Heber City Trailhead Plaza CM/GC RFP Summary

This Request for Proposals (RFP) is issued by Heber City, Utah, for Construction Manager/General Contractor (CM/GC) services to develop the Trailhead Plaza (Main Street Park) project. The scope includes construction of park improvements such as multipurpose event seating, an ice-skating ribbon with support buildings, a pavilion, pedestrian pathways, bicycle connections, play and recreation features, shade structures, site furnishings, restroom facilities, parking, service access, utilities, infrastructure, stormwater improvements, landscaping, and irrigation. The project is structured in two phases: a Pre-Construction (Design) Phase during which the CM/GC will coordinate with the City and Architect (Terracon Consultants Inc.) to provide cost estimates, constructability reviews, value engineering recommendations, and design support; and a Construction Phase anticipated to span two construction seasons (two years) subject to approved phasing. RFP questions are due December 1, 2026, at 5:00 p.m. Mountain Time, and proposals must be submitted electronically through the Utah Public Procurement Place (U3P) by December 8, 2026, at 5:00 p.m. Mountain Time. The issue date is November 23, 2026.

Pricing is submitted on Schedule D as a separate "Price Proposal" document and includes a lump-sum Pre-Construction Fee, a lump-sum Construction Management Fee (covering overhead, profit, office personnel, and excluding General Conditions), cost of payment and performance bonds based on 100 percent of the Fixed Limit of Construction Cost (FLCC) of $5 million to $20 million, a Contractor Change Order Markup percentage, and a Self-Performed Work Markup percentage. The Guaranteed Maximum Price (GMP) will be established upon completion of construction documents and receipt of subcontractor bids, with the City maintaining a Construction Contingency of 5–8 percent for owner-directed changes, design revisions, unforeseen conditions, and material escalations. Liquidated damages are assessed at $1,500 to $2,500 per calendar day for delays beyond the negotiated contract time. Evaluation criteria total 500 technical points (60 points for Project Team Experience, 40 for Project Manager Experience, 40 for Superintendent Experience, 20 for Estimator Experience, 40 for Additional Project-Specific Team Members, 100 for Past Performance, 100 for Management Plan Approach, and 100 for Fee Proposal), with an optional presentation stage worth up to 100 points for offerors achieving at least 70 percent of technical points (350 points minimum). The CM/GC must hold a valid Utah General Contractor license, maintain appropriate insurance and bonds, and comply with State of Utah standard terms and conditions, including E-Verify requirements, applicable employment laws, and audit provisions.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSALS

Construction Manager / General Contractor (CM/GC)

HEBER CITY TRAILHEAD PLAZA

Main Street Park | Heber City, Utah Issue Date: November 23, 2026

HEBER CITY | TRAILHEAD PLAZA (MAIN STREET PARK) | CM/GC RFP

INTRODUCTION

Pursuant to Utah Procurement Code 63G-6a and Administrative Rule 33, Heber City (City) finds that using a Construction Manager/General Contractor (CM/GC) for this project is in the best interest of the City because a CM/GC will be accessible early in the cost-effective design of the project. This request for proposals (RFP) seeks qualified contractors, licensed and certified as applicable in the State of Utah, to construct new park improvements associated with the Trailhead Plaza (Main Street Park) project.

SUBMITTAL DEADLINE

Submissions and questions will be accepted electronically through the Utah Public Procurement Place (U3P).

PROPOSAL DUE DATE: December 8, 2026, at 5 pm RFP Questions Due Date: December 1, 2026, at 5 pm

DESCRIPTION OF WORK

The CM/GC must be capable of and willing to work closely with the City’s representatives and Terracon Consultants Inc. (Architect), through the design phase, providing cost estimates, schedules, and feedback on design details, phasing, and availability of materials selected.

· The project consists of construction of the Heber City Trailhead Plaza improvements to Main Street Park. The work is anticipated to create a flexible civic gathering place that supports daily park use, civic functions, community events, and year-round recreation. Improvements may include, but are not limited to, multipurpose event seating, an ice-skating ribbon and support buildings, a pavilion, pedestrian pathways, bicycle connections, play and recreation features, shade and site furnishings, restroom or support facilities, parking and service access, utilities and infrastructure, stormwater improvements, landscaping, and irrigation. Final scope, alternates, and phasing will be confirmed in the contract documents.

CM/GC WORK PHASES

The project consists of two (2) phases: Pre-Construction (Design) Phase and Construction Phase.

Pre-Construction (Design) Phase:

This phase of work includes, but is not limited to: assistance to and coordinating with the City and the Architect for the design development; recommendations for specific language to incorporate into the construction documents; recommendations on value engineering (e.g. ways to reduce risk and decrease cost); review constructability and completeness of plans; develop conceptual construction schedule and construction cost estimates at major project milestones (30% (SD), 60% (DD), 90%); and other tasks as they arise that are needed for a full and complete design of the project.

In general, tasks may include: attending design coordination meetings; providing input and recommendations; commenting and providing objective feedback on materials and methods; identifying and proposing mitigation for potential conflicts; assisting the City with risk management; providing the City with detailed construction cost estimates and proposed cost control measures; constructability reviews; staging and construction sequencing strategies; material procurement strategies; construction schedule development; design drawing and constructability reviews; and other items and areas related to constructability of the project. The CM/GC shall assist the City and the Architect in maintaining the project’s construction cost within the proposed construction budget and scheduling for the duration of construction to keep within the project schedule.

More specific items of scope under this phase shall include but are not limited to:

During the Pre-Construction (Design) Phase, the CM/GC shall be expected to assist and advise the City and the Architect, as follows:

A. The City expects to make decisions based on the anticipated Guaranteed Maximum Price (GMP) for the project.

1. CM/GC shall develop a GMP for the project within the City’s budget and schedule.

2. Throughout the design process, CM/GC will be expected to maintain a running total of the GMP such that the City may make informed decisions about changes to the scope. Estimates will be required for every design decision that affects the GMP.

B. Provide regular construction cost estimates to coincide with the project’s design milestones (30%, 60% and 90%) to verify the proposed design aligns with the City’s allocated construction budget. CM/GC will provide feedback as to the constructability and expected construction costs associated with the design in progress. The CM/GC will also prepare a detailed construction schedule to accompany each construction cost estimate. At each stage (30%, 60% and 90%), the City and the Architect will provide a review of the proposed costs provided by the CM/GC and provide comments and recommendations accordingly.

C. The construction documents will be developed in sufficient detail at 90% for the CM/GC to produce a preliminary GMP to construct the overall project. Construction documents at 100% will be used by the CM/GC to present to and negotiate with the City for a final GMP to construct the project.

D. Coordinate with the City’s representatives and Architect during design. Throughout the design, the City expects/anticipates that in-person design coordination meetings will be held at the 30%, 60% and 90% design milestones. These meetings will also include review of construction cost estimates and reconciliation of scope/cost gaps (including recommendations from CM/GC for cost reductions). In-person meetings will be in addition to all regular phone calls, virtual meetings, emails or other necessary communication and coordination needed during the Pre-Construction (Design) Phase of the project.

E. CM/GC will submit a Management Plan (Approach) as part of the response to this RFP. The requirements are described in Schedule B. During the Pre-Construction (Design) Phase, this plan will be refined and agreed between the City and CM/GC.

F. Assist/Advise the Architect with preparation of construction documents. Provide recommendations as to language and specific information to be incorporated into the final construction documents. The construction documents will include complete project drawings and specifications that establish, in detail, the quality, quantity and levels of materials and systems required for construction.

Construction Phase: This phase of the work consists of the CM/GC furnishing and installing all work as required in the contract documents. The CM/GC shall construct, provide assistance to, and coordinate with, the City and the Architect for the complete construction of the project which includes but is not limited to: construction of Trailhead Plaza (Main Street Park) improvements, including multipurpose event seating, an ice-skating ribbon and support buildings, a pavilion, pedestrian pathways, bicycle connections, play and recreation features, shade and site furnishings, restroom or support facilities, parking and service access, utilities and infrastructure, stormwater improvements, landscaping, and irrigation.

This work shall commence on the date of notice to proceed and continue through construction, close-out and up to the date of final acceptance of the project by the City. The construction period is anticipated to be completed over two construction season(s) (2 years), subject to the approved phasing and schedule.

A. More specific items of scope under this phase shall include but are not limited to: The CM/GC shall provide complete construction of the project throughout the duration of the construction phase of the project. This shall include but not be limited to: all office and or field personnel, equipment, labor, tools, overhead, etc. necessary to successfully complete construction of the project in a timely and efficient manner. Construction of the project will include all costs associated with General Conditions.

B. The CM/GC shall provide complete construction supervision and management services throughout the duration of the construction phase of the project. This shall include but not be limited to: all office and or field personnel, equipment, labor, tools, overhead, etc. necessary to successfully complete construction of the project in a timely and efficient manner. The construction supervision and management work will include all costs associated with General Conditions.

C. Throughout the construction phase of the project, the City anticipates that construction coordination meetings could be held weekly. These meetings will be in addition to all regular phone calls, emails or other necessary communication and coordination required during the construction phase of the project.

D. The CM/GC shall provide construction expertise and contract management and to be contractually responsible for price, schedule and quality during construction.

E. The selected CM/GC firm shall be responsible to ensure that all personnel working under this project be qualified through training, experience, and appropriate certification for the tasks assigned and shall have a working knowledge of industry best practices and pertinent laws in the State of Utah. The selected CM/GC firm agrees to make the personnel available to complete the work on the contract at whatever level the project requires.

FLCC,GMP, LIQUIDATED DAMAGES

A. FLCC: The Fixed Limit of Construction Cost or FLCC is $5 million - $20 million. The City, the design team and the CM/GC agree to work together to keep the cost of construction, as represented in the design, within the FLCC.

B. Guaranteed Maximum Price (GMP): The guaranteed Maximum Price is the final price that the contractor agrees to accept in full performance of the work and is based on the final construction documents. The GMP shall include all fees and percentages required by the RFP, as well as the costs for General Conditions and all work as required in the construction documents.

C. Liquidated Damages: Work will be Complete, including punch-list items, within the negotiated time frame after receipt of the Notice to Proceed. Liquidated Damages will be assessed in the amount of $1,500 to $2,500 per calendar day for each day after expiration of the Contract Time.

The GMP will be determined at the completion of the contract documents and upon receipt of the subcontractor bids.

OWNER CONTINGENCY & SUBCONTRACTORS

A. The City will maintain a Construction Contingency throughout the course of construction. The City, Architect and CM/GC will determine an appropriate contingency percentage at the time an agreed upon GMP is established (expected between 5%-8%). The Owner controlled Contingency is a fund allocation intended to cover, but is not limited to, the following:

a. Owner directed design or scope changes;

b. Design revisions, changes or clarifications not represented in the Construction Documents used as the basis of the GMP;

c. Design errors or omissions;

d. Unforeseen conditions;

e. Possible material cost escalations, if any;

At the conclusion of Construction, any unused funds, allowances or contingency dollars, whether identified within the Construction Documents or by the CM/GC, shall be retained by Heber City. All contingency request costs are required to be actual costs for both self-performed and subcontracted work. No additional markup will be allowed on contingency requests for overhead and profit and other additions that are not actual cost by the subcontractor or CMGC.

B. Subcontracted Work – The CM/GC will be allowed to subcontract work. The CM/GC must specifically state in the proposal what work they intend to subcontract out (e.g. concrete flat work, building erection, landscaping, civil site work, etc.).

The CM/GC must make the selection of Subcontractors in accordance with the formal procurement rules established by the City. The subcontractor bids will then be evaluated by the City and the Architect and must be determined to be the best value bid for the subcontracted work to be awarded to a particular subcontractor as per City policy.

The cost of any work that is subcontracted, including allowed CM/GC Multiplier, will be part of the established GMP.

For Contingency Request: This work must be billed for at actual cost incurred plus the CM/GC Multiplier. The CM/GC Multiplier is equal to the “Construction Supervision and Management Fee” percentage. Actual costs for subcontracted work will be subject to audit. No billing rates will be allowed.

OTHER INFORMATION

A. The contractor will be allowed to self-perform work. This work must be billed for at actual cost incurred, plus the self-performed work markup. Actual costs for self-performed work will be subject to audit. No billing rates will be allowed. The contractor must bid any/all self-performed work against other sub-contractors. The contractor’s bid will then be evaluated by the City and Architect and must be determined to be the best value bid for the work to be awarded to the contractor.

B. It is anticipated that the City and the selected CM/GC will enter into a contract for the proposed work on the project. Award of the project and approval to enter into a contract with the selected CM/GC may only be approved by the Heber City Council.

C. As a contract is awarded and then proceeds, the CM/GC must furnish the City with all appropriate Bonds and Insurance as required by the contract documents, including but not limited to appropriate insurance, performance bond(s), payment bond(s), etc. Insurance must be at least equal to contract limits and bonds must be for the full value of construction costs for the scope of work to be completed and must comply with applicable state and/or City standards.

D. A Notice to Proceed may be issued by the City only after the project is awarded and the contract is signed by all parties and returned to the City.

E. All costs related to the preparation of proposals and all related activities are the sole responsibility of the CM/GC. The City assumes no liability for any costs incurred by CM/GC firms throughout the entire proposal process.

F. Proposals become the property of the City and are protected during the evaluation. After a contract is awarded, proposal information will be made public as per Utah’s Government Records Access and Management Act (GRAMA). Vendors may specify in their proposals which information is confidential for protected trade secrets. To the extent permitted by Utah and Heber City Law and Utah State GRAMA, the City will keep that information confidential.

G. This RFP is subject to the State of Utah Terms & Conditions as shown in Attachment A.

SUBMITTAL INFORMATION REQUIREMENTS

A. SCHEDULE ‘A’ – CM/GC Firm’s Statement of Experience/Qualifications

1. Experience and qualifications of the CM/GC and the project team key individuals as identified in the management plan. Include a description of each member of the team; including qualifications and experience. Provide a team organization chart to demonstrate work and communication flows. Project team members shall be agreed upon between the CM/GC and the City prior to entering into a contract. This team shall not be changed throughout the project unless agreed upon by both the CM/GC and the City. Failure to adhere to this may be grounds for termination of the contract. Enter on the Fee Breakdown form the name of the project manager and superintendent you intend to assign to the job.

2. Similar projects that have been completed by the CM/GC and the project team. When listing similar projects, include information to indicate the dates, size, firm worked for at the time and what the responsibility of each individual was on the project. Include projects that involved the construction of civic plazas, trailheads, parks, event spaces, and public-realm improvements and any relevant information regarding the construction of these projects. Include projects with a minimum of three (3) references from the past five (5) years, including company name, contact name, phone number and email address, etc.

3. Experience and special qualifications of the team that are applicable to this project(s) and/or are part of the project-specific selection criteria.

4. All firms or individuals your company anticipates utilizing to provide any consulting, estimating and any other necessary professional services.

5. Ability to perform services as reflected by workload and the availability of adequate personnel, equipment, and facilities to perform the services expeditiously.

6. Present level of professional liability insurance coverage for the company.

7. Any litigation, arbitration, or other alternative dispute resolution proceedings your company has been involved in with an owner within the past ten years.

8. Other pertinent information regarding qualifications and performance data that may be requested by the City.

B. SCHEDULE ‘B’ – Management Plan

1. Statement of your understanding of the project and a general description of your proposed pre-construction approach to the project scope.

2. How the construction of the project will be managed, including items such as approach to quality control management, managing the overall construction schedule, managing subcontracted work, security and safety controls, and coordination with the City.

3. Describe your experience working with a design Architect. Include any experience specific to the CM/GC delivery method, and in particular, experience working with public entities.

4. Include a description of the company’s safety plan and a safety drawing for this project per Utah Procurement Code 63G-6a.

5. A detailed proposed construction schedule.

6. Project-specific criteria; risks that have been identified from the RFP, additional risks that the team has identified, and how those risks will be mitigated.

C. SCHEDULE ‘C’ – Licensure

1. CM/GC firms and their employees shall comply with, and require all of their subcontractor’s employees to comply with, the licensure laws of the State of Utah. All proposals must include proof of a valid Utah General Contractor license at the time of submission.

D. SCHEDULE ‘D’ – Fee Proposal, GMP All contractors shall furnish the following fees and markups as part of the cost proposal (Price (Schedule D) must be submitted as a separate document, labeled 'Price Proposal):

a. Pr e-Construction Fee: This lump sum fee consists of all costs for the CM/GC to provide the required services of the Pre-Construction (Design) Phase, except pre-authorized, out-of-state travel. No other reimbursable costs will be allowed or considered in addition to this fee.

b. Construction Management Fee: This lump sum fee shall consist of and include overhead (e.g., office), profit, and office personnel who will be managing the project during bidding, construction, and closeout, including the warranty period. The fee does not include General Conditions.

c. Costs of Bonds: This is the cost of payment and performance bonds based on an amount equal to 100% of the FLCC amount.

d. Contractor Change Order Markup: This is the fixed percentage markup that the Contractor may apply to a change order for scope increase to the CM/GC Agreement. The markup shall replace the percentages indicated elsewhere in the construction documents and shall apply to sub-contractors.

e. Self-Performed Work Markup: This is the fixed percentage markup that will be applied to the cost for the CM/GC’s actual labor plus burden cost, material costs, and equipment costs for self-performed work.

PRESENTATION

Offerors must achieve a minimum of 70% of the total technical points to advance to the presentation stage. A presentation may be required at the sole discretion of the City. However, the City may award a contract based on the initial proposals received without discussion with the offeror. If presentations are required, they will be scheduled after the submission of proposals.

EVALUATION CRITERIA

WEIGHTED CRITERIA:

200pts
STRENGTH OF CONTRACTOR’S TEAM:

60 Points – Project Team Experience: Show the overall experience of the project team in relation to projects of similar scope and cost.

40 Points – Project Manager Experience: Show the experience of past relevant projects. Consider availability, other current projects and percent of commitment, years of experience and years of experience with current company.

40 Points – Superintendent Experience: Show the experience of past relevant projects, availability, years of experience and years of experience with current company.

20 Points – Project Estimator Experience: Show the experience on relevant past projects, roles, availability, current assignments and percent of commitment.

40 Points – Experience of Additional Project Specific Team Members: Show experience with the unique requirements of the project.

100pts
PAST PERFORMANCE: Each contractor will be given a past performance rating based on past projects with the City, or similar entities, and supplemented by references supplied by the contractor at the time the proposals are submitted. The City reserves the right to contact other references and/or entities of the submitting firm that are not specifically included or listed in the RFP.
100pts
MANAGEMENT PLAN APPROACH: Each contractor will be rated on the items included in Schedule ‘B’
100pts
FEE PROPOSAL: The contractor’s cost proposal will be considered with all other criteria to determine the ranking of the firm. The offeror with lowest price gets full 100 points in the Fee Proposal category. The offeror with the lowest proposed price receives 100% of the available price points, and all other offerors receive a proportional share based on their price relative to the lowest. For example: “Price Points = 100 × (Lowest Proposed Price / Proposed Price).

Proposals will be scored initially with only the non-Fee Proposal Evaluation Criteria by the Scoring Committee, prior to the Scoring Committee members seeing the Fee Proposal. The Scoring Committee will then review the Fee Proposals and add the Fee Proposal Score to the total score.

Each contractor may be given the opportunity to present their proposal to the City if earning at least 70% of the total technical points (70% of 500 points = 350 minimum points to advance to presentation stage)

100 pts
Presentation (Optional). If the City elects to conduct a presentation stage, those advancing will have their presentation points added to their technical points, and the Offeror earning the highest score will be awarded the solicitation.

10 points-Presentation organization and clarity:

Is the information accurate, relevant, and responsive to the City's goals and project requirements?

Are key concepts communicated clearly and concisely?

Does the presentation have a logical structure, including a clear introduction, organized content, and effective conclusion?

Are visual aids and supporting materials professional and effective?

Does the team manage time appropriately and remain within the allotted presentation period?

20 points-Presentation professionalism:

Does the project team communicate clearly, confidently, and professionally?

Do team members demonstrate preparedness and familiarity with the project?

Are responses to questions direct, thoughtful, and complete?

Does the team demonstrate strong listening skills and adaptability during discussion?

Does the team establish credibility and inspire confidence in its ability to successfully deliver the project?

70 points-Evidence:

Does the team demonstrate a thorough understanding of the project, its objectives, risks, and constraints?

Does the team present a clear and practical approach to preconstruction services, cost management, scheduling, and risk mitigation?

Does the team demonstrate a collaborative approach that aligns with the City's interests and project goals?

Does the team inspire confidence through transparency, accountability, and problem-solving capabilities?

Does the team demonstrate successful experience delivering projects of similar size, scope, complexity, and delivery method?

Does the team clearly articulate how lessons learned from past projects will benefit this project?

Does the team demonstrate the qualifications, availability, and leadership of key personnel proposed for the project?

The evaluation committee, for this RFP, will tally the final scores per criteria for each contractor. The highest scoring proposal will be awarded the solicitation.

After scoring, the City will initiate a Background Check/Due Diligence Review, including a SAM.gov Check, Business Registration Verification, Comprehensive Internet Search, Leadership Review and Internal Reporting. The City will consider Adverse media / Negative news articles, Lawsuits, Recent changes in leadership, Risk indicators or derogatory information, Prior issues with fulfilling other contracts and Arrests or legal issues involving leadership. Any Contractor not passing the Background Check may be subject to rejection.

The City may reject any or all proposals or cancel this RFP at any time and for any reason.

SCHEDULE ‘D’ - FEE PROPOSAL FORM

Price (Schedule D) must be submitted as a separate document, labeled 'Price Proposal Name of Bidder: Date:

Phone: Email:

HEBER CITY TRAILHEAD PLAZA (MAIN STREET PARK) – CM/GC

A. Pre-construction Fee: For all work during the pre-construction period, I/we agree to perform for the lump sum of:

DOLLARS ($ )*

B. Construction Management Fee: For all work during the construction phase of the contract for the management of the project, I/we agree to perform for the lump sum of:

DOLLARS ($ )*

C. Cost of Bonds: The cost of payment and performance bonds based on the amount of the FLCC.

DOLLARS ($ )*

*(In case of discrepancy, written amount shall govern)

D. Contractor Change Order Markup:

For all work added to the contract by change, I/we agree to add not more than % to the subcontractor/supplier costs for the additional work.

E. Self-Performed Work Markup:

For all self-performed work, I/we agree to add no more than % to our labor and material costs to perform the work.

With the cooperation of Heber City and the Design Consultant, the undersigned will continue to work with due diligence to provide a Guaranteed Maximum Price (GMP) within the FLCC.

Authorized Signature:

ATTACHMENT A: STATE OF UTAH STANDARD TERMS AND CONDITIONS FOR GOODS AND SERVICES

1. DEFINITIONS: The following terms shall have the meanings set forth below:

a) “Confidential Information” means information that is deemed as confidential under applicable state and federal laws, including personal information. The State Entity reserves the right to identify, during and after this Contract, additional reasonable types of categories of information that must be kept confidential under federal and state laws.

b) “Contract” means the Contract Signature Page(s), including all referenced attachments and documents incorporated by reference. The term “Contract” shall include any purchase orders that result from this Contract.

c) “Contract Signature Page(s)” means the State of Utah cover page(s) that the State Entity and Contractor signed.

d) “Contractor” means the individual or entity delivering the Procurement Item identified in this Contract. The term “Contractor” shall include Contractor’s agents, officers, employees, and partners.

e) “Custom Deliverable” means the Work Product that Contractor is required to deliver to the State Entity under this Contract.

f) "Procurement Item" means a supply, a service, Custom Deliverable, construction, or technology that Contractor is required to deliver to the State Entity under this Contract.

g) “Response” means the Contractor’s bid, proposals, quote, or any other document used by the Contractor to respond to the State Entity’s Solicitation.

h) “Solicitation” means an invitation for bids, request for proposals, notice of a sole source procurement, request for statement of qualifications, request for information, or any document used to obtain bids, proposals, pricing, qualifications, or information for the purpose of entering into this Contract.

i) “State Entity” means the department, division, office, bureau, agency, or other organization identified on the Contract Signature Page(s).

j) “State of Utah” means the State of Utah, in its entirety, including its institutions, agencies, departments, divisions, authorities, instrumentalities, boards, commissions, elected or appointed officers, employees, agents, and authorized volunteers.

k) “Subcontractors” means a person under contract with a contractor or another subcontractor to provide services or labor for design or construction, including a trade contractor or specialty contractor.

l) “Work Product” means every invention, modification, discovery, design, development, customization, configuration, improvement, process, software program, work of authorship, documentation, formula, datum, technique, know how, secret, or intellectual property right whatsoever or any interest therein (whether patentable or not patentable or registerable under copyright or similar statutes or subject to analogous protection) that is specifically made, conceived, discovered, or reduced to practice by Contractor or Contractor’s Subcontractors (either alone or with others) pursuant to this Contract. Work Product shall be considered a work made for hire under federal, state, and local laws; and all interest and title shall be transferred to and owned by the State Entity. Notwithstanding anything in the immediately preceding sentence to the contrary, Work Product does not include any State Entity intellectual property, Contractor’s intellectual property (that it owned or licensed prior to this Contract) or Third Party intellectual property

2.GOVERNING LAW AND VENUE: This Contract shall be governed by the laws, rules, and regulations of the State of Utah. Any action or proceeding arising from this Contract shall be brought in a court of competent jurisdiction in the State of Utah. Venue shall be in Salt Lake City, in the Third Judicial District Court for Salt Lake County.
3.LAWS AND REGULATIONS: At all times during this Contract, Contractor and all Procurement Items delivered and/or performed under this Contract will comply with all applicable federal and state constitutions, laws, rules, codes, orders, and regulations, including applicable licensure and certification requirements. If this Contract is funded by federal funds, either in whole or in part, then any federal regulation related to the federal funding, including CFR Appendix II to Part 200, will supersede this Attachment A.
4.RECORDS ADMINISTRATION: Contractor shall maintain or supervise the maintenance of all records necessary to properly account for Contractor’s performance and the payments made by the State Entity to Contractor under this Contract. These records shall be retained by Contractor for at least six (6) years after final payment, or until all audits initiated within the six (6) years have been completed, whichever is later. Contractor agrees to allow, at no additional cost, the State of Utah, federal auditors, State Entity staff, or their designees, access to all such records during normal business hours and to allow interviews of any employees or others who might reasonably have information related to such records. Further, Contractor agrees to include a similar right of the State to audit records and interview staff in any subcontract related to performance of this Contract.
5.PERMITS: If necessary Contractor shall procure and pay for all permits, licenses, and approvals necessary for the execution of this Contract.
6.CERTIFY REGISTRATION AND USE OF EMPLOYMENT "STATUS VERIFICATION SYSTEM”: The Status Verification System, also referred to as “E-verify”, only applies to contracts issued through a Request for Proposal process, to sole sources that are included within a Request for Proposal, and when Contractor employs any personnel in Utah.
a.Contractor certifies as to its own entity, under penalty of perjury, that Contractor has registered and is participating in the Status Verification System to verify the work eligibility status of Contractor’s new employees that are employed in the State of Utah in accordance with applicable immigration laws.
b.Contractor shall require that each of its Subcontractors certify by affidavit, as to their own entity, under penalty of perjury, that each Subcontractor has registered and is participating in the Status Verification System to verify the work eligibility status of Subcontractor’s new employees that are employed in the State of Utah in accordance with applicable immigration laws.
c.Contractor’s failure to comply with this section will be considered a material breach of this Contract.
7.CONFLICT OF INTEREST: Contractor represents that none of its officers or employees are officers or employees of the State Entity or the State of Utah, unless disclosure has been made to the State Entity.
8.INDEPENDENT CONTRACTOR: Contractor and Subcontractors, in the performance of this Contract, shall act in an independent capacity and not as officers or employees or agents of the State Entity or the State of Utah.
9.CONTRACTOR RESPONSIBILITY: Contractor is solely responsible for fulfilling the contract, with responsibility for all Procurement Items delivered and/or performed as stated in this Contract. Contractor shall be the sole point of contact regarding all contractual matters. Contractor must incorporate Contractor’s responsibilities under this Contract into every subcontract with its Subcontractors that will provide the Procurement Item(s) to the State Entity under this Contract. Moreover, Contractor is responsible for its Subcontractors compliance under this Contract.
10.INDEMNITY: Contractor shall be fully liable for the actions of its agents, employees, officers, partners, and Subcontractors, and shall fully indemnify, defend, and save harmless the State Entity and the State of Utah from all claims, losses, suits, actions, damages, and costs of every name and description arising out of Contractor’s performance of this Contract to the extent caused by any intentional wrongful act or negligence of Contractor, its agents, employees, officers, partners, or Subcontractors, without limitation; provided, however, that the Contractor shall not indemnify for that portion of any claim, loss, or damage arising hereunder due to the fault of the State Entity. The parties agree that if there are any limitations of the Contractor’s liability, including a limitation of liability clause for anyone for whom the Contractor is responsible, such limitations of liability will not apply to injuries to persons, including death, or to damages to property.
11.EMPLOYMENT PRACTICES: Contractor agrees to abide by the following federal and state employment laws, including: (i) Title VI and VII of the Civil Rights Act of 1964 (42 U.S.C. 2000e), which prohibits discrimination against any employee or applicant for employment or any applicant or recipient of services on the basis of race, religion, color, or national origin; (ii) Executive Order No. 11246, as amended, which prohibits discrimination on the basis of sex; (iii) 45 CFR 90, which prohibits discrimination on the basis of age; (iv) Section 504 of the Rehabilitation Act of 1973, or the Americans with Disabilities Act of 1990, which prohibits discrimination on the basis of disabilities; and (v) Utah's Executive Order 2019-1, dated February 5, 2019, which prohibits unlawful harassment in the workplace. Contractor further agrees to abide by any other laws, regulations, or orders that prohibit the discrimination of any kind by any of Contractor’s employees.
12.AMENDMENTS: This Contract may only be amended by the mutual written agreement of the parties, provided that the amendment is within the Scope of Work of this Contract and is within the scope/purpose of the original solicitation for which this Contract was derived. The amendment will be attached and made part of this Contract. Automatic renewals will not apply to this Contract, even if listed elsewhere in this Contract.
13.DEBARMENT: Contractor certifies that it is not presently nor has ever been debarred, suspended, proposed for debarment, or declared ineligible by any governmental department or agency, whether international, national, state, or local. Contractor must notify the State Entity within thirty (30) days if debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participation in any contract by any governmental entity during this Contract.
14.TERMINATION: This Contract may be terminated, with cause by either party, in advance of the specified expiration date, upon written notice given by the other party. The party in violation will be given ten (10) days after written notification to correct and cease the violations, after which this Contract may be terminated for cause immediately and subject to the remedies below. This Contract may also be terminated without cause (for convenience), in advance of the specified expiration date, by the State Entity, upon thirty (30) days written termination notice being given to the Contractor. The State Entity and the Contractor may terminate this Contract, in whole or in part, at any time, by mutual agreement in writing.

On termination of this Contract, all accounts and payments will be processed according to the financial arrangements set forth herein for approved and conforming Procurement Items ordered prior to date of termination. In no event shall the State Entity be liable to the Contractor for compensation for any Good neither requested nor accepted by the State Entity. In no event shall the State Entity’s exercise of its right to terminate this Contract for convenience relieve the Contractor of any liability to the State Entity for any damages or claims arising under this Contract.

15. NONAPPROPRIATION OF FUNDS, REDUCTION OF FUNDS, OR CHANGES IN LAW: Upon thirty (30) days written notice delivered to the Contractor, this Contract may be terminated in whole or in part at the sole discretion of the State Entity, if the State Entity reasonably determines that: (i) a change in Federal or State legislation or applicable laws materially affects the ability of either party to perform under the terms of this Contract; or (ii) that a change in available funds affects the State Entity’s ability to pay under this Contract. A change of available funds as used in this paragraph includes, but is not limited to a change in Federal or State funding, whether as a result of a legislative act or by order of the President or the Governor.

If a written notice is delivered under this section, the State Entity will reimburse Contractor for the Procurement Item(s) properly ordered and/or Services properly performed until the effective date of said notice. The State Entity will not be liable for any performance, commitments, penalties, or liquidated damages that accrue after the effective date of said written notice.

16. SALES TAX EXEMPTION: The Procurement Item(s) under this Contract will be paid for from the State Entity’s funds and used in the exercise of the State Entity’s essential functions as a State of Utah entity. Upon request, the State Entity will provide Contractor with its sales tax exemption number. It is Contractor’s responsibility to request the State Entity’s sales tax exemption number. It also is Contractor’s sole responsibility to ascertain whether any tax deduction or benefits apply to any aspect of this Contract.

17. WARRANTY OF PROCUREMENT ITEM(S): Contractor warrants, represents and conveys full ownership and clear title, free of all liens and encumbrances, to the Procurement Item(s) delivered to the State Entity under this Contract. Contractor warrants for a period of one (1) year that: (i) the Procurement Item(s) perform according to all specific claims that Contractor made in its Response; (ii) the Procurement Item(s) are suitable for the ordinary purposes for which such Procurement Item(s) are used; (iii) the Procurement Item(s) are suitable for any special purposes identified in the Contractor’s Response; (iv) the Procurement Item(s) are designed and manufactured in a commercially reasonable manner; (v) the Procurement Item(s) are manufactured and in all other respects create no harm to persons or property; and (vi) the Procurement Item(s) are free of defects. Unless otherwise specified, all Procurement Item(s) provided shall be new and unused of the latest model or design.

Remedies available to the State Entity under this section include, but are not limited to, the following: Contractor will repair or replace Procurement Item(s) at no charge to the State Entity within ten (10) days of any written notification informing Contractor of the Goods not performing as required under this Contract. If the repaired and/or replaced Procurement Item(s) prove to be inadequate, or fail its essential purpose, Contractor will refund the full amount of any payments that have been made. Nothing in this warranty will be construed to limit any rights or remedies the State Entity may otherwise have under this Contract.

18. CONTRACTOR’S INSURANCE RESPONSIBILITY. The Contractor shall maintain the following insurance coverage:

a. Workers’ compensation insurance during the term of this Contract for all its employees and any Subcontractor employees related to this Contract. Workers’ compensation insurance shall cover full liability under the workers’ compensation laws of the jurisdiction in which the work is performed at the statutory limits required by said jurisdiction.

b. Commercial general liability [CGL] insurance from an insurance company authorized to do business in the State of Utah. The limits of the CGL insurance policy will be no less than one million dollars ($1,000,000.00) per person per occurrence and three million dollars ($3,000,000.00) aggregate.

c. Commercial automobile liability [CAL] insurance from an insurance company authorized to do business in the State of Utah. The CAL insurance policy must cover bodily injury and property damage liability and be applicable to all vehicles used in your performance of Services under this Agreement whether owned, non-owned, leased, or hired. The minimum liability limit must be $1 million per occurrence, combined single limit. The CAL insurance policy is required if Contractor will use a vehicle in the performance of this Contract.

d. Other insurance policies required in the Solicitation.

Certificate of Insurance, showing up-to-date coverage, shall be on file with the State Entity before the Contract may commence.

The State reserves the right to require higher or lower insurance limits where warranted. Failure to provide proof of insurance as required will be deemed a material breach of this Contract. Contractor’s failure to maintain this insurance requirement for the term of this Contract will be grounds for immediate termination of this Contract.

19. RESERVED.

20.PUBLIC INFORMATION: Contractor agrees that this Contract, related purchase orders, related pricing documents, and invoices will be public documents and may be available for public and private distribution in accordance with the State of Utah’s Government Records Access and Management Act (GRAMA). Contractor gives the State Entity and the State of Utah express permission to make copies of this Contract, related sales orders, related pricing documents, and invoices in accordance with GRAMA. Except for sections identified in writing by Contractor and expressly approved by the State of Utah Division of Purchasing and General Services, Contractor also agrees that the Contractor’s Response will be a public document, and copies may be given to the public as permitted under GRAMA. The State Entity and the State of Utah are not obligated to inform Contractor of any GRAMA requests for disclosure of this Contract, related purchase orders, related pricing documents, or invoices.
21.DELIVERY: All deliveries under this Contract will be F.O.B. destination with all transportation and handling charges paid for by Contractor. Responsibility and liability for loss or damage will remain with Contractor until final inspection and acceptance when responsibility will pass to the State Entity, except as to latent defects or fraud. Contractor shall strictly adhere to the delivery and completion schedules specified in this Contract.
22.ACCEPTANCE AND REJECTION: The State Entity shall have thirty (30) days after delivery of the Procurement Item(s) to perform an inspection of the Procurement Item(s) to determine whether the Procurement Item(s) conform to the standards specified in the Solicitation and this Contract prior to acceptance of the Procurement Item(s) by the State Entity.
If Contractor delivers nonconforming Procurement Item(s), the State Entity may, at its option and at Contractor’s expense: (i) return the Procurement Item(s) for a full refund; (ii) require Contractor to promptly correct or replace the nonconforming Procurement Item(s); or (iii) obtain replacement Procurement Item(s) from another source, subject to Contractor being responsible for any cover costs. Contractor shall not redeliver corrected or rejected Procurement Item(s) without: first, disclosing the former rejection or requirement for correction; and second, obtaining written consent of the State Entity to redeliver the corrected Procurement Item(s). Repair, replacement, and other correction and redelivery shall be subject to the terms of this Contract.
23.INVOICING: Contractor will submit invoices within thirty (30) days of the delivery date of the Procurement Item(s) to the State Entity. The contract number shall be listed on all invoices, freight tickets, and correspondence relating to this Contract. The prices paid by the State Entity will be those prices listed in this Contract, unless Contractor offers a prompt payment discount within its Response or on its invoice. The State Entity has the right to adjust or return any invoice reflecting incorrect pricing.
24.PAYMENT: Payments are to be made within thirty (30) days after a correct invoice is received. All payments to Contractor will be remitted by mail, electronic funds transfer, or the State of Utah’s Purchasing Card (major credit card). If payment has not been made after sixty (60) days from the date a correct invoice is received by the State Entity, then interest may be added by Contractor as prescribed in the Utah Prompt Payment Act. The acceptance by Contractor of final payment, without a written protest filed with the State Entity within ten (10) business days of receipt of final payment, shall release the State Entity and the State of Utah from all claims and all liability to the Contractor. The State Entity’s payment for the Procurement Item(s) and/or Services shall not be deemed an acceptance of the Procurement Item(s) and is without prejudice to any and all claims that the State Entity or the State of Utah may have against Contractor. The State of Utah and the State Entity will not allow the Contractor to charge end users electronic payment fees of any kind.
25.INDEMNIFICATION RELATING TO INTELLECTUAL PROPERTY: Contractor will indemnify and hold the State Entity and the State of Utah harmless from and against any and all damages, expenses (including reasonable attorneys' fees), claims, judgments, liabilities, and costs in any action or claim brought against the State Entity or the State of Utah for infringement of a third party’s copyright, trademark, trade secret, or other proprietary right. The parties agree that if there are any limitations of Contractor’s liability, such limitations of liability will not apply to this section.
26.OWNERSHIP IN INTELLECTUAL PROPERTY: The State Entity and Contractor each recognizes that each has no right, title, or interest, proprietary or otherwise, in the intellectual property owned or licensed by the other, unless otherwise agreed upon by the parties in writing. All Procurement Item(s), documents, records, programs, data, articles, memoranda, and other materials not developed or licensed by Contractor prior to the execution of this Contract, but specifically manufactured under this Contract shall be considered work made for hire, and Contractor shall transfer any ownership claim to the State Entity.
27.OWNERSHIP IN CUSTOM DELIVERABLES: In the event that Contractor provides Custom Deliverables to the State Entity, pursuant to this Contract, Contractor grants the ownership in Custom Deliverables, which have been developed and delivered by Contractor exclusively for the State Entity and are specifically within the framework of fulfilling Contractor’s contractual obligations under this contract. Custom Deliverables shall be deemed work made for hire, such that all intellectual property rights, title and interest in the Custom Deliverables shall pass to the State Entity, to the extent that the Custom Deliverables are not recognized as work made for hire, Contractor hereby assigns to the State Entity any and all copyrights in and to the Custom Deliverables, subject to the following:

1. Contractor has received payment for the Custom Deliverables,

2. Each party will retain all rights to patents, utility models, mask works, copyrights, trademarks, trade secrets, and any other form of protection afforded by law to inventions, models, designs, technical information, and applications (“Intellectual Property Rights”) that it owned or controlled prior to the effective date of this contract or that it develops or acquires from activities independent of the services performed under this contract (“Background IP”), and

3. Contractor will retain all right, title, and interest in and to all Intellectual Property Rights in or related to the services, or tangible components thereof, including but not limited to (a) all know-how, intellectual property, methodologies, processes, technologies, algorithms, software, or development tools used in performing the Services (collectively, the “Utilities”), and (b) such ideas, concepts, know-how, processes and reusable reports, designs, charts, plans, specifications, documentation, forms, templates, or output…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .