1-26-0034 Attachment C CMAR GMP Summary (excel format).pdf
PDF 142 KB Posted
- Solicitation number
- 26-0034
- Issued by
- Maricopa County, Arizona
About this file
This is a Guaranteed Maximum Price (GMP) summary form for the Fire Station 189 project, a Construction Manager at Risk (CMAR) delivery method project for the City of Goodyear, Arizona. The document serves as a standardized template for the contractor to develop and present the project's total cost estimate. The form is structured to capture all direct costs including labor and burden, equipment, materials and supplies, subcontracts, and allowances and contingencies, along with indirect costs such as general conditions, contractor's fee, bonds and insurance allowances, and sales tax. The contractor is responsible for completing only the highlighted direct cost areas (Section A) during the cost estimate development phase, while indirect cost percentages (Sections B, C, and D) are to be negotiated during the preconstruction phase. The project is identified as CIP Project No. with a location in Goodyear, Arizona.
The GMP summary form includes specific formulas for calculating subtotals and the final project cost, incorporating a 5.07% sales tax rate applied to the subtotal before bonds and insurance allowances. The total project cost (line I) aggregates the GMP proposal, preconstruction services costs, and any previous approved GMPs. The form indicates that preconstruction services funding of approximately $750,000 is programmed for FY2026, with approximately $14.5 million budgeted for construction in FY2027. All cost fields currently display zero or dash values, indicating this is a blank template awaiting contractor input. The contractor must fill in all highlighted areas as the cost estimate develops, with indirect cost percentages to be established through negotiation during the preconstruction phase.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3-26-0034 RFQ CMAR - Final.pdf | ||
| 2-26-0034 Attachment D CMAR Agreement Pre-Con and GMP 3 10 25.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: Fire Station 189 Date:
Project Location:
CIP Project No:
A. Direct Costs: Amount
A1 Labor and Burden -$
A2 Equipment (Owned and Rented) -$
A3 Material, Supplies, and Fees -$
A4 Subcontracts -$
A5 Allowances & Contingencies -$
A. - Total of Direct Costs: -$
B. General Conditions: 0.00% -$
Subtotal 1 (Cost Of The Work) -$
C. Contractor's Fee: 0.00% -$
Subtotal 2 -$
D. Bonds and Insurance Allowances:
D1 Bonds 0.00% -$
D2 Insurance 0.00% -$
D. - Bonds & Insurance Allowance Total: -$
Subtotal 3 0.00% -$
E. Sales Tax
E1 Sales Tax 5.07% -$
E2 Tax Credits -$
E. - Sales Tax Total: -$
F. GMP Proposal: -$
G. Preconstruction Services: -$
H. Previous GMP's: -$
I. Total Project Cost Avai
NOTES:
1. Contractor to fill in highlighted areas only:
a. Direct Costs (A) to be completed as the cost estimate is developed.
b. Indirect Cost (B, C and D) percentages to be established during preconstruction phase negotiations.
2. Formulas Used in Calculations:
Subtotal 1 = A + B
Contractor's Fee (C) = C Percentage x Subtotal 1
Subtotal 2 = C + Subtotal 1
Bond & Insurance Allowances = D Percentages x Subtotal 2
Subtotal 3 = D + Subtotal 2
Sales Tax (E1) = Subtotal 3 x 5.07%
GMP Proposal (F) = Subtotal 3 + E
Preconstruction Services (G) is Contractor's costs associated with that phase.
Previous GMP's (H) includes total cost of previous approved GMP's
Total Project Cost (I) = F + G + H
ATTACHMENT C - CMAR GMP SUMMARY
Form 4.3.4.1.3 - GMP Summary
File details come from the government source that posted it. Updated .