This document is a mechanical systems design specification and bidding package for the Clinical Laboratory and Pharmacy Building (Project 13-127) located in Prescott, Arizona, prepared for the Department of Veterans Affairs.
The specifications establish comprehensive requirements for the mechanical contractor to furnish and install complete HVAC, piping, and control systems. Key deliverables include air handling units (AHU-1 through AHU-4), variable air volume (VAV) boxes, exhaust fans, humidification systems, steam pressure reducing stations, chilled water and hot water distribution piping, condensate pumps, glycol makeup units, and building automation controls. Design conditions specify indoor temperatures of 73°F with 25% relative humidity for winter operation and 73°F with 30% relative humidity for summer operation, with outdoor design based on Prescott, Arizona weather data. The contractor must perform system balancing through an independent AABC/NEBB-certified balancing contractor, submit shop drawings for approval prior to installation, provide as-built drawings in reproducible form, conduct equipment startup and operator training, and guarantee all work and materials per specification requirements. All work must comply with current federal building codes, ASHRAE standards, local utility requirements, and OSHA safety provisions. The contractor bears responsibility for all permit fees, plan review fees, licenses, inspections, and taxes. Ductwork must meet SMACNA construction standards with specified leakage rates based on system pressure classifications. The project includes future provisions for expanded cytology and histology laboratories with capped ductwork and piping stub-outs. Bid submission deadline was December 3, 2015, with the project designated as 100% bid document revision 1.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 10-B162 Controls3.pdf | ||
| 7- Chiller Plant System Drawing.pdf | ||
| 6-B162 Controls1.pdf | ||
| 8-B158 Mechanical Schedules.pdf | ||
| 2- 70-M-601.pdf | ||
| 5-B158 HVAC Layout.pdf | ||
| 4-2016_649-409_162_Mechanical.pdf | ||
| 3- 70-M-602.pdf | ||
| 9-B162 Controls2.pdf | ||
| CS RFQ- Delta BAS Enteliweb- 36C26226Q1025- Unrestricted.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEGEND MECHANICAL GENERAL NOTES
A. READING AND TESTS OF ALL AIR DEVICES SHALL INCLUDE REQUIRED
VELOCITIES (FPM), TEST RESULTANT VELOCITIES, REQUIRED
CAPACITIES (CFM) AND TEST RESULTANT CAPACITIES AFTER
ADJUSTMENTS.
B. IDENTIFY EACH AIR DEVICE BY LOCATION. TYPE AND SIZE.
C. TEST AND ADJUST EACH AIR DEVICE TO WITHIN 10% OF DESIGN.
MECHANICAL CONTRACTOR SHALL FURNISH AND INSTALL A COMPLETE
TEMPERATURE CONTROL SYSTEM.
ALL THERMOSTATS SHALL BE MOUNTED AT +54" ABOVE FINISHED
FLOOR (UNLESS OTHERWISE SPECIFIED). THERMOSTATS SHALL NOT
INTERFERE WITH SHELVING, VENDING MACHINES, OTHER FIXTURES OR
CONTROLS.
ALL WORK SHALL BE DONE IN ACCORDANCE WITH ALL CURRENT
FEDERAL BUILDING CODES, REGULATIONS, AND REQUIREMENTS, LOCAL
UTILITY COMPANY REQUIREMENTS, AND ASHRAE STANDARDS.
THIS CONTRACTOR SHALL PAY ALL PERMIT FEES, PLAN REVIEW FEES,
LICENSE FEES, INSPECTIONS, AND TAXES APPLICABLE TO THEIR DIVISION
AND SHALL BE INCLUDED IN THE BASE BID AS PART OF THEIR CONTRACT.
THIS CONTRACTOR SHALL BE LICENSED, BONDED, INSURED, AND CAPABLE
OF PERFORMING QUALITY WORKMANSHIP. THIS CONTRACTOR GUARANTEES
ALL OF HIS WORK AND MATERIALS FOR THE PERIOD AS REQUIRED IN THE
SPECIFICATIONS. FROM FINAL ACCEPTANCE BY THE OWNER/COR.
THIS CONTRACTOR SHALL ESTABLISH SAFE WORKING PROCEDURES FOR
THE PROTECTION OF THE WORKMEN IN ALL PHASES OF WORK, COMPLYING
WITH ALL APPLICABLE PROVISIONS OF CITY, STATE, AND FEDERAL SAFETY
LAWS (OSHA) AND AS RECOMMENDED IN THE "MANUAL OF ACCIDENT
PREVENTION IN CONSTRUCTION" AS ISSUED BY THE ASSOCIATION OF
GENERAL CONTRACTORS OF AMERICA, IN., 20TH AND E. STREETS, N.W.
WASHINGTON, D.C.
THIS CONTRACTOR IS RESPONSIBLE FOR SCHEDULING THE PURCHASE,
DELIVERY, RECEIVING, UNLOADING, UNCRATING, STORING, SETTING IN
PLACE, AND PROTECTING ALL NEW EQUIPMENT FURNISHED BY THIS
CONTRACTOR AND EQUIPMENT FURNISHED BY OWNER FROM DAMAGE BY
VANDALISM AND WEATHER DURING CONSTRUCTION.
THIS CONTRACTOR SHALL SUBMIT SHOP DRAWINGS AS REQUIRED IN THE
SPECIFICATIONS PRIOR TO THE START OF INSTALLATION FOR OWNER /
COR APPROVAL AND THE SUCCESSFUL REVIEW BY THE ARCHITECT
***ENGINEER***.
THIS CONTRACTOR SHALL FURNISH AS-BUILT DRAWINGS TO THE
OWNER BEFORE FINAL PAYMENT WILL BE ISSUED. THE AS-BUILT
DRAWINGS SHALL BE SUBMITTED IN REPRODUCIBLE FORM.
THIS CONTRACTOR SHALL BE RESPONSIBLE FOR THE STARTUP OF
ALL HEATING, VENTING, AND AIR-CONDITIONING EQUIPMENT.
THIS CONTRACTOR SHALL PROVIDE A COMPETENT OPERATING
TECHNICIAN TO INSTRUCT THE OWNER IN THE OPERATION AND
MAINTENANCE OF THE NEW EQUIPMENT.
UPON COMPLETION OF THE WORK, THIS CONTRACTOR SHALL
REVIEW AND CHECK THE ENTIRE PORTION OF WORK, CLEAN
EQUIPMENT AND DEVICES. REMOVE SURPLUS MATERIALS AND
RUBBISH FROM THE PROPERTY AND LEAVE THE WORK IN NEAT AND
CLEAN ORDER AND IN COMPLETE WORKING CONDITION. EACH
RESPECTIVE CONTRACTOR SHALL BE RESPONSIBLE FOR THE
REMOVAL OF ANY CARTONS, DEBRIS, EQUIPMENT, ETC. INSTALLED
BY THIS CONTRACTOR INCLUDING EQUIPMENT FURNISHED BY
OTHERS AND UNPACKED OR REMOVED FROM CARTONS BY THIS
CONTRACTOR.
THIS CONTRACTOR SHALL REVIEW ENTIRE SET OF CONTRACT DOCUMENTS: INCLUDING BUT
NOT NECESSARILY LIMITED TO ALL ARCHITECTURAL, ALL STRUCTURAL, ALL MECHANICAL,
ALL PLUMBING, ALL FIRE PROTECTION, ALL ELECTRICAL DRAWINGS AND ENTIRE PROJECT
MANUAL. THIS CONTRACTOR SHALL ACKNOWLEDGE AND INCLUDE IN THE SCOPE OF WORK
(CONTRACT) ALL CONDITIONS PERTINENT TO THE COMPLETION OF HIS WORK. THIS
CONTRACTOR SHALL FULLY COORDINATE HIS WORK WITH THE INSTALLATION OF WORK BY
OTHER TRADES AND MAKE NECESSARY FIELD ADJUSTMENTS AS REQUIRED TO
ACCOMODATE THE INSTALLATION. ALL OF THE ABOVE SHALL BE INCLUDED IN THE SCOPE
OF WORK AT NO ADDITIONAL CHARGE TO THE OWNER.
THIS CONTRACTOR SHALL CAREFULLY EXAMINE THE DRAWINGS AND SPECIFICATIONS,
VISIT THE SITE OF THE WORK AND FULLY INFORM THEMSELVES AS TO ALL CONDITIONS
AND MATTERS THAT CAN, IN ANY WAY, AFFECT THE WORK OR THE COST THEREOF.
SHOULD THIS CONTRACTOR FIND DISCREPANCIES IN, OR OMISSIONS FROM THE
DRAWINGS, SPECIFICATIONS OR OTHER DOCUMENTS, OR BE IN DOUBT AS TO THEIR
MEANING, NOTIFY THE OWNER AND THE ARCHITECT AT ONCE, IN WRITING, OF ANY
DISCREPANCIES BETWEEN EXISTING CONDITIONS AND NEW WORK, OR BETWEEN THEIR
WORK AND THE WORK OF THEIR TRADES AND OBTAIN CLARIFICATION PRIOR TO
SUBMITTING ANY BID. LACK OF SUCH NOTIFICATION SHALL BE CONSTRUED AS TO
INDICATE NO DISCREPANCIES WILL NOT BE GRANTED AFTER THE AWARD OF CONTRACT
FOR ANY WORK REQUIRED TO COMPLY WITH THESE REQUIREMENTS.
THE DRAWINGS INDICATE DIAGRAMMATICALLY THE INTENT, GENERAL CHARACTER,
REQUIREMENTS AND LOCATION OF THE WORK SHOWN AND INCLUDED. THE
WORK INDICATED BUT HAVING MINOR DETAILS OBVIOUSLY OMITTED SHALL BE
PROVIDED AT NO ADDITIONAL COST TO THE OWNER.
THIS CONTRACTOR IS REQUIRED TO BID, AS SPECIFIED, ON THE DRAWINGS
WITHOUT DEVIATION. THIS CONTRACTOR IS INVITED TO SUBMIT SUBSTITUTIONS
FROM THE BASE BID, ONLY IF THE SUBSTITUTIONS ARE APPROVED BY THE
OWNER / COORDINATE AND SUCCESSFULLY REVIEWED BY THE ARCHITECT,
PRIOR TO SUBMITTING THE BID.
IT IS THE INTENT OF THESE DOCUMENTS THAT THE MECHANICAL
CONTRACTOR PROVIDE ALL LABOR, MATERIAL, EQUIPMENT AND TOOLS FOR
THE COMPLETE INSTALLATION OF ALL WORK SHOWN ON THE PLANS AND/OR
DESCRIBED HEREIN, INCLUDING ALL DEVICES, CONTROLS AND
APPURTENANCES REQUIRED TO SET NEW SYSTEMS INTO OPERATION.
SHOULD CONDITIONS NECESSITATE ANY REARRANGEMENTS, OR IF
DUCTWORK CAN BE RUN TO BETTER ADVANTAGE, PREPARE AND SUBMIT
SHOP DRAWINGS SHOWING THE CHANGES BEFORE PROCEEDING WITH THE
WORK. IF SUCH CHANGES ARE APPROVED BY THE OWNER AND
SUCCESSFULLY REVIEWED BY THE ARCHITECT, THEY SHALL BECOME A PART
OF THE CONTRACT AFTER THEIR APPROVAL.
THIS CONTRACTOR SHALL VERIFY ALL MOUNTING, ALL ARRANGEMENTS,
HEIGHTS AND LOCATIONS PRIOR TO ROUGH-IN. ANY MENTION OF A SPECIFIC
MOUNTING ARRANGEMENT, WEIGHT OR LOCATION SHALL NOT RELIEVE THE
CONTRACTOR OF THE RESPONSIBILITY TO VERIFY THE SPECIFIC
REQUIREMENT FURNISHED OR THE OTHER TRADES WORKING IN THE SAME
AREA. NO ADDITIONS TO THE CONTRACT SUM WILL BE PERMITTED FOR ITEMS
INSTALLED IN WRONG LOCATIONS, IN CONFLICT WITH OTHER WORK, ETC.
AN INDEPENDENT BALANCING CONTRACTOR SHALL BE A SUBCONTRACTOR
OF THE MECHANICAL CONTRACTOR AND SHALL BE RESPONSIBLE FOR
BALANCING ALL NEW AND EXISTING DUCTWORK SYSTEMS RELATED TO THE
PREMISES. SUCH BALANCING SHALL BE PERFORMED BY A MEMBER OF THE
ASSOCIATED AIR BALANCE COUNCIL AND NATIONAL ENVIRONMENTAL
BALANCING BUREAU. SUBMIT THE REQUIRED COPIES OF THE AIR BALANCING
REPORT TO THE OWNER FOR APPROVAL AND SUCCESSFUL REVIEW BY THE
ARCHITECT. CONTAINING THE FOLLOWING INFORMATION:
N CONSTRUCTION NOTE
A
B
VIEW CALLOUT
A = VIEW NUMBER
B = SHEET NUMBER
A
B-C
AIR TERMINAL TAG
A = AIR TERMINAL TYPE AND NECK SIZE
B = AIRFLOW
C = FLOW DIRECTION (S=SUPPLY, R=RETURN,
E=EXHAUST, T=TRANSFER)
A
B
MECHANICAL EQUIPMENT TAG
A = EQUIPMENT TYPE
B = EQUIPMENT NUMBER
ACFM ACTUAL CUBIC FEET PER MINUTE
AFF ABOVE FINISHED FLOOR
AFMD AIR FLOW MEASURING DEVICE
AHU AIR HANDLING UNIT
APD AIR PRESSURE DROP
AS AIR SEPARATOR
BC BOOSTER COIL
CD CONDENSATE DRAIN
CHWR CHILLED WATER RETURN
CHWS CHILLER WATER SUPPLY
CP CONDENSATE PUMP
CUH CABINET UNIT HEATER
CV CONSTANT VOLUME, CONTROL VALVE
DEG DEGREE
EA EXHAUST AIR
EAT ENTERING AIR TEMPERATURE
EAV EXHAUST AIR VALVE
EF EXHAUST FAN
ESP EXTERNAL STATIC PRESSURE
ET EXPANSION TANK
EWT ENTERING WATER TEMPERATURE
EX EXISTING
GMU GLYCOL MAKEUP UNIT
HUM HUMIDIFIER
HWR HOT WATER RETURN
HWS HOT WATER SUPPLY
HX HEAT EXCHANGER
LAT LEAVING AIR TEMPERATURE
LPS LOW PRESSURE STEAM
LWT LEAVING WATER TEMPERATURE
MA MIXED AIR
MD MOTORIZED DAMPER
MPS MEDIUM PRESSURE STEAM
OA OUTSIDE AIR
PC PUMPED CONDENSATE
PG PROPYLENE GLYCOL
PHWR PREHEAT WATER RETURN
PHWS PREHEAT WATER SUPPLY
PRV PRESSURE REGULATING VALVE
RA RETURN AIR
RO REVERSE OSMOSIS
RF RETURN FAN
SA SUPPLY AIR
SAV SUPPLY AIR VALVE
SF SUPPLY FAN, SQUARE FEET
ST STEAM TRAP
UH UNIT HEATER
VAV VARIABLE AIR VOLUME
VD VOLUME DAMPER
WPD WATER PRESSURE DROP
A
B
ROOM TAG
A = ROOM NAME
B = ROOM NUMBER
GENERAL TAGS AND IDENTIFICATION
COMMON ABBREVIATIONS
DUCTWORK
CEILING SUPPLY DIFFUSER
CEILING RETURN/TRANSFER REGISTER
CEILING EXHAUST REGISTER
CONICAL TAKEOFF
FIRE DAMPER
FLEXIBLE DUCTWORK
RADIUS ELBOW
MITERED ELBOW
SUPPLY AIR DUCT TURNING UP
SUPPLY AIR DUCT TURNING DOWN
RETURN AIR OR TRANSFER AIR DUCT TURNING UP
RETURN AIR OR TRANSFER AIR DUCT TURNING DOWN
EXHAUST AIR DUCT TURNING UP
EXHAUST AIR DUCT TURNING DOWN
AxB C"Ø DUCT SIZE (RECTANGULAR/FLAT OVAL AND ROUND)
MOTORIZED DAMPER
VOLUME DAMPER
45 DEGREE BEVELED TAKEOFF
PIPING
TEE
CAPPED PIPE
PIPE SIZE A AND
DESIGNATION BA" B
PIPE CONTINUATION
ISOLATION VALVE
BALL VALVE
BUTTERFLY VALVE
GLOBE VALVE
GATE VALVE
BALANCING VALVE
2 WAY MOTORIZED VALVE
PRESSURE REDUCING VALVE
TRIPLE DUTY VALVE
CHECK VALVE
STRAINER WITH BALL VALVE
PIPE UP
PIPE DOWN
THERMOMETER
PRESSURE GAUGE
STEAM TRAP
TEST PLUG
PRESSURE SAFETY VALVE
UNION
POINT OF CONNECTION (NEW WORK)
POINT OF DISCONNECTION (DEMO WORK)
FLOW DIRECTION
COMMON EQUIPMENT
SINGLE DUCT VAV BOX
SINGLE DUCT VAV BOX WITH REHEAT COIL
VENTURI AIR VALVE
UNIT HEATER
CABINET UNIT HEATER
INLINE PUMP
AIR SEPARATOR
VARIABLE FREQUENCY DRIVE
CONTROLS
AI ANALOG INPUT (TO PANEL)
AO ANALOG OUTPUT (OUT OF PANEL)
BI BINARY INPUT (TO PANEL)
BO BINARY OUTPUT (OUT OF PANEL)
C COMMON
NC NORMALLY CLOSED
NO NORMALLY OPEN
P STATIC PRESSURE SENSOR
S SENSOR
M MOTORIZED AIR DAMPER PARALLEL BLADE
M MOTORIZED AIR DAMPER OPPOSED BLADE
DP DIFFERENTIAL PRESSURE SENSOR
MS MOTOR STARTER
VFD VARIABLE FREQUENCY DRIVE
SD DUCT SMOKE DETECTOR
CT CURRENT TRANSMITTER
FZ FREEZE STAT
T TEMPERATURE SENSOR
T H/C
THERMOSTAT-HEATING AND COOLING
T C
THERMOSTAT-COOLING ONLY
T V
THERMOSTAT-VENTILATION ONLY
T H
THERMOSTAT-HEATING ONLY
HUMIDISTAT/HUMIDIFIER
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
H
HOT WATER SUPPLYHWS
PIPING DESIGNATIONS
HOT WATER RETURNHWR
PREHEAT WATER SUPPLY - WITH 20% PROPYLENE GLYCOL WHERE APPLICABLEPHWS
PREHEAT WATER RETURN - WITH 20% PROPYLENE GLYCOL WHERE APPLICABLEPHWR
CHILLED WATER SUPPLY - WITH 20% PROPYLENE GLYCOL WHERE APPLICABLECHWS
CHILLED WATER RETURN - WITH 20% PROPYLENE GLYCOL WHERE APPLICABLECHWR
LOW PRESSURE STEAM (DOWNSTREAM OF PRV)LPS
MEDIUM PRESSURE STEAMMPS
CONDENSATE DRAINCD
CONDENSATE RETURNCR
PUMPED CONDENSATEPC
HUMIDIFICATION STEAMHUM
REVERSE OSMOSIS WATERRO
OUTSIDE AIR DUCT TURNING DOWN
OUTSIDE AIR DUCT TURNING UP
DUCT CONSTRUCTION AND LEAKAGE SCHEDULE
SYSTEM PRESSURE
CLASS
SEAL
CLASSIFICATION
LEAKAGE
RATE
RECTANGULAR ROUND
+4 A 6 3MEDIUM PRESSURE SUPPLY
+2 A
-2 A
-4 A
-1 A
LOW PRESSURE SUPPLY
GENERAL EXHAUST
HOOD EXHAUST
OUTSIDE AIR
NOTES:
1. DUCT CONSTRUCTION SHALL BE IN ACCORDANCE WITH SMACNA DUCT CONSTRUCTION STANDARDS
2. ALL SYSTEM DUCT WORK SHALL BE LEAKAGE TESTED IN ACCORDANCE WITH SMACNA HVAC AIR DUCT LEAKAGE TEST MANUAL
MOTOR STARTER SCHEDULE
MOTOR MAX NEMA STARTER
VOLTAGE / PHASE HP SIZE
120/1 1/3 0
208/3 1-1/2 0
208/3 3 0
208/3 5 1
208/3 7-1/2 1
208/3 10 1
208/3 15 1
DESIGN CONDITIONS
SPACE TYPE
WINTER INDOOR WINTER OUTDOOR SUMMER INDOOR SUMMER OUTDOOR
NOTES
DB (°F) %RH DB (°F) WB (°F) DB (°F) %RH DB (°F) WB (°F)
LAB AREA 73 25 17 - 94.3 61.2 1,2
OFFICES 30
WAITING AREA 30
PHARMACY AREA 30
CHEMO 30
STERILE PREP 30
HISTOLOGY 30
CYTOLOGY 30
COMM ROOM 72
NOTES:
1. OUTDOOR DESIGN TEMPERATURES BASED ON VA DESIGN GUIDE VALUES (99.6% HEATING; 0.4% COOLING) FOR PRESCOTT, AZ
2. INDOOR DESIGN VALUES BASED ON PRESCOTT VA PREFERENCES.
3. INDOOR DESIGN VALUES ARE BASED ON STANDARD COMM ROOM DESIGN.
73 25
94.3
94.3
94.3
94.3
94.3
94.3
94.3
94.3
61.2
61.2
61.2
61.2
61.2
61.2
61.2
61.2
1,2
1,2
1,2
1,2
1,2
1,2
1,2
1,3
4. OUTDOOR DESIGN HUMIDITY BASED ON ASHRAE WEATHER DATA (99.6% HUMIDIFICATION) FOR PRESCOTT, AZ .
THIS OCCURS AT 36.9°F DB, -1.9°F DEW POINT, AND HUMIDITY RATIO OF 6.0 GRAINS MOISTURE PER POUND OF DRY AIR.
Project Number
Pl ot
D a te
Date
Location
ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
Date:Revisions:
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F
Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot
6"
6"
6"
6"
PRESCOTT, ARIZONA
Fi le
-201 W. CUS HING S TREET
TUCS ON, AZ 85 718
T: 520.882.4484 F: 520.882.5560
100% BID DOCUMENT
/3
/2
3:
:4
P
M C
:\U se rs \a sa nd le r\D oc um en ts
\1 3-
M C
D _A
S an dl er
.rv t
MECHANICAL SYMBOLS AND ABBREVIATIONS
M001
13-127
ASST
CLINICAL LABORATORY AND
PHARMACY BUILDING
12/03/2015
BIDDING DOCUMENT REV. 1 Nov. 02, 2015 BID SUBMISSION Dec. 03, 2015 vhapreboydt Highlight
HYDRONIC RETURN
HYDRONIC SUPPLY
AUTOMATIC AIR
VENT (TYP)
SHUT OFF
VALVE (TYP)
STRAINER WITH
BLOWDOWN VALVE
TEST PLUG (TYP)
DRAIN VALVE WITH
HOSE CONNECTION HEATING COIL
MANUAL
AIR VENT
UNION (TYP)
BALANCING
VALVE
2-WAY
CONTROL
VALVE
PRESSURE
GAUGE (TYP)
THERMOMETER (TYP)
NOTES:
1. COIL SHALL BE PIPED COUNTER FLOW TO AIR FLOW.
2. COOLING COILS SHALL HAVE 3 WAY CONTROL VALVES
AND SERVED BY EXISTING YORK CHILLERS.
HYDRONIC RETURN
HYDRONIC SUPPLY
AUTOMATIC AIR
VENT (TYP)
SHUT OFF
VALVE (TYP)
STRAINER WITH
BLOWDOWN VALVE
TEST PLUG (TYP)
DRAIN VALVE WITH
HOSE CONNECTION COOLING COIL
MANUAL
AIR VENT
UNION (TYP)
BALANCING
VALVE (TYP)
3-WAY
CONTROL
VALVE
PRESSURE
GAUGE (TYP)
THERMOMETER (TYP)
NOTES:
1. THIS DETAIL IS TYPICAL FOR CABINET UNIT HEATERS,
UNIT HEATERS, AND BOOSTER COILS.
HYDRONIC COIL
WATER RETURN
WATER SUPPLY
MANUAL AIR VENT 2-WAY CONTROL VALVE
BALANCING
VALVE
SHUT OFF
VALVE (TYP)
STRAINER WITH
BALL VALVE
DRAIN VALVE
WITH HOSE
CONNECTION
TEST PLUG (TYP)
M A
IN
D
U C
T
CONICAL OR
BELLMOUTH
CONNECTION
NOTE 1
NOTE 2 AND NOTE 3
CONTROL BOX
VARIABLE VOLUME
TERMINAL UNIT
HOT WATER REHEAT COIL
(WHERE AVAILABLE) TRANSITION AS
NECESSARY
LOW PRESSURE DUCT
HOT WATER RETURN
HOT WATER SUPPLY
2-WAY CONTROL VALVE
BALANCING VALVE
BALL VALVE (TYP)
STRAINER
MANUAL AIR
VENT (TYP)
NOTES:
1. MAXIMUM FLEXIBLE DUCT LENGTH SHALL BE 1'-0".
2. RIGID STRAIGHT DUCT LENGTH TO INLET OF TERMINAL UNIT SHALL BE MINIMUM 3
TIMES THE DIAMETER OF INLET.
3. A BRANCH DUCT SERVING AN INDIVIDUAL BOX MAY BE THE SAME SIZE AS THE BOX
INLET, PROVIDED THE EQUIVALENT LENGTH OF THE BRANCH DUCT, AS SHOWN,
DOES NOT EXCEED 10 FEET (3 METERS). FOR LONGER LENGTHS, INCREASE THE
DUCT SIZE AND PROVIDE A DUCT TRANSITION TO MAINTAIN THE DUCT STATIC
PRESSURE DROP AT OR BELOW 0.2"/100' [1.64Pa/m].
4. COMPONENT ARRANGEMENT MAY VARY BY MANUFACTURER. PROVIDE INSULATION
W/VAPOR BARRIER FOR CONNECTING DUCT SECTIONS.
UNION (TYP)
ROS
HUM
1 HUM
HUM
1" RO
3/ 4"
R O
3/4" RO
1" DCW
NOTES:
1. HUM-1, HUM-3, AND HUM-4 ARE ULTRASONIC HUMIDIFIERS.
2. HUM-2 ARE ELECTRIC RESISTIVE HUMIDIFIERS.
3. RO PIPING SHALL BE STAINLESS STEEL.
3/4" RO
HUM
4CAP PIPE FOR FUTURE
HUMIDIFIER SERVING
FUTURE CYTOLOGY AND
HISTOLOGY LABS.
Y-STRAINER
55 GALLON TANK
TRIPLE DUTY VALVE
PRESSURE SWITCH
LOW WATER CUT
OFF SWITCH
PUMP
DIAPHRAGM
EXPANSION TANK
PRESSURE GAUGE
SYSTEM OUTLET 3/4" NPT
SYSTEM
PRESSURE
RELIEF VALVENOT PART OF GMU PACKAGE
GATE VALVE (TYP)
BALL VALVE
PRESSURE
REDUCING VALVE
NOTE:
1.
2.
SECURE HOOD TO WOOD NAILING STRIP WITH 3/8" [10mm] CADMIUM PLATED LAG BOLTS NOT OVER 12" [300mm] ON CENTER.
SECURE ROOF CURB, DUCTWORK AND DAMPER TO ROOF WITH EXPANSION
BOLTS (CONCRETE ROOF) OR RUST RESISTANT BOLTS (MENTAL DECK & BAR
JOIST ROOF).
GRAVITY BACKDRAFT
DAMPER
SEE NOTE 2
PREFABRICATED
ROOF CURB
WOOD
NAILING STRIP
TRANSITION DUCT TO FULL SIZE OF
DAMPER SUPPLIED WITH HOOD.
ROOF
SEE NOTE 2
SEE NOTE 1
CURB CAP
FACTORY ASSEMBLED HINGED HOOD
WITH LATCH & BIRD SCREEN
DUCT
Project Number
Pl ot
D a te
Date
Location
ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
Date:Revisions:
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F
Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot
6"
6"
6"
6"
PRESCOTT, ARIZONA
Fi le
-201 W. CUS HING S TREET
TUCS ON, AZ 85 718
T: 520.882.4484 F: 520.882.5560
100% BID DOCUMENT
/3
/2
3:
:1
P
M C
:\U se rs \a sa nd le r\D oc um en ts
\1 3-
M C
D _A
S an dl er
.rv t
MECHANICAL DETAILS
M503
13-127
ASST
CLINICAL LABORATORY AND
PHARMACY BUILDING
12/03/2015
NOT TO SCALEM503
1 AHU WATER COIL PIPING DETAIL
NOT TO SCALEM503
3 WATER COIL PIPING DETAIL
NOT TO SCALEM503
2 VAV BOX DETAIL
NOT TO SCALEM503
4 RO WATER FLOW DIAGRAM
NOT TO SCALEM503
5 GLYCOL MAKEUP UNIT DETAIL
NOT TO SCALEM503
6 INTAKE HOOD DETAIL
BIDDING DOCUMENT REV. 1 Nov. 02, 2015 BID SUBMISSION Dec. 03, 2015
PRV
PRV
MEDIUM PRESSURE STEAM
FROM BUILDING 148
GLOBE VALVE
PRESSURE
GAUGE (TYP)
VENT ABOVE ROOF TO
ATMOSPHERE
CONDENSATE
RETURN
CONDENSATE
RETURN
LOW PRESSURE STEAM
TO HEAT EXCHANGERS
50 PSI MPS 30 PSI LPS
3" MPS
3" LPS
PILOT CONTROL
LINE (TYP)
3" BYPASS
LINE
GATE
VALVE
(TYP)
STRAINER
(TYP)
10 PIPE DIAMETERS MIN.
PRESSURE
SAFETY VALVE
10 PIPE DIAMETERS
MIN.
STEAM TRAP
ASSEMBLY (TYP)
NOTES:
1. MPS REFERS TO STEAM UPSTREAM OF PRV AND LPS
REFERS TO STEAM DOWNSTREAM OF PRV.
2. SEE PRV SCHEDULE FOR VALVE DATA.
3. PROVIDE NECCESARY UNIONS FOR REMOVAL OF VALVES
WITH SCREWED CONNECTIONS.
3" MPS
3" MPS
3" LPS
3" LPS
NOTES:
1. UNLESS OTHERWISE SHOWN ON DRAWINGS, SIZE THE
VENT PIPE SO THAT THE STEAM IS NOT BLOWN OUT
AT THE VENT PIPE ENTRANCE. UTILIZE THE
CALCULATION METHOD CONTAINED IN ANSI B31.1.
POWER PIPING CODE, APPENDIX II.
2. VENT PIPE SHALL TERMINATE 6' MIN. ABOVE FINISHED
ROOF.
3. DISCHARGE OF DRAIN MUST BE DIRECTED AWAY
FROM PLATFORMS OR OTHER AREAS WHICH
PERSONNEL MAY OCCUPY.
4. DO NOT CONNECT ANY OTHER DRAIN TO THE DRIP
PAN ELBOW DRAIN PIPE.
SAFETY VALVE
CONNECTION TO PRESSURE
VESSEL OR PIPE
24" MAX.
VENT PIPE
THROUGH ROOF
PROVIDE UNION UNLESS
SAFETY VALVE HAS
FLANGED OUTLET
D
DRIP PAN ELBOW
FLEXIBLE
CONNECTOR
PIPE THREADED INTO ELBOW
(SAME SIZE AS ELBOW)
3/4" DRAIN TO FLOOR
DRAIN OR OPEN
SIGHT DRAIN
HX
N
PRESSURE GAUGE
STEAM TRAP
ASSEMBLY
CONDENSATE RETURN TO
CONDENSATE PUMP/RECEIVER
LOW PRESSURE STEAM
FROM STEAM PRESSURE
REDUCING STATION
STEAM CONTROL
VALVE
GATE VALVE (TYP)
STRAINER
PREHEAT/HOT
WATER SUPPLY TO
PUMPS
PREHEAT/HOT WATER
RETURN FROM LOAD
EQUIPMENT
MOTORIZED ISOLATION VALVE
AIR VENT
MANUAL ISOLATION
VALVE (TYP)
CHECK
VALVE (TYP)
THERMOMETER (TYP)
PRESSURE
GAUGE (TYP)
MOTORIZED ISOLATION VALVE
CONCRETE
HOUSEKEEPING PAD
FLUSHING
CONNECTION
LPR
FLOOR
3/4" DRAIN, DISCHARGE INTO
NEAREST FLOOR DRAIN, NC.
GRAVITY RETURN FROM
FLASH TANK IF SHOWN ON
FLOOR PLAN
PUMP DISCHARGE
CONTROL CABINET
VENT
RECEIVER
WATER LEVEL
GAUGE
THERMOMETER (TYP)
STRAINER WITH
BALL VALVE
ISOLATIONG VALVE (TYP)
CHECK VALVE (TYP)
PRESSURE GAUGE (TYP)
EXISTING MPS PIPE AT
BUILDING 148
NEW 3" MPS PIPE ROUTED
TO NEW PRV STATION IN
PENTHOUSE.
3" MPS
3" MPS
3" LPS
1-1/4" PC
2" L
P S
EXISTING CR PIPE AT
BUILDING 160
NEW 1-1/4" PC ROUTED TO
CP-1 IN PENTHOUSE
1-1/4" PC
CHEMICAL
POT FEEDER
CHEMICAL
POT FEEDER
3" HWR
3" HWS
3" PHWR
3" PHWS
SCV
PREHEAT HOT WATER PIPING TO AND
FROM AHU PREHEAT COILS. FUTURE
LOADS INCLUDE FUTURE HISTOLOGY
AND CYTOLOGY LABS AND EXPANDED
WAITING AREA BETWEEN BUILDING 164
AND BUILDING 117.
CURRENT REQUIRED FLOW: 57.2 GPM
FUTURE ESTIMATED FLOW: 27.8 GPM
TOTAL DESIGN FLOW: 85.0 GPM
HOT WATER PIPING TO AND FROM VAV
BOX REHEAT COILS, BOOSTER COILS,
UNIT HEATERS, AND CABINET UNIT
HEATERS.
CURRENT REQUIRED FLOW: 79.9 GPM
FUTURE ESTIMATED FLOW: 10.1 GPM
TOTAL DESIGN FLOW: 90.0 GPM
SCV
SCV
SCV
PRV
PRV
CP
HX
HX
HX
HX
GMU
ET
AS
HWP
HWP
HWP
HWP
ET
AS
(E) 8" CHWS (E) 8" CHWR
(E) 10" CHWS (E) 10" CHWR
EXISTING YORK CHILLER
EXISTING YORK CHILLER
EXISTING CHILLED
WATER PUMP
(TYPICAL OF 3)
(E) 10" CHWR
(E) 10" CHWS
CHILLER YARD
BUILDING 164
LOWER LEVEL
MIRACLE MILE
CHILLED WATER PIPING TO AND FROM
AHU COOLING COILS. FUTURE LOADS
INCLUDE FUTURE HISTOLOGY AND
CYTOLOGY LABS, AND EXPANDED
WAITING AREA BETWEEN BUILDING 164
AND BUILDING 117.
CURRENT REQUIRED FLOW: 140.6 GPM
FUTURE ESTIMATED FLOW: 64.4 GPM
TOTAL DESIGN FLOW: 205.0 GPM
EXISTING CHILLED WATER
PIPING TO EXISTING BUILDINGS
CONNECT NEW 4" CHWR PIPE
TO EXISTING CHWR AT RISER
WITH SHUT-OFF VALVE
CONNECT NEW 4" CHWS PIPE
TO EXISTING CHWS AT RISER
WITH SHUT-OFF VALVE
CHILLER YARD
BUILDING 108 |
MIRACLE MILE
(N) 4" CHWS
(N) 4" CHWR
BUTTERFLY
VALVE (TYP)
PRESSURE
GAUGE (TYP)
THERMOMETER (TYP)
Project Number
Pl ot
D a te
Date
Location
ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
Date:Revisions:
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F
Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot
6"
6"
6"
6"
PRESCOTT, ARIZONA
Fi le
-201 W. CUS HING S TREET
TUCS ON, AZ 85 718
T: 520.882.4484 F: 520.882.5560
100% BID DOCUMENT
/3
/2
3:
:1
P
M C
:\U se rs \a sa nd le r\D oc um en ts
\1 3-
M C
D _A
S an dl er
.rv t
MECHANICAL DETAILS
M504
13-127
ASST
CLINICAL LABORATORY AND
PHARMACY BUILDING
12/03/2015
NOT TO SCALEM504
1 STEAM PRESSURE REDUCING STATION DETAIL
NOT TO SCALEM504
2 STEAM SAFETY VALVE DETAIL
NOT TO SCALEM504
3 STEAM TO HOT WATER HEAT EXCHANGER DETAIL
NOT TO SCALEM504
4 CONDENSATE PUMP DETAIL
NOT TO SCALEM504
5 STEAM AND HOT WATER FLOW DIAGRAM
NOT TO SCALEM504
6 CHILLED WATER FLOW DIAGRAM
BIDDING DOCUMENT REV. 1 Nov. 02, 2015 BID SUBMISSION Dec. 03, 2015
PIPE
PIPE CLAMP
STOP WASHER
AND NUT (TYP)
ISOLATION
HANGER (TYP)
SNUBBER PLATE
ROD STIFFINER ANGLE
ROD TO ANGLE CLAMP
CHANNEL NUT
WITH SPRING
UNISTRUT
45°
ISOLATION
HANGER
SNUBBER
PLATE
ROD STIFFINER
ANGLE
ROD TO ANGLE
PLATE
CABLE
INSTALLED
SWIVEL CONNECTIONS
BOTH ENDS
45°
CHAIN
SHACKLE
HEAVY WIRE
ROPE THIMBLE
U-BOLT
CLIP
7x19 GALVANIZED
AIRCRAFT CABLE
NOTE:
TENSION CABLE ONLY
ENOUGH TO REMOVE SAG.
TYPE SBC SEISMIC
CABLE BRACE
TYPE SRC SEISMIC
ROD CLAMP
EQUIPMENT
EQUIPMENT
TOP VIEW
ELEVATION
ISOLATION HANGER
SNUBBER PLATE
ROD STIFFINER
ANGLE
ROD TO ANGLE
CLAMP
ISOLATION
HANGER
STEEL
CABLE
45°
45°
SIDE VIEW TRAPEZE HANGER FOR UP
TO 1000 LB. UNIFORM LOAD
1" M
A X
PROVIDE INSULATION SHIELD
& INSERT FOR ALL PIPING (8" MIN.) BAND
1-5/8" 12 GAUGE
CHANNEL OR 2"x2"x1/4" ANGLE
1/2" DIA. HANGER RODS WITH 36"
MAX. SPACING ON EACH CHANNEL
WELD
SADDLE
INSULATION SHIELD
AT HANGER
PROVIDE HIGH
COMPRESSIVE STRENGTH
INSULATION (9 PSF MIN.
DENSITY) UNDER
INSULATION SHIELD
INSULATION (VAPOR
BARRIER TYPE IS
REQUIRED FOR LOW
TEMPERATURE PIPE)
HANGER ROD
NOTE:
SEE SPECIFER FOR DETAILED
HANGER REQUIREMENTS
NOTES:
1. PROVIDE ANCHORS ONLY WHERE SHOWN
ON DRAWINGS.
2. EXTEND SLEEVE ABOVE FLOOR WHERE
SPECIFIED.
INSULATION
BOLT
(TYPICAL)
FLOOR SLAB
FIRE-STOPPING
MATERIAL
BOLT
PIPEPIPE SLEEVE
WHERE SPECIFIED
RISER CLAMP
RISER
RISER CLAMP. BOTTOM
CLAMP REQUIRED AT
ANCHOR POINTS ONLY.
RISER CLAMP
(TYPICAL)
8"x8"x3/8" STEEL PLATE
WELD PLATE TO PIPE
SECURE TO ROOF SLAB
WITH (4) 3/8"∅ EXPANSION
BOLTS OR WELD TO STEEL
DECK
CONCRETE ROOF SLAB
OR STEEL ROOF DECK
ROOF SYSTEM
INSULATION AND
MEMBRANE
PRE-MOULDED FLEXIBLE PIPE
COUNTER FLASHING
CLAMPING RING
ROOF SURFACE
WELD PIPE SADDLE SUPPORT TO
PIPE. PROVIDE WATER TIGHT
CONNECTION
HIGH COMPRESSIVE
STRENGTH INSULATION
INSERT UNDER SHIELD
PIPE
INSULATION PROTECTION
SHIELD
SEALANT
2" STEEL PIPE
2-1/2" STEEL PIPE
PROVIDE ALUMINUM
JACKET
NOTES:
PROVIDE RESTRAINING CLAMPS 8'-0" O.C.
" M
IN
8" 4"
Project Number
Pl ot
D a te
Date
Location
ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
Date:Revisions:
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F
Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot
6"
6"
6"
6"
PRESCOTT, ARIZONA
Fi le
-201 W. CUS HING S TREET
TUCS ON, AZ 85 718
T: 520.882.4484 F: 520.882.5560
100% BID DOCUMENT
/3
/2
3:
:1
P
M C
:\U se rs \a sa nd le r\D oc um en ts
\1 3-
M C
D _A
S an dl er
.rv t
MECHANICAL DETAILS
M505
13-127
ASST
CLINICAL LABORATORY AND
PHARMACY BUILDING
12/03/2015
NOT TO SCALEM505
1 SEISMIC PIPE SUPPORT DETAIL
NOT TO SCALEM505
2 SC PIPING CABLE RESTRAINT
NOT TO SCALEM505
3 SEISMIC CABLE ATTACHMENT FOR PIPING
NOT TO SCALEM505
4 SEISMIC CABLE DETAILS
NOT TO SCALEM505
5 SC EQUIPMENT CABLE RESTRAINT
NOT TO SCALEM505
6 PIPE HANGER DETAIL
NOT TO SCALEM505
7 PIPE SUPPORT ANCHORS
NOT TO SCALEM505
8 PIPE SUPPORT ON ROOF DETAIL
Project Number
Pl ot
D a te
Date
Location
Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot
6"
6"
6" 6"
Fi le ot
D a te
Date
Location
Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot
6"
6"
6" 6"
Fi ot
D a te
Date
Location
Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot
6"
6"
6" 6"
Fi ot
D a te
Date
Location
Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot
6"
6"
6" 6"
Fi
M
M
M
M
T-3 AI
C
H
C
T-1DP
M
SPS-2
HS
SD-2
H-2
AI
M
T-5
HIGH PRESSURE STATIC
AFMS-2
M
N.O.
BO - OUTSIDE AIR DAMPER
(OPEN/CLOSE)
BI - OUTSIDE AIR DAMPER
(POSITION)
AFMS-1AI - OUTDOOR AIRFLOW
M
BO - EXHAUST AIR DAMPER
(OPEN/CLOSE)
BI - EXHAUST AIR DAMPER
(POSITION)
N.O.
DP
BI - PREFILTER STATUS
TSL
VFD
BO - FAN START/STOP
AO - VFD SPEED CONTROL
BI - VFD FAULT
BI - FAN STATUS
H
VFD
BO - FAN START/STOP
AO - VFD SPEED CONTROL
BI - VFD FAULT
BI - FAN STATUS
H-1
SD-2
BI
SPS-2
BI - HIGH PRESSURE STATIC
SPS-1
AO - RELIEF DAMPER
(MODULATE)
AI - RELIEF DAMPER
(POSITION) SD-1
AO - OUTSIDE AIR DAMPER
(MODULATE)
AI - OUTSIDE AIR DAMPER
(POSITION)
BO - OUTSIDE AIR DAMPER
(OPEN/CLOSE)
BI - OUTSIDE AIR DAMPER
(POSITION)
BI - FILTER STATUS
C
DP
BI - FILTER STATUS
FZ
BI-TEMPERATURE
TSL
H
T-4 AI SPS-1
AFMS-1
ULTRASONIC HUMIDIFIER
DP
BI - FILTER STATUS
AFMS-2 AI - EXHAUST AIRFLOW
SD-1
BI
AFMS-3
AI
AFMS-4
AI
M
T-2
T-1
H-2
DP
BI - FILTER STATUS
M
M
M
M
BYPASS
PRIMARY
PRIMARY
BYPASS
OUTSIDE AIR SUPPLY AIR
RETURN AIREXHAUST AIR
APPLICABLE FOR
AHU-4 HEPA FILTER
AO - OUTSIDE AIR DAMPER
(MODULATE)
AI - OUTSIDE AIR DAMPER
(POSITION)
* NORTEC RS HUMIDIFIER AT AHU-2.
ULTRASONIC HUMIDIFIER AT AHU-4.
H-5
GLOBAL TEMPERATURE AND
ENTHALPY SENSOR.
T-3
HEAT EXCHANGE
MEDIA
BO - PRIMARY OUTSIDE AIR DAMPER
(OPEN/CLOSE)
BI - PRIMARY OUTSIDE AIR DAMPER
(POSITION)
BO - BYPASS RETURN AIR DAMPER
(OPEN/CLOSE)
BI - BYPASS RETURN AIR DAMPER
(POSITION)
BO - BYPASS OUTSIDE AIR DAMPER
(OPEN/CLOSE)
BI - BYPASS OUTSIDE AIR DAMPER
(POSITION)
BO - PRIMARY RETURN AIR DAMPER
(OPEN/CLOSE)
BI - PRIMARY RETURN AIR DAMPER
(POSITION)
D-1
D-2
D-3
D-4
D-5
D-6
Project Number
Pl ot
D a te
Date
Location
Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot
6"
6"
6" 6"
Fi
HWS
HX-1
CR
NO
LPS
HWR
HWP-1
HWS
HWP-2
HWS
HWR
HWS
HWS
HX-2
NC
LPS
HWR
NC
NC
CR
NO
NO PHWS
HX-3
CR
NO
LPS
PHWR
HWP-3
PHWS
HWP-4
PHWS
PHWR
PHWS
PHWS
HX-4
NC
LPS
PHWR
NC
NC
CR
NO
NO
Project Number
Pl ot
D a te
Date
Location
Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot
6"
6"
6" 6"
Fi ot
D a te
Date
Location
Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot
6"
6"
6" 6"
Fi
SUPPLY VAV TERMINAL UNITS
THE UNIT SHALL BE INTERLOCKED WITH THE CORRESPONDING AIR
HANDLING UNIT AND ENABLED ACCORDING TO A USER DEFINABLE
OCCUPANCY SCHEDULE IN THE FOLLOWING MODES:
• OCCUPIED MODE: THE UNIT SHALL MAINTAIN
o A 73°F (ADJ.) COOLING SETPOINT o A 73°F (ADJ.) HEATING SETPOINT
• UNOCCUPIED MODE (NIGHT SETBACK): THE UNIT SHALL MAINTAIN
o A 80°F (ADJ.) COOLING SETPOINT o A 65°F (ADJ.) HEATING SETPOINT
THE UNIT SHALL MAINTAIN ZONE SETPOINTS BY CONTROLLING THE
AIRFLOW THROUGH ONE OF THE FOLLOWING:
OCCUPIED:
• WHEN THE ZONE TEMPERATURE IS GREATER THAN THE COOLING
SETPOINT, THE ZONE DAMPER SHALL MODULATE BETWEEN THE
MINIMUM OCCUPIED AIRFLOW (ADJ.) AND THE MAXIMUM COOLING
AIRFLOW (ADJ.) UNTIL THE ZONE IS SATISFIED.
• WHEN THE ZONE TEMPERATURE IS BETWEEN THE COOLING
SETPOINT AND THE HEATING SETPOINT, THE ZONE DAMPER SHALL
MAINTAIN THE MINIMUM ZONE AIRFLOW (ADJ.).
• WHEN THE ZONE TEMPERATURE IS LESS THAN THE HEATING
SETPOINT, THE CONTROLLER SHALL ENABLE HEATING AND THE
ZONE DAMPER SHALL MODULATE TO MAINTAIN THE ZONE
TEMPERATURE AT THE HEATING SETPOINT.
UNOCCUPIED:
• WHEN THE ZONE IS UNOCCUPIED THE ZONE DAMPER SHALL
CONTROL TO ITS MINIMUM UNOCCUPIED AIRFLOW (ADJ.).
• WHEN THE ZONE TEMPERATURE IS GREATER THAN THE COOLING
SETPOINT, THE ZONE DAMPER SHALL MODULATE BETWEEN THE
MINIMUM UNOCCUPIED AIRFLOW (ADJ.) AND THE MAXIMUM COOLING
AIRFLOW (ADJ.) UNTIL THE ZONE IS SATISFIED.
• WHEN THE ZONE TEMPERATURE IS LESS THAN ITS UNOCCUPIED
HEATING SETPOINT, THE CONTROLLER SHALL ENABLE HEATING TO
MAINTAIN THE ZONE TEMPERATURE AT THE SETPOINT.
ADDITIONALLY, IF WARM AIR IS AVAILABLE FROM THE AHU, THE
ZONE DAMPER SHALL MODULATE BETWEEN THE MINIMUM
UNOCCUPIED AIRFLOW (ADJ.) AND THE AUXILIARY HEATING
AIRFLOW (ADJ.) UNTIL THE ZONE IS SATISFIED.
ZONE OPTIMAL START:
THE UNIT SHALL USE AN OPTIMAL START ALGORITHM FOR MORNING
START-UP. THIS ALGORITHM SHALL MINIMIZE THE UNOCCUPIED
WARM-UP OR COOL-DOWN PERIOD WHILE STILL ACHIEVING COMFORT
CONDITIONS BY THE START OF SCHEDULED OCCUPIED PERIOD.
TERMINAL UNIT HOT WATER HEAT SHALL NOT BE USED DURING
MORNING WARM-UP.
ZONE UNOCCUPIED OVERRIDE:
A TIMED LOCAL OVERRIDE CONTROL SHALL ALLOW AN OCCUPANT TO
OVERRIDE THE SCHEDULE AND PLACE THE UNIT INTO AN OCCUPIED
MODE FOR AN ADJUSTABLE PERIOD OF TIME (MINIMUM 30 MINUTES, IN 30
MINUTES INCREMENTS). AT THE EXPIRATION OF THIS TIME, CONTROL OF
THE UNIT SHALL AUTOMATICALLY RETURN TO THE SCHEDULE.
HOT WATER HEATING:
THE CONTROLLER SHALL MEASURE THE ZONE TEMPERATURE AND
STAGE THE HOT WATER HEAT TO MAINTAIN THE SETPOINT. TO PREVENT
SHORT CYCLING, THERE SHALL BE A USER DEFINABLE (ADJ.) DELAY
BETWEEN STAGES, AND EACH STAGE SHALL HAVE A USER DEFINABLE
(ADJ.) MINIMUM RUNTIME. THE HOT WATER HEATING SHALL BE ENABLED
WHENEVER THE ZONE TEMPERATURE IS BELOW SETPOINT AND
SUFFICIENT AIRFLOW IS PROVIDED.
REHEATING - HIGH DISCHARGE AIR TEMPERATURE LIMIT:
THE CONTROLLER SHALL MEASURE THE DISCHARGE AIR TEMPERATURE
AND LIMIT REHEATING IF THE DISCHARGE AIR TEMPERATURE IS MORE
THAN 15°F (ADJ.) ABOVE THE ZONE TEMPERATURE.
DISCHARGE AIR TEMPERATURE:
THE CONTROLLER SHALL MONITOR THE DISCHARGE AIR TEMPERATURE.
ALARMS SHALL BE PROVIDED AS FOLLOWS:
• HIGH ZONE TEMP: IF THE ZONE TEMPERATURE IS GREATER THAN
THE COOLING SETPOINT BY A USER DEFINABLE AMOUNT (ADJ.).
• LOW ZONE TEMP: IF THE ZONE TEMPERATURE IS LESS THAN THE
HEATING SETPOINT BY A USER DEFINABLE AMOUNT (ADJ.).
ALARMS SHALL BE PROVIDED AS FOLLOWS:
• HIGH DISCHARGE AIR TEMP: IF THE DISCHARGE AIR TEMPERATURE
IS GREATER THAN 120°F (ADJ.).
• LOW DISCHARGE AIR TEMP: IF THE DISCHARGE AIR TEMPERATURE IS
LESS THAN 40°F (ADJ.).
M
M
MS
BO
EP
BI
M
N.C.
M
M
MS
PACKAGED
REVERSE OSMOSIS
RO
PS
T
H
Project Number
Pl ot
D a te
Date
Location
Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F on e ei gh th in ch o ne fo ot on e q ua rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e q ua rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h al f i nc he s = o ne fo ot th re e in ch es o ne fo ot
6"
6"
6" 6"
Fi
MECHANICAL SHEET NOTES
1. 48x48 RELIEF AIR OPENING WITH BAROMETRIC DAMPER.
2. 16x16 EXHAUST AIR DUCT (EF-1) UP. TERMINATE DUCT HORIZONTALLY AT 45
DEGREES, EXHAUST AIR AWAY FROM BUILDING. PROVIDE INSECT SCREEN AT
TERMINATION.
3. 16x16 EXHAUST AIR DUCT (EF-2) UP. TERMINATE DUCT HORIZONTALLY AT 45
DEGREES, EXHAUST AIR AWAY FROM BUILDING. PROVIDE INSECT SCREEN AT
TERMINATION.
4. 48x48 TRANSFER AIR DUCT ABOVE CONDUIT BANK. PROVIDE WIRE MESH AT
WALL OPENINGS ON BOTH SIDES.
5. KEYNOTE NOT USED.
6. KEYNOTE NOT USED.
7. 14x14 SUPPLY AIR DUCT SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY
LABS. .
8. KEYNOTE NOT USED.
9. KEYNOTE NOT USED.
10. EXISTING MIRACLE MILE AHU AND ASSOCIATED DUCTWORK SHALL REMAIN.
11. 36x24 OUTSIDE AIR DUCT (AHU-2) UP TO ROOF. OUTSIDE AIR DUCT SHALL BE
INSULATED.
12. KEYNOTE NOT USED.
13. KEYNOTE NOT USED.
14. 40x20 SUPPLY AIR DUCT (AHU-2).
15. 48x22 RETURN AIR DUCT (AHU-2).
16. 50x18 RELIEF AIR DUCT (AHU-2).
17. ROUTE REFRIGERANT PIPING FROM INDOOR UNIT AS DIRECTLY AS POSSIBLE,
TO OUTDOOR UNIT, MINIMIZING THE AMOUNT OF EXTERIOR EXPOSED
REFRIGERANT PIPING.
18. 16x18 SUPPLY AIR DUCT (AHU-2) UP TO UPPER LEVEL.
19. 20x20 RETURN AIR DUCT (AHU-2) UP TO UPPER LEVEL.
20. 50x24 OUTSIDE AIR DUCT (AHU-2) OPENING.
21. AHU-2 SUPPLY FAN VFD.
22. AHU-2 RETURN FAN VFD.
23. AIR HANDLING UNIT MOUNTED ON A 6" HOUSEKEEPING PAD. AHU-2 SHALL BE
SPLIT INTO SECTIONS WITH 42" MAX. WIDTH PER SECTION TO FIT THROUGH
48" WIDE DOOR. ROUTE CONDENSATE TO NEARBY FLOOR DRAIN.
24. HUMIDIFIER DISCONNECT SWITCH.
25. AFMS TRANSMITTER.
MECHANICAL GENERAL NOTES
A. AIRFLOWS INDICATED ARE ACTUAL CUBIC FEET PER MINUTE (ACFM).
B. FINAL LOCATION OF THERMOSTATS, ROOM PRESSURE MONITORS, AND
DIFFERENTIAL PRESSURE SENSORS SHALL BE COORDINATED WITH
OWNER, TEMPERATURE CONTROLS CONTRACTOR, AND GENERAL
CONTRACTOR.
C. ALL DUCTWORK ASSOCIATED WITH STROBIC FANS SHALL BE
STAINLESS STEEL.
D. PROVIDE WEATHERPROOF JACKETING FOR ALL EXPOSED DUCTWORK.
E. INSULATE ALL SUPPLY AIR AND OUTSIDE AIR DUCTWORK.
F. BRANCH DUCTWORK TO AIR TERMINAL SHALL BE SAME AS NECK SIZE
UNLESS OTHERWISE NOTED.
G. BRANCH HOT WATER PIPING TO VAV BOXES, BOOSTER COILS, UNIT
HEATERS, ETC... SHALL BE MIN. 3/4" NOMINAL DIAMETER.
H. INSULATE ALL PIPING. SEE SPECIFICATIONS FOR INSULATION TYPE AND
THICKNESS.
I. PROVIDE ACCESS DOORS IN HARD CEILINGS FOR ACCESS TO
EQUIPMENT.
H H.3 H.9
IT CLOSET
164-011
DELIVERY
164-017
CORRIDOR
164-012 OFFICE
164-013
OFFICE
164-014
FUTURE SPACE
164-015
AHU
DSS
12x12 x1 x1
12x12 x1
EXISTING ELECTRICAL
CONDUIT DUCT BANK
CAP 12"Ø SUPPLY AIR DUCT TO
FUTURE HISTOLOGY LAB AT WALL.
B6x6 70-R
B6x6 70-R
A6 70-S
1 1/4" PHWR
1 1/4" PHWS
3/4" RO
2" CHWR
2" CHWS
HUM
A10 420-S
B10x10 190-R
B10x10 220-R
A8 270-S
F8x8 50-S
A6 70-S
AFMS
AFMS
30x18
STAIR
S-1
STACKED DUCTS:
30x18 SUPPLY AIR DUCT (HIGH) 30x22 RETURN AIR DUCT (LOW)
T C
TH/C
(EXCAVATED
CRAWLSPACE)
CAP 14"Ø SUPPLY AIR DUCT SERVING
FUTURE CYTOLOGY LAB AT WALL.
CAP 14x14 EXHAUST AIR DUCT
SERVING FUTURE CYTOLOGY AND
HISTOLOGY BELOW UPPER LEVEL
FLOOR. EXHAUST AIR DUCT SHALL
BE STAINLESS STEEL.CAP 1" HWS/HWR SERVING FUTURE
CYTOLOGY LAB AT WALL.
1" HWS
1" HWR
CAP 1" HWS/HWR SERVING FUTURE
CYTOLOGY LAB AT WALL.
x1
"Ø
1" HWS
1" HWR
0.1
0.5
G H H.3 H.9 JFD
EF
(E) 20x20
VAV
VAV
VAV
VAV
CUH
VAV
VAV
VAV
VAV
EF
VAV
DSS
UH
UH
x1
20x14
10x10
10x12
20x14 26x14 x1
12x10
12x12
14x12 8x10
16x16 x1
12x12 x1
12x12
B10x10 255-E
B10x10 255-E
B10x10 240-E
B10x10 240-E
A10 355-S
A10 335-S
G10x10 120-E
F12x8 210-S
G12x12 210-R
G24x12 770-E
F14x14 770-S
A10 445-S
B12x12 380-R
A8 290-S
A8 285-S
B15x15 575-R
B15x15 575-R
A8 285-S
A8 290-S
PHARMACY
STORAGE
164-010
LAB STORAGE
164-009
ELECTRICAL
ROOM
164-002
MEN'S TOILET
164-003
WOMEN'S
TOILET
164-004
HAC
164-005
20x14 x1
MACHINE ROOM
164-008
STAIR
S-1
CORRIDOR
164-006
A10 445-S
FUTURE SPACE
164-007
CORRIDOR
164-001
CORRIDOR
164-012
OFFICE
164-013
OFFICE
164-014
FUTURE SPACE
164-015
IT CLOSET
164-011
16x18
20x20 x1
VD (TYP)
T H TH
T C
TH/C
TC
TH/C
TH/C
TH/C
T C
TH/C
FIRE
DAMPER
(TYP)
12x108x10
12x12
12x12
8x10
12x8 x1
12x12
MH101
AHU
MD (TYP)
AFMS
AFMS
A8 190-S
B8x8 100-R
Project Number
Pl ot
D a te
Date
Location
ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
Date:Revisions:
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F
Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot
6"
6"
6"
6"
PRESCOTT, ARIZONA
KEY PLAN
NORTH
Fi le
-201 W. CUS HING S TREET
TUCS ON, AZ 85 718
T: 520.882.4484 F: 520.882.5560
BUILDING
BUILDING
MIRACLE MILE
100% BID DOCUMENT
O
PE
N A
IR
E
N
TR
A N
C E
/3
/2
3:
:1
P
M C
:\U se rs \a sa nd le r\D oc um en ts
\1 3-
M C
D _A
S an dl er
.rv t
OVERALL LOWER LEVEL HVAC PLAN
MH101
13-127
ASST
CLINICAL LABORATORY AND
PHARMACY BUILDING
12/03/2015
1/4" = 1'-0"MH101
2 ENLARGED LOWER LEVEL HVAC PLAN - SOUTH
1/8" = 1'-0"MH101
1 OVERALL LOWER LEVEL HVAC PLAN
0.1
0.5
G H H.3 H.9 J K K.5 LFD
12x12 x1
40x20
26x16
(E ) 2
0x x1
VAV
VAV
VAV
24x20 x8 x8 x1
16x15
DSS
VAV
VAV
TEF
VAV
VAV
VAV
VAV
VAV
VAV
VAV
VAV
VAV
VAV
VAV
16VAV
EAV
D8 250-S
D8 250-S
D8 250-S
D8 270-S
D10 435-S
D10 435-S
D10 440-S
D10 440-S
A12 585-S
A12 585-S
A12 580-S
B18x18 900-E
B18x18 900-E
B18x18 900-E
B18x18 900-E
B18x18 900-E
B18x18 900-E
A12 585-S
A12 585-S
A12 580-S
A12 585-S A12
585-S A12
580-S
B18x18 900-E
B18x18 900-E
B18x18 900-E
B8x8 100-R
D8 200-S
B12x12 520-R
D8 200-S
A6 70-S
D8 200-S
B12x12 500-R
D8 215-S
D8 250-S
D6 150-S
B8x8 160-R
A8 150-S
A8 150-S
B12x12 465-R
B6x6 70-R
B6x6 70-R
F8x8 50-S
A6 100-S
VAV
A8 300-S
B8x8 100-R
B6x6 50-R
A6 50-S
A6 100-S
A6 70-S
A6 100-S
B8x8 100-R
B8x8 110-E
B8x8 180-E
B8x8 180-E
G12x8 120-E
A6 80-S
A6 130-S
A6 130-S
A8 300-S
A8 300-S
B15x15 650-E
B15x15 650-E
B15x15 660-E
A8 200-S
A8 200-S
A8 200-S
A8 300-S
B12x12 500-R A8
300-S
A8 300-S
B12x12 500-R
A8 300-S
B12x12 500-R x1 x1
I10 380-S
H12x12 380-R
A8 170-S
A6 70-S
LAB
164-115
BLOOD DRAW
164-111
BLOOD DRAW
164-110
WAITING
164-104
DELIVERY
STORAGE
164-116
STAIR
S-2
IT CLOSET
164-128
VAULT
NARCOTICS
164-121
CORRIDOR
164-127
TOILET
164-131
LAB MANAGER
OFFICE
164-130
PSA OFFICE
164-129
WOMEN'S
TOILET
164-105
MEN'S TOILET
164-106
FAMILY TOILET
164-107
HAC
164-108
CHEMO
164-125
SECRETARY
OFFICE
164-138
MANAGER
OFFICE
164-137
TH/C
T H/C
T H/C
16x14 12x14
TH/C
TH/C
T H/C
T H/C
T H/C T H/C
TH/C
T H/C
TH/C
TH/C TH/C
T H/C
TH/C
PHARMACY
164-124
TC
T C
T H/C
16x14
12x1410x14 x8
14x14 16x14 10x14
32x16
10x10
8x
12x10
12x12
10x10
10x10
PHLEBOTOMY
164-109
8x10 14x16
12x12
10x8
MH102
MH102
TEF
3MEN'S TOILET
164-139
16x14 12x148x14
8x
D8 250-S
D8 250-S
12x12VAV
VAV
24x12
18x8 18x8
18x12 6x10
12x10 8x10
14x12 12x12 14 x1 x1
20x1624x16
VAV
8x8
D8 200-S
12x12
8x10
STACKED DUCTS:
18x18 RETURN AIR DUCT (HIGH) 18x12 SUPPLY AIR DUCT (LOW)
OPEN OFFICE
164-132
DP
DP
MECHANICAL SHEET NOTES
1. 6"Ø EXHAUST DUCT UP THROUGH ROOF.
2. 16x16 EXHAUST AIR DUCT (EF-1) DOWN . TERMINATE DUCT
HORIZONTALLY AT 45 DEGREES, EXHAUST AIR AWAY FROM BUILDING.
PROVIDE INSECT SCREEN AT TERMINATION.
3. 12x12 EXHAUST AIR DUCT UP TO STRF-1 ON ROOF.
4. ROUTE REFRIGERANT PIPING FROM INDOOR UNIT AS DIRECTLY AS
POSSIBLE, TO OUTDOOR UNIT, MINIMIZING THE AMOUNT OF EXTERIOR
EXPOSED REFRIGERANT PIPING.
5. 60x40 EXHAUST AIR DUCT UP TO AHU-1 ON ROOF. TRANSITION TO HORIZONTAL 40x20 DUCT WITH VARIABLE INLET/OUTLET ELBOW.
6. KEYNOTE NOT USED.
7. 15x15 TRANSFER AIR DUCT.
8. 42x18 EXHAUST AIR DUCT UP TO AHU-3 ON ROOF. TRANSITION TO 24x12
DUCT IN VERTICAL.
9. 16x16 EXHAUST AIR DUCT (EF-2) DOWN . TERMINATE DUCT
HORIZONTALLY AT 45 DEGREES, EXHAUST AIR AWAY FROM BUILDING.
PROVIDE INSECT SCREEN AT TERMINATION.
10. KEYNOTE NOT USED.
11. 42x18 SUPPLY AIR DUCT UP TO AHU-3 ON ROOF. TRANSITION TO 18x14
DUCT IN VERTICAL.
12. 15x15 TRANSFER AIR DUCT.
13. 16x18 SUPPLY AIR DUCT (AHU-2) DOWN TO LOWER LEVEL.
14. 20x20 RETURN AIR DUCT (AHU-2) DOWN TO LOWER LEVEL.
15. 10x10 TRANSFER AIR DUCT.
16. 42x24 SUPPLY AIR DUCT UP TO AHU-1 ON ROOF. TRANSITION TO 32x16
DUCT IN VERTICAL.
17. KEYNOTE NOT USED.
18. 14x14 EXHAUST AIR DUCT UP TO FUTURE STROBIC FAN ON ROOF.
TERMINATE DUCT AND CAP DUCT BELOW ROOF. EXHAUST AIR DUCT
SHALL BE STAINLESS STEEL.
19. 12x12 EXHAUST AIR DUCT UP TO STRF-2 ON ROOF.
20. 14x14 EXHAUST AIR DUCT DOWN TO LOWER LEVEL. EXHAUST DUCT
SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY LABS. EXHAUST AIR
DUCT SHALL BE STAINLESS STEEL.
21. 30x30 RETURN AIR DUCT UP TO AHU-4 ON ROOF.
22. 36x24 OUTSIDE AIR DUCT DOWN TO LOWER LEVEL.
23. 36x24 OUTSIDE AIR DUCT UP TO PENTHOUSE.
24. 16x12 SUPPLY AIR DUCT UP AND DOWN. TRANSITION AND OFFSET AS
NECESSARY TO AVOID STRUCTURE. SUPPLY AIR DUCT SHALL SERVE
FUTURE CYTOLOGY AND HISTOLOGY LABS.
25. 10x10 EXHAUST AIR DUCT UP TO EF-3 ON ROOF.
26. 50x20 SUPPLY AIR DUCT UP TO AHU-4 ON ROOF. TRANSITION TO 26x16
DUCT IN VERTICAL.
27. VENTURI AIR VALVE IN VERTICAL POSITION ABOVE LAB HOOD. CONNECT
UPSTREAM DUCT TO LAB HOOD. HOOD DESIGN BASED ON 500 ACFM
AND 0.3" W.C. STATIC PRESSURE [BAKER SG303]. FURNISH AND INSTALL
ZONE PRESCENCE SENSOR ON HOOD. ZONE PRESCENCE SENSOR
SHALL BE PHOENIX CONTROLS MODEL ZPS OR VA APPROVED EQUAL.
LAB HOOD SHALL BE PROVIDED BY OTHERS.
28. KEYNOTE NOT USED.
29. AFMS TRANSMITTER ABOVE CEILING.
30. CONTAINMENT CHAMBER SHALL NOT BE DUCTED. CHAMBER DESIGN
BASED ON 250 SCFM RECIRCULATED AIR [CTG MIC DUAL CHAMBER
A2000S]. CONTAINMENT CHAMBER SHALL BE PROVIDED BY OTHERS.
31. CONNECT 8"Ø EXHAUST DUCT TO CHEMO HOOD. HOOD DESIGN BASED
ON 510 ACFM AND 2.0" W.C. STATIC PRESSURE [NUAIRE NU-NTE797-400].
FURNISH AND INSTALL ZONE PRESCENCE SENSOR ON HOOD. ZONE
PRESCENCE SENSOR SHALL BE PHOENIX CONTROLS MODEL ZPS OR VA
APPROVED EQUAL. CHEMO HOOD SHALL BE PROVIDED BY OTHERS.
32. KEYNOTE NOT USED.
33. KEYNOTE NOT USED.
34. FURNISH AND INSTALL ROOM PRESSURE MONITOR AND DIFFERENTIAL
PRESSURE SENSORS THAT WILL MONITOR (1) DIFFERENTIAL PRESSURE
BETWEEN CHEMO AND CHEMO AIR LOCK AND (2) DIFFERENTIAL
PRESSURE BETWEEN CHEMO AIR LOCK AND PHARMACY. ROOM
PRESSURE MONITOR SHALL BE TSI MODEL RPM20 OR VA APPROVED
EQUAL. INSTALL PRESSURE SENSOR PER MANUFACTURER'S
INSTALLATION INSTRUCTION.
35. FURNISH AND INSTALL ROOM PRESSURE MONITOR AND DIFFERENTIAL
PRESSURE SENSORS THAT WILL MONITOR (1) DIFFERENTIAL PRESSURE
BETWEEN STERILE PREP AND STERILE PREP AIR LOCK AND (2)
DIFFERENTIAL PRESSURE BETWEEN STERILE PREP AIR LOCK AND
PHARMACY. ROOM PRESSURE MONITOR SHALL BE TSI MODEL RPM20
OR VA APPROVED EQUAL. INSTALL PRESSURE SENSOR PER
MANUFACTURER'S INSTALLATION INSTRUCTION.
36. FURNISH AND INSTALL ROOM PRESSURE MONITOR AND DIFFERENTIAL
PRESSURE SENSORS THAT WILL MONITOR (1) DIFFERENTIAL PRESSURE
BETWEEN LAB AND PHLEBOTOMY AND (2) DIFFERENTIAL PRESSURE
BETWEEN LAB AND CORRIDOR. ROOM PRESSURE MONITOR SHALL BE
TSI MODEL RPM20 OR VA APPROVED EQUAL. INSTALL PRESSURE
SENSOR PER MANUFACTURER'S INSTALLATION INSTRUCTION.
37. FURNISH AND INSTALL NEW ELBOW SILENCER AT THE BOTTOM OF THE
DUCT. SILENCER SHALL BE VAW SYSTEMS MODEL # REL OR VA
APPROVED EQUAL. INSTALL PER MANUFACTURER'S INSTALLATION
INSTRUCTION.
MECHANICAL GENERAL NOTES
A. AIRFLOWS INDICATED ARE ACTUAL CUBIC FEET PER MINUTE (ACFM).
B. FINAL LOCATION OF THERMOSTATS, ROOM PRESSURE MONITORS, AND
DIFFERENTIAL PRESSURE SENSORS SHALL BE COORDINATED WITH
OWNER, TEMPERATURE CONTROLS CONTRACTOR, AND GENERAL
CONTRACTOR.
C. ALL DUCTWORK ASSOCIATED WITH STROBIC FANS SHALL BE
STAINLESS STEEL.
D. PROVIDE WEATHERPROOF JACKETING FOR ALL EXPOSED DUCTWORK.
E. INSULATE ALL SUPPLY AIR AND OUTSIDE AIR DUCTWORK.
F. BRANCH DUCTWORK TO AIR TERMINAL SHALL BE SAME AS NECK SIZE
UNLESS OTHERWISE NOTED.
G. BRANCH HOT WATER PIPING TO VAV BOXES, BOOSTER COILS, UNIT
HEATERS, ETC... SHALL BE MIN. 3/4" NOMINAL DIAMETER.
H. INSULATE ALL PIPING. SEE SPECIFICATIONS FOR INSULATION TYPE AND
THICKNESS.
I. PROVIDE ACCESS DOORS IN HARD CEILINGS FOR ACCESS TO
EQUIPMENT.
H H.3 H.9 J K
TH/C
T H/C
TH/C
I10 350-S
C10 300-E
A8 300-S
31I10 390-S
C12 330-E
A8 300-S
STERILE PREP
164-126
CHEMO
164-125
PHARMACY
164-124
26x16
AFMS
AFMS
26x16
8x 8 12x8 x1
A8 300-S
B12x12 500-R
B12x12 500-R
B8x8 110-R
B12x12 500-R
A6 110-S
VD (TYP)
30x30 RETURN AIR DUCT TO
AHU-4 ON ROOF. TRANSITION
TO 26x26 DUCT IN VERTICAL.
3/4" RO UP
TO AHU-4 3/4" HWR
3/4" HWS
EF
x1 x1
18x14
24x16 20x16 x1
VAV
I10 380-S
C14 530-E
TH/C
EAV
CLOSET
164-135
C8 100-E
I6 120-S
EAV
EAV
SAV
SAV
VAV
12x12
EAV
12x10 12x814x10
SAV
SAV
EAV
10x10
VAV
10"Ø
10"Ø
8" Ø
A8 300-S
10x10
12x12
8x12 A8
300-S
A8 300-S
1 1/2" HWS
1 1/2" HWR
1" HWS
1" HWR
CHEMO AIR
LOCK
164-133
STERILE PREP
AIR LOCK
164-134
TH/C
"Ø
8"Ø
1 1/4" HWS
1 1/4" HWR
8x12
DP
DP
DPDP
G H H.3 H.9
8x8
8x8
10x10 x1
3 10 x1
18x18 x1 x1
VAV
TEF
4" CHWS
4" CHWR
3/4" RO
1 1/4" PHWS
1 1/4" PHWR
3" MPS
B6x6 70-R
A6
70-S VAV
A6 70-S
B6x6 70-R
A8 300-S
A8 300-S
A6 70-S
B6x6 70-R
A6 70-S
B6x6 70-R
A8 200-S
8x8
3" HWR
3" HWS
1 1/4" HWR
1 1/4" HWS
A6 70-S
B8x8 100-RB8x8
100-R
A6
100-SA6
50-S
B6x6 50-R
10x10
TH/C
BLOOD DRAW
164-111 BLOOD DRAW
164-110
PHLEBOTOMY
164-109
BLOOD DRAW
164-114 BLOOD DRAW
164-112
PASS-THRU
164-122STORAGE BH &
AR
164-117
PROCUREMENT
STATION
164-118
PRIVATE
CONSULTATION
164-123
PHARMACY
164-124
WAITING
164-104
1 1/4" PC
3/4" RO
3/4" RO
TEF
MEN'S TOILET
164-139
8x
A6 100-S
24x12
2" HWR
2" HWS
x8 x1
STACKED DUCTS:
18x18 RETURN AIR DUCT (HIGH) 18x14 SUPPLY AIR DUCT (LOW)
Project Number
Pl ot
D a te
Date
Location
ARCHITECT + ENGINEERS:CONSULTANTS: Drawing Title:
Approved: Project Director
Project Title
Checked Drawn
Drawing Number
Dwg. of
Building Number
Date:Revisions:
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
A
B
C
D
E
F
Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot on e qu a rte r i nc h on e fo ot th re e ei gh th s i nc h on e fo ot on e ha lf in ch o ne fo ot th re e qu a rte rs in ch o ne fo ot on e in ch o ne fo ot on e a nd o ne h a lf in ch es o ne fo ot th re e in ch es o ne fo ot
6"
6"
6"
6"
PRESCOTT, ARIZONA
KEY PLAN
NORTH
Fi le
-201 W. CUS HING S TREET
TUCS ON, AZ 85 718
T: 520.882.4484 F: 520.882.5560
BUILDING
BUILDING
MIRACLE MILE
100% BID DOCUMENT
O
PE
N A
IR
E
N
TR
A N
C E
/3
/2
3:
:1
P
M C
:\U se rs \a sa nd le r\D oc um en ts
\1 3-
M C
D _A
S an dl er
.rv t
OVERALL UPPER LEVEL HVAC PLAN
MH102
13-127
ASST
CLINICAL LABORATORY AND
PHARMACY BUILDING
12/03/2015
1/8" = 1'-0"MH102
1 OVERALL UPPER LEVEL HVAC PLAN
1/4" = 1'-0"MH102
3 ENLARGED UPPER LEVEL HVAC PLAN - CHEMO AND STERILE PREP
1/4" = 1'-0"MH102
2 ENLARGED UPPER LEVEL HVAC PLAN - PHLEBOTOMY AND PHARMACY
BIDDING DOCUMENT REV. 1 Nov. 02, 2015 BID SUBMISSION Dec. 03, 2015 vhapreboydt Highlight vhapreboydt Highlight vhapreboydt Highlight vhapreboydt Highlight
0.1
0.5
G H H.3 H.9 J K K.5 LFD
ACCU
ACCU
EF
AHU
AHU
ROS
PENTHOUSE
164-201
STAIR
S-3
64x24
STRF
STRF
MH104
MH104
AHU
G H
EF
EF
IH
6"Ø TOILET EXHAUST FROM
BELOW. TERMINATE ABOVE
PENTHOUSE ROOF.
MECHANICAL SHEET NOTES
1. 12x16 SUPPLY AIR DUCT DOWN TO LOWER LEVEL. SUPPLY AIR DUCT
SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY LABS. OFFSET
AS NECESSARY TO AVOID BEAMS. CAP DUCT AT PENTHOUSE
SHAFT.
2. EXHAUST FAN MOUNTED ON 12" HIGH ROOF CURB.
3. AIR HANDLING UNIT AHU-3 MOUNTED ON 18" HIGH ROOF CURB.
CURB SHALL BE DESIGNED TO SUPPORT AHU-3 AND ASSOCIATED
COMPONENTS INCLUDING DUCTWORK AND PIPING ABOVE CURB AT
15,000 LBS. CURB SHALL BE INSULATED AND HAVE VIBRATION
ISOLATORS.
4. AIR HANDLING UNIT AHU-1 MOUNTED ON 18" HIGH ROOF CURB.
CURB SHALL BE DESIGNED TO SUPPORT AHU-1 AND ASSOCIATED
COMPONENTS INCLUDING DUCTWORK AND PIPING ABOVE CURB AT
15,000 LBS. CURB SHALL BE INSULATED AND HAVE VIBRATION
ISOLATORS.
5. AIR HANDLING UNIT AHU-4 MOUNTED ON 14" HIGH ROOF CURB.
CURB SHALL BE DESIGNED TO SUPPORT AHU-3 AND ASSOCIATED
COMPONENTS INCLUDING DUCTWORK AND PIPING ABOVE CURB AT
8,000 LBS. CURB SHALL BE INSULATED AND HAVE VIBRATION
ISOLATORS.
6. APPROXIMATE LOCATION AND SIZE OF FUTURE AIR HANDLING UNIT
THAT SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY LABS.
ALLOCATE SUFFICIENT SPACE IN PENTHOUSE FOR FUTURE
DUCTWORK, PIPING, EQUIPMENT, AND CLEARANCES ASSOCIATED
WITH FUTURE AIR HANDLING UNIT.
7. AIR COOLED CONDENSING UNIT MOUNTED ON 4" HIGH CONCRETE
PAD.
8. EXHAUST AIR DUCT HIGH. TERMINATE WITH GRILLE.
9. STROBIC FAN STRF-1 MOUNTED ON 12" HIGH ROOF CURB. CURB
SHALL BE DESIGNED TO SUPPORT THE STROBIC FAN AT 500 LBS.
CURB SHALL BE INSULATED AND HAVE VIBRATION ISOLATORS.
10. 12x12 EXHAUST AIR DUCT DOWN TO UPPER LEVEL. TRANSITION FROM 20x20 DUCT IN VERTICAL.
11. 60x24 SUPPLY AIR DUCT TRANSITION TO 32x24 DUCT DOWN TO
UPPER LEVEL.
12. 60x20 EXHAUST AIR DUCT DOWN TO UPPER LEVEL.
13. 42x24 SUPPLY AIR DUCT DOWN TO UPPER LEVEL.
14. 64x40 EXHAUST AIR DUCT DOWN TO UPPER LEVEL.
15. NOT USED.
16. BLANK OFF LOUVER. LOUVER SHALL BE FOR FUTURE AIR HANDLING
UNIT OUTSIDE AIR INTAKE SERVING FUTURE CYTOLOGY AND
HISTOLOGY LABS.
17. 50x20 SUPPLY AIR DUCT DOWN TO UPPER LEVEL.
18. 30x30 RETURN AIR DUCT DOWN TO UPPER LEVEL.
19. 54x18 OUTSIDE AIR DUCT ABOVE AHU-4.
20. NEMA 3R RATED VARIABLE FREQUENCY DRIVES ASSOCIATED WITH
STROBIC FAN. MOUNT STRF-1 VFD ON WALL. MOUNT STRF-2 VFD
AND STRF-3 VFD ON UNISTRUT.
21. 6"Ø CLOSET EXHAUST DUCT DOWN THROUGH ROOF. TERMINATE
DUCT ABOVE ROOF.
22. 6"Ø TOILET EXHAUST DUCT DOWN THROUGH ROOF.
23. MOUNT REVERSE OSMOSIS SKID AND TANK ON 4" HOUSEKEEPING
PAD. REFER TO SECTION 22 67 19.16 FOR SPECIFICATION ON
REVERSE OSMOSIS SYSTEM.
24. PNEUMATIC TUBE SYSTEM BLOWER SHOWN FOR REFERENCE
ONLY.
25. STROBIC FAN STRF-2 MOUNTED ON 12" HIGH ROOF CURB. CURB
SHALL BE DESIGNED TO SUPPORT THE STROBIC FAN AT 1,500 LBS.
CURB SHALL BE INSULATED AND HAVE VIBRATION ISOLATORS.
26. KEYNOTE NOT USED.
27. APPROXIMATE SIZE AND LOCATION OF FUTURE STROBIC FAN THAT
SHALL SERVE FUTURE CYTOLOGY AND HISTOLOGY LABS.
28. KEYNOTE NOT USED.
29. PNEUMATIC TUBE SYSTEM TRANSFER UNIT SHOWN FOR
REFERENCE ONLY.
30. DOMESTIC HOT WATER HEATERS SHOWN FOR REFERENCE ONLY.
31. GRAVITY INTAKE HOOD IH-1 MOUNTED ON ROOF CURB.
32. 36x36 OUTSIDE AIR DUCT DOWN TO PENTHOUSE.
MECHANICAL GENERAL NOTES
A. AIRFLOWS INDICATED ARE ACTUAL CUBIC FEET PER MINUTE (ACFM).
B. FINAL LOCATION OF THERMOSTATS, ROOM PRESSURE MONITORS, AND
DIFFERENTIAL PRESSURE SENSORS SHALL BE COORDINATED WITH
OWNER, TEMPERATURE CONTROLS CONTRACTOR, AND GENERAL
CONTRACTOR.
C. ALL DUCTWORK…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .