About this file

This is a comprehensive project manual and bidding document for the City of Olathe, Kansas, Infrastructure Department for The Creek - Mill Creek Park Pool Building and Splashpad Improvements (Project No. 4-C-014-25). The project encompasses demolition of an existing park restroom and partial removal of the existing bathhouse with associated infrastructure removal, followed by construction of a new bathhouse and splashpad including associated walkways, utilities, and infrastructure. The scope requires provision of construction plans, specifications, material designations, Olathe codes compliance and permitting, operations and maintenance manuals, warranty information, and as-built drawings of finished improvements. A pre-bid conference is scheduled for June 9, 2026, at 10:00 a.m. local time at 1908 W. Ironwood Street, Olathe, Kansas 66061, with a site tour to follow. Sealed bids will be received electronically at https://olatheks.bonfirehub.com until 10:00 a.m. on Tuesday, June 30, 2026, with public bid opening occurring online at the same location. The contract specifies 182 days for substantial completion and 213 days total for completion and final payment from the date the contract times commence. The project manual includes 122 drawing sheets and comprehensive technical specifications organized into multiple divisions covering demolition, concrete, masonry, metals, wood, thermal and moisture protection, openings, finishes, specialties, special construction, plumbing, HVAC, electrical systems, and exterior improvements.

Bid security in the form of a bid bond equal to five percent of the total bid amount must be submitted with the electronic bid, with the original bond copy due to the engineer within 48 hours of bid opening. The successful bidder must furnish performance and maintenance bonds in an amount equal to one hundred percent of the contract sum, valid for two years from the date of final payment, and a statutory bond as required by Kansas law for contracts exceeding one hundred thousand dollars. Progress payments will be made monthly at 95 percent of work completed with five percent retainage; upon substantial completion, payments increase to 97 percent less the estimated value of punch list items; final payment occurs upon completion and acceptance. Liquidated damages are assessed at $1,000 per day for failure to achieve substantial completion and $1,000 per day for failure to complete remaining work after substantial completion, and $500 per day for failure to meet designated milestones. Non-resident contractors and subcontractors must comply with Kansas statutes including registration with the Director of Revenue and posting of a $1,000 surety bond; all applicable sales, consumer, and use taxes are exempt and must not be included in bid pricing. The contract documents include the EJCDC C-700 2013 Edition Standard General Conditions, supplementary conditions, project requirements, technical specifications, and all referenced drawings and addenda. The City of Olathe reserves the right to reject any or all bids, waive informalities, and hold bids for up to 60 days from opening before award.

View the file

Other files

File Type Posted
2-4-C-014-25 Mill Creek Pool Splashpad Bid Set.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Documents for:

The Creek - Mill Creek Park Pool Building and Splashpad Improvements

Project No. 4-C-014-25

Prepared by:

City of Olathe, Kansas

Infrastructure Department

Engineering Division

GBA

9801 Renner Blvd

Lenexa, KS 66219

May 2026

PROJECT MANUAL

City of Olathe Project No. 4-C-014-25

Mill Creek Pool & Splashpad

Improvements 000101 - 1 Project Title Page

SECTION 000101

PROJECT TITLE PAGE

PROJECT MANUAL

THE CREEK

16890 MILL CREEK POOL AND SPLASHPAD IMPROVEMENTS

320 E POPLAR, OLATHE, KS 66061

CITY OF OLATHE PROJECT NO. 4-C-014-25:

ARCHITECT'S PROJECT 16890:

DATE: MAY. 2026

PREPARED BY: GBA, 9801 RENNER BLVD, LENEXA, KS

(913) 492.0400

GBATEAM.COM

END OF SECTION

Improvements 000107 - 1 Seals Page

SECTION 000107

SEALS PAGE

END OF SECTION

05.15.2026

Nick Ferrara, PLA Landscape Architect KS Lic No. 1017

Treadwell Jones Architect KS Lic A7166

Kevin Juhl, PE MEP Engineer KS Lic No. 21698

Jacob Fajen, PE Electrical Engineer KS Lic No. 20892

Nick Ferrara, PLA Landscape Architect KS Lic No. 1017

05.15.2026

Jacob Schweiker, PE Civil Engineer KS Lic No. 31279

Andrew Smith, PE Aquatics Engineer KS Lic No. 13201

16890 Mill Creek Aquatics

Center - City of Olathe

TABLE OF CONTENTS 05-14-2026

TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

000101 PROJECT TITLE PAGE

000107 SEALS PAGE

000110 TABLE OF CONTENTS

000115 LIST OF DRAWING SHEETS

DIVISION 00 OWNER CONTRACT FORMS

NTB NOTICE TO BIDDERS

ITB INSTRUCTIONS TO BIDDERS

ADF ANTI-DISCRIMINATION FORM

BQ SATEMENT OF BIDDERS QUALIFICAIONS

BB BID BOND

004100 BID FORM

SV SCHEDULE OF VALUES

EJCD-1 STANDARD FORM OF AGREEMENT

EJCD-9 PERFORMANCE AND MAINTENANCE BOND

EJCD-15 STATUTORY BOND

EJCD-20 APPOINTMENT OF PROCESS AGENT

EJCD-21 NON-COLLUSIVE AFFIDAVIT OF PRIME BIDDER

100 STANDARD GENERAL CONDITIONS

SC SUPPLEMENTARY CONDITIONS

PR PROJECT REQUIREMENTS

TF TEMPORARY FACILITIES

SB SUBMITTALS

TS TECHNICAL SPECIFICATIONS

SPC SPECIAL CONDITIONS

M&P MEASUREMENT AND PAYMENT

GIR GENERAL INSURANCE REQUIRMENTS

ACH ACH AUTHORIZATION FORM

DIVISION 01 - GENERAL REQUIREMENTS

011000 SUMMARY

012500 SUBSTITUTION PROCEDURES

013000 ADMINISTRATIVE REQUIREMENTS

013216 CONSTRUCTION PROGRESS SCHEDULE

014000 QUALITY REQUIREMENTS

014216 DEFINITIONS

014533 CODE-REQUIRED SPECIAL INSPECTIONS AND PROCEDURES

015000 TEMPORARY FACILITIES AND CONTROLS

015813 TEMPORARY PROJECT SIGNAGE

016000 PRODUCT REQUIREMENTS

TABLE OF CONTENTS 05-14-2026

017000 EXECUTION AND CLOSEOUT REQUIREMENTS

017800 CLOSEOUT SUBMITTALS

017900 DEMONSTRATION AND TRAINING

DIVISION 02 - EXISTING CONDITIONS

024100 DEMOLITION

DIVISION 03 - CONCRETE

033000 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

042000 UNIT MASONRY

042300 GLASS UNIT MASONRY

DIVISION 05 - METALS

055000 METAL FABRICATIONS

055213 PIPE AND TUBE RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

061000 ROUGH CARPENTRY

061733 WOOD I-JOISTS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

070150.19 PREPARATION FOR RE-ROOFING

072100 THERMAL INSULATION

074113 METAL ROOF PANELS

074646 FIBER-CEMENT SIDING

076200 SHEET METAL FLASHING AND TRIM

079200 JOINT SEALANTS

DIVISION 08 - OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES

081613 FIBERGLASS DOORS

083323 OVERHEAD COILING DOORS

085113 ALUMINUM WINDOWS

085659 SERVICE AND TELLER WINDOW UNITS

086300 METAL-FRAMED SKYLIGHTS

087100 DOOR HARDWARE

088000 GLAZING

088400 PLASTIC GLAZING

DIVISION 09 - FINISHES

092116 GYPSUM BOARD ASSEMBLIES

099000 USER - INTERIOR, EXTERIOR AND HIGH PERFORMANCE PAINTS

AND COATINGS

DIVISION 10 - SPECIALTIES

101419 DIMENSIONAL LETTER SIGNAGE

101423 PANEL SIGNAGE

TABLE OF CONTENTS 05-14-2026

102113.19 PLASTIC TOILET COMPARTMENTS - ASI

102800 TOILET, BATH, AND LAUNDRY ACCESSORIES

105113 METAL LOCKERS

107313 AWNINGS

DIVISION 13 – SPECIAL CONSTRUCTION

131100 SUMMARY OF WORK FOR SPRAY PADS

131100.16 SPRAY PAD EQUIPMNET

131100.19 UV SYSTEM

131400 SPRAY PAD FEATURES

DIVISION 22 - PLUMBING

220517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

220519 METERS AND GAUGES FOR PLUMBING PIPING

220523 GENERAL-DUTY VALVES FOR PLUMBING PIPING

220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND

EQUIPMENT

220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

220719 PLUMBING PIPING INSULATION

220719.11 UNDER-LAVATORY PIPE AND SUPPLY COVERS - PLUMBEREX

221005 PLUMBING PIPING

221006 PLUMBING PIPING SPECIALTIES

223000 PLUMBING EQUIPMENT

224000 PLUMBING FIXTURES

224500 EMERGENCY PLUMBING FIXTURES

DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

231123 FACILITY NATURAL-GAS PIPING

233100 HVAC DUCTS AND CASINGS

233300 AIR DUCT ACCESSORIES

233423 HVAC POWER VENTILATORS

233600 AIR TERMINAL UNITS

233700 AIR OUTLETS AND INLETS

DIVISION 26 - ELECTRICAL

260505 SELECTIVE DEMOLITION FOR ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND

CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533.13 CONDUIT FOR ELECTRICAL SYSTEMS

260533.16 BOXES FOR ELECTRICAL SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

260583 WIRING CONNECTIONS

TABLE OF CONTENTS 05-14-2026

260923 LIGHTING CONTROL DEVICES

262416 PANELBOARDS

262726 WIRING DEVICES

262816.16 ENCLOSED SWITCHES

262913 ENCLOSED CONTROLLERS

265100 INTERIOR LIGHTING

265600 EXTERIOR LIGHTING

DIVISION 32 - EXTERIOR IMPROVEMENTS

329100 SOIL PREPARATION

329200 TURF AND GRASSES

321313 CONCRETE PAVING

323113 CHAIN LINK FENCES AND GATES

323136 SECURITY GATES AND BARRIERS

323313 SITE BICYCLE RACKS

Improvements 000115 - List of Drawing Sheets

ARCHITECTURAL

REV # SHEET # DESCRIPTION

A4.01 ENLARGED PLANS

LS0.00 CODE ANALYSIS - GENERAL

A0.00 SYMBOLS, ABBREVIATIONS, & DISCLAIMER - 24x36

A0.30 TYPICAL DETAILS

A0.31 TYPICAL ADA CLEARANCES & RESTROOM MOUNTING HEIGHTS

AD0.50 ARCHITECTURAL SITE DEMOLITION PLAN

AD1.10 BATHHOUSE DEMOLITION PLAN

AD1.12 OVERALL ROOF DEMOLITION PLAN

A0.51 OVERALL ARCHITECTURAL SITE PLAN

A1.00 BUILDING AXONOMETRIC

A1.01 BUILDING AXONOMETRIC

A1.02 PERSPECTIVES

A1.10 OVERALL FIRST FLOOR PLAN

A1.11 CONCESSIONS / PUMP HOUSE FLOOR PLAN

A1.12 BATHHOUSE FLOOR PLAN

A1.20 OVERALL ROOF PLAN - CONSTRUCTION

A2.10 OVERALL FIRST FLOOR REFLECTED CEILING PLAN - CONSTRUCTION

A3.01 EXTERIOR BUILDING ELEVATIONS

A3.11 BUILDING SECTIONS

A3.21 WALL SECTIONS

A3.22 WALL SECTIONS

A3.23 WALL SECTIONS

A4.10 INTERIOR ELEVATIONS

A5.02 SECTION DETAILS

A5.03 SECTION DETAILS

A5.04 SECTION DETAILS

A5.05 SECTION DETAILS

A5.10 SCREENING DETAILS

A6.01 DOOR SCHEDULE / DETAILS

A7.01 ROOM FINISH SCHEDULE

A7.11 ROOM FINISH PLAN

STRUCTURAL

REV # SHEET # DESCRIPTION

S0.00 STRUCTURAL GENERAL NOTES

S0.01 STRUCTURAL GENERAL NOTES

S0.02 STRUCTURAL SPECIAL INSPECTIONS

S0.03 STRUCTURAL SPECIAL INSPECTIONS

S1.10 FOUNDATION PLAN

S1.20 ROOF FRAMING PLAN

S3.00 FOUNDATION SECTIONS

S3.10 FRAMING SECTIONS

S5.10 TYPICAL FOUNDATION DETAILS

S5.20 TYPICAL SLAB DETAILS

S5.30 TYPICAL CONCRETE MASONRY DETAILS

S5.40 RESERVIOUR TANK PLAN & DETAILS

CIVIL / LANDSCAPING

REV # SHEET # DESCRIPTION

C100 GENERAL NOTES

C200 DEMOLITION PLAN

C300 SITE PLAN

C400 GRADING PLAN

C500 DIMENSION PLAN

C600 UTILITY PLAN

C700 EROSION CONTROL PLAN

C800 CONSTRUCTION DETAILS

C801 CONSTRUCTION DETAILS

L001 MATERIAL LEGEND

L100 LANDSCAPE PLAN

L101 LANDSCAPE DETAILS

L200 TREE PRESERVATION PLAN

L300 HARDSCAPE PLAN

L301 FINE GRADING PLAN - SPLASH PAD

L302 LAYOUT AND DIMENSION PLAN - SPLASH PAD

L400 HARDSCAPE DETAILS

L401 HARDSCAPE DETAILS

L402 HARDSCAPE DETAILS

L403 HARDSCAPE DETAILS

L404 HARDSCAPE DETAILS

SECTION 000115

LIST OF DRAWING SHEETS

Improvements 000115 - List of Drawing Sheets

ARCHITECTURAL

REV # SHEET # DESCRIPTION

A4.01 ENLARGED PLANS

LS0.00 CODE ANALYSIS - GENERAL

A0.00 SYMBOLS, ABBREVIATIONS, & DISCLAIMER - 24x36

A0.30 TYPICAL DETAILS

A0.31 TYPICAL ADA CLEARANCES & RESTROOM MOUNTING HEIGHTS

AD0.50 ARCHITECTURAL SITE DEMOLITION PLAN

AD1.10 BATHHOUSE DEMOLITION PLAN

AD1.12 OVERALL ROOF DEMOLITION PLAN

A0.51 OVERALL ARCHITECTURAL SITE PLAN

A1.00 BUILDING AXONOMETRIC

A1.01 BUILDING AXONOMETRIC

A1.02 PERSPECTIVES

A1.10 OVERALL FIRST FLOOR PLAN

A1.11 CONCESSIONS / PUMP HOUSE FLOOR PLAN

A1.12 BATHHOUSE FLOOR PLAN

A1.20 OVERALL ROOF PLAN - CONSTRUCTION

A2.10 OVERALL FIRST FLOOR REFLECTED CEILING PLAN - CONSTRUCTION

A3.01 EXTERIOR BUILDING ELEVATIONS

A3.11 BUILDING SECTIONS

A3.21 WALL SECTIONS

A3.22 WALL SECTIONS

A3.23 WALL SECTIONS

A4.10 INTERIOR ELEVATIONS

A5.02 SECTION DETAILS

A5.03 SECTION DETAILS

A5.04 SECTION DETAILS

A5.05 SECTION DETAILS

A5.10 SCREENING DETAILS

A6.01 DOOR SCHEDULE / DETAILS

A7.01 ROOM FINISH SCHEDULE

A7.11 ROOM FINISH PLAN

ARCHITECTURAL

REV # SHEET # DESCRIPTION

A4.01 ENLARGED PLANS

LS0.00 CODE ANALYSIS - GENERAL

A0.00 SYMBOLS, ABBREVIATIONS, & DISCLAIMER - 24x36

A0.30 TYPICAL DETAILS

A0.31 TYPICAL ADA CLEARANCES & RESTROOM MOUNTING HEIGHTS

AD0.50 ARCHITECTURAL SITE DEMOLITION PLAN

AD1.10 BATHHOUSE DEMOLITION PLAN

AD1.12 OVERALL ROOF DEMOLITION PLAN

A0.51 OVERALL ARCHITECTURAL SITE PLAN

A1.00 BUILDING AXONOMETRIC

A1.01 BUILDING AXONOMETRIC

A1.02 PERSPECTIVES

A1.10 OVERALL FIRST FLOOR PLAN

A1.11 CONCESSIONS / PUMP HOUSE FLOOR PLAN

A1.12 BATHHOUSE FLOOR PLAN

A1.20 OVERALL ROOF PLAN - CONSTRUCTION

A2.10 OVERALL FIRST FLOOR REFLECTED CEILING PLAN - CONSTRUCTION

A3.01 EXTERIOR BUILDING ELEVATIONS

A3.11 BUILDING SECTIONS

A3.21 WALL SECTIONS

A3.22 WALL SECTIONS

A3.23 WALL SECTIONS

A4.10 INTERIOR ELEVATIONS

A5.02 SECTION DETAILS

A5.03 SECTION DETAILS

A5.04 SECTION DETAILS

A5.05 SECTION DETAILS

A5.10 SCREENING DETAILS

A6.01 DOOR SCHEDULE / DETAILS

A7.01 ROOM FINISH SCHEDULE

A7.11 ROOM FINISH PLAN

Improvements 000115 - List of Drawing Sheets

AQ-000 GENERAL NOTES

AQ-001 SITE PLAN

AQ-002 SPRAY PAD DETAILS

AQ-100 PIPING AND CONTROLS SCHEMATIC

AQ-110 SPAY PAD SITE PIPING

AQ-120 MECHANICAL ROOM PLAN

AQ-121 MECHANICAL ROOM ELEVATIONS AND SECTIONS

AQ-122 MECHANICAL DETAILS

AQ-123 MECHANICAL DETAILS

SPRAY PAD CONSULTANT

REV # SHEET # DESCRIPTION

MECHANICAL HVAC

REV # SHEET # DESCRIPTION

M0.00 HVAC SYMBOLS/ MATERIALS/ ABBREVIATIONS/ DISCLAIMER

M0.01 HVAC SYMBOLS/ MATERIALS/ ABBREVIATIONS/ DISCLAIMER

MHD1.10 OVERALL HVAC PLAN - DEMO

MHD1.11 HVAC PLAN - AREA A - DEMO

MH1.10 OVERALL HVAC PLAN

MH1.11 HVAC PLAN - AREA A

MH1.12 HVAC PLAN - AREA B

M5.00 MECHANICAL DETAILS

M6.00 MECHANICAL SCHEDULES

ELECTRICAL

REV # SHEET # DESCRIPTION

E0.00 SYMBOLS/ NOTES/ ABBREVIATIONS/ DISCLAIMER

EPD1.10 OVERALL POWER FLOOR PLAN - DEMOLITION

EPD1.11 CONCESSIONS / PUMP HOUSE POWER FLOOR PLAN - DEMOLITION

ELD1.10 OVERALL LIGHTING FLOOR PLAN - DEMOLITION

EL1.10 OVERALL LIGHTING FLOOR PLAN - CONSTRUCTION

EL1.11 CONCESSIONS / PUMP HOUSE LIGHTING FLOOR PLAN - CONSTRUCTION

EL1.12 BATHHOUSE LIGHTING FLOOR PLAN - CONSTRUCTION

EP1.10 OVERALL POWER FLOOR PLAN - CONSTRUCTION

EP1.11 CONCESSIONS / PUMP HOUSE POWER FLOOR PLAN - CONSTRUCTION

EP1.12 BATHHOUSE POWER FLOOR PLAN - CONSTRUCTION

ES1.11 CONCESSIONS / PUMP HOUSE SPECIAL SYSTEMS FLOOR PLAN - CONSTRUCTION

ES1.10 OVERALL SPECIAL SYSTEMS FLOOR PLAN - CONSTRUCTION

E3.00 EQUIPMENT ROOM SECTION

E5.00 ELECTRICAL DETAILS

E5.01 ELECTRICAL DETAILS

E6.00 ELECTRICAL SCHEDULES

E6.01 ELECTRICAL SCHEDULES

E8.00 ELECTRICAL ONE-LINE DIAGRAMS

City of Olathe NB-1 Project No. 4-C-014-25

CITY OF OLATHE, KANSAS

ENGINEERING DIVISION

NOTICE TO BIDDERS

Sealed bids will be received online at https://olatheks.bonfirehub.com, until 10 a.m. local time, on Tuesday, June 30, 2026, for the construction of The Creek – Mill Creek Park (Pool Building and Splashpad Improvements), Project No. 4-C-014-25.

Pre-Bid Conference. Contractors wishing to bid on this work are encouraged to attend the pre-bid meeting on June 9, 2026 at 10 A.M. local time at 1908 W. Ironwood St. Olathe, KS 66061. A site tour will follow.

Public Bid Opening. At said time and place, and promptly thereafter, all bids that have been duly received will be publicly opened online at https://olatheks.bonfirehub.com.

Scope. The project scope of work includes demolition of a park restroom and partial removal of existing bathhouse with associated infrastructure removal. Provide construction of a new bathhouse and splashpad including associated walkways and infrastructure. Construction plans, specifications, material designations, Olathe codes compliance and permitting, Operations and Maintenance Manuals, Warranty Information and “As-Builts” of finished improvements are required.

Plans. Bid documents including drawings and specifications are on file at the office of Public Works of Olathe, Kansas, and are open for public inspections. Bid documents and drawings may be downloaded free of charge from https://olatheks.bonfirehub.com. Only bids submitted electronically at https://olatheks.bonfirehub.com will be accepted.

Questions concerning this bid can be directed to: https://olatheks.bonfirehub.com.

Bid Bond. A satisfactory bid bond executed by the bidder or an acceptable surety, in an amount equal to five percent (5%) of the total bid for work shall be submitted with each proposal. A scanned copy of the BID BOND must be included with the online bid submitted at https://olatheks.bonfirehub.com. The original copy of the BID BOND form must be submitted to the ENGINEER within 48 hours of bid opening. Failure to submit original copy of the bid bond will result in rejection of bid and OWNER’s selection of the next low qualified bidder.

Addenda. All bidders shall verify that they have considered all written addenda. Any written addenda issued during the time of bidding shall be covered and included in the bid. There will be no clarifications or exceptions allowed on the Bid. Bids are for a total bid package, and total contract price.

The successful bidder will be required to furnish and pay satisfactory performance and payment bond or bonds.

The City of Olathe, Kansas, reserves the right to reject any or all bids or to waive any informality in the bidding.

City of Olathe NB-2 Project No. 4-C-014-25

Bids may be held by the City of Olathe, Kansas, for a period not to exceed sixty (60) days from the date of the opening of bids for the purpose of reviewing the bids and investigating the qualifications of bidders, prior to awarding the contract.

BY Brenda Swearingian City Clerk

City of Olathe TC - 1 Project No. 4-C-014-25

TABLE OF CONTENTS

NOTICE TO BIDDERS .................................................................................................NB-1 TABLE OF CONTENTS ...............................................................................................TC-1 INSTRUCTIONS TO BIDDERS ...................................................................................ITB-1 01 Terms ...........................................................................................................ITB-1 02 Copies of Bidding Documents....................... ..............................................ITB-1 03 Qualifications of Bidders......................... ....................................................ITB-1 04 Examination of Contract Documents & Site.......... .....................................ITB-1 05 Interpretations................................... ...........................................................ITB-2 06 Bid Security...................................... ...........................................................ITB-2 07 Contract Time..................................... .........................................................ITB-2 08 Liquidated Damages................................ ....................................................ITB-3 09 Substitute Material & Equipment................... .............................................ITB-3 10 Subcontractors, Etc............................... .......................................................ITB-3 11 Bid Form.......................................... ............................................................ITB-4 12 Submission of Bids................................ ......................................................ITB-4 13 Modification and Withdrawal of Bids............... ..........................................ITB-4 14 Opening of Bids................................... ........................................................ITB-4 15 Bids to Remain Open............................... ....................................................ITB-4 16 Award of Contract................................. ......................................................ITB-4 17 Performance and Other Bonds....................... ..............................................ITB-5 18 Signing of Agreement.............................. ....................................................ITB-5 19 Special Legal Requirements........................ ................................................ITB-5 20 Non-Resident Contractors.......................... .................................................ITB-6 21 Equal Employment Opportunity...................... ............................................ITB-6 22 Tax Exemption..................................... .......................................................ITB-6 ANTI-DISCRIMINATION FORM ................................................................................ADF-1 STATEMENT OF BIDDERS QUALIFICATIONS........................ ..............................BQ-1 BID BOND................................................... ..................................................................BB-1 BID FORM................................................... ..................................................................BF-1 SCHEDULE OF VALUES.............................................................................................SV-1 STANDARD FORM OF AGREEMENT....................... ...............................................EJCDC-1 PERFORMANCE AND MAINTENANCE BOND........................... ...........................EJCDC-9 STATUTORY BOND............................................. .......................................................EJCDC-15 APPOINTMENT OF PROCESS AGENT............................... ......................................EJCDC-20 NON-COLLUSIVE AFFIDAVIT OF PRIME BIDDER.................... ...........................EJCDC-21 STANDARD GENERAL CONDITIONS................................ .....................................100-1 SUPPLEMENTARY CONDITIONS................................... ..........................................SC-1 PROJECT REQUIREMENTS........................................................................................PR-1 TEMPORARY FACILITIES....................................... ..................................................TF-1 SUBMITTALS................................................. ..............................................................SB-1 TECHNICAL SPECIFICATIONS................................... ..............................................TS-1 SPECIAL CONDITIONS......................................... ......................................................SPC-1 MEASUREMENT AND PAYMENT.................................... ........................................M&P-1 GENERAL INSURANCE REQUIREMENTS.................................... ..........................GIR-1 ACH AUTHORIZATION FORM.................................... ..............................................ACH-1

City of Olathe ITB- Project No. 4-C-014-25

INSTRUCTIONS TO BIDDERS

1. DEFINED TERMS

These Instructions to Bidders which are defined in the Standard General Conditions of the

Construction Contract, EJCDC C-700, 2013 Edition have the meanings assigned to them in the General Conditions. The term “Successful Bidder” means the lowest qualified, responsible BIDDER to whom OWNER (on the basis of OWNER’S evaluation as hereinafter provided) makes an award.

2. COPIES OF BIDDING DOCUMENTS

A. Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the Advertisement or Invitation may be obtained from ENGINEER via https://olatheks.bonfirehub.com.

B. Complete sets of Bidding Documents shall be used in preparing bids; neither OWNER nor

ENGINEER assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

C. OWNER and ENGINEER in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining bids on the work and do not confer a license or grant for any other use.

3. QUALIFICATIONS OF BIDDERS

A. Contractor to provide a Certificate of Good Standing from the Kansas Secretary of State prior to the project award.

B. To demonstrate qualifications to perform the work, each BIDDER must be prepared to submit, within five (5) days of OWNER's request, a notarized "Statement of Bidder's Qualifications." A form for this purpose is included in this document. All information requested on the form must be provided. Each bid must contain evidence of BIDDER's qualification to do business in the state where the project is located or covenant to obtain such qualification prior to award of the contract.

4. EXAMINATION OF CONTRACT DOCUMENTS AND SITE

A. Before submitting a bid, each BIDDER must (a) examine the Contract Documents thoroughly, (b) visit the site to familiarize himself with local conditions that may in any manner affect cost, progress or performance of the work, (c) familiarize himself with federal, state and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the work; and (d) study and carefully correlate BIDDER'S observations with the Contract Documents.

B. Reference may be made in the Supplementary Conditions for the identification of those reports of investigations and tests of subsurface and latent physical conditions at the site or otherwise affecting cost, progress, or performance of the work which have been relied upon by the ENGINEER used in preparing the drawings and specifications. OWNER will make copies of such reports available to any BIDDER requesting them. These reports are not guaranteed as to accuracy or completeness, nor are they part of the Contract Documents.

Before submitting his bid each BIDDER will, at his own expense, make such additional investigations and tests as the BIDDER may deem necessary to determine his bid for performance of the work in accordance with the time, price and other terms and conditions of the Contract Documents.

C. On request, OWNER will provide each BIDDER access to the site to conduct such investigations and tests as each BIDDER deems necessary for submission of his bid.

D. The lands upon which the work is to be performed, rights-of-way for access thereto and other lands designated for use by CONTRACTOR in performing the work are identified in the Supplementary Conditions, General Requirements, or drawings.

E. The submission of a bid will constitute an incontrovertible representation by the BIDDER that he has complied with every requirement of this Article 4 and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of the work.

5. INTERPRETATIONS

All questions about the meaning or intent of the Contract Documents shall be entered on line via

Bonfire. Replies will be issued by addenda via Bonfire to all parties recorded as having received the bidding documents. Questions received less than three (3) days prior to the date for opening of bids will not be answered. Only questions answered via Bonfire through an addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

6. BID SECURITY

A. Bid Security shall be made payable to OWNER in an amount of five percent (5%) of the

BIDDER'S maximum bid price and in the form of a Bid Bond (on form attached, if a form is prescribed) issued by a Surety meeting the requirements of paragraph 6.01 of the General Conditions.

B. The Bid Security of the successful BIDDER will be retained until such BIDDER has executed the agreement and furnished the required Contract Security, whereupon it will be returned; if the successful BIDDER fails to execute and deliver the agreement and furnish the required Contract Security within ten (10) days of the Notice of Award, OWNER may annul the Notice of Award and the Bid Security of that BIDDER will be forfeited. The Bid Security of any BIDDER whom OWNER believes to have a reasonable chance of receiving the award may be retained by OWNER until the earlier of the seventh day after the "effective date of the agreement" (which term is defined in the General Conditions) by OWNER to CONTRACTOR and the required Contract Security is furnished on the sixty-first (61) day after the bid opening. Bid Security of other BIDDERS will be returned within sixty (60) days of the bid opening.

C. A scanned copy of the BID BOND must be included with the online bid submitted at https://olatheks.bonfirehub.com. The original copy of the BID BOND form must be submitted to the ENGINEER within 48 hours of bid opening. Failure to submit original copy of the bid bond will result in rejection of bid and OWNER’s selection of the next low qualified bidder.

7. CONTRACT TIME

The number of days within which, or the date by which, the work is to be completed (the contract time) is set forth in the Bid Form and will be included in the Agreement.

8. LIQUIDATED DAMAGES

Provisions for liquidated damages, if any, are set forth in the Agreement.

9. SUBSTITUTE MATERIAL AND EQUIPMENT

The contract, if awarded, will be on the basis of material and equipment described in the drawings or specified in the specifications without consideration of possible substitute or "or-equal" items.

Whenever it is indicated in the drawings or specified in the specifications that a substitute or "or-equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to ENGINEER, application for such acceptance will not be considered by ENGINEER until after the "effective date of the agreement." The procedure for submittal of any such application by CONTRACTOR and consideration by ENGINEER is set forth in paragraphs 7.04 and 7.05 of the General Conditions and paragraphs SC 7.04.A and SC 7.04.D of the Supplementary Conditions.

10. SUBCONTRACTORS, ETC.

A. If the Supplementary Conditions require the identity-identities of certain

SUBCONTRACTORS and other persons and organizations to be submitted to OWNER in advance of the Notice of Award, the apparent Successful BIDDER, and any other BIDDER so requested, will within thirty (30) days after the day of the bid opening submit to OWNER a list of all SUBCONTRACTORS and other persons and organizations (including those who are to furnish the principal items of material and equipment) proposed for those portions of the work as to which such identification is so required. Such list shall be accompanied by an experience statement with pertinent information as to similar projects and other evidence of qualification for each such SUBCONTRACTOR, person and organization if requested by OWNER. If OWNER or ENGINEER, after due investigation-investigations, has reasonable objection to any proposed SUBCONTRACTOR, other person or organization, either may before giving the Notice of Award request the apparent Successful BIDDER to submit an acceptable substitute without an increase in bid price. If the apparent Successful BIDDER declines to make any such substitution, the contract shall not be awarded to such BIDDER, but his declining to make any such substitution will not constitute grounds for sacrificing his Bid Security. Any SUBCONTRACTOR, other person or organization so listed and to whom OWNER or ENGINEER does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to OWNER and ENGINEER.

B. In contracts where the contract price is on the basis of cost-of-the-work plus a fee, the apparent Successful BIDDER, prior to the Notice of Award, shall identify in writing to OWNER those portions of the work that such BIDDER proposes to subcontract and after the Notice of Award may only subcontract other portions of the work with OWNER'S written consent.

C No CONTRACTOR shall be required to employ any SUBCONTRACTOR, other person, or organization against whom he has reasonable objection.

D As provided in Article 7 of the General Conditions, the CONTRACTOR may utilize the services of SUBCONTRACTORS on those parts of the Work which, under normal contracting practices, are performed by SUBCONTRACTORS; provided, however that the CONTRACTOR shall not award subcontracts which total more than 60% of the total Contract Price based upon the unit prices within the Bid submitted to the OWNER by the

CONTRACTOR.

11. BID FORM

The bid form attached hereto is for reference only; bidders must download and complete the required bid form and enter line item unit amounts online at https://olatheks.bonfirehub.com.

12. SUBMISSION OF BIDS

Bids shall be submitted at the time and place indicated in the Invitation to Bid, only bids submitted electronically at https://olatheks.bonfirehub.com will be considered. A scanned copy of the BID BOND must be included with the online bid. Bidders shall acknowledge receipt of any bid addenda issued by signing the bid addendum form and uploading with the Bid.

13. MODIFICATION AND WITHDRAWAL OF BIDS

A. Bids may be modified or withdrawn online at any time up to the time and date of bid opening listed on the Notice to Bidders.

B. If, within twenty-four (24) hours after bids are opened, any BIDDER files a duly signed written notice with OWNER and promptly thereafter demonstrates to the reasonable satisfaction of OWNER that there was a material and substantial mistake in the preparation of his bid, that BIDDER may withdraw his bid and the Bid Security will be returned.

Thereafter, that BIDDER will be disqualified from further bidding on the work.

14. OPENING OF BIDS

Bids will be opened (publicly).

A. Bids will be opened publicly online at https://olatheks.bonfirehub.com. The online process shall be utilized in place of a bid opening meeting, unless otherwise noted in the contract documents. An abstract of the base bids and major alternatives (if any) will be available online after the opening of the bids.

B. When bids are opened publicly at a bid opening meeting they will be read aloud, and an abstract of the amounts of the base bids and major alternates (if any) will be made available after the opening of bids.

C. When bids are opened privately, an abstract of the same information will be made available to BIDDERS within seven (7) days after the date of bid opening upon receipt of a written request to the OWNER by the CONTRACTOR.

15. BIDS TO REMAIN OPEN

All bids shall remain open for sixty (60) days after the date of the bid opening, but OWNER may, in his sole discretion, release any bid and return the Bid Security prior to that date.

16. AWARD OF CONTRACT

A. OWNER reserves the right to reject any and all bids, to waive any and all informalities and to negotiate contract terms with the Successful BIDDER, and the right to disregard all nonconforming, non-responsive or conditional bids. Discrepancies between words and figures will be resolved in favor of words. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

B. In evaluating bids, OWNER shall consider the qualifications of the BIDDERS, whether or not the bids comply with the prescribed requirements, and alternates and unit prices if requested in the bid forms. It is OWNER'S intent to accept alternates (if any are accepted) in the order in which they are listed in the bid form but OWNER may accept them in any order or combination.

C. OWNER may consider the qualifications and experience of SUBCONTRACTORS and other persons and organizations (including those who are to furnish the principal items of material or equipment) proposed for those portions of the work as to which the identity of SUBCONTRACTORS and other persons and organizations must be submitted as provided in the Supplementary Conditions. Operating costs, maintenance considerations, performance data and guarantees of materials and equipment may also be considered by

OWNER.

D. OWNER may conduct such investigations as he deems necessary to assist in the evaluation of any bid and to establish the responsibility, qualifications and financial ability of the BIDDERS, proposed SUBCONTRACTORS and other persons and organizations to do the work in accordance with the Contract Documents to OWNER'S satisfaction within the prescribed time.

E. OWNER reserves the right to reject the bid of any BIDDER who does not pass any such evaluation to OWNER'S satisfaction.

F. If the contract is to be awarded it will be awarded to the lowest responsive and responsible

BIDDER whose evaluation by OWNER indicates to OWNER that the award will be in the best interests of the project.

G. If the contract is to be awarded, OWNER will give the Successful BIDDER a Notice of

Award within sixty (60) days after the day of the bid opening.

17. PERFORMANCE AND OTHER BONDS

Paragraph 6.01 of the General Conditions and Section SC 6.01.A of the Supplementary Conditions set forth OWNER'S requirements as to performance and other bonds. When the Successful BIDDER delivers the executed agreement to OWNER it shall be accompanied by the required Contract Security.

18. SIGNING OF AGREEMENT

When OWNER gives a Notice of Award to the Successful BIDDER, it will be accompanied by at least five (5) unsigned counterparts of the agreement and all other Contract Documents. Within ten (10) days thereafter CONTRACTOR shall sign and deliver at least five (5) counterparts of the agreement to OWNER with all other Contract Documents attached. Within fifteen (15) days thereafter OWNER will deliver all fully signed counterparts to CONTRACTOR. ENGINEER will identify those portions of the Contract Documents not fully signed by OWNER and CONTRACTOR and such identification shall be binding on all parties.

19. SPECIAL LEGAL REQUIREMENTS

The contract awardee, if not a resident of Kansas, shall appoint a Process Agent as provided by the form in these documents. Refer to the Supplementary Conditions for further instructions.

20. NON-RESIDENT CONTRACTORS

A. If the Successful BIDDER is a corporation organized outside the state of Kansas, it will be necessary to apply to the Secretary of State for authority to engage in business in this state as a foreign corporation (see K.S.A. 17-7301 et. seg.).

B. All non-resident CONTRACTORS and SUBCONTRACTORS, as defined in K.S.A. 79-

1008, desiring to engage in the business of construction in the State of Kansas and who have not registered this contract with the Director of Revenue for the state of Kansas, post a good and valid surety bond in the sum of $1,000.00 and conditioned that all taxes, including contributions due under the employment security law, which may accrue to the state of Kansas and all taxes, including contributions due under the employment security law, which may accrue to the State of Kansas, and all taxes which may accrue to the political sub-divisions thereof on such Contract shall be paid (see K.S.A. 79-1009 et. seg.).

21. EQUAL EMPLOYMENT OPPORTUNITY

Attention of BIDDERS is particularly called to the requirements for assuring that employees and applicants for employment are not discriminated against in the performance of any work done under the contract because of race, religion, color, sex, physical handicap unrelated to such person's ability to engage in the particular work, or national origin or ancestry.

22. TAX EXEMPTION

All applicable taxes, sales, consumer, use and other similar taxes, imposed by any taxing authority, on materials, equipment or supplies to be incorporated in the work, shall be tax exempt and not included in the Bid.

The low BIDDER shall be required to furnish taxing authorities any necessary information or reports pertaining thereto, as required.

Pursuant to KSA 79-3606, both services and materials for this project are exempt from the Kansas

Retailers' Sales Tax and the Kansas Compensating Tax. Within fifteen (15) days after the date of Contract, OWNER will provide a Kansas sales and compensating tax exemption certificate number to CONTRACTOR. CONTRACTOR and each SUBCONTRACTOR or repairman must furnish the exemption certificate number to each supplier on Kansas Sales Tax Division Form STD 74.

The exemption certificate number shall be placed on all invoices for material to be incorporated in the work. All invoices shall be held by CONTRACTOR for five (5) years, and shall be subject to audit by the Director of Taxation. Upon completion of the work, CONTRACTOR shall file with OWNER on a form provided by the Director of Taxation, a sworn statement that all purchases made under the exemption certificate were entitled to be exempt from the Kansas Retailers' Sales Tax and the Kansas Compensating Tax. CONTRACTOR shall assume full responsibility for proper use of the exemption certificate number and shall pay all legally assessed penalties for improper use of the certificate number.

City of Olathe ADF-1 Project No. 4-C-014-25

***For completion by bid finalists ONLY***

When selected as the successful bidder for a contract with the City of Olathe, the Contracting Company, Firm or Agency will submit the following information in accordance with the requirements of the Municipal Code. All questions must be answered, and the data given must be clear and comprehensive.

If necessary, questions may be answered on separate attached sheets. This questionnaire must be notarized. Misrepresentation of fact will disqualify the bidder. Please e-mail the completed Questionnaire separately to your Olathe contract liaison if you are selected as a bid finalist. If you have already completed this questionnaire or received Compliance Certification after August 2017, you do not need to resubmit these forms unless there have been significant changes to your ownership and/or business practices. Instead, please submit the date and project number and project description related to your submission of these form. For questions, please contact the Office of Community Relations at

(913) 971-8827.

Name of Contracting Company, Firm or Agency:

Name of your Equal Employment Officer or designated contact person:

Address: ________________________________________________________

City: ______________________State: _____________________Zip: ________

Contact Person’s Phone: __________________________________________

Email: _______________________________________________________________

Type of Company, Firm or Agency: __________________________________

Name of Company, Firm or Agency President: _________________________

I certify that that my company:

1. Does not discriminate, will not discriminate, and has never discriminated against any employee or applicant for employment because of Race, Religion, Color, Sex, Age, Disability, National Origin or Ancestry.

Yes ☐ No☐

If No, explain

City of Olathe ADF-2 Project No. 4-C-014-25

2. Will adhere to Local, State, and Federal laws and mandates; and will adhere to Affirmative Action/Equal Opportunity in all its employment procedures including advertising, recruiting, hiring, training, promotions and upgrading.

3. Will require that any subcontractor my company hires for any work for the City comply with these non-discrimination policies.

I understand that an act of discrimination is a breach contract with the City. I also understand that the Community Relations Manager or designee is authorized to initiate investigations, receive discrimination complaints, and refer them to the Olathe Human Relations Commission on an ongoing basis. An Act of discrimination or a misleading or a dishonest response to this form may result in the contract being rescinded, terminated, or suspended in whole or in part.

Dated this ___________day of ____________, 202___.

Firm Name _________________________________________________________________

Signature of Person Completing Form: __________________________________________________________________

Print Name __________________________________________________________________

Title __________________________________________________________________

Email______________________________________ Phone _________________

To be completed by a Notary Public:

State of ___________________________

(County) of ________________________

Signed and sworn to (or affirmed) before me on _______________ by ___________________________.

(Signature of notarial officer)

(Seal)

Title (and Rank)

[My appointment expires: ________]

City of Olathe BQ - 1 Project No. 4-C-014-25

STATEMENT OF BIDDER'S QUALIFICATIONS

(To be submitted by the Bidder only upon specific request of the City of Olathe).

All questions must be answered and the data given must be clear and comprehensive. This statement must be notarized. If necessary, questions may be answered on separate attached sheets. The Bidder may submit any additional information he desires.

1. Name of Bidder:

2. Permanent main office address:

3. When organized:

4. If a corporation, where incorporated:

5. How many years have you been engaged in the contracting business under your present firm or trade name?

6. Contracts on hand: (Schedule these, showing amount of each contract and the appropriate anticipated dates of completion.)

7. General character of work performed by your company:

8. Have you ever failed to complete any work awarded to you?

If so, where and why?

9. Have you ever defaulted on a contract?

If so, where and why?

10. List the more important projects recently completed by your company, stating the approximate cost for each, and the month and year completed:

11. Experience in construction work similar in importance to this project:

12. List your major equipment available for this contract:

City of Olathe BQ - 2 Project No. 4-C-014-25

13. Background and experience of the principal members of your organization, including the officers.

14. Credit available: $_______________________.

15. Give bank references:

16. Will you, upon request, fill out a detailed financial statement and furnish any other information that may be required by the City of Olathe?

17. The undersigned hereby authorized and requests any person, firm, or corporation to furnish any information requested by the City of Olathe in verification of the recitals comprising this Statement of Bidder's Qualifications.

Dated at ______________________this ________ day of _________________________, 20____.

By _________________________________

Title ________________________________

State of )

)ss

County of ) being duly sworn, deposes and says that he is ________________________________________________ of

___________________________________________________ and that the answers to the foregoing questions and all statements therein contained are true and correct.

Subscribed and sworn to me before this _____ day of _______________________, 20____.

Notary Public

My commission expires ________________________, 20_________.

City of Olathe BB - 1 Project No. 4-C-014-25

BID BOND

KNOW ALL MEN BY THESE PRESENTS, that we ______________________________________________, a

___________________________________________ duly organized under the laws of the State of ___________, as PRINCIPAL, and

_____________________________________, a corporation duly organized under the laws of the State of ___________, as SURETY, are held and firmly bound unto the City of Olathe, Kansas, herein after called the City of Olathe, in the penal sum of ______ Percent of the Amount of Bid

( __%), for the payment of which sum will and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal has submitted the accompanying bid, dated__________________________,20________, for the following project:

NOW, THEREFORE, if the Principal shall not withdraw said Bids within the period specified therein after the opening of the same, or, if no period be specified, within thirty (30) days after the said opening, and shall within the period specified therefore, or if no period be specified, within ten (10) days after the prescribed forms are presented to SURETY for signature, enter into a written Contract with the City of

Olathe in accordance with the Bid as accepted, and give bond with good and sufficient surety or sureties, as may be required, for the faithful performance and proper fulfillment of such Contract; or in the event of the withdrawal of said Bid within the period specified, or the failure to enter into such Contract and give such bond within the time specified, if the Principal shall pay the City of Olathe the difference between the amount specified in said Bid and the amount for which the City of Olathe may procure the required work or supplies for both, if the latter be in excess of the former, then the above obligation shall be void and of no effect, otherwise to remain in full force and virtue.

IN WITNESS WHEREOF, the above-bounded parties have executed this instrument under their several seals this _____ day of_____________________, 20____, the name and corporate seal of each corporate party being hereto affixed.

PRINCIPAL SURETY

_____________________________________________ (SEAL) _______________________________________________ (SEAL)

(Principal) (Surety)

Business Address: ___________________________________ By: __________________________________________________

___________________________________ Attorney-in-Fact, State of _______________________

By: _______________________________________________ Surety Phone No: ______________________________________

(Corp. Principal)

__________________________________________________ Witness: _____________________________________________ (Title)

Witness: ___________________________________________

Improvements 004100 - 1 Bid Form

SECTION 004100

BID FORM

THE PROJECT AND THE PARTIES

1.01 TO:

A. Owner Olathe, Kansas66061

1.02 FOR:

A. Project: 16890 Mill Creek Aquatics Center - City of Olathe

1.03 DATE: ______________ (BIDDER TO ENTER DATE)

1.04 SUBMITTED BY: (BIDDER TO ENTER NAME AND ADDRESS)

A. Bidder's Full Name _________________________

1. Address _________________________

2. City, State, Zip_________________________

1.05 OFFER

A. Having examined the Place of The Work and all matters referred to in the Instructions to

Bidders and the Bid Documents prepared by GBA for the above mentioned project, we, the undersigned, hereby offer to enter into a Contract to perform the Work for the Sum of:

B. _________________________________________________________ _________________________________________________________ dollars ($______________________), in lawful money of the United States of America.

C. We have included the required security deposit as required by the Instruction to Bidders.

D. We have included the required performance assurance bonds in the Bid Amount as required by the Instructions to Bidders.

E. All applicable federal taxes are included and City of Olathe taxes are excluded from the Bid

Sum.

1.06 ACCEPTANCE

A. This offer shall be open to acceptance and is irrevocable for thirty days from the bid closing date.

1.07 CONTRACT TIME

A. If this Bid is accepted, we will:

B. Complete the Work by the _____ day of ________.

1.08 ADDENDA

A. The following Addenda have been received. The modifications to the Bid Documents noted below have been considered and all costs are included in the Bid Sum.

1. Addendum # _______ Dated ________________.

2. Addendum # _______ Dated ________________.

1.09 BID FORM SUPPLEMENTS

A. The following information is included with Bid submission:

1. Alternates: 1, 2, 3.4

1.10 BID FORM SIGNATURE(S)

A. ____________________________________________ B. (Bidder - print the full name of your firm) C. was hereunto affixed in the presence of:

D. ____________________________________________

Improvements 004100 - 2 Bid Form

E. (Authorized signing officer, Title) F. ____________________________________________ G. (Authorized signing officer, Title)

1.11 LIST OF SUBCONTRACTORS

A. In the following spaces please list the required information for all sub-contractors working on this project:

1. Sub contractor #1 - Mechanical

a. Contractor Name:

b. Street Address:

c. City, State, Zip:

d. Phone Number:

e. Number of years in business performing this type of work:

f. Lump Sum Cost: _____________________________________________

2. Sub contractor #2 - Electrical

a. Contractor Name:

b. Street Address:

c. City, State, Zip:

d. Phone Number:

e. Number of years in business performing this type of work:

f. Lump Sum Cost: _____________________________________________

3. Sub contractor #3 - Plumbing

a. Contractor Name:

b. Street Address:

c. City, State, Zip:

d. Phone Number:

e. Number of years in business performing this type of work:

f. Lump Sum Cost: _____________________________________________

4. Sub contractor #4 - Masonry

a. Contractor Name:

b. Street Address:

c. City, State, Zip:

d. Phone Number:

e. Number of years in business performing this type of work:

f. Lump Sum Cost: _____________________________________________

5. Sub contractor #5 - Roofing

a. Contractor Name:

b. Street Address:

c. City, State, Zip:

d. Phone Number:

e. Number of years in business performing this type of work: _____________

f. Lump Sum Cost: ______________________________________________

END OF SECTION

UNITS APPROX. AMOUNT

QUANTITY DOLLARS CENTS DOLLARS

Project No. 4-C-014-25

1 Mobilization LS 1

2 Project Management LS 1

3 Bonds and Insurance LS 1

4 Construction Staking LS 1

5 Demolition LS 1

6 Bathhouse LS 1

7 Earthwork CY 319

8 Utilities LS 1

9 Drains and Drainlines LS 1

10 4" Concrete (Sidewalks) SF 8,500

11 8" Concrete (Vehicular Pavement) SF 1,000

12 8" Splashpad Concrete SF 1,400

13 Concrete Walls LF 250

14 Concrete Stairs LF 350

15 Trash Enclosure LS 1

16 Fencing LF 50

17 Handrails LF 25

18 Site Amenities LS 6

19 Site Electrical (Conduit, Lighting, etc.) LS 1

20 Tree Preservation LS 1

21 Sod SF 7,500

22 Splashpad Construction LS 1

23 Equipotential Bonding LS 1

$0.00

Schedule of Values

The undersigned successfully completed the bid process online at olatheks.bonfire.com and affirms that the schedule of values table above matches the unit prices, line item amounts, and bid total amount submitted electronically.

The following table is a list of bid items, estimated quantities, and the unit prices submitted by the bidder for the The Creek in Mill Creek Park, Project No. 4-C-014-25, Pool Building and Splashpad Improvements.

TOTAL:

ITEM UNIT PRICE

BID FORM

CITY OF OLATHE, KANSAS

Project No. 4-C-014-25

City of Olathe…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .