONLY IF THE SUBSTITUTIONS ARE APPROVED BY THE

OWNER / COORDINATE AND SUCCESSFULLY REVIEWED BY THE ARCHITECT,

PRIOR TO SUBMITTING THE BID.

IT IS THE INTENT OF THESE DOCUMENTS THAT THE MECHANICAL

CONTRACTOR PROVIDE ALL LABOR, MATERIAL, EQUIPMENT AND TOOLS FOR

THE COMPLETE INSTALLATION OF ALL WORK SHOWN ON THE PLANS AND/OR

DESCRIBED HEREIN, INCLUDING ALL DEVICES, CONTROLS AND

APPURTENANCES REQUIRED TO SET NEW SYSTEMS INTO OPERATION.

SHOULD CONDITIONS NECESSITATE ANY REARRANGEMENTS, OR IF

DUCTWORK CAN BE RUN TO BETTER ADVANTAGE, PREPARE AND SUBMIT

SHOP DRAWINGS SHOWING THE CHANGES BEFORE PROCEEDING WITH THE

WORK. IF SUCH CHANGES ARE APPROVED BY THE OWNER AND

SUCCESSFULLY REVIEWED BY THE ARCHITECT, THEY SHALL BECOME A PART

OF THE CONTRACT AFTER THEIR APPROVAL.

THIS CONTRACTOR SHALL VERIFY ALL MOUNTING, ALL ARRANGEMENTS,

HEIGHTS AND LOCATIONS PRIOR TO ROUGH-IN. ANY MENTION OF A SPECIFIC

MOUNTING ARRANGEMENT, WEIGHT OR LOCATION SHALL NOT RELIEVE THE

CONTRACTOR OF THE RESPONSIBILITY TO VERIFY THE SPECIFIC

REQUIREMENT FURNISHED OR THE OTHER TRADES WORKING IN THE SAME

AREA. NO ADDITIONS TO THE CONTRACT SUM WILL BE PERMITTED FOR ITEMS

INSTALLED IN WRONG LOCATIONS, IN CONFLICT WITH OTHER WORK, ETC.

AN INDEPENDENT BALANCING CONTRACTOR SHALL BE A SUBCONTRACTOR

OF THE MECHANICAL CONTRACTOR AND SHALL BE RESPONSIBLE FOR

BALANCING ALL NEW AND EXISTING DUCTWORK SYSTEMS RELATED TO THE

PREMISES. SUCH BALANCING SHALL BE PERFORMED BY A MEMBER OF THE

ASSOCIATED AIR BALANCE COUNCIL AND NATIONAL ENVIRONMENTAL

BALANCING BUREAU. SUBMIT THE REQUIRED COPIES OF THE AIR BALANCING

REPORT TO THE OWNER FOR APPROVAL AND SUCCESSFUL REVIEW BY THE

ARCHITECT. CONTAINING THE FOLLOWING INFORMATION:

N CONSTRUCTION NOTE

A

B

VIEW CALLOUT

A = VIEW NUMBER

B = SHEET NUMBER

A

B-C

AIR TERMINAL TAG

A = AIR TERMINAL TYPE AND NECK SIZE

B = AIRFLOW

C = FLOW DIRECTION (S=SUPPLY, R=RETURN,

E=EXHAUST, T=TRANSFER)

A

B

MECHANICAL EQUIPMENT TAG

A = EQUIPMENT TYPE

B = EQUIPMENT NUMBER

ACFM ACTUAL CUBIC FEET PER MINUTE

AFF ABOVE FINISHED FLOOR

AFMD AIR FLOW MEASURING DEVICE

AHU AIR HANDLING UNIT

APD AIR PRESSURE DROP

AS AIR SEPARATOR

BC BOOSTER COIL

CD CONDENSATE DRAIN

CHWR CHILLED WATER RETURN

CHWS CHILLER WATER SUPPLY

CP CONDENSATE PUMP

CUH CABINET UNIT HEATER

CV CONSTANT VOLUME, CONTROL VALVE

DEG DEGREE

EA EXHAUST AIR

EAT ENTERING AIR TEMPERATURE

EAV EXHAUST AIR VALVE

EF EXHAUST FAN

ESP EXTERNAL STATIC PRESSURE

ET EXPANSION TANK

EWT ENTERING WATER TEMPERATURE

EX EXISTING

GMU GLYCOL MAKEUP UNIT

HUM HUMIDIFIER

HWR HOT WATER RETURN

HWS HOT WATER SUPPLY

HX HEAT EXCHANGER

LAT LEAVING AIR TEMPERATURE

LPS LOW PRESSURE STEAM

LWT LEAVING WATER TEMPERATURE

MA MIXED AIR

MD MOTORIZED DAMPER

MPS MEDIUM PRESSURE STEAM

OA OUTSIDE AIR

PC PUMPED CONDENSATE

PG PROPYLENE GLYCOL

PHWR PREHEAT WATER RETURN

PHWS PREHEAT WATER SUPPLY

PRV PRESSURE REGULATING VALVE

RA RETURN AIR

RO REVERSE OSMOSIS

RF RETURN FAN

SA SUPPLY AIR

SAV SUPPLY AIR VALVE

SF SUPPLY FAN, SQUARE FEET

ST STEAM TRAP

UH UNIT HEATER

VAV VARIABLE AIR VOLUME

VD VOLUME DAMPER

WPD WATER PRESSURE DROP

A

B

ROOM TAG

A = ROOM NAME

B = ROOM NUMBER

GENERAL TAGS AND IDENTIFICATION

COMMON ABBREVIATIONS

DUCTWORK

CEILING SUPPLY DIFFUSER

CEILING RETURN/TRANSFER REGISTER

CEILING EXHAUST REGISTER

CONICAL TAKEOFF

FIRE DAMPER

FLEXIBLE DUCTWORK

RADIUS ELBOW

MITERED ELBOW

SUPPLY AIR DUCT TURNING UP

SUPPLY AIR DUCT TURNING DOWN

RETURN AIR OR TRANSFER AIR DUCT TURNING UP

RETURN AIR OR TRANSFER AIR DUCT TURNING DOWN

EXHAUST AIR DUCT TURNING UP

EXHAUST AIR DUCT TURNING DOWN

AxB C"Ø DUCT SIZE (RECTANGULAR/FLAT OVAL AND ROUND)

MOTORIZED DAMPER

VOLUME DAMPER

45 DEGREE BEVELED TAKEOFF

PIPING

TEE

CAPPED PIPE

PIPE SIZE A AND

DESIGNATION BA" B

PIPE CONTINUATION

ISOLATION VALVE

BALL VALVE

BUTTERFLY VALVE

GLOBE VALVE

GATE VALVE

BALANCING VALVE

2 WAY MOTORIZED VALVE

PRESSURE REDUCING VALVE

TRIPLE DUTY VALVE

CHECK VALVE

STRAINER WITH BALL VALVE

PIPE UP

PIPE DOWN

THERMOMETER

PRESSURE GAUGE

STEAM TRAP

TEST PLUG

PRESSURE SAFETY VALVE

UNION

POINT OF CONNECTION (NEW WORK)

POINT OF DISCONNECTION (DEMO WORK)

FLOW DIRECTION

COMMON EQUIPMENT

SINGLE DUCT VAV BOX

SINGLE DUCT VAV BOX WITH REHEAT COIL

VENTURI AIR VALVE

UNIT HEATER

CABINET UNIT HEATER

INLINE PUMP

AIR SEPARATOR

VARIABLE FREQUENCY DRIVE

CONTROLS

AI ANALOG INPUT (TO PANEL)

AO ANALOG OUTPUT (OUT OF PANEL)

BI BINARY INPUT (TO PANEL)

BO BINARY OUTPUT (OUT OF PANEL)

C COMMON

NC NORMALLY CLOSED

NO NORMALLY OPEN

P STATIC PRESSURE SENSOR

S SENSOR

M MOTORIZED AIR DAMPER PARALLEL BLADE

M MOTORIZED AIR DAMPER OPPOSED BLADE

DP DIFFERENTIAL PRESSURE SENSOR

MS MOTOR STARTER

VFD VARIABLE FREQUENCY DRIVE

SD DUCT SMOKE DETECTOR

CT CURRENT TRANSMITTER

FZ FREEZE STAT

T TEMPERATURE SENSOR

T H/C

THERMOSTAT-HEATING AND COOLING

T C

THERMOSTAT-COOLING ONLY

T V

THERMOSTAT-VENTILATION ONLY

T H

THERMOSTAT-HEATING ONLY

HUMIDISTAT/HUMIDIFIER

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

20.

H

HOT WATER SUPPLYHWS

PIPING DESIGNATIONS

HOT WATER RETURNHWR

PREHEAT WATER SUPPLY - WITH 20% PROPYLENE GLYCOL WHERE APPLICABLEPHWS

PREHEAT WATER RETURN - WITH 20% PROPYLENE GLYCOL WHERE APPLICABLEPHWR

CHILLED WATER SUPPLY - WITH 20% PROPYLENE GLYCOL WHERE APPLICABLECHWS

CHILLED WATER RETURN - WITH 20% PROPYLENE GLYCOL WHERE APPLICABLECHWR

LOW PRESSURE STEAM (DOWNSTREAM OF PRV)LPS

MEDIUM PRESSURE STEAMMPS

CONDENSATE DRAINCD

CONDENSATE RETURNCR

PUMPED CONDENSATEPC

HUMIDIFICATION STEAMHUM

REVERSE OSMOSIS WATERRO

OUTSIDE AIR DUCT TURNING DOWN

OUTSIDE AIR DUCT TURNING UP

DUCT CONSTRUCTION AND LEAKAGE SCHEDULE

SYSTEM PRESSURE

CLASS

SEAL

CLASSIFICATION

LEAKAGE

RATE

RECTANGULAR ROUND

+4 A 6 3MEDIUM PRESSURE SUPPLY

+2 A

-2 A

-4 A

-1 A

LOW PRESSURE SUPPLY

GENERAL EXHAUST

HOOD EXHAUST

OUTSIDE AIR

NOTES:

1. DUCT CONSTRUCTION SHALL BE IN ACCORDANCE WITH SMACNA DUCT CONSTRUCTION STANDARDS

2. ALL SYSTEM DUCT WORK SHALL BE LEAKAGE TESTED IN ACCORDANCE WITH SMACNA HVAC AIR DUCT LEAKAGE TEST MANUAL

MOTOR STARTER SCHEDULE

MOTOR MAX NEMA STARTER

VOLTAGE / PHASE HP SIZE

120/1 1/3 0

208/3 1-1/2 0

208/3 3 0

208/3 5 1

208/3 7-1/2 1

208/3 10 1

208/3 15 1

DESIGN CONDITIONS

SPACE TYPE

WINTER INDOOR WINTER OUTDOOR SUMMER INDOOR SUMMER OUTDOOR

NOTES

DB (°F) %RH DB (°F) WB (°F) DB (°F) %RH DB (°F) WB (°F)

LAB AREA 73 25 17 - 94.3 61.2 1,2

OFFICES 30

WAITING AREA 30

PHARMACY AREA 30

CHEMO 30

STERILE PREP 30

HISTOLOGY 30

CYTOLOGY 30

COMM ROOM 72

NOTES:

1. OUTDOOR DESIGN TEMPERATURES BASED ON VA DESIGN GUIDE VALUES (99.6% HEATING; 0.4% COOLING) FOR PRESCOTT, AZ

2. INDOOR DESIGN VALUES BASED ON PRESCOTT VA PREFERENCES.

3. INDOOR DESIGN VALUES ARE BASED ON STANDARD COMM ROOM DESIGN.

73 25

94.3

94.3

94.3

94.3

94.3

94.3

94.3

94.3

61.2

61.2

61.2

61.2

61.2

61.2

61.2

61.2

1,2

1,2

1,2

1,2

1,2

1,2

1,2

1,3

4. OUTDOOR DESIGN HUMIDITY BASED ON ASHRAE WEATHER DATA (99.6% HUMIDIFICATION) FOR PRESCOTT, AZ .

THIS OCCURS AT 36.9°F DB, -1.9°F DEW POINT, AND HUMIDITY RATIO OF 6.0 GRAINS MOISTURE PER POUND OF DRY AIR.

Project Number

Pl ot

D a te

Date

Location

ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

Date:Revisions:

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot

6"

6"

6"

6"

PRESCOTT, ARIZONA

Fi le

-201 W. CUS HING S TREET

TUCS ON, AZ 85 718

T: 520.882.4484 F: 520.882.5560

100% BID DOCUMENT

/3

/2

3:

:4

P

M C

:\U se rs \a sa nd le r\D oc um en ts

\1 3-

M C

D _A

S an dl er

.rv t

MECHANICAL SYMBOLS AND ABBREVIATIONS

M001

13-127

ASST

CLINICAL LABORATORY AND

PHARMACY BUILDING

12/03/2015

BIDDING DOCUMENT REV. 1 Nov. 02, 2015 BID SUBMISSION Dec. 03, 2015 vhapreboydt Highlight

HYDRONIC RETURN

HYDRONIC SUPPLY

AUTOMATIC AIR

VENT (TYP)

SHUT OFF

VALVE (TYP)

STRAINER WITH

BLOWDOWN VALVE

TEST PLUG (TYP)

DRAIN VALVE WITH

HOSE CONNECTION HEATING COIL

MANUAL

AIR VENT

UNION (TYP)

BALANCING

VALVE

2-WAY

CONTROL

VALVE

PRESSURE

GAUGE (TYP)

THERMOMETER (TYP)

NOTES:

1. COIL SHALL BE PIPED COUNTER FLOW TO AIR FLOW.

2. COOLING COILS SHALL HAVE 3 WAY CONTROL VALVES

AND SERVED BY EXISTING YORK CHILLERS.

HYDRONIC RETURN

HYDRONIC SUPPLY

AUTOMATIC AIR

VENT (TYP)

SHUT OFF

VALVE (TYP)

STRAINER WITH

BLOWDOWN VALVE

TEST PLUG (TYP)

DRAIN VALVE WITH

HOSE CONNECTION COOLING COIL

MANUAL

AIR VENT

UNION (TYP)

BALANCING

VALVE (TYP)

3-WAY

CONTROL

VALVE

PRESSURE

GAUGE (TYP)

THERMOMETER (TYP)

NOTES:

1. THIS DETAIL IS TYPICAL FOR CABINET UNIT HEATERS,

UNIT HEATERS, AND BOOSTER COILS.

HYDRONIC COIL

WATER RETURN

WATER SUPPLY

MANUAL AIR VENT 2-WAY CONTROL VALVE

BALANCING

VALVE

SHUT OFF

VALVE (TYP)

STRAINER WITH

BALL VALVE

DRAIN VALVE

WITH HOSE

CONNECTION

TEST PLUG (TYP)

M A

IN

D

U C

T

CONICAL OR

BELLMOUTH

CONNECTION

NOTE 1

NOTE 2 AND NOTE 3

CONTROL BOX

VARIABLE VOLUME

TERMINAL UNIT

HOT WATER REHEAT COIL

(WHERE AVAILABLE) TRANSITION AS

NECESSARY

LOW PRESSURE DUCT

HOT WATER RETURN

HOT WATER SUPPLY

2-WAY CONTROL VALVE

BALANCING VALVE

BALL VALVE (TYP)

STRAINER

MANUAL AIR

VENT (TYP)

NOTES:

1. MAXIMUM FLEXIBLE DUCT LENGTH SHALL BE 1'-0".

2. RIGID STRAIGHT DUCT LENGTH TO INLET OF TERMINAL UNIT SHALL BE MINIMUM 3

TIMES THE DIAMETER OF INLET.

3. A BRANCH DUCT SERVING AN INDIVIDUAL BOX MAY BE THE SAME SIZE AS THE BOX

INLET, PROVIDED THE EQUIVALENT LENGTH OF THE BRANCH DUCT, AS SHOWN,

DOES NOT EXCEED 10 FEET (3 METERS). FOR LONGER LENGTHS, INCREASE THE

DUCT SIZE AND PROVIDE A DUCT TRANSITION TO MAINTAIN THE DUCT STATIC

PRESSURE DROP AT OR BELOW 0.2"/100' [1.64Pa/m].

4. COMPONENT ARRANGEMENT MAY VARY BY MANUFACTURER. PROVIDE INSULATION

W/VAPOR BARRIER FOR CONNECTING DUCT SECTIONS.

UNION (TYP)

ROS

HUM

1 HUM

HUM

1" RO

3/ 4"

R O

3/4" RO

1" DCW

NOTES:

1. HUM-1, HUM-3, AND HUM-4 ARE ULTRASONIC HUMIDIFIERS.

2. HUM-2 ARE ELECTRIC RESISTIVE HUMIDIFIERS.

3. RO PIPING SHALL BE STAINLESS STEEL.

3/4" RO

HUM

4CAP PIPE FOR FUTURE

HUMIDIFIER SERVING

FUTURE CYTOLOGY AND

HISTOLOGY LABS.

Y-STRAINER

55 GALLON TANK

TRIPLE DUTY VALVE

PRESSURE SWITCH

LOW WATER CUT

OFF SWITCH

PUMP

DIAPHRAGM

EXPANSION TANK

PRESSURE GAUGE

SYSTEM OUTLET 3/4" NPT

SYSTEM

PRESSURE

RELIEF VALVENOT PART OF GMU PACKAGE

GATE VALVE (TYP)

BALL VALVE

PRESSURE

REDUCING VALVE

NOTE:

1.

2.

SECURE HOOD TO WOOD NAILING STRIP WITH 3/8" [10mm] CADMIUM PLATED LAG BOLTS NOT OVER 12" [300mm] ON CENTER.

SECURE ROOF CURB, DUCTWORK AND DAMPER TO ROOF WITH EXPANSION

BOLTS (CONCRETE ROOF) OR RUST RESISTANT BOLTS (MENTAL DECK & BAR

JOIST ROOF).

GRAVITY BACKDRAFT

DAMPER

SEE NOTE 2

PREFABRICATED

ROOF CURB

WOOD

NAILING STRIP

TRANSITION DUCT TO FULL SIZE OF

DAMPER SUPPLIED WITH HOOD.

ROOF

SEE NOTE 2

SEE NOTE 1

CURB CAP

FACTORY ASSEMBLED HINGED HOOD

WITH LATCH & BIRD SCREEN

DUCT

Project Number

Pl ot

D a te

Date

Location

ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

Date:Revisions:

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot

6"

6"

6"

6"

PRESCOTT, ARIZONA

Fi le

-201 W. CUS HING S TREET

TUCS ON, AZ 85 718

T: 520.882.4484 F: 520.882.5560

100% BID DOCUMENT

/3

/2

3:

:1

P

M C

:\U se rs \a sa nd le r\D oc um en ts

\1 3-

M C

D _A

S an dl er

.rv t

MECHANICAL DETAILS

M503

13-127

ASST

CLINICAL LABORATORY AND

PHARMACY BUILDING

12/03/2015

NOT TO SCALEM503

1 AHU WATER COIL PIPING DETAIL

NOT TO SCALEM503

3 WATER COIL PIPING DETAIL

NOT TO SCALEM503

2 VAV BOX DETAIL

NOT TO SCALEM503

4 RO WATER FLOW DIAGRAM

NOT TO SCALEM503

5 GLYCOL MAKEUP UNIT DETAIL

NOT TO SCALEM503

6 INTAKE HOOD DETAIL

BIDDING DOCUMENT REV. 1 Nov. 02, 2015 BID SUBMISSION Dec. 03, 2015

PRV

PRV

MEDIUM PRESSURE STEAM

FROM BUILDING 148

GLOBE VALVE

PRESSURE

GAUGE (TYP)

VENT ABOVE ROOF TO

ATMOSPHERE

CONDENSATE

RETURN

CONDENSATE

RETURN

LOW PRESSURE STEAM

TO HEAT EXCHANGERS

50 PSI MPS 30 PSI LPS

3" MPS

3" LPS

PILOT CONTROL

LINE (TYP)

3" BYPASS

LINE

GATE

VALVE

(TYP)

STRAINER

(TYP)

10 PIPE DIAMETERS MIN.

PRESSURE

SAFETY VALVE

10 PIPE DIAMETERS

MIN.

STEAM TRAP

ASSEMBLY (TYP)

NOTES:

1. MPS REFERS TO STEAM UPSTREAM OF PRV AND LPS

REFERS TO STEAM DOWNSTREAM OF PRV.

2. SEE PRV SCHEDULE FOR VALVE DATA.

3. PROVIDE NECCESARY UNIONS FOR REMOVAL OF VALVES

WITH SCREWED CONNECTIONS.

3" MPS

3" MPS

3" LPS

3" LPS

NOTES:

1. UNLESS OTHERWISE SHOWN ON DRAWINGS, SIZE THE

VENT PIPE SO THAT THE STEAM IS NOT BLOWN OUT

AT THE VENT PIPE ENTRANCE. UTILIZE THE

CALCULATION METHOD CONTAINED IN ANSI B31.1.

POWER PIPING CODE, APPENDIX II.

2. VENT PIPE SHALL TERMINATE 6' MIN. ABOVE FINISHED

ROOF.

3. DISCHARGE OF DRAIN MUST BE DIRECTED AWAY

FROM PLATFORMS OR OTHER AREAS WHICH

PERSONNEL MAY OCCUPY.

4. DO NOT CONNECT ANY OTHER DRAIN TO THE DRIP

PAN ELBOW DRAIN PIPE.

SAFETY VALVE

CONNECTION TO PRESSURE

VESSEL OR PIPE

24" MAX.

VENT PIPE

THROUGH ROOF

PROVIDE UNION UNLESS

SAFETY VALVE HAS

FLANGED OUTLET

D

DRIP PAN ELBOW

FLEXIBLE

CONNECTOR

PIPE THREADED INTO ELBOW

(SAME SIZE AS ELBOW)

3/4" DRAIN TO FLOOR

DRAIN OR OPEN

SIGHT DRAIN

HX

N

PRESSURE GAUGE

STEAM TRAP

ASSEMBLY

CONDENSATE RETURN TO

CONDENSATE PUMP/RECEIVER

LOW PRESSURE STEAM

FROM STEAM PRESSURE

REDUCING STATION

STEAM CONTROL

VALVE

GATE VALVE (TYP)

STRAINER

PREHEAT/HOT

WATER SUPPLY TO

PUMPS

PREHEAT/HOT WATER

RETURN FROM LOAD

EQUIPMENT

MOTORIZED ISOLATION VALVE

AIR VENT

MANUAL ISOLATION

VALVE (TYP)

CHECK

VALVE (TYP)

THERMOMETER (TYP)

PRESSURE

GAUGE (TYP)

MOTORIZED ISOLATION VALVE

CONCRETE

HOUSEKEEPING PAD

FLUSHING

CONNECTION

LPR

FLOOR

3/4" DRAIN, DISCHARGE INTO

NEAREST FLOOR DRAIN, NC.

GRAVITY RETURN FROM

FLASH TANK IF SHOWN ON

FLOOR PLAN

PUMP DISCHARGE

CONTROL CABINET

VENT

RECEIVER

WATER LEVEL

GAUGE

THERMOMETER (TYP)

STRAINER WITH

BALL VALVE

ISOLATIONG VALVE (TYP)

CHECK VALVE (TYP)

PRESSURE GAUGE (TYP)

EXISTING MPS PIPE AT

BUILDING 148

NEW 3" MPS PIPE ROUTED

TO NEW PRV STATION IN

PENTHOUSE.

3" MPS

3" MPS

3" LPS

1-1/4" PC

2" L

P S

EXISTING CR PIPE AT

BUILDING 160

NEW 1-1/4" PC ROUTED TO

CP-1 IN PENTHOUSE

1-1/4" PC

CHEMICAL

POT FEEDER

CHEMICAL

POT FEEDER

3" HWR

3" HWS

3" PHWR

3" PHWS

SCV

PREHEAT HOT WATER PIPING TO AND

FROM AHU PREHEAT COILS. FUTURE

LOADS INCLUDE FUTURE HISTOLOGY

AND CYTOLOGY LABS AND EXPANDED

WAITING AREA BETWEEN BUILDING 164

AND BUILDING 117.

CURRENT REQUIRED FLOW: 57.2 GPM

FUTURE ESTIMATED FLOW: 27.8 GPM

TOTAL DESIGN FLOW: 85.0 GPM

HOT WATER PIPING TO AND FROM VAV

BOX REHEAT COILS, BOOSTER COILS,

UNIT HEATERS, AND CABINET UNIT

HEATERS.

CURRENT REQUIRED FLOW: 79.9 GPM

FUTURE ESTIMATED FLOW: 10.1 GPM

TOTAL DESIGN FLOW: 90.0 GPM

SCV

SCV

SCV

PRV

PRV

CP

HX

HX

HX

HX

GMU

ET

AS

HWP

HWP

HWP

HWP

ET

AS

(E) 8" CHWS (E) 8" CHWR

(E) 10" CHWS (E) 10" CHWR

EXISTING YORK CHILLER

EXISTING YORK CHILLER

EXISTING CHILLED

WATER PUMP

(TYPICAL OF 3)

(E) 10" CHWR

(E) 10" CHWS

CHILLER YARD

BUILDING 164

LOWER LEVEL

MIRACLE MILE

CHILLED WATER PIPING TO AND FROM

AHU COOLING COILS. FUTURE LOADS

INCLUDE FUTURE HISTOLOGY AND

CYTOLOGY LABS, AND EXPANDED

WAITING AREA BETWEEN BUILDING 164

AND BUILDING 117.

CURRENT REQUIRED FLOW: 140.6 GPM

FUTURE ESTIMATED FLOW: 64.4 GPM

TOTAL DESIGN FLOW: 205.0 GPM

EXISTING CHILLED WATER

PIPING TO EXISTING BUILDINGS

CONNECT NEW 4" CHWR PIPE

TO EXISTING CHWR AT RISER

WITH SHUT-OFF VALVE

CONNECT NEW 4" CHWS PIPE

TO EXISTING CHWS AT RISER

WITH SHUT-OFF VALVE

CHILLER YARD

BUILDING 108 |

MIRACLE MILE

(N) 4" CHWS

(N) 4" CHWR

BUTTERFLY

VALVE (TYP)

PRESSURE

GAUGE (TYP)

THERMOMETER (TYP)

Project Number

Pl ot

D a te

Date

Location

ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

Date:Revisions:

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot

6"

6"

6"

6"

PRESCOTT, ARIZONA

Fi le

-201 W. CUS HING S TREET

TUCS ON, AZ 85 718

T: 520.882.4484 F: 520.882.5560

100% BID DOCUMENT

/3

/2

3:

:1

P

M C

:\U se rs \a sa nd le r\D oc um en ts

\1 3-

M C

D _A

S an dl er

.rv t

MECHANICAL DETAILS

M504

13-127

ASST

CLINICAL LABORATORY AND

PHARMACY BUILDING

12/03/2015

NOT TO SCALEM504

1 STEAM PRESSURE REDUCING STATION DETAIL

NOT TO SCALEM504

2 STEAM SAFETY VALVE DETAIL

NOT TO SCALEM504

3 STEAM TO HOT WATER HEAT EXCHANGER DETAIL

NOT TO SCALEM504

4 CONDENSATE PUMP DETAIL

NOT TO SCALEM504

5 STEAM AND HOT WATER FLOW DIAGRAM

NOT TO SCALEM504

6 CHILLED WATER FLOW DIAGRAM

BIDDING DOCUMENT REV. 1 Nov. 02, 2015 BID SUBMISSION Dec. 03, 2015

PIPE

PIPE CLAMP

STOP WASHER

AND NUT (TYP)

ISOLATION

HANGER (TYP)

SNUBBER PLATE

ROD STIFFINER ANGLE

ROD TO ANGLE CLAMP

CHANNEL NUT

WITH SPRING

UNISTRUT

45°

ISOLATION

HANGER

SNUBBER

PLATE

ROD STIFFINER

ANGLE

ROD TO ANGLE

PLATE

CABLE

INSTALLED

SWIVEL CONNECTIONS

BOTH ENDS

45°

CHAIN

SHACKLE

HEAVY WIRE

ROPE THIMBLE

U-BOLT

CLIP

7x19 GALVANIZED

AIRCRAFT CABLE

NOTE:

TENSION CABLE ONLY

ENOUGH TO REMOVE SAG.

TYPE SBC SEISMIC

CABLE BRACE

TYPE SRC SEISMIC

ROD CLAMP

EQUIPMENT

EQUIPMENT

TOP VIEW

ELEVATION

ISOLATION HANGER

SNUBBER PLATE

ROD STIFFINER

ANGLE

ROD TO ANGLE

CLAMP

ISOLATION

HANGER

STEEL

CABLE

45°

45°

SIDE VIEW TRAPEZE HANGER FOR UP

TO 1000 LB. UNIFORM LOAD

1" M

A X

PROVIDE INSULATION SHIELD

& INSERT FOR ALL PIPING (8" MIN.) BAND

1-5/8" 12 GAUGE

CHANNEL OR 2"x2"x1/4" ANGLE

1/2" DIA. HANGER RODS WITH 36"

MAX. SPACING ON EACH CHANNEL

WELD

SADDLE

INSULATION SHIELD

AT HANGER

PROVIDE HIGH

COMPRESSIVE STRENGTH

INSULATION (9 PSF MIN.

DENSITY) UNDER

INSULATION SHIELD

INSULATION (VAPOR

BARRIER TYPE IS

REQUIRED FOR LOW

TEMPERATURE PIPE)

HANGER ROD

NOTE:

SEE SPECIFER FOR DETAILED

HANGER REQUIREMENTS

NOTES:

1. PROVIDE ANCHORS ONLY WHERE SHOWN

ON DRAWINGS.

2. EXTEND SLEEVE ABOVE FLOOR WHERE

SPECIFIED.

INSULATION

BOLT

(TYPICAL)

FLOOR SLAB

FIRE-STOPPING

MATERIAL

BOLT

PIPEPIPE SLEEVE

WHERE SPECIFIED

RISER CLAMP

RISER

RISER CLAMP. BOTTOM

CLAMP REQUIRED AT

ANCHOR POINTS ONLY.

RISER CLAMP

(TYPICAL)

8"x8"x3/8" STEEL PLATE

WELD PLATE TO PIPE

SECURE TO ROOF SLAB

WITH (4) 3/8"∅ EXPANSION

BOLTS OR WELD TO STEEL

DECK

CONCRETE ROOF SLAB

OR STEEL ROOF DECK

ROOF SYSTEM

INSULATION AND

MEMBRANE

PRE-MOULDED FLEXIBLE PIPE

COUNTER FLASHING

CLAMPING RING

ROOF SURFACE

WELD PIPE SADDLE SUPPORT TO

PIPE. PROVIDE WATER TIGHT

CONNECTION

HIGH COMPRESSIVE

STRENGTH INSULATION

INSERT UNDER SHIELD

PIPE

INSULATION PROTECTION

SHIELD

SEALANT

2" STEEL PIPE

2-1/2" STEEL PIPE

PROVIDE ALUMINUM

JACKET

NOTES:

PROVIDE RESTRAINING CLAMPS 8'-0" O.C.

" M

IN

8" 4"

Project Number

Pl ot

D a te

Date

Location

ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

Date:Revisions:

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot

6"

6"

6"

6"

PRESCOTT, ARIZONA

Fi le

-201 W. CUS HING S TREET

TUCS ON, AZ 85 718

T: 520.882.4484 F: 520.882.5560

100% BID DOCUMENT

/3

/2

3:

:1

P

M C

:\U se rs \a sa nd le r\D oc um en ts

\1 3-

M C

D _A

S an dl er

.rv t

MECHANICAL DETAILS

M505

13-127

ASST

CLINICAL LABORATORY AND

PHARMACY BUILDING

12/03/2015

NOT TO SCALEM505

1 SEISMIC PIPE SUPPORT DETAIL

NOT TO SCALEM505

2 SC PIPING CABLE RESTRAINT

NOT TO SCALEM505

3 SEISMIC CABLE ATTACHMENT FOR PIPING

NOT TO SCALEM505

4 SEISMIC CABLE DETAILS

NOT TO SCALEM505

5 SC EQUIPMENT CABLE RESTRAINT

NOT TO SCALEM505

6 PIPE HANGER DETAIL

NOT TO SCALEM505

7 PIPE SUPPORT ANCHORS

NOT TO SCALEM505

8 PIPE SUPPORT ON ROOF DETAIL

Project Number

Pl ot

D a te

Date

Location

Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot

6"

6"

6" 6"

Fi le ot

D a te

Date

Location

Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot

6"

6"

6" 6"

Fi ot

D a te

Date

Location

Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot

6"

6"

6" 6"

Fi ot

D a te

Date

Location

Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot

6"

6"

6" 6"

Fi

M

M

M

M

T-3 AI

C

H

C

T-1DP

M

SPS-2

HS

SD-2

H-2

AI

M

T-5

HIGH PRESSURE STATIC

AFMS-2

M

N.O.

BO - OUTSIDE AIR DAMPER

(OPEN/CLOSE)

BI - OUTSIDE AIR DAMPER

(POSITION)

AFMS-1AI - OUTDOOR AIRFLOW

M

BO - EXHAUST AIR DAMPER

(OPEN/CLOSE)

BI - EXHAUST AIR DAMPER

(POSITION)

N.O.

DP

BI - PREFILTER STATUS

TSL

VFD

BO - FAN START/STOP

AO - VFD SPEED CONTROL

BI - VFD FAULT

BI - FAN STATUS

H

VFD

BO - FAN START/STOP

AO - VFD SPEED CONTROL

BI - VFD FAULT

BI - FAN STATUS

H-1

SD-2

BI

SPS-2

BI - HIGH PRESSURE STATIC

SPS-1

AO - RELIEF DAMPER

(MODULATE)

AI - RELIEF DAMPER

(POSITION) SD-1

AO - OUTSIDE AIR DAMPER

(MODULATE)

AI - OUTSIDE AIR DAMPER

(POSITION)

BO - OUTSIDE AIR DAMPER

(OPEN/CLOSE)

BI - OUTSIDE AIR DAMPER

(POSITION)

BI - FILTER STATUS

C

DP

BI - FILTER STATUS

FZ

BI-TEMPERATURE

TSL

H

T-4 AI SPS-1

AFMS-1

ULTRASONIC HUMIDIFIER

DP

BI - FILTER STATUS

AFMS-2 AI - EXHAUST AIRFLOW

SD-1

BI

AFMS-3

AI

AFMS-4

AI

M

T-2

T-1

H-2

DP

BI - FILTER STATUS

M

M

M

M

BYPASS

PRIMARY

PRIMARY

BYPASS

OUTSIDE AIR SUPPLY AIR

RETURN AIREXHAUST AIR

APPLICABLE FOR

AHU-4 HEPA FILTER

AO - OUTSIDE AIR DAMPER

(MODULATE)

AI - OUTSIDE AIR DAMPER

(POSITION)

* NORTEC RS HUMIDIFIER AT AHU-2.

ULTRASONIC HUMIDIFIER AT AHU-4.

H-5

GLOBAL TEMPERATURE AND

ENTHALPY SENSOR.

T-3

HEAT EXCHANGE

MEDIA

BO - PRIMARY OUTSIDE AIR DAMPER

(OPEN/CLOSE)

BI - PRIMARY OUTSIDE AIR DAMPER

(POSITION)

BO - BYPASS RETURN AIR DAMPER

(OPEN/CLOSE)

BI - BYPASS RETURN AIR DAMPER

(POSITION)

BO - BYPASS OUTSIDE AIR DAMPER

(OPEN/CLOSE)

BI - BYPASS OUTSIDE AIR DAMPER

(POSITION)

BO - PRIMARY RETURN AIR DAMPER

(OPEN/CLOSE)

BI - PRIMARY RETURN AIR DAMPER

(POSITION)

D-1

D-2

D-3

D-4

D-5

D-6

Project Number

Pl ot

D a te

Date

Location

Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot

6"

6"

6" 6"

Fi

HWS

HX-1

CR

NO

LPS

HWR

HWP-1

HWS

HWP-2

HWS

HWR

HWS

HWS

HX-2

NC

LPS

HWR

NC

NC

CR

NO

NO PHWS

HX-3

CR

NO

LPS

PHWR

HWP-3

PHWS

HWP-4

PHWS

PHWR

PHWS

PHWS

HX-4

NC

LPS

PHWR

NC

NC

CR

NO

NO

Project Number

Pl ot

D a te

Date

Location

Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot

6"

6"

6" 6"

Fi ot

D a te

Date

Location

Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot

6"

6"

6" 6"

Fi

SUPPLY VAV TERMINAL UNITS

THE UNIT SHALL BE INTERLOCKED WITH THE CORRESPONDING AIR

HANDLING UNIT AND ENABLED ACCORDING TO A USER DEFINABLE

OCCUPANCY SCHEDULE IN THE FOLLOWING MODES:

• OCCUPIED MODE: THE UNIT SHALL MAINTAIN

o A 73°F (ADJ.) COOLING SETPOINT o A 73°F (ADJ.) HEATING SETPOINT

• UNOCCUPIED MODE (NIGHT SETBACK): THE UNIT SHALL MAINTAIN

o A 80°F (ADJ.) COOLING SETPOINT o A 65°F (ADJ.) HEATING SETPOINT

THE UNIT SHALL MAINTAIN ZONE SETPOINTS BY CONTROLLING THE

AIRFLOW THROUGH ONE OF THE FOLLOWING:

OCCUPIED:

• WHEN THE ZONE TEMPERATURE IS GREATER THAN THE COOLING

SETPOINT, THE ZONE DAMPER SHALL MODULATE BETWEEN THE

MINIMUM OCCUPIED AIRFLOW (ADJ.) AND THE MAXIMUM COOLING

AIRFLOW (ADJ.) UNTIL THE ZONE IS SATISFIED.

• WHEN THE ZONE TEMPERATURE IS BETWEEN THE COOLING

SETPOINT AND THE HEATING SETPOINT, THE ZONE DAMPER SHALL

MAINTAIN THE MINIMUM ZONE AIRFLOW (ADJ.).

• WHEN THE ZONE TEMPERATURE IS LESS THAN THE HEATING

SETPOINT, THE CONTROLLER SHALL ENABLE HEATING AND THE

ZONE DAMPER SHALL MODULATE TO MAINTAIN THE ZONE

TEMPERATURE AT THE HEATING SETPOINT.

UNOCCUPIED:

• WHEN THE ZONE IS UNOCCUPIED THE ZONE DAMPER SHALL

CONTROL TO ITS MINIMUM UNOCCUPIED AIRFLOW (ADJ.).

• WHEN THE ZONE TEMPERATURE IS GREATER THAN THE COOLING

SETPOINT, THE ZONE DAMPER SHALL MODULATE BETWEEN THE

MINIMUM UNOCCUPIED AIRFLOW (ADJ.) AND THE MAXIMUM COOLING

AIRFLOW (ADJ.) UNTIL THE ZONE IS SATISFIED.

• WHEN THE ZONE TEMPERATURE IS LESS THAN ITS UNOCCUPIED

HEATING SETPOINT, THE CONTROLLER SHALL ENABLE HEATING TO

MAINTAIN THE ZONE TEMPERATURE AT THE SETPOINT.

ADDITIONALLY, IF WARM AIR IS AVAILABLE FROM THE AHU, THE

ZONE DAMPER SHALL MODULATE BETWEEN THE MINIMUM

UNOCCUPIED AIRFLOW (ADJ.) AND THE AUXILIARY HEATING

AIRFLOW (ADJ.) UNTIL THE ZONE IS SATISFIED.

ZONE OPTIMAL START:

THE UNIT SHALL USE AN OPTIMAL START ALGORITHM FOR MORNING

START-UP. THIS ALGORITHM SHALL MINIMIZE THE UNOCCUPIED

WARM-UP OR COOL-DOWN PERIOD WHILE STILL ACHIEVING COMFORT

CONDITIONS BY THE START OF SCHEDULED OCCUPIED PERIOD.

TERMINAL UNIT HOT WATER HEAT SHALL NOT BE USED DURING

MORNING WARM-UP.

ZONE UNOCCUPIED OVERRIDE:

A TIMED LOCAL OVERRIDE CONTROL SHALL ALLOW AN OCCUPANT TO

OVERRIDE THE SCHEDULE AND PLACE THE UNIT INTO AN OCCUPIED

MODE FOR AN ADJUSTABLE PERIOD OF TIME (MINIMUM 30 MINUTES, IN 30

MINUTES INCREMENTS). AT THE EXPIRATION OF THIS TIME, CONTROL OF

THE UNIT SHALL AUTOMATICALLY RETURN TO THE SCHEDULE.

HOT WATER HEATING:

THE CONTROLLER SHALL MEASURE THE ZONE TEMPERATURE AND

STAGE THE HOT WATER HEAT TO MAINTAIN THE SETPOINT. TO PREVENT

SHORT CYCLING, THERE SHALL BE A USER DEFINABLE (ADJ.) DELAY

BETWEEN STAGES, AND EACH STAGE SHALL HAVE A USER DEFINABLE

(ADJ.) MINIMUM RUNTIME. THE HOT WATER HEATING SHALL BE ENABLED

WHENEVER THE ZONE TEMPERATURE IS BELOW SETPOINT AND

SUFFICIENT AIRFLOW IS PROVIDED.

REHEATING - HIGH DISCHARGE AIR TEMPERATURE LIMIT:

THE CONTROLLER SHALL MEASURE THE DISCHARGE AIR TEMPERATURE

AND LIMIT REHEATING IF THE DISCHARGE AIR TEMPERATURE IS MORE

THAN 15°F (ADJ.) ABOVE THE ZONE TEMPERATURE.

DISCHARGE AIR TEMPERATURE:

THE CONTROLLER SHALL MONITOR THE DISCHARGE AIR TEMPERATURE.

ALARMS SHALL BE PROVIDED AS FOLLOWS:

• HIGH ZONE TEMP: IF THE ZONE TEMPERATURE IS GREATER THAN

THE COOLING SETPOINT BY A USER DEFINABLE AMOUNT (ADJ.).

• LOW ZONE TEMP: IF THE ZONE TEMPERATURE IS LESS THAN THE

HEATING SETPOINT BY A USER DEFINABLE AMOUNT (ADJ.).

ALARMS SHALL BE PROVIDED AS FOLLOWS:

• HIGH DISCHARGE AIR TEMP: IF THE DISCHARGE AIR TEMPERATURE

IS GREATER THAN 120°F (ADJ.).

• LOW DISCHARGE AIR TEMP: IF THE DISCHARGE AIR TEMPERATURE IS

LESS THAN 40°F (ADJ.).

M

M

MS

BO

EP

BI

M

N.C.

M

M

MS

PACKAGED

REVERSE OSMOSIS

RO

PS

T

H

Project Number

Pl ot

D a te

Date

Location

Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot

6"

6"

6" 6"

Fi

MECHANICAL SHEET NOTES

1. 48x48 RELIEF AIR OPENING WITH BAROMETRIC DAMPER.

2. 16x16 EXHAUST AIR DUCT (EF-1) UP. TERMINATE DUCT HORIZONTALLY AT 45

DEGREES, EXHAUST AIR AWAY FROM BUILDING. PROVIDE INSECT SCREEN AT

TERMINATION.

3. 16x16 EXHAUST AIR DUCT (EF-2) UP. TERMINATE DUCT HORIZONTALLY AT 45

DEGREES, EXHAUST AIR AWAY FROM BUILDING. PROVIDE INSECT SCREEN AT

TERMINATION.

4. 48x48 TRANSFER AIR DUCT ABOVE CONDUIT BANK. PROVIDE WIRE MESH AT

WALL OPENINGS ON BOTH SIDES.

5. KEYNOTE NOT USED.

6. KEYNOTE NOT USED.

7. 14x14 SUPPLY AIR DUCT SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY

LABS. .

8. KEYNOTE NOT USED.

9. KEYNOTE NOT USED.

10. EXISTING MIRACLE MILE AHU AND ASSOCIATED DUCTWORK SHALL REMAIN.

11. 36x24 OUTSIDE AIR DUCT (AHU-2) UP TO ROOF. OUTSIDE AIR DUCT SHALL BE

INSULATED.

12. KEYNOTE NOT USED.

13. KEYNOTE NOT USED.

14. 40x20 SUPPLY AIR DUCT (AHU-2).

15. 48x22 RETURN AIR DUCT (AHU-2).

16. 50x18 RELIEF AIR DUCT (AHU-2).

17. ROUTE REFRIGERANT PIPING FROM INDOOR UNIT AS DIRECTLY AS POSSIBLE,

TO OUTDOOR UNIT, MINIMIZING THE AMOUNT OF EXTERIOR EXPOSED

REFRIGERANT PIPING.

18. 16x18 SUPPLY AIR DUCT (AHU-2) UP TO UPPER LEVEL.

19. 20x20 RETURN AIR DUCT (AHU-2) UP TO UPPER LEVEL.

20. 50x24 OUTSIDE AIR DUCT (AHU-2) OPENING.

21. AHU-2 SUPPLY FAN VFD.

22. AHU-2 RETURN FAN VFD.

23. AIR HANDLING UNIT MOUNTED ON A 6" HOUSEKEEPING PAD. AHU-2 SHALL BE

SPLIT INTO SECTIONS WITH 42" MAX. WIDTH PER SECTION TO FIT THROUGH

48" WIDE DOOR. ROUTE CONDENSATE TO NEARBY FLOOR DRAIN.

24. HUMIDIFIER DISCONNECT SWITCH.

25. AFMS TRANSMITTER.

MECHANICAL GENERAL NOTES

A. AIRFLOWS INDICATED ARE ACTUAL CUBIC FEET PER MINUTE (ACFM).

B. FINAL LOCATION OF THERMOSTATS, ROOM PRESSURE MONITORS, AND

DIFFERENTIAL PRESSURE SENSORS SHALL BE COORDINATED WITH

OWNER, TEMPERATURE CONTROLS CONTRACTOR, AND GENERAL

CONTRACTOR.

C. ALL DUCTWORK ASSOCIATED WITH STROBIC FANS SHALL BE

STAINLESS STEEL.

D. PROVIDE WEATHERPROOF JACKETING FOR ALL EXPOSED DUCTWORK.

E. INSULATE ALL SUPPLY AIR AND OUTSIDE AIR DUCTWORK.

F. BRANCH DUCTWORK TO AIR TERMINAL SHALL BE SAME AS NECK SIZE

UNLESS OTHERWISE NOTED.

G. BRANCH HOT WATER PIPING TO VAV BOXES, BOOSTER COILS, UNIT

HEATERS, ETC... SHALL BE MIN. 3/4" NOMINAL DIAMETER.

H. INSULATE ALL PIPING. SEE SPECIFICATIONS FOR INSULATION TYPE AND

THICKNESS.

I. PROVIDE ACCESS DOORS IN HARD CEILINGS FOR ACCESS TO

EQUIPMENT.

H H.3 H.9

IT CLOSET

164-011

DELIVERY

164-017

CORRIDOR

164-012 OFFICE

164-013

OFFICE

164-014

FUTURE SPACE

164-015

AHU

DSS

12x12 x1 x1

12x12 x1

EXISTING ELECTRICAL

CONDUIT DUCT BANK

CAP 12"Ø SUPPLY AIR DUCT TO

FUTURE HISTOLOGY LAB AT WALL.

B6x6 70-R

B6x6 70-R

A6 70-S

1 1/4" PHWR

1 1/4" PHWS

3/4" RO

2" CHWR

2" CHWS

HUM

A10 420-S

B10x10 190-R

B10x10 220-R

A8 270-S

F8x8 50-S

A6 70-S

AFMS

AFMS

30x18

STAIR

S-1

STACKED DUCTS:

30x18 SUPPLY AIR DUCT (HIGH) 30x22 RETURN AIR DUCT (LOW)

T C

TH/C

(EXCAVATED

CRAWLSPACE)

CAP 14"Ø SUPPLY AIR DUCT SERVING

FUTURE CYTOLOGY LAB AT WALL.

CAP 14x14 EXHAUST AIR DUCT

SERVING FUTURE CYTOLOGY AND

HISTOLOGY BELOW UPPER LEVEL

FLOOR. EXHAUST AIR DUCT SHALL

BE STAINLESS STEEL.CAP 1" HWS/HWR SERVING FUTURE

CYTOLOGY LAB AT WALL.

1" HWS

1" HWR

CAP 1" HWS/HWR SERVING FUTURE

CYTOLOGY LAB AT WALL.

x1

"Ø

1" HWS

1" HWR

0.1

0.5

G H H.3 H.9 JFD

EF

(E) 20x20

VAV

VAV

VAV

VAV

CUH

VAV

VAV

VAV

VAV

EF

VAV

DSS

UH

UH

x1

20x14

10x10

10x12

20x14 26x14 x1

12x10

12x12

14x12 8x10

16x16 x1

12x12 x1

12x12

B10x10 255-E

B10x10 255-E

B10x10 240-E

B10x10 240-E

A10 355-S

A10 335-S

G10x10 120-E

F12x8 210-S

G12x12 210-R

G24x12 770-E

F14x14 770-S

A10 445-S

B12x12 380-R

A8 290-S

A8 285-S

B15x15 575-R

B15x15 575-R

A8 285-S

A8 290-S

PHARMACY

STORAGE

164-010

LAB STORAGE

164-009

ELECTRICAL

ROOM

164-002

MEN'S TOILET

164-003

WOMEN'S

TOILET

164-004

HAC

164-005

20x14 x1

MACHINE ROOM

164-008

STAIR

S-1

CORRIDOR

164-006

A10 445-S

FUTURE SPACE

164-007

CORRIDOR

164-001

CORRIDOR

164-012

OFFICE

164-013

OFFICE

164-014

FUTURE SPACE

164-015

IT CLOSET

164-011

16x18

20x20 x1

VD (TYP)

T H TH

T C

TH/C

TC

TH/C

TH/C

TH/C

T C

TH/C

FIRE

DAMPER

(TYP)

12x108x10

12x12

12x12

8x10

12x8 x1

12x12

MH101

AHU

MD (TYP)

AFMS

AFMS

A8 190-S

B8x8 100-R

Project Number

Pl ot

D a te

Date

Location

ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

Date:Revisions:

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot

6"

6"

6"

6"

PRESCOTT, ARIZONA

KEY PLAN

NORTH

Fi le

-201 W. CUS HING S TREET

TUCS ON, AZ 85 718

T: 520.882.4484 F: 520.882.5560

BUILDING

BUILDING

MIRACLE MILE

100% BID DOCUMENT

O

PE

N A

IR

E

N

TR

A N

C E

/3

/2

3:

:1

P

M C

:\U se rs \a sa nd le r\D oc um en ts

\1 3-

M C

D _A

S an dl er

.rv t

OVERALL LOWER LEVEL HVAC PLAN

MH101

13-127

ASST

CLINICAL LABORATORY AND

PHARMACY BUILDING

12/03/2015

1/4" = 1'-0"MH101

2 ENLARGED LOWER LEVEL HVAC PLAN - SOUTH

1/8" = 1'-0"MH101

1 OVERALL LOWER LEVEL HVAC PLAN

0.1

0.5

G H H.3 H.9 J K K.5 LFD

12x12 x1

40x20

26x16

(E ) 2

0x x1

VAV

VAV

VAV

24x20 x8 x8 x1

16x15

DSS

VAV

VAV

TEF

VAV

VAV

VAV

VAV

VAV

VAV

VAV

VAV

VAV

VAV

VAV

16VAV

EAV

D8 250-S

D8 250-S

D8 250-S

D8 270-S

D10 435-S

D10 435-S

D10 440-S

D10 440-S

A12 585-S

A12 585-S

A12 580-S

B18x18 900-E

B18x18 900-E

B18x18 900-E

B18x18 900-E

B18x18 900-E

B18x18 900-E

A12 585-S

A12 585-S

A12 580-S

A12 585-S A12

585-S A12

580-S

B18x18 900-E

B18x18 900-E

B18x18 900-E

B8x8 100-R

D8 200-S

B12x12 520-R

D8 200-S

A6 70-S

D8 200-S

B12x12 500-R

D8 215-S

D8 250-S

D6 150-S

B8x8 160-R

A8 150-S

A8 150-S

B12x12 465-R

B6x6 70-R

B6x6 70-R

F8x8 50-S

A6 100-S

VAV

A8 300-S

B8x8 100-R

B6x6 50-R

A6 50-S

A6 100-S

A6 70-S

A6 100-S

B8x8 100-R

B8x8 110-E

B8x8 180-E

B8x8 180-E

G12x8 120-E

A6 80-S

A6 130-S

A6 130-S

A8 300-S

A8 300-S

B15x15 650-E

B15x15 650-E

B15x15 660-E

A8 200-S

A8 200-S

A8 200-S

A8 300-S

B12x12 500-R A8

300-S

A8 300-S

B12x12 500-R

A8 300-S

B12x12 500-R x1 x1

I10 380-S

H12x12 380-R

A8 170-S

A6 70-S

LAB

164-115

BLOOD DRAW

164-111

BLOOD DRAW

164-110

WAITING

164-104

DELIVERY

STORAGE

164-116

STAIR

S-2

IT CLOSET

164-128

VAULT

NARCOTICS

164-121

CORRIDOR

164-127

TOILET

164-131

LAB MANAGER

OFFICE

164-130

PSA OFFICE

164-129

WOMEN'S

TOILET

164-105

MEN'S TOILET

164-106

FAMILY TOILET

164-107

HAC

164-108

CHEMO

164-125

SECRETARY

OFFICE

164-138

MANAGER

OFFICE

164-137

TH/C

T H/C

T H/C

16x14 12x14

TH/C

TH/C

T H/C

T H/C

T H/C T H/C

TH/C

T H/C

TH/C

TH/C TH/C

T H/C

TH/C

PHARMACY

164-124

TC

T C

T H/C

16x14

12x1410x14 x8

14x14 16x14 10x14

32x16

10x10

8x

12x10

12x12

10x10

10x10

PHLEBOTOMY

164-109

8x10 14x16

12x12

10x8

MH102

MH102

TEF

3MEN'S TOILET

164-139

16x14 12x148x14

8x

D8 250-S

D8 250-S

12x12VAV

VAV

24x12

18x8 18x8

18x12 6x10

12x10 8x10

14x12 12x12 14 x1 x1

20x1624x16

VAV

8x8

D8 200-S

12x12

8x10

STACKED DUCTS:

18x18 RETURN AIR DUCT (HIGH) 18x12 SUPPLY AIR DUCT (LOW)

OPEN OFFICE

164-132

DP

DP

MECHANICAL SHEET NOTES

1. 6"Ø EXHAUST DUCT UP THROUGH ROOF.

2. 16x16 EXHAUST AIR DUCT (EF-1) DOWN . TERMINATE DUCT

HORIZONTALLY AT 45 DEGREES, EXHAUST AIR AWAY FROM BUILDING.

PROVIDE INSECT SCREEN AT TERMINATION.

3. 12x12 EXHAUST AIR DUCT UP TO STRF-1 ON ROOF.

4. ROUTE REFRIGERANT PIPING FROM INDOOR UNIT AS DIRECTLY AS

POSSIBLE, TO OUTDOOR UNIT, MINIMIZING THE AMOUNT OF EXTERIOR

EXPOSED REFRIGERANT PIPING.

5. 60x40 EXHAUST AIR DUCT UP TO AHU-1 ON ROOF. TRANSITION TO HORIZONTAL 40x20 DUCT WITH VARIABLE INLET/OUTLET ELBOW.

6. KEYNOTE NOT USED.

7. 15x15 TRANSFER AIR DUCT.

8. 42x18 EXHAUST AIR DUCT UP TO AHU-3 ON ROOF. TRANSITION TO 24x12

DUCT IN VERTICAL.

9. 16x16 EXHAUST AIR DUCT (EF-2) DOWN . TERMINATE DUCT

HORIZONTALLY AT 45 DEGREES, EXHAUST AIR AWAY FROM BUILDING.

PROVIDE INSECT SCREEN AT TERMINATION.

10. KEYNOTE NOT USED.

11. 42x18 SUPPLY AIR DUCT UP TO AHU-3 ON ROOF. TRANSITION TO 18x14

DUCT IN VERTICAL.

12. 15x15 TRANSFER AIR DUCT.

13. 16x18 SUPPLY AIR DUCT (AHU-2) DOWN TO LOWER LEVEL.

14. 20x20 RETURN AIR DUCT (AHU-2) DOWN TO LOWER LEVEL.

15. 10x10 TRANSFER AIR DUCT.

16. 42x24 SUPPLY AIR DUCT UP TO AHU-1 ON ROOF. TRANSITION TO 32x16

DUCT IN VERTICAL.

17. KEYNOTE NOT USED.

18. 14x14 EXHAUST AIR DUCT UP TO FUTURE STROBIC FAN ON ROOF.

TERMINATE DUCT AND CAP DUCT BELOW ROOF. EXHAUST AIR DUCT

SHALL BE STAINLESS STEEL.

19. 12x12 EXHAUST AIR DUCT UP TO STRF-2 ON ROOF.

20. 14x14 EXHAUST AIR DUCT DOWN TO LOWER LEVEL. EXHAUST DUCT

SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY LABS. EXHAUST AIR

DUCT SHALL BE STAINLESS STEEL.

21. 30x30 RETURN AIR DUCT UP TO AHU-4 ON ROOF.

22. 36x24 OUTSIDE AIR DUCT DOWN TO LOWER LEVEL.

23. 36x24 OUTSIDE AIR DUCT UP TO PENTHOUSE.

24. 16x12 SUPPLY AIR DUCT UP AND DOWN. TRANSITION AND OFFSET AS

NECESSARY TO AVOID STRUCTURE. SUPPLY AIR DUCT SHALL SERVE

FUTURE CYTOLOGY AND HISTOLOGY LABS.

25. 10x10 EXHAUST AIR DUCT UP TO EF-3 ON ROOF.

26. 50x20 SUPPLY AIR DUCT UP TO AHU-4 ON ROOF. TRANSITION TO 26x16

DUCT IN VERTICAL.

27. VENTURI AIR VALVE IN VERTICAL POSITION ABOVE LAB HOOD. CONNECT

UPSTREAM DUCT TO LAB HOOD. HOOD DESIGN BASED ON 500 ACFM

AND 0.3" W.C. STATIC PRESSURE [BAKER SG303]. FURNISH AND INSTALL

ZONE PRESCENCE SENSOR ON HOOD. ZONE PRESCENCE SENSOR

SHALL BE PHOENIX CONTROLS MODEL ZPS OR VA APPROVED EQUAL.

LAB HOOD SHALL BE PROVIDED BY OTHERS.

28. KEYNOTE NOT USED.

29. AFMS TRANSMITTER ABOVE CEILING.

30. CONTAINMENT CHAMBER SHALL NOT BE DUCTED. CHAMBER DESIGN

BASED ON 250 SCFM RECIRCULATED AIR [CTG MIC DUAL CHAMBER

A2000S]. CONTAINMENT CHAMBER SHALL BE PROVIDED BY OTHERS.

31. CONNECT 8"Ø EXHAUST DUCT TO CHEMO HOOD. HOOD DESIGN BASED

ON 510 ACFM AND 2.0" W.C. STATIC PRESSURE [NUAIRE NU-NTE797-400].

FURNISH AND INSTALL ZONE PRESCENCE SENSOR ON HOOD. ZONE

PRESCENCE SENSOR SHALL BE PHOENIX CONTROLS MODEL ZPS OR VA

APPROVED EQUAL. CHEMO HOOD SHALL BE PROVIDED BY OTHERS.

32. KEYNOTE NOT USED.

33. KEYNOTE NOT USED.

34. FURNISH AND INSTALL ROOM PRESSURE MONITOR AND DIFFERENTIAL

PRESSURE SENSORS THAT WILL MONITOR (1) DIFFERENTIAL PRESSURE

BETWEEN CHEMO AND CHEMO AIR LOCK AND (2) DIFFERENTIAL

PRESSURE BETWEEN CHEMO AIR LOCK AND PHARMACY. ROOM

PRESSURE MONITOR SHALL BE TSI MODEL RPM20 OR VA APPROVED

EQUAL. INSTALL PRESSURE SENSOR PER MANUFACTURER'S

INSTALLATION INSTRUCTION.

35. FURNISH AND INSTALL ROOM PRESSURE MONITOR AND DIFFERENTIAL

PRESSURE SENSORS THAT WILL MONITOR (1) DIFFERENTIAL PRESSURE

BETWEEN STERILE PREP AND STERILE PREP AIR LOCK AND (2)

DIFFERENTIAL PRESSURE BETWEEN STERILE PREP AIR LOCK AND

PHARMACY. ROOM PRESSURE MONITOR SHALL BE TSI MODEL RPM20

OR VA APPROVED EQUAL. INSTALL PRESSURE SENSOR PER

MANUFACTURER'S INSTALLATION INSTRUCTION.

36. FURNISH AND INSTALL ROOM PRESSURE MONITOR AND DIFFERENTIAL

PRESSURE SENSORS THAT WILL MONITOR (1) DIFFERENTIAL PRESSURE

BETWEEN LAB AND PHLEBOTOMY AND (2) DIFFERENTIAL PRESSURE

BETWEEN LAB AND CORRIDOR. ROOM PRESSURE MONITOR SHALL BE

TSI MODEL RPM20 OR VA APPROVED EQUAL. INSTALL PRESSURE

SENSOR PER MANUFACTURER'S INSTALLATION INSTRUCTION.

37. FURNISH AND INSTALL NEW ELBOW SILENCER AT THE BOTTOM OF THE

DUCT. SILENCER SHALL BE VAW SYSTEMS MODEL # REL OR VA

APPROVED EQUAL. INSTALL PER MANUFACTURER'S INSTALLATION

INSTRUCTION.

MECHANICAL GENERAL NOTES

A. AIRFLOWS INDICATED ARE ACTUAL CUBIC FEET PER MINUTE (ACFM).

B. FINAL LOCATION OF THERMOSTATS, ROOM PRESSURE MONITORS, AND

DIFFERENTIAL PRESSURE SENSORS SHALL BE COORDINATED WITH

OWNER, TEMPERATURE CONTROLS CONTRACTOR, AND GENERAL

CONTRACTOR.

C. ALL DUCTWORK ASSOCIATED WITH STROBIC FANS SHALL BE

STAINLESS STEEL.

D. PROVIDE WEATHERPROOF JACKETING FOR ALL EXPOSED DUCTWORK.

E. INSULATE ALL SUPPLY AIR AND OUTSIDE AIR DUCTWORK.

F. BRANCH DUCTWORK TO AIR TERMINAL SHALL BE SAME AS NECK SIZE

UNLESS OTHERWISE NOTED.

G. BRANCH HOT WATER PIPING TO VAV BOXES, BOOSTER COILS, UNIT

HEATERS, ETC... SHALL BE MIN. 3/4" NOMINAL DIAMETER.

H. INSULATE ALL PIPING. SEE SPECIFICATIONS FOR INSULATION TYPE AND

THICKNESS.

I. PROVIDE ACCESS DOORS IN HARD CEILINGS FOR ACCESS TO

EQUIPMENT.

H H.3 H.9 J K

TH/C

T H/C

TH/C

I10 350-S

C10 300-E

A8 300-S

31I10 390-S

C12 330-E

A8 300-S

STERILE PREP

164-126

CHEMO

164-125

PHARMACY

164-124

26x16

AFMS

AFMS

26x16

8x 8 12x8 x1

A8 300-S

B12x12 500-R

B12x12 500-R

B8x8 110-R

B12x12 500-R

A6 110-S

VD (TYP)

30x30 RETURN AIR DUCT TO

AHU-4 ON ROOF. TRANSITION

TO 26x26 DUCT IN VERTICAL.

3/4" RO UP

TO AHU-4 3/4" HWR

3/4" HWS

EF

x1 x1

18x14

24x16 20x16 x1

VAV

I10 380-S

C14 530-E

TH/C

EAV

CLOSET

164-135

C8 100-E

I6 120-S

EAV

EAV

SAV

SAV

VAV

12x12

EAV

12x10 12x814x10

SAV

SAV

EAV

10x10

VAV

10"Ø

10"Ø

8" Ø

A8 300-S

10x10

12x12

8x12 A8

300-S

A8 300-S

1 1/2" HWS

1 1/2" HWR

1" HWS

1" HWR

CHEMO AIR

LOCK

164-133

STERILE PREP

AIR LOCK

164-134

TH/C

"Ø

8"Ø

1 1/4" HWS

1 1/4" HWR

8x12

DP

DP

DPDP

G H H.3 H.9

8x8

8x8

10x10 x1

3 10 x1

18x18 x1 x1

VAV

TEF

4" CHWS

4" CHWR

3/4" RO

1 1/4" PHWS

1 1/4" PHWR

3" MPS

B6x6 70-R

A6

70-S VAV

A6 70-S

B6x6 70-R

A8 300-S

A8 300-S

A6 70-S

B6x6 70-R

A6 70-S

B6x6 70-R

A8 200-S

8x8

3" HWR

3" HWS

1 1/4" HWR

1 1/4" HWS

A6 70-S

B8x8 100-RB8x8

100-R

A6

100-SA6

50-S

B6x6 50-R

10x10

TH/C

BLOOD DRAW

164-111 BLOOD DRAW

164-110

PHLEBOTOMY

164-109

BLOOD DRAW

164-114 BLOOD DRAW

164-112

PASS-THRU

164-122STORAGE BH &

AR

164-117

PROCUREMENT

STATION

164-118

PRIVATE

CONSULTATION

164-123

PHARMACY

164-124

WAITING

164-104

1 1/4" PC

3/4" RO

3/4" RO

TEF

MEN'S TOILET

164-139

8x

A6 100-S

24x12

2" HWR

2" HWS

x8 x1

STACKED DUCTS:

18x18 RETURN AIR DUCT (HIGH) 18x14 SUPPLY AIR DUCT (LOW)

Project Number

Pl ot

D a te

Date

Location

ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:

Approved: Project Director

Project Title

Checked Drawn

Drawing Number

Dwg. of

Building Number

Date:Revisions:

VA FORM 08-6231

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot

6"

6"

6"

6"

PRESCOTT, ARIZONA

KEY PLAN

NORTH

Fi le

-201 W. CUS HING S TREET

TUCS ON, AZ 85 718

T: 520.882.4484 F: 520.882.5560

BUILDING

BUILDING

MIRACLE MILE

100% BID DOCUMENT

O

PE

N A

IR

E

N

TR

A N

C E

/3

/2

3:

:1

P

M C

:\U se rs \a sa nd le r\D oc um en ts

\1 3-

M C

D _A

S an dl er

.rv t

OVERALL UPPER LEVEL HVAC PLAN

MH102

13-127

ASST

CLINICAL LABORATORY AND

PHARMACY BUILDING

12/03/2015

1/8" = 1'-0"MH102

1 OVERALL UPPER LEVEL HVAC PLAN

1/4" = 1'-0"MH102

3 ENLARGED UPPER LEVEL HVAC PLAN - CHEMO AND STERILE PREP

1/4" = 1'-0"MH102

2 ENLARGED UPPER LEVEL HVAC PLAN - PHLEBOTOMY AND PHARMACY

BIDDING DOCUMENT REV. 1 Nov. 02, 2015 BID SUBMISSION Dec. 03, 2015 vhapreboydt Highlight vhapreboydt Highlight vhapreboydt Highlight vhapreboydt Highlight

0.1

0.5

G H H.3 H.9 J K K.5 LFD

ACCU

ACCU

EF

AHU

AHU

ROS

PENTHOUSE

164-201

STAIR

S-3

64x24

STRF

STRF

MH104

MH104

AHU

G H

EF

EF

IH

6"Ø TOILET EXHAUST FROM

BELOW. TERMINATE ABOVE

PENTHOUSE ROOF.

MECHANICAL SHEET NOTES

1. 12x16 SUPPLY AIR DUCT DOWN TO LOWER LEVEL. SUPPLY AIR DUCT

SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY LABS. OFFSET

AS NECESSARY TO AVOID BEAMS. CAP DUCT AT PENTHOUSE

SHAFT.

2. EXHAUST FAN MOUNTED ON 12" HIGH ROOF CURB.

3. AIR HANDLING UNIT AHU-3 MOUNTED ON 18" HIGH ROOF CURB.

CURB SHALL BE DESIGNED TO SUPPORT AHU-3 AND ASSOCIATED

COMPONENTS INCLUDING DUCTWORK AND PIPING ABOVE CURB AT

15,000 LBS. CURB SHALL BE INSULATED AND HAVE VIBRATION

ISOLATORS.

4. AIR HANDLING UNIT AHU-1 MOUNTED ON 18" HIGH ROOF CURB.

CURB SHALL BE DESIGNED TO SUPPORT AHU-1 AND ASSOCIATED

COMPONENTS INCLUDING DUCTWORK AND PIPING ABOVE CURB AT

15,000 LBS. CURB SHALL BE INSULATED AND HAVE VIBRATION

ISOLATORS.

5. AIR HANDLING UNIT AHU-4 MOUNTED ON 14" HIGH ROOF CURB.

CURB SHALL BE DESIGNED TO SUPPORT AHU-3 AND ASSOCIATED

COMPONENTS INCLUDING DUCTWORK AND PIPING ABOVE CURB AT

8,000 LBS. CURB SHALL BE INSULATED AND HAVE VIBRATION

ISOLATORS.

6. APPROXIMATE LOCATION AND SIZE OF FUTURE AIR HANDLING UNIT

THAT SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY LABS.

ALLOCATE SUFFICIENT SPACE IN PENTHOUSE FOR FUTURE

DUCTWORK, PIPING, EQUIPMENT, AND CLEARANCES ASSOCIATED

WITH FUTURE AIR HANDLING UNIT.

7. AIR COOLED CONDENSING UNIT MOUNTED ON 4" HIGH CONCRETE

PAD.

8. EXHAUST AIR DUCT HIGH. TERMINATE WITH GRILLE.

9. STROBIC FAN STRF-1 MOUNTED ON 12" HIGH ROOF CURB. CURB

SHALL BE DESIGNED TO SUPPORT THE STROBIC FAN AT 500 LBS.

CURB SHALL BE INSULATED AND HAVE VIBRATION ISOLATORS.

10. 12x12 EXHAUST AIR DUCT DOWN TO UPPER LEVEL. TRANSITION FROM 20x20 DUCT IN VERTICAL.

11. 60x24 SUPPLY AIR DUCT TRANSITION TO 32x24 DUCT DOWN TO

UPPER LEVEL.

12. 60x20 EXHAUST AIR DUCT DOWN TO UPPER LEVEL.

13. 42x24 SUPPLY AIR DUCT DOWN TO UPPER LEVEL.

14. 64x40 EXHAUST AIR DUCT DOWN TO UPPER LEVEL.

15. NOT USED.

16. BLANK OFF LOUVER. LOUVER SHALL BE FOR FUTURE AIR HANDLING

UNIT OUTSIDE AIR INTAKE SERVING FUTURE CYTOLOGY AND

HISTOLOGY LABS.

17. 50x20 SUPPLY AIR DUCT DOWN TO UPPER LEVEL.

18. 30x30 RETURN AIR DUCT DOWN TO UPPER LEVEL.

19. 54x18 OUTSIDE AIR DUCT ABOVE AHU-4.

20. NEMA 3R RATED VARIABLE FREQUENCY DRIVES ASSOCIATED WITH

STROBIC FAN. MOUNT STRF-1 VFD ON WALL. MOUNT STRF-2 VFD

AND STRF-3 VFD ON UNISTRUT.

21. 6"Ø CLOSET EXHAUST DUCT DOWN THROUGH ROOF. TERMINATE

DUCT ABOVE ROOF.

22. 6"Ø TOILET EXHAUST DUCT DOWN THROUGH ROOF.

23. MOUNT REVERSE OSMOSIS SKID AND TANK ON 4" HOUSEKEEPING

PAD. REFER TO SECTION 22 67 19.16 FOR SPECIFICATION ON

REVERSE OSMOSIS SYSTEM.

24. PNEUMATIC TUBE SYSTEM BLOWER SHOWN FOR REFERENCE

ONLY.

25. STROBIC FAN STRF-2 MOUNTED ON 12" HIGH ROOF CURB. CURB

SHALL BE DESIGNED TO SUPPORT THE STROBIC FAN AT 1,500 LBS.

CURB SHALL BE INSULATED AND HAVE VIBRATION ISOLATORS.

26. KEYNOTE NOT USED.

27. APPROXIMATE SIZE AND LOCATION OF FUTURE STROBIC FAN THAT

SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY LABS.

28. KEYNOTE NOT USED.

29. PNEUMATIC TUBE SYSTEM TRANSFER UNIT SHOWN FOR

REFERENCE ONLY.

30. DOMESTIC HOT WATER HEATERS SHOWN FOR REFERENCE ONLY.

31. GRAVITY INTAKE HOOD IH-1 MOUNTED ON ROOF CURB.

32. 36x36 OUTSIDE AIR DUCT DOWN TO PENTHOUSE.

MECHANICAL GENERAL NOTES

A. AIRFLOWS INDICATED ARE ACTUAL CUBIC FEET PER MINUTE (ACFM).

B. FINAL LOCATION OF THERMOSTATS, ROOM PRESSURE MONITORS, AND

DIFFERENTIAL PRESSURE SENSORS SHALL BE COORDINATED WITH

OWNER, TEMPERATURE CONTROLS CONTRACTOR, AND GENERAL

CONTRACTOR.

C. ALL DUCTWORK…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .