1-2026.01.27 Final Bid Set (Specifications) Bull Run Sanitary Sewer Lining.pdf

PDF 7 MB Posted

Attached to
Bull Run Pump Station Basin: Sanitary Sewer Lining Project
Solicitation number
Not on record
Issued by
Lycoming County, Pennsylvania

About this file

Bull Run Pump Station Basin: Sanitary Sewer Lining Project - Bidding Documents

This comprehensive bidding document package is issued by the Williamsport Sanitary Authority for a general construction contract to perform cured-in-place pipe (CIPP) lining installation on existing sanitary sewer gravity mains in Loyalsock Township, Lycoming County, Pennsylvania. The project involves installing inverted, resin-impregnated tube pipe liners within sanitary sewers along Country Club Drive, Nast Avenue, North Hills Drive, Orchard Avenue, Sheridan Street, and Lincoln Drive. The work includes preparatory activities such as sewer main cleaning and flushing, television inspection, hydrophilic seal installation, lateral reinstatement, internal grinding or cutting of existing laterals, and surface restoration. Sealed bids will be accepted online through the PennBid platform until February 27, 2026, at 10:00 AM local time, with public opening and reading of bids to follow immediately thereafter. The contract establishes a Substantial Completion date of August 22, 2026, and a final completion date of September 21, 2026. Bid security of 10 percent of the total bid amount is required in the form of a certified check or bid bond from an acceptable surety.

The project is financed through a grant from the Commonwealth of Pennsylvania via the Commonwealth Financing Authority's PA Small Water and Sewer Program. The contract is based on unit price work for the primary lining activities, with estimated quantities including 5,361 linear feet of 8-inch CIPP lining, 68 sewer lateral reinstatements, and 7 internal grinding/cutting operations, along with lump sum allowances for mobilization and traffic maintenance and protection. Liquidated damages are assessed at $115 per day for delays beyond Substantial Completion and $60 per day for delays beyond final completion. The bidding documents incorporate EJCDC C-700 Standard General Conditions and require compliance with Pennsylvania prevailing wage requirements under the Davis-Bacon Act, the Public Works Employment Verification Act (Act 127 of 2012), Pennsylvania Steel Products Procurement Act, and various other state and federal labor and environmental standards. Performance and payment bonds equal to the full contract price are required, and contractors must demonstrate qualifications including a minimum of three years' documented experience in CIPP installation. All work must comply with ASTM standards for cured-in-place pipe systems, NASSCO performance specifications, and specified design criteria assuming full pipe deterioration and minimum 50-year service life.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BULL RUN PUMP STATION BASIN: SANITARY SEWER

LINING PROJECT

Williamsport Sanitary Authority 253 West Fourth Street Williamsport, PA 17701

R002544.0439

776 Bull Run Crossing, Suite 200 Lewisburg, PA 17837

570.524.6744 www.hrg-inc.com

Herbert, Rowland & Grubic, Inc.

Engineering | Planning | Infrastructure Solutions January 2026

BIDDING DOCUMENTS

Contract 2026-01: General Construction

01/27/2026

Herbert, Rowland & Grubic, Inc. 00 01 10 - 1 R002544.0439

Bull Run Lining Project

WILLIAMSPORT SANITARY AUTHORITY

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS SECTION: PAGES

Procurement Requirements ADVERTISEMENT FOR BIDS ............................................................................................................... 00 11 13: 2 INSTRUCTIONS TO BIDDERS .............................................................................................................. 00 21 13: 11 PERMITS ............................................................................................................................................ 00 31 46: 1 BID FORM (Single Contract) .............................................................................................................. 00 41 16: 5 BID BOND .......................................................................................................................................... 00 43 13: 2 NON-COLLUSION AFFIDAVIT ............................................................................................................. 00 45 19: 1

CERTIFICATION OF NON-SEGREGATED FACILITIES AND

NON-EMPLOYMENY OF ILLEGAL ALIEN LABOR ................................................................................. 00 45 33: 1 EEO CERTICATE ................................................................................................................................. 00 45 36: 1 NONDISCRIMINATION AND SEXUAL HARASSMENT CLAUSE ............................................................ 00 45 40: 2 PUBLIC WORKS EMPLOYMENT VERIFICATION FORM ....................................................................... 00 45 46: 1

Contracting Requirements AGREEMENT BETWEEN OWNER and CONTRACTOR for CONSTRUCTION CONTRACT ..................... 00 52 00: 7 NOTICE TO PROCEED FORM.............................................................................................................. 00 55 00: 1 PROJECT FORMS ............................................................................................................................... 00 60 00: 1 PERFORMANCE BOND ...................................................................................................................... 00 61 13.13: 4 PAYMENT BOND ............................................................................................................................... 00 61 13.16: 4 CONTRACTORS APPLICATION FOR PAYMENT ................................................................................... 00 62 76: 6 REQUEST FOR INFORMATION FORM ................................................................................................ 00 63 13: 1 FIELD ORDER FORM .......................................................................................................................... 00 63 36: 1 WORK CHANGE DIRECTIVE FORM .................................................................................................... 00 63 49: 1 CHANGE ORDER FORM ..................................................................................................................... 00 63 63: 1 CERTIFICATE OF SUBSTANTIAL COMPLETION FORM ........................................................................ 00 65 16: 1 AFFADAVIT OF RELEASE OF LIENS FORM .......................................................................................... 00 65 19.16: 1 CONSENT OF SURETY FOR FINAL PAYMENT FORM .......................................................................... 00 65 19.19: 1 GENERAL CONDITIONS ...................................................................................................................... 00 72 00: 93 WAGE RATE REQUIREMENTS ............................................................................................................ 00 73 43: 3 WAGE DETERMINATION SCHEDULE ................................................................................................. 00 73 46: 20 ANTI-POLLUTION MEASURES ............................................................................................................ 00 73 53: 1 STATUTORY REQUIREMENTS ............................................................................................................ 00 73 73: 6

Specifications

DIVISION 01 – GENERAL REQUIREMENTS PAGES

01 10 00 PROJECT SUMMARY

01 22 00 UNIT PRICES

01 26 00 CONTRACT MODIFICATIONS

01 26 13 REQUEST FOR INTERPRETATION

01 29 00 PAYMENT PROCEDURES

01 31 13 PROJECT COORDINATION

01 31 19 PROJECT MEETINGS

01 31 23 PROJECT DOCUMENTATION WEBSITE

01 32 16 CONSTRUCTION PROGRESS SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 00a STEEL PRODUCTS PROCUREMENT CERTIFICATION

01 40 00 QUALITY REQUIREMENTS

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 57 28 TEMPORARY FLOW CONTROL

01 61 00 PRODUCT REQUIREMENTS

TABLE OF CONTENTS

Herbert, Rowland & Grubic, Inc. 00 01 10 - 2 R002544.0439

01 73 00 EXECUTION REQUIREMENTS

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 77 00 CLOSEOUT PROCEDURES

01 78 36 WARRANTIES

01 78 39 PROJECT RECORD DOCUMENTS

DIVISION 33 – UTILITIES PAGES

33 01 30.11 TELEVISION INSPECTION OF SEWERS

33 01 30.72 CURED-IN-PLACE PIPE LINING

Herbert, Rowland & Grubic, Inc. 00 11 13 - 1 R002544.0439

ADVERTISEMENT FOR BIDS

WILLIAMSPORT SANITARY AUTHORITY

LYCOMING COUNTY, PENNSYLVANIA

BULL RUN PUMP STATION BASIN: SANITARY SEWER LINING PROJECT

General Notice

Williamsport Sanitary Authority (Owner) is requesting Bids for the construction of the following Project:

Bull Run Pump Station Basin: Sanitary Sewer Lining Project Contract 2026-01: General Construction

Bids for construction of the project will be received online until February 27, 2026 at 10:00 AM local time.

At that time the Bids received will be publicly opened and read.

The Project includes the following Work:

Installation of cured-in-place pipe lining within existing sanitary sewer gravity mains along Country Club Drive, Nast Avenue, North Hills Drive, Orchard Avenue, Sheridan Street and Lincoln Drive.

Bids are requested for the following Contract: Contract 2026-01: General Construction

This Project is financed by a grant from the Commonwealth of Pennsylvania, through the Commonwealth Financing Authority’s PA Small Water and Sewer Program.

Sealed Bids shall be accepted online via the PennBid Platform. All Bidding Documents and solicitation details will be available at no cost at the following designated website:

https://pennbid.bonfirehub.com

Bidding Documents may be downloaded from the designated website. Prospective Bidders are urged to register with the designated website as a plan holder, even if Bidding Documents are obtained from a plan room or source other than the designated website in either electronic or paper format. The designated website will be updated periodically with addenda, lists of registered plan holders, reports, and other information relevant to submitting a Bid for the Project. All official notifications, addenda, and other Bidding Documents will be offered only through the designated website. Neither Owner nor Engineer will be responsible for Bidding Documents, including addenda, if any, obtained from sources other than the designated website.

Instruction to Bidders

Bid security in the form of a Certified Check or Bid Bond and an acceptable Surety payable to the Owner shall be furnished with the bid in an amount not less than 10% of the total bid.

All questions about the meaning or intent of the Bidding Documents are to be submitted in accordance with the Instructions to Bidders. Telephone inquiries are unacceptable. For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.

For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.

Herbert, Rowland & Grubic, Inc. 00 11 13 - 2 R002544.0439

Statutory Requirements

Bidders must comply with all State antibid-rigging regulations pertaining to work associated with this project and must submit an executed and fully completed non-collusion affidavit with the bid.

Bidders should refer to provisions of federal and state statutes, rules and regulations dealing with the prevention of environmental pollution and preservation of public natural resources that affect the project, pursuant to Act No. 247 of the General Assembly of the Commonwealth of Pennsylvania, approved October 26, 1972.

This Project falls under The Commonwealth of Pennsylvania enacted Act 127 of 2012, known as the Public Works Employment Verification Act (‘the Act’) which requires all public work contractors and subcontractors to utilize the Federal Government’s E-Verify system to ensure that all employees performing work on public work projects are authorized to work in the United States. All Bidders are required to submit a Public Works Employment Verification Form as a precondition for the Contract Award.

The estimated cost of this Project is greater than Two Thousand Dollars ($2,000) and the federal Davis- Bacon Act shall apply.

All bids shall be irrevocable for 60 days after the bid opening date unless award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant or grants, in which case this Bid shall remain subject to acceptance for 120 days after the bid opening date as provided by the Act of November 26, 1978 (P.L. 1309, No. 317), as amended by the Act of December 12, 1994 (P.L.

1042, No. 142).

All bidders are hereby notified that in regard to any contract pursuant to this advertisement, businesses will be afforded full opportunity to submit bids in response to this notice and will not be subjected to discrimination on the basis of gender, race, color, creed, sex, age, physical disability, or national origin in consideration for an award. Similarly, the successful bidder shall in no manner discriminate against or intimidate any employee involved in the manufacture of supplies, the performance of work, or any other activity required under the contract on account of gender, race, creed, or color.

The Owner reserves the right to waive any defects, errors, omissions, mistakes, informalities, to accept any bid or combination of bids that are deemed to be in the best interest of the Owner, and to reject any or all proposals.

Herbert, Rowland & Grubic, Inc. 00 21 13 - 1 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Article 21— Sales and Use Taxes

Article 22— Contracts to Be Assigned

Herbert, Rowland & Grubic, Inc. 00 21 13 - 2 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.

2.04 Bidder may register as a plan holder and obtain complete sets of Bidding Documents, in the number and format stated in the Advertisement or invitation to bid, from the Issuing Office.

Bidders may rely that sets of Bidding Documents obtained from the Issuing Office are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.

2.05 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents, or make them available for examination.

Those prospective bidders that obtain an electronic (digital) copy of the Bidding Documents from a plan room are encouraged to register as plan holders from the Bidding Documents Website or Issuing Office. Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.

2.06 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader. It is the intent of the Engineer and Owner

Herbert, Rowland & Grubic, Inc. 00 21 13 - 3 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within 10 days of Owner’s request, Bidder must submit the following information:

A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.

C. Bidder’s state or other contractor license number, if applicable.

D. Subcontractor and Supplier qualification information.

E. Other required information regarding qualifications.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 The Owner will not award any Contract to a Bidder that has been debarred by the Pennsylvania Department of Labor and Industry for noncompliance with the Pennsylvania Prevailing Wage Act (43 P.S. §165.17).

3.05 If any portion of the Work is to be accomplished on rights-of-way of the Pennsylvania Department of Transportation or under a PENNDOT permit, the owner will not award any Contract to a bidder that has been debarred under Title 67, Chapter 459.3(1).

3.06 When so required in the Bid Form, each bidder must provide evidence of Pennsylvania Department of Transportation Prequalification for the indicated types of Work.

3.07 All Bidders must complete and execute the enclosed Non-Collusion Affidavit. This Affidavit is material to any Contract awarded pursuant to this project and is in accordance with Pennsylvania Antibid-Rigging Act, 62 P.S. §4501 et seq. The Affidavit should be executed by an officer or the person approved to sign the Bid. In the case of joint ventures, all parties must execute separately.

Herbert, Rowland & Grubic, Inc. 00 21 13 - 4 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Failure to file an Affidavit in compliance with these instructions may result in disqualification of the bid.

3.08 This Project falls under The Commonwealth of Pennsylvania enacted Act 127 of 2012, known as the Public Works Employment Verification Act (‘the Act’) which requires all Public Work Contractors and Subcontractors to utilize the Federal Government’s E-Verify system to ensure that all employees performing work on Public Work Projects are authorized to work in the United States. All Bidders are required to submit a Public Works Employment Verification Form (00 45

46) as a precondition for the Contract Award.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A pre-bid conference will not be conducted for this Project.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

Herbert, Rowland & Grubic, Inc. 00 21 13 - 5 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. Owner contact to schedule Site visit is:

Noah Caputo, Assistant Field Operations Manager (570) 419 - 4988

C. Bidders visiting the Site are required to arrange their own transportation to the Site.

D. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

E. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

F. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

G. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

5.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for

Herbert, Rowland & Grubic, Inc. 00 21 13 - 6 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information and submittal procedures for such questions are as follows:

A. All questions shall be submitted using Bidding Documents Website (PennBid).

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a certified check or a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s

Herbert, Rowland & Grubic, Inc. 00 21 13 - 7 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders.

Bidders cannot rely upon approvals made in any other manner.

10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

Herbert, Rowland & Grubic, Inc. 00 21 13 - 8 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed within five days after Owner’s request.

11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

12.02 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

12.03 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.04 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.05 A Bid by an individual must show the Bidder’s name and official address.

12.06 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.07 All names must be printed below the signatures.

12.08 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

Herbert, Rowland & Grubic, Inc. 00 21 13 - 9 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

12.09 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.10 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.11 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 13—BASIS OF BID

13.01 Unit Price

A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

ARTICLE 14—SUBMITTAL OF BID

14.01 Sealed bids are to be submitted online via PennBid. Bidders can submit, update, and withdraw bids until the date and time described in the Advertisement for Bids.

A. Submitting electronic bid:

1. Enter financial bid.

a. All Per Unit Price and/or lump sum fields must be entered. To no-bid a line item, inserts a zero (0).

2. Answer questions (if any).

3. Attach a single portable document file (pdf) or compressed digital (zipped) folder containing digitally scanned copies of fully completed “other documents” required to be submitted under the terms of Article 2 of the Bid Form.

14.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and any hard copy bids will be returned to the Bidder unopened.

Herbert, Rowland & Grubic, Inc. 00 21 13 - 10 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 A Bid may be electronically withdrawn or modified prior to the date and time for the opening of Bids.

15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

15.03 If within 24 hours two business days after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 16—OPENING OF BIDS

16.01 Bids will be opened via PennBid at the date and time described in the Advertisement for Bids.

Following the evaluation of the Bids, an abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. In the comparison of Bids, Owner will award based on the “Base Bid”. After determination of the Successful Bidder, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its Base Bid and any combination of its

Herbert, Rowland & Grubic, Inc. 00 21 13 - 11 R002544.0439

This document is a MODIFIED version of EJCDC® C-200, Instructions to Bidders for Construction Contract. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Additive Alternate Bids for which Owner determines funds will be available at the time of award.

C. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 19—BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

ARTICLE 21—SALES AND USE TAXES

21.01 Owner is exempt from Pennsylvania state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes must not be included in the Bid. Refer to Paragraph 7.10 of the General Conditions for additional information.

ARTICLE 22—CONTRACTS TO BE ASSIGNED

22.01 No Contracts Will be assigned for completion of the Work.

Herbert, Rowland & Grubic, Inc. 00 31 46 - 1 R002544.0439

SECTION 00 31 46 – PERMITS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Available Permitting Information

1.2 PERMITTING INFORMATION

A. This Section with its attachments is referenced in Paragraph 7.09 of Section 00 72 00 – General Conditions as Permits and Licenses. They provide Owner's information for Bidders' convenience and are intended to supplement rather than serve in lieu of Bidders' own investigations. This Document and its attachments are not part of the Contract Documents.

B. The following permits are anticipated for the Project:

1. None.

END OF SECTION

This document is a MODIFIED version of EJCDC® C-410, Copyright © 2018 by the National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers, or is based in part on excerpts from copyrighted EJCDC documents. Those portions of the text that originated in copyrighted EJCDC documents remain subject to the copyright.

Herbert, Rowland & Grubic, Inc. 00 41 16 - 1 R002544.0439

BID FORM FOR CONSTRUCTION CONTRACT

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to: Williamsport Sanitary Authority 253 West Fourth Street Williamsport, PA 17701

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security (00 43 13);

B. Non-Collusion Affidavit (00 45 19);

C. Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor (00 45 33);

D. Certification of Bidder Regarding Equal Employment Opportunity (00 45 36);

E. Nondiscrimination and Sexual Harassment Clause (00 45 40);

F. Public Works Employment Verification Form (00 45 46);

ARTICLE 3—BASIS OF BID

3.01 Unit Price Bids

A. Bidder will perform the following Work in accordance with the Contract Documents at the indicated Unit Prices:

Item No.

Description Unit Estimated Quantity

Bid Unit Price Bid Amount

GENERAL

1-1 Mobilization and Project Management

L.S. 1 $

1-2 Traffic Maintenance and Protection

L.S. 1 $

SEWER MAIN AND APPURTENANCES

2-1 8” CIPP Lining L.F. 5,361 $

2-2 CIPP Sewer Lateral Reinstatement

E.A. 68 $

2-3 CIPP Internal Grinder/Cutting of Existing Laterals

E.A. 7 $

This document is a MODIFIED version of EJCDC® C-410, Copyright © 2018 by the National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers, or is based in part on excerpts from copyrighted EJCDC documents. Those portions of the text that originated in copyrighted EJCDC documents remain subject to the copyright.

Herbert, Rowland & Grubic, Inc. 00 41 16 - 2 R002544.0439

Total of All Unit Price Bid Items $

B. Bidder acknowledges that:

1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and

2. estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.

ARTICLE 4—TIME OF COMPLETION

4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

5.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

5.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

5.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda (List Addendum No. and Date for each issued Addendum. If No Addendum issued, indicate “None”).

Addendum Number Addendum Date

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

This document is a MODIFIED version of EJCDC® C-410, Copyright © 2018 by the National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers, or is based in part on excerpts from copyrighted EJCDC documents. Those portions of the text that originated in copyrighted EJCDC documents remain subject to the copyright.

Herbert, Rowland & Grubic, Inc. 00 41 16 - 3 R002544.0439

3. Bidder is…