1_16_26_TABBY TRAIL_ROOKERY.pdf
PDF 11 MB Posted
- Attached to
- ITB - Tabby Trail - The Rookery
- Solicitation number
- PE-66960-NONST-2026-000000051
- Issued by
- Georgia
About this file
This is a permit set and construction plan document for the City of St. Marys, Georgia, prepared by MC2D Engineering for the Tabby Trail - Rookery project located in St. Marys Industrial Park, Site 2. The project involves the installation of a concrete multi-purpose trail and road crossing within Camden County, Georgia, with receiving waters identified as the St. Marys River. The work scope includes site preparation, grading, erosion and sediment control measures, concrete sidewalk/multiuse path construction (4 inches minimum 3000 PSI concrete), and staking activities across approximately 500 linear feet of improvements. The project encompasses seven detailed sheets including cover, construction notes, existing conditions, staking plan, grading plan, erosion and sediment pollution control (ES&PC) plan, and construction details. The contract term is 120 consecutive calendar days from the Notice to Proceed, with construction activities requiring coordination with existing utilities including electric, telephone, gas, and cable infrastructure. General contractors must obtain all required permits prior to commencement, maintain local traffic throughout construction, provide certified compaction test results from an independent qualified laboratory, and submit as-built plans on Mylar to the City of St. Marys upon project completion.
The construction documents establish comprehensive general notes and specifications requiring the contractor to adhere to all local, state, and federal regulations, field-verify all existing elevations and infrastructure conflicts before construction begins, and assume full responsibility for sheeting, shoring, bracing, de-watering, and OSHA compliance. The contractor must provide at least one week advance notice to the City Engineer and Public Works Director and 24 hours notice to the owner before beginning work, submit a traffic control plan meeting Georgia Department of Transportation and MUTCD requirements, and notify the City of traffic closures at least one week in advance. Erosion control measures must be installed prior to other construction activities and maintained until permanent ground cover is established, with any disturbed areas left exposed longer than 14 days requiring stabilization via mulch or temporary seeding. The project site lies within 250 feet of state waters and jurisdictional wetlands, and contractors are required to call 811 (1-800-282-7411) for utility location prior to any excavation activities. All unsuitable materials must be disposed of off-site at the contractor's expense, and the contractor is responsible for relocating and reinstalling any property owner mailbox displaced during construction at no additional cost to the owner.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Invitation to Bid.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ST. MARYS INDUSTRIAL PARK, SITE 2
M A
T C
H
LI
N E
M A
T C
H
LI
N E
ST. MARYS INDUSTRIAL PARK, SITE 2
P O I N T P E T E R R O A D P O I N T P E T E R R O A D
IN
D
U
ST
R
IA
L D
R
IV
E
NOW OR FORMERLY LANDS OF
OLD WEED & READY
PLANTATION, LLC
NOW OR FORMERLY LANDS OF
OLD WEED & READY
PLANTATION, LLC
NOW OR FORMERLY LANDS OF
MANNA PROPERTIES, INC.
NOW OR FORMERLY LANDS OF
CITY OF ST. MARYS
NOW OR FORMERLY LANDS OF
HARBOR CITY MANAGEMENT & DEVELOPMENT COMPANY, INC. M
A T
C H
LI
N
E
M A
T C
H
LI
N E
JM
JM
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
CONTENT:
RE
VI
SI
O
N S
NO
DE
SC
RI
PT
IO
N
DA
TE
PERMIT SET
(FOR 24"X36" PLOT)
12/3/2025
No. 043385
PROFESSIONAL
JONATHAN MCDILL, P.E.
LEVEL II CERTIFICATION #: 0000069802
ST
. M
AR
YS
, G
EO
R G
IA
PR
EP
AR
ED
F
O R:
CI
TY
O F
ST
. M
AR
Y
Re ad di ck
A ve nu e
Ki ng sla nd
, G A
1" = 20'
TABBY TRAIL - ROOKERY
FOR
CAMDEN COUNTY, GEORGIA
LOCATION MAP
COVER
C O
VE
R
CITY OF ST. MARY
RECEIVING WATERS:
ST MARYS RIVER
RECEIVING WATERS:
ST MARYS RIVER
1" = 1000'
PROJECT LOCATION
ENGINEER
MC2D
109 READDICK AVE,
KINGSLAND GA
912-322-5516
SURVEYOR:
AKM SURVEYING, INC.
JEFF FOSTER
(912) 729-1507
819 POINT PETER RD
P.O. BOX 5730
ST. MARYS, GA. 31558
OWNER :
ST. MARYS
912-882-4415 www.stmarysga.gov
CITY OF ST. MARYS APPROVAL
PLANNING AND ZONING
CITY OF ST. MARYS APPROVAL
FIRE DEPARTMENT
CITY OF ST. MARYS APPROVAL
PUBLIC WORKS
DATE ISSUED FOR CONSTRUCTION
Sheet List Table Sheet
Number Sheet Title
01 COVER 12/3/2025
02 CONSTRUCTION NOTES 12/3/2025
03 EXISTING CONDITIONS 12/3/2025
04 STAKING PLAN 12/3/2025
05 GRADING 12/3/2025
06 ES&PC PLAN 12/3/2025
07 DETAILS 12/3/2025
1.16.26
JM
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
CONTENT:
RE
VI
SI
O
N S
NO
DE
SC
RI
PT
IO
N
DA
TE
PERMIT SET
(FOR 24"X36" PLOT)
12/3/2025
No. 043385
PROFESSIONAL
JONATHAN MCDILL, P.E.
LEVEL II CERTIFICATION #: 0000069802
ST
. M
AR
YS
, G
EO
R G
IA
PR
EP
AR
ED
F
O R:
CI
TY
O F
ST
. M
AR
Y
Re ad di ck
A ve nu e
Ki ng sla nd
, G A
1" = 20'
CONSTRUCTION NOTES
C O
N
ST
R U
C
TI
O N
N O
TE
S
N.T.S.
GENERAL NOTES
1. CONTRACTOR SHALL ADHERE TO ALL LOCAL, STATE, OR FEDERAL REGULATIONS AS THEY SHALL SUPERCEDE THE REQUIREMENTS OF
THE CONTRACT DOCUMENTS, THEY SHOULD IMMEDIATELY BRING THIS TO THE ATTENTION OF THE ENGINEER.
2. THE CONTRACTOR IS SPECIFICALLY CAUTIONED THAT THE LOCATIONS AND/OR ELEVATIONS OF EXISTING INFRASTRUCTURE AS
SHOWN ON THESE PLANS ARE BASED ON EXISTING RECORDS AND WHERE POSSIBLE, MEASUREMENTS TAKEN IN THE FIELD. THIS INFORMATION IS NOT TO BE RELIED ON AS BEING EXACT OR COMPLETE. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO EVALUATE ALL EXISTING INFRASTRUCTURE WHICH MAY CONFLICT WITH THE PROPOSED IMPROVEMENTS SHOWN ON THE PLANS AND COORDINATE WITH THE ENGINEER FOR ADJUSTMENT OF THE WORK AS NECESSARY TO MAINTAIN ADEQUATE SEPARATION SHOULD A CONFLICT EXIST. CONTRACTOR SHALL FIELD-VERIFY ALL EXISTING ELEVATIONS BEFORE AND DURING (WHILE UNCOVERED)
CONSTRUCTION.
3. ALL IN-PLACE IMPROVEMENTS WILL BE PROTECTED BY THE CONTRACTOR DURING CONSTRUCTION. ANY DAMAGES WILL BE REPAIRED TO THE RESPECTIVE OWNER'S SATISFACTION BY THE CONTRACTOR AT NO ADDITIONAL COMPENSATION.
4. THE CONTRACTOR IS RESPONSIBLE FOR THE DESIGN AND IMPLEMENTATION OF ALL SHEETING, SHORING, BRACING, DE-WATERING, AND SPECIAL EXCAVATION MEASURES REQUIRED TO MEET OSHA, FEDERAL, STATE AND LOCAL REGULATIONS PURSUANT TO THE INSTALLATION OF THE WORK INDICATED ON THESE DRAWINGS AS WELL AS SUBSEQUENT WORK AGREED TO BETWEEN THE OWNER AND CONTRACTOR. THE OWNER AND THE DESIGN ENGINEER ACCEPT NO RESPONSIBILITY FOR THE DESIGN(S) TO INSTALL SAID ITEMS.
5. THE CONTRACTOR SHALL COORDINATE SITE CONSTRUCTION WITH ALL UTILITY CONSTRUCTION (POWER, TELEPHONE, GAS, CABLE, ETC.) AND OTHER WHICH MAY BE SPECIFIC TO THE PROJECT.
6. THE CONTRACTOR IS RESPONSIBLE FOR NOTIFICATION AND LIAISON WITH UTILITY COMPANIES IN THE PROCESS OF LOCATION, RELOCATION, AND TIE-IN TO PUBLIC UTILITIES. ALSO, THE CONTRACTOR IS RESPONSIBLE FOR NOTIFYING ALL INSPECTORS, INCLUDING, THE CITY INSPECTORS, PRIOR TO SITE CONSTRUCTION,
7. THE OFFICE OF THE CITY ENGINEER AND PUBLIC WORKS DIRECTOR SHALL BE GIVEN AT LEAST ONE (1) WEEK'S NOTICE PRIOR TO BEGINNING ANY CONSTRUCTION, ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE APPROVED PLANS AND SPECIFICATIONS.
8. NO WORK SHALL BEGIN ON THIS PROJECT WITHOUT AT LEAST 24 HOURS ADVANCE NOTIFICATION TO THE OWNER AND THE ENGINEER.
IN ADDITION, NO WORK IS TO TAKE PLACE WITHOUT AN APPROVED SET OF PLANS AND SPECIFICATIONS ON THE JOB SITE. WORK IS TO
BE COORDINATED WITH ALL OTHER OPERATIONS ACTIVITIES.
9. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO INSURE THAT ALL REQUIRED PERMITS ARE OBTAINED AND IN HAND PRIOR TO THE
COMMENCEMENT OF CONSTRUCTION.
10. THE CONTRACTOR IS REQUIRED TO MEET ALL APPLICABLE REGULATIONS CONCERNING PROJECT SAFETY AND ASSUMES FULL
RESPONSIBILITY FOR SAFETY ON THE PROJECT.
11. THE CONTRACTOR SHALL MAKE HIS OWN DETERMINATION OF ALL SURFACE AND SUBSURFACE CONDITIONS. THE CONTRACTOR WITH CONSULTATION WITH THE ENGINEER SHALL TOGETHER DETERMINE WHAT MATERIAL, IF ANY, IS TO BE WASTED.
12. ALL UNSUITABLE MATERIALS FROM CLEARING, GRUBBING, AND OTHER ACTIVITIES SHALL BE DISPOSED OF OFF-SITE AT THE
CONTRACTOR'S EXPENSE.
13. AFTER THE FINAL INSPECTION HAS BEEN PERFORMED AND ALL ITEMS ARE SATISFACTORY TO THE CITY, AS-BUILTS SHALL BE SUBMITTED THE ENGINEER ALONG WITH A LETTER OF TRANSMITTAL. ACCEPTABLE SUBMITTALS WILL BE APPROVED IN WRITING.
SUBMITTALS REQUIRING CORRECTIONS BEFORE BEING ACCEPTABLE WILL SO BE NOTED. AS-BUILTS MUST BE RESUBMITTED FOR REVIEW AND APPROVAL PRIOR TO THE LETTER OF ACCEPTANCE BEING ISSUED BY THE ENGINEER(S).
14. ALL FIELD CHANGES SHALL BE AUTHORIZED BY THE OWNER IN WRITING IN ADVANCE OF THE WORK. IF CHANGES ARE MADE BY THE CONTRACTOR WITHOUT PRIOR WRITTEN CONSENT FROM THE OWNER, CONTRACTOR SHALL BEAR FULL RESPONSIBILITY FOR MAKING THE NECESSARY CHANGES TO BRING THE CONSTRUCTION INTO CONFORMANCE WITH APPROVED PLANS AND SPECIFICATIONS AT NO
COST TO THE OWNER.
15. THE AREAS DISTURBED BY THE CONTRACTOR SHALL BE RESTORED TO THEIR ORIGINAL CONDITION UNLESS OTHERWISE NOTED ON
THE PLANS.
16. ALL CITY WATER UTILIZED DURING CONSTRUCTION SHALL BE METERED THROUGH A CONSTRUCTION WATER METER (OBTAINED FROM
THE CITY OF ST. MARY'S) EQUIPPED WITH AN APPROVED BACK FLOW DEVICE.
17. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO FIELD VERIFY ALL PROPOSED CONSTRUCTION FOR FEASIBILITY AND FUNCTION. THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE ENGINEER OF ANY DISCREPANCIES OR WARRANTED CONCERNS
PERTAINING TO DESIGN AND CONSTRUCTION.
18. THE PLANS WERE PREPARED IN ACCORDANCE WITH ESTABLISHED PRACTICES OF CIVIL ENGINEERING DESIGN. THE ENGINEER, NOR ITS PERSONNEL, CAN OR DO WARRANT THESE PLANS AS CONSTRUCTED EXCEPT WHERE THE ENGINEER INSPECTS AND CONTROLS
THE PHYSICAL CONSTRUCTION ON A CONTEMPORARY BASIS AT THE SITE.
19. ALL CONSTRUCTION AND MATERIALS SHALL CONFORM WITH THE CURRENT CITY OF ST. MARYS STANDARDS AND SPECIFICATIONS AND
WITH ALL OTHER APPLICABLE FEDERAL, STATE AND LOCAL ORDINANCES AND LAWS.
20. THE CONTRACTOR SHALL OBTAIN ALL PERMITS NECESSARY TO COMPLETE THE CONSTRUCTION.
21. ALL CONTRACTORS SHALL FURNISH "AS-BUILTS" ON MYLAR AS REQUIRED BY THE CITY OF ST. MARYS.
22. DEVIATION FROM THESE PLANS AND SPECIFICATIONS WITHOUT THE PRIOR WRITTEN CONSENT OF THE ENGINEER MAY CAUSE THE
WORK TO BE UNACCEPTABLE.
23. THE CONTRACTOR IS RESPONSIBLE FOR NOTIFICATIONS AND LIAISON WITH UTILITY COMPANIES IN THE PROCESS OF LOCATING, RELOCATION AND TIE-IN TO PUBLIC UTILITIES. ALSO, THE CONTRACTOR IS RESPONSIBLE FOR NOTIFYING ALL INSPECTORS, INCLUDING
CITY INSPECTORS PRIOR TO BEGINNING SITE CONSTRUCTION.
24. IN THE CASE OF UNFORESEEN CONSTRUCTION COMPLICATIONS OR DISCREPANCIES, THE CONTRACTOR IS TO NOTIFY THE ENGINEER
IMMEDIATELY.
25. ALL WORK TO BE DONE IN ACCORDANCE WITH THE GEORGIA DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATION OF ROADS & BRIDGES CURRENT EDITION, SUPPLEMENTAL SPECIFICATION & SPECIAL PROVISIONS.
26. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REMOVING, RELOCATING, MAINTAINING AND REINSTALLING THE THE PROPERTY OWNER'S MAILBOX TO AN AREA OUTSIDE THE CONSTRUCTION LIMITS DURING THE LIFE OF THE CONTRACT. THE LOCATION OF THE MAILBOX SHALL BE CONVENIENT TO BOTH THE MAIL CARRIER AND THE PATRON, YET NOT INTERFERE WITH THE PROPOSED WORK. IT MAY BE NECESSARY FOR THE CONTRACTOR TO CONFER WITH THE POST OFFICE SERVING THE AREA. ALL COSTS INCURRED FOR
COMPLIANCE WITH THESE REQUIREMENTS SHALL BE INCLUDED IN THE BID PRICE.
27. AT LOCATIONS WHERE NEW PAVEMENT IS TO BE PLACED ADJACENT TO EXISTING PAVEMENT WITHOUT OVERLAY, A JOINT SHALL BE SAWCUT ON A LINE ESTABLISHED BY THE ENGINEER TO ENSURE PAVEMENT REMOVAL TO A NEAT LINE. COSTS INCURRED FOR
SAWCUT JOINTS, WHEN REQUIRED, SHALL BE INCLUDED IN THE BID PRICE.
28. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO FURNISH SUITABLE BORROW MATERIAL FOR THE PROJECT AND DISPOSE OF ANY
UNSUITABLE MATERIAL.
SURVEY NOTES
1. FOR BOUNDARY INFORMATION, SEE SURVEY PREPARED BY PRIVETT AND
ASSOCIATES, INC..
2. FOR TOPOGRAPHICAL INFORMATION, SEE SURVEY PREPARED BY PRIVETT AND
ASSOCIATES, INC..
3. ELEVATIONS ARE BASED ON NATIONAL GEODETIC VERTICAL DATUM OF 1988
(N.G.V.D.) AS DETERMINED BY PRIVETT AND ASSOCIATES, INC..
PAVING
1. RIGHT-OF-WAY INFORMATION OBTAINED FROM AKM SURVEYORS.
2. ALL ELEVATIONS SHOWN ARE IN FEET AND BASED ON 1988 N.G.V.D..
3. ALL BASES SHALL BE PRIMED IN ACCORDANCE WITH THE D.O.T.
STANDARD SPECIFICATIONS, CURRENT EDITION. TACK COAT SHALL NOT
BE REQUIRED ON PRIMED BASES EXCEPT ON AREAS WHICH HAVE
BECOME EXCESSIVELY DIRTY AND CANNOT BE CLEANED, OR, IN AREAS
WHERE THE PRIME HAS CURED AND LOST ALL BONDING EFFECT. TACK
COAT MATERIALS AND CONSTRUCTION METHODS SHALL CONFORM TO
D.O.T. STANDARD SPECIFICATIONS, 1993 EDITION.
4. TESTS FOR BASE THICKNESS AND COMPACTION SHALL BE LOCATED NO
MORE THAN 150 FEET APART AND SHALL BE STAGGERED TO THE LEFT,
RIGHT, AND CENTER OF THE ROADWAY. IF TESTS INDICATE THICKNESS
LESS THAN THOSE ALLOWED BY D.O.T. SPECIFICATIONS, THE
CONTRACTOR MAY EITHER INCREASE THE THICKNESS, RECOMPACT
AND RETEST TO MEET SPECIFIED VALUES, OR SUBSTITUTE 1/2 INCH
ADDITIONAL SURFACE COURSE FOR EACH INCH OR FRACTION THEREOF
THE BASE COURSE WHICH DOES NOT MEET THE SPECIFIED THICKNESS.
5. ALL PAVEMENT SECTION ELEMENTS SHALL BE TESTED AS REQUIRED BY
THE CITY OF ST. MARYS AT THE CONTRACTOR'S EXPENSE.
TRAFFIC CONTROL
1. THE CONTRACTOR SHALL SUBMIT FOR APPROVAL A TRAFFIC CONTROL PLAN
TO THE CITY OF ST. MARYS THAT MEETS ALL CURRENT GEORGIA DEPARTMENT
OF TRANSPORTATION AND MUTCD REQUIREMENTS. THE CONTRACTOR SHALL
NOTIFY THE CITY OF ST. MARYS OF TRAFFIC CLOSURE AT LEAST ONE WEEK
BEFORE CONSTRUCTION.
PROJECT SPECIFIC NOTES
1. THIS PROJECT HAS A TOTAL AREA OF X.XX ACRES AND THE EXPECTED
DISTURBANCE IS X.XX ACRES.
2. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO LOCATE AND
FURNISH THE DISPOSAL AREAS NECESSARY FOR THIS PROJECT AND SHALL
BE DONE IN A MANNER ACCEPTABLE TO AND AS DIRECTED BY THE ENGINEER.
3. LOCAL TRAFFIC SHALL BE MAINTAINED AT ALL TIMES DURING
CONSTRUCTION.
4. NO CONSTRUCTION ACTIVITIES SHALL OCCUR OUTSIDE CONSTRUCTION
LIMITS IN WETLAND AREAS.
5. ONLY CONCRETE PIPE SHALL BE USED ON THIS PROJECT.
6. IN COMPLIANCE WITH GEORGIA LAW, CALL BEFORE YOU DIG. THE TOOL FREE
NUMBER IS 1-800-282-7411.
7. ALL DRIVEWAYS, WHERE ACCESS IS ALLOWED, SHALL BE PLACED AS
DIRECTED BY THE ENGINEER IN ACCORDANCE WITH THE RULES AND
REGULATIONS FOR CONTROL AND PROTECTION OF DEPARTMENT OF
TRANSPORTATION RIGHTS-OF-WAY, ADOPTED BY THE STATE HIGHWAY
BOARD OF GEORGIA. ALL DRIVEWAYS SHALL BE CONSTRUCTED IN
ACCORDANCE WITH THE DETAILED DRAWING, SEE SHEET --. THE DRIVEWAY
LOCATIONS INDICATED ON THE PLANS ARE FROM THE BEST AVAILABLE DATA.
THE CONTRACTOR SHALL CONSTRUCT NEW DRIVEWAYS TO MATCH THE
ACTUAL FIELD LOCATION OF EXISTING DRIVEWAYS WHERE THEY ARE NOT IN
CONFLICT WITH THE RULES AND REGULATIONS. THE CONTRACTOR SHALL
OBTAIN THE APPROVAL OF THE ENGINEER PRIOR TO MAKING ANY REVISIONS
SUCH AS TO LOCATION, WIDTH, AND/OR NUMBER OF DRIVES TO BE
CONSTRUCTED WHERE REQUIRED.
8. UTILITY OWNERS LISTED BELOW HAVE FACILITIES IN THE AREA WHICH MAY
CONFLICT WITH CONSTRUCTION:
ELECTRIC UTILITY
OWNER:
CONTACT:
TELEPHONE UTILITY
OWNER:
CONTACT:
EARTHWORK
1. SEE SOIL AND EROSION CONTROL PLAN FOR SOILS CLASSIFICATION.
2. SUBGRADE: SUBSURFACE HAS BEEN INVESTIGATED ONLY AS
SHOWN. ALL UNSUITABLE MATERIAL IN PAVEMENT OR BUILDING
AREAS SHALL BE REMOVED TO A DEPTH OF 3.0 FEET BELOW
SUBGRADE. BACKFILL WITH SUITABLE MATERIAL.
3. WHERE EXISTING SOILS TO BE USED IN THE STABILIZED SUBGRADE
HAVE THE REQUIRED BEARING VALUE, NO ADDITIONAL STABILIZING
MATERIAL NEED BE ADDED OR MIXED IN. THE STABILIZING MATERIAL,
IF REQUIRED, SHALL BE HIGH-BEARING VALUE SOIL, SAND-CLAY,
LIMEROCK, OR OTHER MATERIAL APPROVED BY THE CITY. THE
CONSTRUCTION OF THE STABILIZED SUBGRADE, INCLUDING
COMPACTION, SHALL CONFORM TO THE D.O.T. STANDARD
SPECIFICATIONS, 1993 EDITION.
4. THE UPPER ONE FOOT OF MATERIAL BELOW THE ROADWAY BASE
COURSE, HEREIN AFTER REFERRED TO AS STABILIZED SUBGRADE,
SHALL BE COMPACTED TO DENSITIES OF AT LEAST 98% OF THE
MODIFIED PROCTOR MAXIMUM DRY WEIGHT DENSITY (ASTM D1557).
AFTER COMPLETING CLEARING/STRIPPING OPERATIONS, THE
NATURAL SOILS BENEATH THE PAVEMENT AREAS SHALL BE
COMPACTED UNTIL DENSITIES OF AT LEAST 98% OF THE MODIFIED
PROCTOR MAXIMUM DRY WEIGHT DENSITY (ASTM D1557) HAVE BEEN
ACHIEVED WITHIN THE UPPER ONE FOOT. NATURAL SOILS SHALL
EXHIBIT MOISTURE CONTENTS WITHIN 2% OF THE MODIFIED
PROCTOR MAXIMUM DRY WEIGHT DENSITY MOISTURE CONTENT.
5. STRUCTURAL FILL REQUIRED FOR BUILDING PADS AND PAVEMENT
AREAS SHALL BE PLACED IN LOOSE LIFTS NOT EXCEEDING 12
INCHES IN THICKNESS AND SHALL BE COMPACTED TO DENSITIES
EQUIVALENT TO 95% OF THE MODIFIED PROCTOR MAXIMUM DRY
WEIGHT DENSITY (ASTM D1557), AND WITHIN 2% OF THE OPTIMUM
MOISTURE CONTENT. STRUCTURAL FILL IS DEFINED AS
NON-PLASTIC, INORGANIC (CONTAINING LESS THAN 4.0% ORGANICS),
GRANULAR SOIL CONTAINING LESS THAN 10% MATERIAL PASSING
THE 200 MESH SIEVE (I.E. RELATIVELY CLEAN SAND). COMPACTION
SHALL BE TESTED IN EACH LIFT AND RESULTS SUBMITTED TO THE
ENGINEER FOR REVIEW.
6. CONTRACTOR MUST PROVIDE CERTIFIED TEST RESULTS OF THE
DEGREES OF COMPACTION OF THE SUBGRADE AND THE BASE FROM
AN INDEPENDENT, QUALIFIED TEST LABORATORY. ALL BUILDING
PAD AND PAVEMENT AREAS SHALL BE PROOF ROLLED PRIOR TO
ACCEPTANCE BY ENGINEER.
7. TESTS FOR THE STABILIZED SUBGRADE BEARING CAPACITY AND
COMPACTION SHALL BE LOCATED NO MORE THAN 300 FEET APART
AND SHALL BE STAGGERED TO THE LEFT, RIGHT, AND CENTERLINE
OF THE ROADWAY.
8. ALL UNDERGROUND UTILITIES MUST BE INSTALLED PRIOR TO
PREPARATION OF SUBGRADE FOR PAVEMENT.
SECONDARY PERMITTEE(S)
NOTE: THIS MASTER LIST TO BE COMPLETED AND SIGNED, KEPT IN THE "ON-SITE"
CONSTRUCTION TRAILER.
SECONDARY PERMITTEE(S) SIGN WHEN RECEIVING PLANS. ALL SECONDARY
PERMITTEE(S) MUST SUBMIT NOI AT LEAST 14 DAYS PRIOR TO BEGINNING CONSTRUCTION
ACTIVITY.
NAME: PHONE:
COMPANY: FAX:
ADDRESS:
SIGNATURE
GSWCC LEVEL IA CERTIFICATION NO.
NAME: PHONE:
COMPANY: FAX:
ADDRESS:
SIGNATURE
GSWCC LEVEL IA CERTIFICATION NO.
NAME: PHONE:
COMPANY: FAX:
ADDRESS:
SIGNATURE
GSWCC LEVEL IA CERTIFICATION NO.
EROSION CONTROL CERTIFICATION
1. I CERTIFY THAT THE PERMITTEE'S EROSION, SEDIMENTATION, AND
POLLUTION CONTROL PLAN PROVIDES FOR AN APPROPRIATE AND
COMPREHENSIVE SYSTEM OF BEST MANAGEMENT PRACTICES
REQUIRED BY THE GEORGIA WATER QUALITY CONTROL ACT AND THE
DOCUMENT "MANUAL FOR EROSION AND SEDIMENT CONTROL IN
GEORGIA" (MANUAL) PUBLISHED BY THE STATE SOIL AND WATER
CONSERVATION COMMISSION AS OF JANUARY 1 OF THE YEAR IN
WHICH LAND DISTURBING ACTIVITY WAS PERMITTED. THE PLAN
PROVIDES FOR THE SAMPLING OF THE RECEIVING WATER(S) OR THE
SAMPLING OF THE STORM OUTFALLS. THE DESIGNED SYSTEM OF
BEST MANAGEMENT PRACTICES AND SAMPLING METHODS IS
EXPECTED TO MEET THE REQUIREMENTS CONTAINED IN THE
GENERAL NPDES PERMIT NO. GAR 100003.
2. "I CERTIFY UNDER PENALTY OF LAW THAT THIS PLAN WAS PREPARED
AFTER A SITE VISIT TO THE LOCATIONS DESCRIBED HEREIN BY
MYSELF OR MY AUTHORIZED AGENT, UNDER MY DIRECT
SUPERVISION."
3. "I CERTIFY UNDER PENALTY OF LAW THAT THIS DOCUMENT AND ALL
ATTACHMENTS WERE PREPARED UNDER MY DIRECTION OR
SUPERVISION IN ACCORDANCE WITH A SYSTEM DESIGNED TO
ASSURE THAT QUALIFIED PERSONAL PROPERLY GATHER AND
EVALUATE THE INFORMATION SUBMITTED. BASED UPON MY INQUIRY
OF THE PERSON OR PERSONS WHO MANAGE THE SYSTEM, OR THOSE
PERSONS DIRECTLY RESPONSIBLE FOR GATHERING THE
INFORMATION, THE INFORMATION SUBMITTED IS, TO THE BEST OF MY
KNOWLEDGE AND BELIEF, TRUE, ACCURATE, AND COMPLETE. I AM
AWARE THAT THERE ARE SIGNIFICANT PENALTIES FOR SUBMITTING
FALSE INFORMATION, INCLUDING THE POSSIBILITY OF FINE AND
IMPRISONMENT FOR KNOWING VIOLATIONS."
JONATHAN MCDILL, P.E.
GSWCC LEVEL II DESIGN PROFESSIONAL
CERTIFICATION NO. 0000069802
EROSION CONTROL NOTES
1. THE PROJECT SITE DOES NOT LIE WITHIN A FLOOD PLAIN.
2. THIS SITE IS WITHIN 250 FEET OF STATE WATERS EXISTING IN THE FORM OF
JURISDICTIONAL WETLANDS AND THEIR TRIBUTARIES.
3. NO SITE ACTIVITY SHALL BE CONDUCTED WITHIN DELINEATED STREAM BUFFERS (IF
ANY) WITHOUT PROPER VARIANCES FROM EPD AND/OR LOCAL ISSUING AUTHORITY.
4. EROSION CONTROL AND TREE PROTECTION MEASURES SHALL BE INSTALLED PRIOR
TO ANY OTHER CONSTRUCTION ACTIVITY AND MAINTAINED UNTIL PERMANENT
GROUND COVER IS ESTABLISHED.
5. NO JURISDICTIONAL WETLANDS EXIST WITHIN THE LIMITS OF THIS PROJECT.
"THE ESCAPE OF SEDIMENT FROM THIS SITE SHALL BE PREVENTED BY THE
INSTALLATION OF EROSION AND SEDIMENT CONTROL MEASURES AND PRACTICES
PRIOR TO, OR CONCURRENT WITH LAND DISTURBING ACTIVITIES.
"EROSION CONTROL MEASURES WILL BE MAINTAINED AT ALL TIMES. IF FULL
IMPLEMENTATION OF THE APPROVED PLAN DOES NOT PROVIDE FOR EFFECTIVE
EROSION CONTROL, ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES
SHALL BE IMPLEMENTED TO CONTROL OR TREAT THE SEDIMENT SOURCE."
"ANY DISTURBED AREA LEFT EXPOSED FOR A PERIOD GREATER THAN 14 DAYS
SHALL BE STABILIZED WITH A MULCH OR TEMPORARY SEEDING."
NAME: CHRIS AMOS, CITY ENGINEER
ADDRESS: 819 POINT PETER RD, ST MARYS, GA 31558
PHONE: (912) 882-4415
JONATHAN MCDILL, P.E.
GSWCC LEVEL II DESIGN PROFESSIONAL
CERTIFICATION NO. 0000069802
NAME: CHRIS AMOS, CITY ENGINEER
ADDRESS: 819 POINT PETER RD, ST. MARYS, GA 31558
PHONE: (912) 882-4415
M
A T
C H
LI
N
E
ST. MARYS INDUSTRIAL PARK, SITE 2
P O I N T P E T E R R O A D P O I N T P E T E R R O A D
IN
D
U
ST
R
IA
L D
R
IV
E NOW OR FORMERLY LANDS OF
CITY OF ST. MARYS
M A
T C
H
LI
N E
15 1515
151515
12 12
13 13
14 14
14 14 14 14
12 12
13 13
JM
JM
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
CONTENT:
RE
VI
SI
O
N S
NO
DE
SC
RI
PT
IO
N
DA
TE
PERMIT SET
(FOR 24"X36" PLOT)
12/3/2025
No. 043385
PROFESSIONAL
JONATHAN MCDILL, P.E.
LEVEL II CERTIFICATION #: 0000069802
ST
. M
AR
YS
, G
EO
R G
IA
PR
EP
AR
ED
F
O R:
CI
TY
O F
ST
. M
AR
Y
Re ad di ck
A ve nu e
Ki ng sla nd
, G A
1" = 20'
EXISTING CONDITIONS
EX
IS
TI
N
G C
O N
D
IT
IO
N
S
LEGEND
EXISTING SEWER MANHOLE
D EXISTING STORM MANHOLE
S
PROPOSED SEWER LINE
EXISTING TELEPHONE LINE
EXISTING WATER
EXISTING STORM PIPE
EXISTING OVERHEAD POWER
EXISTING GAS
Know what's below.
before you dig.Call
R
1" = 20'
40'0' 20'
SCALE
P O I N T P E T E R R O A D P O I N T P E T E R R O A D
IN
D
U
ST
R
IA
L D
R
IV
E NOW OR FORMERLY LANDS OF
CITY OF ST. MARYS
4'
' 10'
10'
D
13+0014+0015+0016+0017+0018+00 7'
10'
JM
JM
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
CONTENT:
RE
VI
SI
O
N S
NO
DE
SC
RI
PT
IO
N
DA
TE
PERMIT SET
(FOR 24"X36" PLOT)
12/3/2025
No. 043385
PROFESSIONAL
JONATHAN MCDILL, P.E.
LEVEL II CERTIFICATION #: 0000069802
ST
. M
AR
YS
, G
EO
R G
IA
PR
EP
AR
ED
F
O R:
CI
TY
O F
ST
. M
AR
Y
Re ad di ck
A ve nu e
Ki ng sla nd
, G A
1" = 20'
ST
AK
IN
G
P
LA
N
STAKING PLAN
Know what's below.
before you dig.Call
R
1" = 20'
40'0' 20'
SCALE
PROPOSED CONCRETE
LEGEND
PROPOSED STRIPING
10' SIDEWALK / MULTIUSE PATH
P O I N T P E T E R R O A D P O I N T P E T E R R O A D
IN
D
U
ST
R
IA
L D
R
IV
E NOW OR FORMERLY LANDS OF
CITY OF ST. MARYS
D
14.64 14.52
14.75 ME
14.58
14.99 ME
14.97
15.24 ME 15.23 ME
14.97 ME 15.03 ME
-0 .8
9%
-1 .5
0%
-1 .5
0%
-1 .5
0%
-1 .2
1%
15 15
14.93'15.14'15.13'15.18'15.24'15.30'15.32'15.07'14.98'14.58'14.69'14.55'
13+0014+0015+0016+0017+0018+00
12 13
12 12
15.09 ME15.12 ME
JM
JM
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
CONTENT:
RE
VI
SI
O
N S
NO
DE
SC
RI
PT
IO
N
DA
TE
PERMIT SET
(FOR 24"X36" PLOT)
12/3/2025
No. 043385
PROFESSIONAL
JONATHAN MCDILL, P.E.
LEVEL II CERTIFICATION #: 0000069802
ST
. M
AR
YS
, G
EO
R G
IA
PR
EP
AR
ED
F
O R:
CI
TY
O F
ST
. M
AR
Y
Re ad di ck
A ve nu e
Ki ng sla nd
, G A
1" = 20'
GRADING
G R
AD
IN
G
PROPOSED CONCRETE
LEGEND
PROPOSED STRIPING
Know what's below.
before you dig.Call
R
1" = 20'
40'0' 20'
SCALE
P O I N T P E T E R R O A D P O I N T P E T E R R O A D
IN
D
U
ST
R
IA
L D
R
IV
E NOW OR FORMERLY LANDS OF
CITY OF ST. MARYS
D
15 1515
14.93'15.14'15.13'15.18'15.24'15.30'15.32'15.07'14.98'14.58'14.69'14.55'
13+0014+0015+0016+0017+0018+00
12 13
12 12
LIMITS OF
DISTURBANCE
Sd1-NS
SINGLE ROW
LIMITS OF
DISTURBANCE
Sd1-NS
SINGLE ROW
Cd-Hb
SEE DETAIL
Cd-Hb
SEE DETAIL
Cd-Hb
SEE DETAIL
JM
JM
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
CONTENT:
RE
VI
SI
O
N S
NO
DE
SC
RI
PT
IO
N
DA
TE
PERMIT SET
(FOR 24"X36" PLOT)
12/3/2025
No. 043385
PROFESSIONAL
JONATHAN MCDILL, P.E.
LEVEL II CERTIFICATION #: 0000069802
ST
. M
AR
YS
, G
EO
R G
IA
PR
EP
AR
ED
F
O R:
CI
TY
O F
ST
. M
AR
Y
Re ad di ck
A ve nu e
Ki ng sla nd
, G A
1" = 20'
ES&PC PLAN
ES
&P
C P
LA
N
LEGEND
Know what's below.
before you dig.Call
R
1" = 20'
40'0' 20'
SCALE
SEDIMENT BARRIER AS NOTEDSd1
LIMIT OF DISTURBANCE
CHECK DAM- STRAW BALES
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
CONTENT:
RE
VI
SI
O
N S
NO
DE
SC
RI
PT
IO
N
DA
TE
PERMIT SET
(FOR 24"X36" PLOT)
12/3/2025
No. 043385
PROFESSIONAL
JONATHAN MCDILL, P.E.
LEVEL II CERTIFICATION #: 0000069802
ST
. M
AR
YS
, G
EO
R G
IA
PR
EP
AR
ED
F
O R:
CI
TY
O F
ST
. M
AR
Y
Re ad di ck
A ve nu e
Ki ng sla nd
, G A
1" = 20'
D
ET
AI
LS
DETAILS
N.T.S.
TYPICAL FLARED END SECTION
NTS
4" CONCRETE
SIDEWALK
(MIN 3000 PSI)
12" SUBGRADE COMPACTED
TO 98% STANDARD
PROCTOR MAXIMUM DRY
WEIGHT DENSITY
SEE PLAN
NOTE: 1. EXPANSION JOINTS LOCATED AT 20' O.C.
2. TOOLED JOINTS LOCATED AT 5' O.C.
3. ALL SIDEWALKS TO HAVE A 1.0% CROSS
SLOPE
6" TURNDOWN,
TYPICAL EACH
SIDE
CONCRETE SIDEWALK DETAIL
NTS
| Sheets and Views |
| 01 COVER |
| 02 CONSTRUCTION NOTES |
| 03 EXISTING CONDITIONS |
| 04 STAKING PLAN |
| 05 GRADING |
| 06 ES&PC PLAN |
| 07 DETAILS |
File details come from the government source that posted it. Updated .