Technical Specifications Summary
This Technical Specifications document supports the 2026 Avondale Pavement Repair Project issued by Avondale Borough, Pennsylvania. The project scope encompasses milling and overlaying approximately 1.42 miles of asphalt roadway and constructing eight (8) ADA-compliant concrete curb ramps. Sealed bids will be received online through PennBid until 11:00 A.M. prevailing time on August 13, 2026, at which time bids will be opened and posted online. All bidding documents, including addenda and project plans, are available exclusively through the PennBid portal at https://pennbid.bonfirehub.com/portal/. No bid may be withdrawn within sixty (60) days of the bid opening date. Avondale Borough reserves the right to reject any and all bids and waive any bidding informalities.
Each bid submission must be accompanied by a certified check or bid bond in favor of Avondale Borough equal to 10% of the bid price. This project is classified as Public Work by a Public Body under the Pennsylvania Prevailing Wage Act, requiring contractors to pay prevailing minimum wage rates as promulgated by the Pennsylvania Secretary of Labor. The awarded contractor shall provide a performance and payment bond equal to 100% of the contract price. PennBid access is provided at no cost to vendors for bid submission; only awarded contractors are assessed fees based on current fee schedules available on the PennBid vendor information page.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-01 - Front End.pdf | ||
| 3-03 - 2026 Avondale Paving Repair Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS
01010-1 (7/26) 264128_400 01010.docx
SECTION 01010
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.01 DESCRIPTION
A. The work to be done under this Contract consists of all labor, equipment and materials and other facilities necessary and proper to complete the following: installation and construction of a paved parking area and detention basin on site.
B. The Drawings and Specifications are intended to cover a complete project, and it shall be thoroughly understood that failure to mention specifically any work which would naturally be required to complete the project shall not relieve the CONTRACTOR of his responsibility to perform such work.
1.02 REFERENCED STANDARDS AND SPECIFICATIONS
A. All work shall comply with the current issues of the following codes, regulations, and requirements
(this list may not be inclusive; failure to mention any specific code, regulation or requirement does not relieve the CONTRACTOR from complying with such):
1. Pennsylvania Department of Labor & Industry, Regulations for Trenches, and Excavations.
2. Federal and State Air Pollution Regulations.
3. OSHA - Occupational Safety and Health Administration.
4. ASTM - American Society of Testing and Materials.
5. PennDOT - Pennsylvania Department of Transportation Publications 72, 213, 408 and TC-
8600.
6. DEP - Pennsylvania Department of Environmental Protection - Erosion and Sedimentation
Control, and Sewerage Manual.
7. AASHTO - American Association of State Highway and Transportation Officials.
8. All codes and regulations of West Goshen Township.
1.03 EQUAL OR APPROVED EQUAL
A. In the various detailed sections of the Specifications, where any item of material or equipment is specified by proprietary name, trade name, and/or name of one or more manufacturers, without the addition of such expressions as “or equal”, it is to be understood that these items are so specified for reasons of standardization or for special requirements of the job. For items so specified, no substitute products will be acceptable.
01010-2
B. In the various detailed sections of the Specifications, where any item of equipment is specified by proprietary name, trade name, and/or name of one or more manufacturers, with the additions of such expressions as "or equal", it is to be understood that equal quality equipment or products, of either a manufacturer named or of a manufacturer not named, which meet the detailed requirements of the specifications, are intended and are subject to the acceptance of the ENGINEER as to the equality thereof. It is distinctly understood that: (1) the ENGINEER is to use his own judgment in determining whether or not any item of equipment or product proposed is equal to that specified;
(2) the decision of the ENGINEER on all such questions of equality shall be final; and (3) in the event of any adverse decision by the ENGINEER, no claim of any sort shall be made or allowed against the ENGINEER or the OWNER.
C. If, subsequent to the award of the Contract, and in normally rare occurrences, it becomes necessary
(because of delays in delivery, strikes, discontinuance of the manufacture of items specified or the equal thereof, or any other similar reasons) for the CONTRACTOR to request the use of any item of equipment or product which is of a different type than the equipment or product specified, or the approved equal thereof, the ENGINEER at his discretion, may authorize the use of such different type equipment or product of the same, greater or less cost than that specified.
D. In such cases as described in Paragraphs B and C above, the CONTRACTOR shall submit to the
ENGINEER in writing (1) his request for permission to make a substitution, (2) a complete description of the proposed item, including dimensions, operational characteristics, changes (if any) that will be required to other related parts of the work, etc., and (3) full information as to the costs of the item specified, the cost of the different type item being proposed, as well as costs (additional or credits) or changes (if any) to any related parts of the work. Such information shall be in such form and detail as to permit the ENGINEER to check, to his satisfaction, the reason and costs involved. Upon acceptance of the substitution, in writing, the proper credits to be allowed the OWNER or the proper additional payments to be made to the CONTRACTOR represent the difference between the net cost to the CONTRACTOR of the substituted item or material, and the price at which he could have obtained the lowest priced item or materials specified.
E. The decision of the ENGINEER, from time to time, as to the proper credits to be allowed by the
OWNER or proper payments to be made by the CONTRACTOR, shall be final and conclusive upon the CONTRACTOR.
1.04 PRIORITY OF AND DISCREPANCIES IN CONTRACT DOCUMENTS
A. If the Bidder or CONTRACTOR finds an error in or a discrepancy between any of the Contract
Documents, such error or discrepancy shall be immediately reported to the ENGINEER for correction. If found during the bidding period, the correction will be issued by Addendum, and if during the Contract period, by field order or change order, as appropriate. No work shall proceed which is affected by the discrepancy prior to the ENGINEER's resolution of the problem.
B. In general, the plans and specifications are complementary; what is called for by one is as binding as if required by all. All items necessary or incidental to completely construct or erect the work denoted shall be furnished as required to provide a complete operating facility whether specifically detailed by the plans and/or specifications or not.
01010-3
C. Where dimensions or locations of existing facilities are of importance to the successful performance of any part of the work of this Contract, the CONTRACTOR shall verify the correctness of such dimension or location in the field before any other procedure, whether of manufacture of related equipment or construction of related structure, shall begin. Failure of the CONTRACTOR to follow the required verification procedure here specified shall cause him to waive all right to claim for additional cost by reason on the later discovery of inaccurate dimensions or locations of existing facilities as depicted in the Contract Documents.
D. Should discrepancy be found to exist between the various Contract Documents, the following order of priority shall be followed in resolving the intent of the effected documents. In decreasing order of importance, the documents are the Specifications; Drawings; Supplementary Conditions. Further, it shall be understood that, in all cases, calculated dimensions shall prevail over scaled dimensions, and larger scale drawings shall take precedence over small scale drawings.
1.05 PRECONSTRUCTION MEETING
A. A pre-construction meeting will be held after award of the contract. A tentative meeting is scheduled for September 16, 2026 at Avondale Borough, 110 Pomeroy Avenue, PO Box 247, Avondale, PA 19311.
B. The CONTRACTOR will be notified of any changes to the date and time of this meeting and will be expected to attend with the designated Project Superintendent.
C. CONTRACTOR is required to submit a construction schedule showing the order in which the
CONTRACTOR proposes to carry on the work, the dates on which he will start several of the more salient features and the contemplated dates for completing the same. The schedule shall be in the form of a progress chart of suitable scale as to approximately indicate the percentage of work completed at any time.
1.06 PROGRESS MEETINGS
A. During the construction period, progress meetings shall be held with the ENGINEER at the job site to discuss recent developments and future work plans as they relate to the schedule specified hereinafter.
B. Progress meetings will be held monthly in general, but the interval between meetings may be increased or decreased by the ENGINEER to suit the then current circumstances.
C. The Construction Manager, CONTRACTOR and major Subcontractors shall be represented at every meeting by a responsible member of their respective organizations.
D. All decisions and interpretations given by the ENGINEER at project meetings shall be on behalf of the OWNER and shall be conclusive on each CONTRACTOR or Subcontractor affected.
E. The proceedings of these meetings will be recorded by the Construction Manager, and each required representative at meetings will be furnished one copy.
01010-4
F. The ENGINEER's act of conducting meetings, recording, and distributing meeting minutes on behalf of the OWNER, shall not be construed as coordinating or scheduling CONTRACTOR's
G. If a change of meeting date/time is required due to causes beyond control of the OWNER or
ENGINEER, the ENGINEER will advise each concerned party in advance of such change.
PART 2 - PRODUCTS
2.01 MATERIALS AND EQUIPMENT
A. All materials and equipment supplied for use on this project shall be new and purchased specifically for incorporation into the work included in the Contract Documents.
2.02 PRODUCT DELIVERY, STORAGE AND HANDLING
A. Proper and suitable tools, equipment, and appliances for the safe and convenient handling and placing of all materials and equipment shall be used.
B. During loading, unloading, and placing, care shall be taken in handling the equipment and materials so that no equipment of materials are damaged.
C. Any precautions necessary to protect items of equipment and materials from damage while stored on the construction site shall be exercised.
D. The CONTRACTOR shall follow all written instructions and recommendations of the equipment manufacturer and all requirements of the ENGINEER regarding the oiling, exercising, maintenance, and protection of the equipment during storage. It shall be the CONTRACTOR's complete responsibility to satisfactorily store and care for equipment and materials.
E. Equipment may be initially delivered to a warehouse, conveniently located in the vicinity of the site, with the approval of and under such conditions as may be further imposed by the ENGINEER.
2.03 SUPPLIERS/MANUFACTURERS
The CONTRACTOR shall provide the names of the suppliers and manufacturers from whom major equipment items will be purchased. The suppliers and manufacturers shall not be altered from those listed without written approval of the ENGINEER. Only one supplier and manufacturer shall be shown for each equipment item. In the event that the ENGINEER determines that the equipment to be furnished is not equal to the equipment specified, the CONTRACTOR will absorb all costs incidental to changing the equipment to that which is determined to be equal. In no event will there be an adjustment of the bid amount. If the CONTRACTOR is required to change the equipment furnished from that listed on the Bid Form attachment.
01010-5
PART 3 - EXECUTION
3.01 INSPECTION
A. The CONTRACTOR is required to carefully examine the site of the work, Drawings, Specifications, applicable State, County and local codes, and other Contract Documents for the work contemplated, and it will be assumed that he has familiarized and satisfied himself as to the conditions and obstacles to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of these Specifications, Drawings and other Contract Documents. He must also be prepared to execute a finished job in every particular, without any extra charge whatever, except as may be specifically provided for elsewhere in these Contract Documents.
3.02 CONDUCT OF WORK
A. All work shall be subject to the control of the ENGINEER and the OWNER. In terms of the performance of the work, the CONTRACTOR shall abide by all orders, directions and requirements of the ENGINEER and the OWNER and shall perform all work in such manner and sequence as the OWNER may require. The ENGINEER and OWNER shall determine the amount, quality, acceptability, and fitness of all parts of the work; shall interpret the Plans, Specifications and Contract Documents; shall issue any extra work orders; and shall decide all other questions in connection with the work. The CONTRACTOR shall employ no plant, equipment, materials, or methods to which the ENGINEER or OWNER objects and shall remove no plant, materials, equipment, or other facilities from the site of the work without the ENGINEER's or OWNER's permission. Upon request, the ENGINEER or OWNER shall confirm in writing, any oral order, direction, requirement or determination. If any person employed on the work by the CONTRACTOR shall appear to the ENGINEER or OWNER to be incompetent or to act in a disorderly or improper manner, such person shall be removed immediately upon request by the
ENGINEER.
B. The CONTRACTOR agrees to use, at all times, on the work, only such labor as will in no way disturb or affect labor employed by the OWNER and/or other CONTRACTORs on the project. The CONTRACTOR and each and every subcontractor performing work at the site of the project shall comply with all "Labor Laws" of the Government, and of the State, County, Township, and Municipality in which the project is located.
3.03 SUBSURFACE INFORMATION
A. The OWNER has not obtained any data concerning subsurface materials or conditions. Bidders shall, therefore, make their own investigation of existing subsurface conditions and if they do not do so, the OWNER will not be responsible in any way for the consequences.
3.04 EXISTING UTILITIES - ACT 172 (187 As Amended)
A. The CONTRACTOR shall check the location of existing utilities, either overhead or underground, and take all necessary precautions to prevent injury or damage the performance of the contract and shall be responsible for any and all damage thereto. The CONTRACTOR’s attention is directed to the provisions of Act 172 enacted by the General Assembly of the Commonwealth of Pennsylvania.
01010-6
3.05 AS-CONSTRUCTED DRAWINGS
A. No As-Constructed Drawings need be provided for this contract.
3.06 CLEANING UP
A. Continuously keep the work, the site, and adjacent properties free from accumulations of waste materials, excess excavation, rubbish, and windblown debris resulting from construction operations.
Periodically remove waste materials, excess excavation, debris, and rubbish from the site and dispose of at legal disposal areas away from the project site.
B. Remove grease, mastics, adhesives, dust, dirt, stains, finger prints, labels, and other foreign materials from site-exposed interior and exterior surfaces of structures. Broom clean exterior paved surfaces;
rake clean other surfaces of the grounds. Restore areas disturbed by construction. Provide continuous dust control during construction.
C. At the completion of the work, or each major portion thereof, the CONTRACTOR shall remove surplus materials, tools, construction equipment, and machinery, and leave the site clean and ready for occupancy by the OWNER.
END OF SECTION
01 2300-1 (7/26) 264128_400 01 2300.docx
SECTION 01 2300
ALTERNATES
1.01 SUMMARY
A. Section Includes:
1. Submission Procedures
2. Documentation of changes to Contract Sum/Price and Contract Time
1.02 RELATED SECTIONS
A. Agreement Form: Incorporating the monetary value of accepted Alternates
B. Bid Form: Requirements for Alternates
1.03 REQUIREMENTS
A. Alternate quotes on Bid Forms will be reviewed and accepted or rejected at OWNER’s option.
Accepted Alternates will be identified in the OWNER-CONTRACTOR Agreement.
B. Coordinate related work and modify surrounding work to integrate the Work of each Alternate.
1.04 SELECTION AND AWARD OF ALTERNATES
A. Indicate variation of Bid Price for Alternates described below and list in Bid Form Document or any supplement to it, which requests a “difference” in Bid Price by adding to or deducting from the base bid price.
B. Bid will be evaluated and awarded according to Articles 14 and 19 of Document 00 2113
Instructions to Bidders.
C. Bid may be evaluated on base bid price or a combination of the base bid one or both alternates.
1.05 ADD ALTERNATE 1 – SIXTH STREET
A. Add the asphalt milling and overlay as detailed on the bid form for this alternate.
1. Reference Drawings: C-108 – SIXTH STREET.
01 2300-2 (7/26) 264128_400 01 2300.docx
PART 2 – PRODUCTS
This part not used.
PART 3 - EXECUTION
01020-1 (7/26) 264128_400 01020.docx
SECTION 01020
MEASUREMENT AND PAYMENT
A. This section includes the description of the various pay items found in the Bid Form and the method of measurement for payment of each pay item.
1.02 QUALITY ASSURANCE
A. Work completed under the Contract shall be measured by the ENGINEER according to the standards of weights and measures recognized by the U.S. Bureau of Standards.
B. The method of measurement and computations to be used in determination of quantities of material furnished and of work performed under the Contract will be those methods generally recognized as conforming to good engineering practice.
C. Measurement for area computations will be made on the surface. Pay measurements for area computations will not exceed the neat dimensions indicated on the Drawings, unless otherwise ordered in writing by the ENGINEER.
D. Structures will be measured according to neat lines indicated on the Drawings or as altered to fit field conditions. No payment will be made for length, width, or depth, in excess of that indicated on the Drawings or specified for any construction, unless otherwise approved by the ENGINEER in writing.
E. Items that are measured by the linear foot, such as pipe and concrete curb will be measured parallel to the base or foundation upon which such items are placed and from outside edge/surface to outside edge/surface of the same.
F. In computing volumes of excavation, the average end area method, based on horizontal measurements, or other acceptable methods, will be used.
G. The term "each", when used as an item of payment, will mean complete payment for the work described in the Contract Documents.
H. The term "lump sum", when used as an item of payment, will mean complete payment for the work described in the Contract Documents, including all incidentals of which includes necessary fittings, accessories, and restoration.
I. The term "incidental" when used will mean items, equipment, materials, labor, etc., incidental, and necessary to obtain a final product satisfactory to the ENGINEER. No additional payment will be made for incidentals.
01020-2 (7/26) 264128_400 01020.docx
PART 2 – PRODUCTS
PART 3 – EXECUTION
3.01 WORK TO BE COMPLETED WITH EACH CONTRACT ITEM
A. Bonds, Insurance, and Mobilization - Lump Sum (LS) - Includes cost for required bonds, insurance, mobilization, or any other miscellaneous costs incidental to the completion of the project as a whole but not expressly required for completion of Contract Bid Form item(s). Cost for this item should not be included in any other Contract Bid Form Item and it shall be assumed unit price(s) bid do not include such costs. No extra payment will be permitted with this item.
01300-1 (7/26) 264128_400 01300.docx
SECTION 01300
SUBMITTALS
1.01 SCHEDULE OF VALUES
A. Within ten (10) days after the Contract Times start to run, CONTRACTOR shall submit a
Schedule of Values for CONTRACTOR’s work including quantities and unit prices of items aggregating the contract price. Submit typed schedule on Forms EJCDC 1910-8 or AIA G703.
Identify each line with number and title indicated on the Bid Form. The Schedule of Values shall be incorporated into the applications for payment upon approval by the ENGINEER. Schedule shall be revised to list any approved Change Orders, with each Application for Payment.
1.02 APPLICATIONS FOR PAYMENT
A. The procedure for submittal, review, and payment of monthly applications for progress payments shall be established at the preconstruction conference. Submit one (1) executed original and four
(4) copies of each application for payment to the ENGINEER in a format similar to AIA Document G702 and Continuation Sheets G703. Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the CONTRACTOR. Incomplete applications will be returned without action. Entries shall match data on the Schedule of Values and Construction Schedule. Use updated schedules if revisions have been made. Include amounts of Change Orders issued prior to the last day of the construction period covered by the application.
1.03 LIST OF SUBCONTRACTORS
A. Within ten (10) days after the Contract Times start to run, the CONTRACTOR shall submit a listing of all subcontractors describing the work to be performed by each.
1.04 LIST OF SUPPLIERS
A. Within ten (10) days after the Contract Times start to run, CONTRACTOR shall submit a listing of the suppliers from whom major equipment items will be purchased. The suppliers listed shall not be altered from those submitted without written approval of the ENGINEER. Only one supplier shall be shown for each equipment item.
1.05 SHOP DRAWING SCHEDULE
A. Within ten (10) days after the Contract Times start to run, each CONTRACTOR shall submit a preliminary schedule of shop drawing submissions.
01300-2
1.06 PROGRESS SCHEDULE
A. Within ten (10) days after the Contract Times start to run, the CONTRACTOR shall submit a proposed program of operation, showing clearly how the CONTRACTOR proposes to conduct the work so as to bring about the completion of the work within the time limit specified. This program shall outline the proposed sequence of operations, the rates of progress and the dates when the work will be sufficiently finished to permit the installation of the work under other Contracts (if applicable).
1.07 CONSTRUCTION SCHEDULE
A. Within ten (10) days after the Contract Times start to run, the CONTRACTOR shall submit a
Construction Schedule. No progress payment shall be approved until an acceptable Construction Schedule is received.
B. Construction Schedule shall be horizontal bar-chart type with a separation time bar for each significant construction activity. Activities should be specific as to type of work and location.
Activity duration shall be the total number of actual days required to perform that activity including consideration of weather impact on completion of that activity.
C. Prepare the schedule on a sheet, or series of sheets, of reproducible media and sufficient width to show data for the entire construction period. Provide a continuous vertical line to identify the first working day of each week. Within each time bar, indicate estimated completion percentage in 10 percent increments. As work progresses, place a contrasting mark in each bar to indicate actual completion.
D. Secure time commitments for performing critical elements of the work from all parties involved.
Coordinate each element on the schedule with other construction activities. Show each activity in proper sequence. Graphically indicate the sequences necessary for completion of related portions of the work.
E. Coordinate the Construction Schedule with the Schedule of Values, list of subcontractors, list of suppliers, and anticipated submittal schedule for shop drawings, product data, and samples.
F. Indicate completion in advance of the date established for Substantial Completion. Indicate
Substantial Completion on the schedule to allow time for the ENGINEER's procedures necessary to issue a Certificate of Substantial Completion.
G. Following favorable response to the submittal by the ENGINEER, print and distribute copies to each subcontractor and other parties required to comply with scheduled dates. Post copies in the temporary field office(s). When revisions are made, distribute to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the work and are no longer involved in construction activities.
H. In general, revise the schedule every month. All Change Orders to the Contracts or other activity, where revisions have been recognized or made, must be incorporated into the schedule.
01300-3
1.08 SHOP DRAWINGS, PRODUCT DATA, SAMPLES AND CERTIFICATIONS
A. Fabricated materials or equipment to be incorporated in the work shall be subject to review by the ENGINEER. The CONTRACTOR shall obtain and check prints of manufacturer's certified shop drawings and other pertinent data. When the CONTRACTOR has reviewed the shop drawings and is satisfied they are correct, CONTRACTOR shall number each submittal (shop drawing, certificate, manual) and submit them to the ENGINEER for review. Submittal numbering system shall be the section number referenced by these Specifications followed by the submittal number (i.e., 02610-1, 03400-1 etc.).
B. Shop drawings are intended to mean fabrication and installation drawings. These drawings and pertinent data shall be complete and in such detail as the ENGINEER may require for providing information regarding the design, installation, testing, and operation for products and/or equipment.
C. All costs necessary for compliance with the requirements of this section of the Specifications shall be included in the bid.
D. Detailed shop drawings, data, and literature for fabricated materials or equipment to be incorporated in the work shall be submitted to the ENGINEER for review at least two weeks before fabrication. The CONTRACTOR shall obtain and check manufacturer's shop drawings, certified prints, and other pertinent data for conformance with all requirements of the Drawings and Specifications in ample time to permit satisfactory progress of the work.
E. After completion of such checking and verification by the CONTRACTOR, the CONTRACTOR shall include a full completed copy of Attachment 1 as a cover sheet for each copy of the shop drawing. In addition, the submittal number shall be written or typed in the lower right-hand corner of all copies of each shop drawing. The submittal numbering system should be the specification section number followed by the submittal number (i.e., 02610.1 - Ductile Iron Pipe,
02610.2 - PVC Pipe). Failure to include a cover sheet for each copy of the shop drawing or not numbering submittals shall be grounds for rejection of the submittal by the ENGINEER. (See Attachment 1 at the end of this section).
F. All data, drawings, and correspondence from subcontractors, material men, or suppliers shall be routed through the CONTRACTOR. This procedure is required so that the CONTRACTOR's superintendent can familiarize himself with all information which the CONTRACTOR sends to the ENGINEER and also to prevent the ENGINEER from taking action upon something other than that which is desired by the CONTRACTOR. The ENGINEER shall consider for review only such data and details as are verified and transmitted to him directly by the CONTRACTOR.
G. All correspondence between the ENGINEER and the CONTRACTOR, all shop drawings, and all data for review of drawings or materials will be handled by the ENGINEER. All such data shall be delivered directly to him at the ENGINEER's office. The replies pertaining to these matters will be delivered to the CONTRACTOR or the CONTRACTOR's representative at the job site.
01300-4
H. A sufficient number of shop drawings and review data shall be submitted to the ENGINEER, who will retain four (4) copies of each submittal. All additional copies, up to a maximum of four (4), received by him will be returned to the CONTRACTOR or his representative at the job site.
The ENGINEER's notations of the action which he has taken will be noted on all the returned copies. Sufficient time for the review of all shop drawing submittals shall be allowed in the CONTRACTOR's schedule. A minimum of two weeks shall be allotted for each shop drawing review.
I. Drawings of minor or incidental fabricated materials and/or equipment may not be required by the ENGINEER. The CONTRACTOR shall furnish the ENGINEER with tabulated lists of such fabrications, showing the names of the manufacturers and catalog numbers, together with samples of general data as may be required to permit intelligent determination as to their accep-tability for incorporation in the work.
J. Upon successful review by the ENGINEER of the shop drawings, data sheets, samples, other data, the fabrications furnished shall be in conformity with the same. The acceptance of the shop drawings, data sheets, samples, or other data shall in no way release the CONTRACTOR from his responsibility for the proper fulfillment, by any fabrication, of the requirements of the Agreement.
K. All reviews of shop drawings, data sheets or literature are subject to the products fulfilling the specific requirements of the Drawings and Specifications. Review of items that do not conform in detail to the specified product shall place upon the CONTRACTOR the responsibility for suc-cessful operation of the proposed product. Should the item subsequently prove to be defective or otherwise unsatisfactory for the service for which it was intended, the CONTRACTOR shall, without cost to the OWNER and without obligation on the part of the ENGINEER, replace the item with the material originally specified. The ENGINEER's review of shop drawings or layout for any material, apparatus, or device shall not relieve the CONTRACTOR from the responsibility of furnishing the same of proper dimension, size, quantity, quality, and all perfor-mance characteristics to efficiently perform the requirements and intent of the Contract Documents. Such review shall not relieve the CONTRACTOR from responsibility for errors of any sort on the shop drawings. If the shop drawings deviate from the Contract Documents, the CONTRACTOR shall advise the ENGINEER of the deviations, in writing accompanying the shop drawings, including the reasons for the deviations, and shall request a deviation from the Contract Documents as hereinafter described.
L. The shop drawings are intended to be utilized by the CONTRACTOR for additional fabrication, assembly, and erection data. The shop drawings do not change or supersede the Drawings and Specifications except in specific cases when the CONTRACTOR requests, in writing, a deviation from the Drawings and Specifications. The CONTRACTOR's request for a change shall give, in detail, the specific change requested and shall state the reason for the change. Changes requested by the CONTRACTOR and reviewed by the ENGINEER shall not be construed to include acceptance of any change except the changed details specifically requested and accepted.
M. It shall be the responsibility of the CONTRACTOR to make all the necessary changes in other items, which result from deviations or changes requested by the CONTRACTOR and reviewed by the ENGINEER, so that all items perform the requirements and intent of the Contract Documents.
01300-5
N. The CONTRACTOR shall furnish the number of samples required by individual sections of the Specifications. Submit samples under separate transmittal letter with appropriate section and article number of the Specifications as identification. A separate transmittal letter is required for each sample submitted.
O. The CONTRACTOR shall furnish all certifications including Statements of Compliance, Installation Certificates, and certified test results as required by individual sections of the Specifications. Submit certificates under separate transmittal letter using the same numbering system as specified for shop drawings and product data. The number of certifications submitted shall be the same as used for shop drawing and review data submittals.
P. CONTRACTOR shall make resubmittals under procedures specified for initial submittals and shall identify changes made since previous submittals. ENGINEER will review the first submittal and the first resubmittal at no cost to the CONTRACTOR. Additional submittals will be reviewed by the ENGINEER and the costs for these reviews will be borne by the CONTRACTOR. These costs when incurred by the CONTRACTOR will be deducted from CONTRACTOR's progress payments. Each resubmittal shall contain the original submittal number with a suffix letter after the original number such as "A" for the first resubmittal, "B" for the second resubmittal, "C" for the third, and so forth.
1.09 WARRANTIES
A. CONTRACTOR shall obtain warranties, executed by responsible subcontractors, suppliers, and manufacturers, within ten (10) days after completion of the applicable item of work. Except for items put into use with the OWNER's permission, leave date of beginning of time warranty until the date of Substantial Completion is determined.
B. Warranties shall be bound in a commercial quality 8 1/2" x 11" three-ring side binders, with hardback, cleanable, plastic covers. Label cover of each binder with type or printed title "WARRANTIES", with title of project; name, address, and telephone number of CONTRACTOR; and name of responsible principle. Provide each binder with a Table of Contents, neatly typed, with each item identified with the number and title of the specification section in which it is specified, and the name of the product or work item. Separate each warranty with index tab sheets keyed to the Table of Contents listing. Provide full information, using separate typed sheets, as necessary. List subcontractor, supplier, and manufacturer, with name, address, and telephone number of responsible principle.
C. Verify that documents are in proper form, contain full information, and are notarized. Co-execute submittals when required. Retain warranties until time specified for submittal.
D. For equipment or component parts of equipment put into service during construction with the
OWNER's permission, submit documents within ten (10) days after acceptance. Make other submittals within ten (10) days after date of Substantial Completion, prior to final Application for Payment. For items of work accepted after the date of Substantial Completion, submit within ten (10) days after acceptance, listing the date of acceptance as the beginning of the warranty period.
01300-6
1.10 PROJECT RECORD DOCUMENTS
A. Record Documents shall consist of the following:
1. Contract Drawings
2. Specifications
3. Addenda
4. Change Orders and other modifications to the Contract(s)
5. Reviewed shop drawings, product data, and samples
6. Manufacturer's Certificates and Statements of Compliance
7. Installation Certificates
8. Certified factory test results and field test records
B. Store Record Documents in field office apart from documents used for construction. Protect from deterioration and loss in a secure, fire resistive location. Provide access to Record Documents for the ENGINEER's reference during normal working hours.
C. Record Drawings: Maintain a clean, undamaged set of blue or black line white prints of Contract
Drawings and shop drawings. Mark the set to show the actual installation where the installation varies substantially from the work as originally shown. Mark whichever drawing is most capable of showing conditions fully and accurately. Where shop drawings are used, record a cross-reference at the corresponding location in the Contract Drawings. Give particular attention to concealed elements that would be difficult to measure and record at a later date.
D. Mark Record Documents with red erasable pencil. Use other colors to distinguish between variations in separate categories of the work. Mark new information that is important to the OWNER but was not shown on the Contract Drawings or shop drawings. Measure and record the horizontal and vertical locations of all underground utilities and appurtenances referenced to permanent surface improvements. Note related Change Order numbers where applicable.
E. At project closeout, CONTRACTOR shall submit Record Drawings to the ENGINEER certified by a principal officer of the CONTRACTOR. In general, the certification statement shall read as follows:
"These Record Drawings have been completed and certified by (Name of CONTRACTOR) as reflecting as-constructed conditions. Responsibility for accuracy of the Record Drawings rests with (Name of CONTRACTOR)."
BY: Principal Officer of Contractor
TITLE: _____________________________
DATE: ____________________________
01300-7
ATTACHMENT 1
Project: Avondale Borough 2026 Pavement Repair Project
Title:
(Submittal Number - Name)
Checked By:
(Contractor's Name)
Signed By:
(Checker's Name)
Date:
This submittal has been reviewed and approved by the CONTRACTOR with respect to the means, methods, techniques, sequences and procedures of construction, and safety precautions and programs incidental thereto. The CONTRACTOR also warrants that this submittal complies with the Contract Documents and comprises no variation thereto.
Notes:
1. The CONTRACTOR is responsible for putting the submittal number in the lower right-hand corner of all copies of each submittal.
2. The CONTRACTOR is responsible for binding or stapling all copies of each submittal individually.
01560-1 (7/26) 264128_400 01560.docx
SECTION 01560
MAINTENANCE OF TRAFFIC
A. The CONTRACTOR shall be responsible to maintain and protect traffic during working and non-working hours. The CONTRACTOR's attention is called to the importance of maintaining and protecting traffic and he shall comply with the requirements called for in these specifications.
MAINTENANCE AND PROTECTION OF TRAFFIC IS INCIDENTAL TO THE
CONTRACT.
B. This modification of the Standard Contract Requirements does not relieve the CONTRACTOR of the responsibility of setting up traffic cones, barricades, flashing danger signal lights and directional signs, of the types approved by the ENGINEER, for safety purposes as required by the Standard Contract Requirements.
This part is not used
3.01 MAINTENANCE AND PROTECTION OF TRAFFIC
A. The CONTRACTOR will be required to notify the OWNER, ENGINEER, and the Police
Department of the Township in which work is being performed ten (10) days prior to the date he desires to restrict traffic in the streets, and one (1) working day notice prior to the completion of the
B. Maintenance and protection of traffic shall be in accordance with PennDOT Publication 213, Work
Zone Traffic Control Guidelines, and this specification.
C. If a flagger is utilized during construction, their only responsibility shall be to direct traffic through the work-zone in a safe and efficient manner.
D. During non-working hours, the CONTRACTOR is required to maintain the full paving width as it existed prior to commencement of work.
E. Access must be maintained at all times to all properties, driveways, and entrances, by the construction and maintenance of bridges across the trenches so that interference with the normal use of properties will be reduced to a minimum.
01560-2 (7/26) 264128_400 01560.docx
F. The CONTRACTOR shall make provisions for the immediate passage of all emergency vehicles operating flashing lights and/or sirens. No such vehicle shall be delayed more than 30 seconds.
G. When construction work has been completed, including re-paving, all temporary safeguards shall be removed, clean-up shall be completed, and the travel-ways restored to their original condition.
H. The CONTRACTOR must notify the OWNER in writing a minimum of two weeks prior to any proposed road closures. The necessity for the road closure and the proposed maintenance of traffic strategy must be approved by the ENGINEER. Access to all properties must be maintained at all times, with the exception that any individual access may be closed for no more than ten (10) minutes at a time.
I. The CONTRACTOR must distribute handbills detailing the type and duration of work no less than
48 hours prior to the commencement of work at any given location to the adjacent property owners.
01565-1 (7/26) 264128_400 01565.docx
SECTION 01565
EROSION AND SEDIMENTATION CONTROL
A. This work shall consist of all temporary and permanent measures required throughout the duration of this Project to provide adequate drainage and erosion and sedimentation control measures for the site and all facilities. The CONTRACTOR shall furnish all labor, materials, and equipment necessary for completion of the work as described herein and as shown or called out on the drawings.
Erosion and Sedimentation Control is incidental to the Contract.
2.01 MATERIALS
A. All materials shall be in accordance with the description herein and as shown or called out on the drawings. Erosion control procedures shall be in accordance with PennDOT Publication 408, latest edition, as well as all Federal, State and County Soil Conservation Specifications and Requirements.
3.01 EROSION AND SEDIMENT CONTROL
A. The CONTRACTOR shall schedule and conduct CONTRACTOR’s operations to minimize erosion of soils and to prevent silting and muddying of wetlands, streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.). Construction of drainage facilities and performance of the contract work which will contribute to the control of erosion and sedimentation shall be carried out in conjunction with earthwork operations, or as soon thereafter as practicable. The area of bare soil exposed at any one time by construction operations shall be kept to a minimum.
B. Prior to the suspension of construction operations for appreciable lengths of time, the
CONTRACTOR shall shape the earthwork in a manner that will permit storm runoff with a minimum of erosion. Temporary erosion and sedimentation control measures such as berms, dikes, or slope drains, deemed necessary by the ENGINEER, shall be provided, and maintained until permanent erosion control features are completed and operative. Temporary erosion control measures will be considered as a subsidiary obligation of the CONTRACTOR during the course of his work.
01565-2
C. The CONTRACTOR shall exercise care to preserve the natural landscape and shall conduct CONTRACTOR’s construction operations so as to prevent any unnecessary destructive scarring or defacing of the natural surroundings in the vicinity of the work area. Except where clearing is required for permanent works, for approved construction roads and for excavation operations, all trees, native shrubbery, and vegetation shall be preserved and shall be protected from damage which may be caused by the CONTRACTOR's construction operations and equipment.
D. Topsoil should be taken from the construction areas and should be stockpiled for reuse in finish grading. Stockpiles should be placed so as not to add any additional sediment to the construction.
The stockpiles should be mulched and/or seeded when exposed beyond twenty (20) days.
E. Graded areas are to be seeded immediately following earthmoving procedures. If the time of the year is not conducive for permanent seeding, temporary mulch and/or seeding should be used.
F. The CONTRACTOR shall also conform to the following practices and controls:
1. Waste or disposal and construction roads shall be located and constructed in a manner that will keep sediment from entering streams.
2. When work areas are located in or adjacent to drainage facilities, such areas shall be separated from the easement by a dike or other barrier to keep sediment from entering a drainage easement. Care shall be taken during the construction and removal of such barriers to minimize the siltation of adjacent drainage facilities or streams.
3. Pollutants such as fuels, lubricants, bitumens, raw sewage and other harmful materials shall not be discharged into or near rivers, streams, wetlands, and impoundments, or into natural or manmade channels leading thereto. Wash water or waste from concrete mixing operations shall not be allowed to enter live streams or discharged in wetlands.
4. All applicable regulations of fish and wildlife agencies and statues relating to the prevention and abatement of pollution shall be complied with in the performance of the contract.
5. Any area disturbed and left bare for three (3) days or more shall have a temporary mulch and/or seeding applied. If construction takes place during winter months when it is not practical to seed, the disturbed area shall be mulched.
6. When drainage ways are crossed, they shall not be left blocked overnight if this blockage could cause siltation downstream, or flooding to adjacent property. All drainage ways shall be restored to existing conditions or improved as directed by the ENGINEER.
7. Dumping of excavated or spoil material into adjacent streams, or on the banks of the stream where it may wash or slide into stream waters shall not be permitted.
8. Pumping of silt laden water from trenches into streams or wetlands shall not be allowed.
9. All construction equipment shall be operated in such a manner as to prevent pollution of any streams.
01565-3
10. Temporary stream crossings will be used to convey equipment and materials from one stream bank to the other. Under no circumstances will construction equipment be permitted to cross natural stream channels.
11. Excavated material or new backfill shall not be stored between trenches and bodies of water, rather they shall be stored on the opposite side of the trench.
12. All restoration work shall proceed as the work progresses and not left until end of the project.
13. Critical slopes shall be stabilized and protected from surface water runoff.
14. Erosion control devices, such as diversion or interceptor dikes, hay bales, shall be used to provide temporary erosion control during construction.
a. No debris or obstructions shall be left un-stabilized in flood plains beyond the period of project construction.
b. The method of construction in flood plains shall provide for daily protection of all disturbed areas to protect outlets.
c. Any cross drainage through flood plains shall be safely channeled through disturbed areas to protect outlets.
d. All materials deposited on public thoroughfares shall be immediately removed.
15. Construction shall not impair surface drainage, constitute a potential erosion hazard, or act as a source of sedimentation to any adjacent property or water course.
16. When it becomes necessary, the ENGINEER will inform the CONTRACTOR of unsatisfactory construction procedures and operations insofar as erosion control and water pollution are concerned. If the unsatisfactory construction procedures and operations are not corrected promptly, OWNER may suspend the performance of the construction until the unsatisfactory condition has been corrected.
01700-1 (7/26) 264128_400 01700.docx
SECTION 01700
PROJECT CLOSEOUT
A. The work under this section includes all administrative procedures for Substantial Completion and
Final Acceptance.
1.02 SUBSTANTIAL COMPLETION
A. Procedures for requesting inspection and issuance of a Certificate of Substantial Completion are explained in the General Conditions. Certificates of Substantial Completion will not be issued until all conditions specified in Section 01010 are satisfied.
1.03 CLEAN-UP
A. The CONTRACTOR shall complete final clean-up operations prior to requesting final inspection.
Final clean-up operations shall be subject to the ENGINEER's approval and acceptance.
B. Upon completion of construction activities, remove all surplus materials, tools, construction equipment, and machinery and clear the site of rubbish, litter, and other foreign substances. Broom clean all paved areas including sidewalks and remove all stains, spills, and other foreign deposits.
Rake grounds that are neither paved nor planted to a smooth even-textured surface.
1.04 FINAL COMPLETION
A. Prior to final payment, the CONTRACTOR shall submit written certification stating the following:
1. Work has been completed in accordance with the Contract Documents.
2. Deficiencies listed with the Certificate of Substantial Completion have been corrected.
B. Prior to Final Payment, the CONTRACTOR shall submit a signed PennDOT MS-NCP (Notice of Completion) Form included in Section 00 5200. The Final Completion Certificate will be reviewed, signed, and returned to the CONTRACTOR by the OWNER provided the work has been satisfactorily completed. Maintenance of the permanent pavement repairs shall be the responsibility of the CONTRACTOR for a period of one year from the date of acceptance.
C. The CONTRACTOR shall submit a completed Certificate of Compliance Form for all materials as required by PennDOT which is included in Section 00 5200.
D. Should the engineer's inspection find work to be incomplete, the engineer will promptly notify the contractor in writing, listing the observed deficiencies.
E. CONTRACTOR shall remedy deficiencies and send a second certification of final completion.
F. When ENGINEER finds work complete, they will consider closeout submittals.
01700-2 (7/26) 264128_400 01700.docx
1.05 REINSPECTION FEES
A. Should status of completion of the work require reinspection by the ENGINEER due to failure of work to comply with CONTRACTOR's claims on initial inspection, OWNER will deduct the amount of ENGINEER compensation for reinspection services from final payment to
CONTRACTOR.
1.06 CLOSEOUT SUBMITTALS
A. Project Record Drawings shall be submitted in accordance with Section 01300.
B. Final Payroll Certificates shall be submitted in accordance with the General Conditions.
C. Contractor's Affidavit of Release of Liens and supporting data shall be furnished by the
CONTRACTOR in accordance with the Contract Forms.
1.07 APPLICATION FOR FINAL PAYMENT
A. The ENGINEER will issue a final change order to the CONTRACTOR reflecting approved adjustments to the contract price. These adjustments shall include, but not be limited to, deductions for uncorrected work, work not performed, liquidated damages, reinspection fees, and resubmittal fees and additions for extra work not previously made by Change Orders.
B. The CONTRACTOR shall submit a final application for payment in accordance with the General
Conditions.
02200-1 (7/26) 264128_400 02200.docx
SECTION 02200
EARTHWORK
A. Earthwork shall be in accordance with PennDOT Publication 408, Section 203 amended as follows:
1. Saw-cutting of the pavement to neat lines at the limits of full depth construction shall be considered incidental to excavation.
03 3000-1 (7/26) 264128_400 03 3000.docx
SECTION 03 3000
CAST-IN-PLACE CONCRETE
A. The work shall consist of the…