Westtown Township 2026 Road Program – West Pleasant Grove Road Improvements

This is a bid and contract documents package for the Westtown Township 2026 Road Program in Chester County, Pennsylvania, administered by Westtown Township with engineering services provided by Cedarville Engineering Group, LLC. The project encompasses improvements to West Pleasant Grove Road, including erosion and sediment control, asphalt milling, select base repair, tree stump removal, unclassified excavation and fill, installation of scratch and leveling courses, stormwater structure installation, new wearing course placement, and replacement of stormwater pipes and structures. Bid options for full-depth pavement removal and replacement are also included. Sealed bids will be received online via the PennBid program until 11:00 AM on April 30, 2026, with no pre-bid meeting scheduled. Bidding will be on a unit price basis, and a single prime contract will be awarded. Bid security of 10 percent of the maximum bid price is required. The work must achieve substantial completion within 60 days and final completion and readiness for payment within 75 days after contract commencement, with liquidated damages of $200 per day assessed for delays beyond these milestones.

Bids will be evaluated based on lowest responsive bid from a responsible bidder, with bidders required to demonstrate current PennDOT pre-qualification and compliance with the Public Works Employment Verification Act. All work is subject to Pennsylvania prevailing wage requirements, with minimum rates established by the Secretary of the Department of Labor and Industry. The contractor must furnish performance and payment bonds equal to the contract price and maintain comprehensive insurance coverage including workers' compensation, commercial general liability, automobile liability, and pollution liability. No specific funding source is identified in the documents, though the project is characterized as publicly funded work subject to Pennsylvania human relations and nondiscrimination requirements. The contract documents establish a comprehensive framework governing contractor responsibilities, quality control, site conditions, safety protocols, and payment procedures, with disputes subject to mediation and potential litigation in Chester County Court of Common Pleas under Pennsylvania law.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID AND CONTRACT DOCUMENTS

FOR

WESTTOWN TOWNSHIP 2026 ROAD PROGRAM

WEST PLEASANT GROVE ROAD IMPROVEMENTS

WESTTOWN TOWNSHIP

CHESTER COUNTY, PENNSYLVANIA

MARCH 27, 2026

Prepared for:

CEG Project No.

0236-25-0228

Prepared By:

0236-25-0228

0236-25-0228

TABLE OF CONTENTS

Division 00 – Procurement and Contracting Requirements

Advertisement for Bids C-111 Instructions to Bidders C-200 Bid Form C-410 Bid Bond C-430 Qualifications Statement C-451 Noncollusion Affidavit C-480 Notice of Award C-510 Agreement Between Owner and Contractor C-520 Notice to Proceed C-550 Performance Bond C-610 Payment Bond C-615 Contractor’s Application for Payment C-620 Certification of Substantial Completion C-625 Maintenance Bond C-650 General Conditions C-700 Supplementary Conditions C-800 Duties of Contractor Under PA Prevailing Wage Act C-810 Pennsylvania Funded Project Regulations C-820 Prevailing Wage Determination C-830 PA Public Works Verification Form C-850 Work Change Directive C-940 Change Order C-941 Field Order C-942

Division 01 - General Requirements

Summary 011000 Allowances 012100 Substitution Procedures 012500 Administrative Requirements 013000 Construction Progress Schedule 013216 Photographic Documentation 013233 Submittal Procedures 013300 Quality Requirements 014000 Temporary Facilities and Controls 015000 Traffic Controls 015526 Product Requirements 016000 Construction Waste Management and Disposal 017419 Closeout Procedures 017700 Division 02 – Existing Conditions Selective Demolition 024119 Division 03 – Concrete Precast Structural Concrete 034100 Division 31 – Earthwork Earth Moving 312000 Division 32 – Exterior Improvements Asphalt Paving 321216 Turf and Grasses 329200 Division 33 – Utilities Storm Utility Drainage Piping 334100

Plans prepared by Cedarville Engineering Group, LLC., consisting of 31 sheets titled “Westtown Township West Pleasant Grove Road Improvements” dated March 20, 2026.

DIVISION 00

Procurement and

Contracting Requirements

ADVERTISEMENT FOR BID C-111 0236-25-0228

Westtown Township 1039 Wilmington Pike, West Chester, PA 19382

Westtown Township 2023 Road Program

Advertisement for Bid

Sealed Bids for the Westtown Township 2026 Road Program associated with the improvements to West Pleasant Grove Road will be received online by Westtown Township, Chester County, Pennsylvania until 11:00 AM local time on April 30, 2026. Online bids shall be submitted by way of the PennBid program. All documents and solicitation details are available online at no cost except to the successful bidder at PennBid

– www.PennBid.net. A nominal fee will be assessed only to the bidder who is awarded a contract. For bidders who are not awarded contracts, there are absolutely no fees.

The Project consists of the following work along West Pleasant Grove Road:

• Erosion and Sediment Control;

• Milling;

• Select base repair;

• Tree stump removal;

• Unclassified excavation and fill;

• Installation of a scratch and leveling course;

• Installation of stormwater structures;

• Placement of new wearing course;

• Replacement of stormwater pipes and structures; and

The Project also includes providing Bid Options for the following items:

• Full depth pavement removal and replacement.

Bids will be received for a single prime Contract. Bids shall be on a unit price basis as indicated in the Bid Form.

No Pre-Bid Meeting will be held for this project.

Bid security shall be furnished in accordance with the Instructions to Bidders.

Attention is called to the fact that prevailing minimum wage rates as determined by the Secretary of the Department of Labor and Industry must be paid by the Contractors on this project and that employees and applicants for employment shall not be discriminated against because of their race, age, color, religion, sex, national origin, or handicap. Each Bidder is required to meet the requirements of Public Works Employment Verification Act, Act 127 of 2012.

Westtown Township, Owner, hereby reserves the right, which is understood and agreed to by all bidders, to refuse and reject any or all bids submitted, and also reserves the right to waive any informality in bids received.

Mila Carter Township Manger http://www.pennbid.net/

EJCDC® C-200 (Rev. 1), Instructions to Bidders for Construction Contracts.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page i

Westtown Township 1039 Wilmington Pike, West Chester, PA 19382

Westtown Township 2026 Road Program Improvements to West Pleasant Grove Road

EJCDC C-200

INSTRUCTIONS TO BIDDERS

TABLE OF CONTENTS

Page ARTICLE 1 – Defined Terms

ARTICLE 2 – Copies of Bidding Documents

ARTICLE 3 – Qualifications of Bidders

ARTICLE 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

ARTICLE 5 – Bidder’s Representations

ARTICLE 6 – Pre-Bid Conference

ARTICLE 7 – Interpretations and Addenda

ARTICLE 8 – Bid Security

ARTICLE 9 – Contract Times

ARTICLE 10 – Liquidated Damages

ARTICLE 11 – Substitute and “Or-Equal” Items

ARTICLE 12 – Subcontractors, Suppliers, and Others

ARTICLE 13 – Preparation of Bid

ARTICLE 14 – Basis of Bid

ARTICLE 15 – Submittal of Bid

ARTICLE 16 – Modification and Withdrawal of Bid

ARTICLE 17 – Opening of Bids

ARTICLE 18 – Bids to Remain Subject to Acceptance

ARTICLE 19 – Evaluation of Bids and Award of Contract

ARTICLE 20 – Bonds and Insurance

ARTICLE 21 – Signing of Agreement

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1 of 9

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the number and format stated in the advertisement or invitation to bid.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall submit with its Bid (a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) the following additional information:

A. Evidence of Bidder’s authority to do business in the Commonwealth of Pennsylvania.

B. Bidder’s state or other contractor license number, if applicable.

C. Subcontractor and Supplier qualification information; coordinate with provisions of Article 12 of these Instructions, “Subcontractors, Suppliers, and Others.”

D. Completion in its entirety of the Qualifications Statement in Section C-451 of these Specifications.

E. Current PennDOT Pre-Qualification.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

4.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2 of 9 storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

4.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify:

a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.

b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

c. reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

4. Copies of these reports and/or drawings may be obtained at a reasonable cost charged by the Issuing Office.

B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or adjacent to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.

4.03 Site Visit and Testing by Bidders

A. Bidder shall conduct the required Site visit during normal working hours and shall not disturb any ongoing operations at the Site.

B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 3 of 9

C. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.

D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

4.04 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. As the General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.

4.05 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 5 – BIDDER’S REPRESENTATIONS

5.01 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;

B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;

C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;

D. understand there are no reports of explorations and tests of subsurface conditions at or adjacent to the Site and (2) there are no reports nor drawings relating to Hazardous Environmental Conditions at or adjacent to the Site;

E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 4 of 9 the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;

F. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;

I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work;

and

J. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

ARTICLE 6 – PRE-BID CONFERENCE

6.01 A pre-Bid conference will be held at the time and location stated in the invitation or advertisement to bid. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Owner in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all parties recorded as having received the Bidding Documents. Questions received less than seven days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.

ARTICLE 8 – BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of TEN (10) percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and

6.02 of the General Conditions. Bidder shall use EJCDC® C 430 (Penal Sum Form) as provided in the Specifications.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 5 of 9

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.

ARTICLE 9 – CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be substantially completed, and completed and ready for final payment, are set forth in the Agreement.

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.

11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 6 of 9

12.03 The apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work: Concrete Subcontractor, Signal Subcontractor, Line Striping Subcontractor, and signal equipment Subcontractor.

If requested by Owner, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity.

ARTICLE 13 – PREPARATION OF BID

13.01 The work in this Contract shall be paid for in accordance with the Pennsylvania Prevailing Wage Act (Act No. 442).

13.02 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.

Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

13.03 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation shall be shown. The corporate seal shall be affixed and attested by the corporate secretary or an assistant corporate secretary.

13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign.

The partnership’s address for receiving notices shall be shown.

13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the firm’s address for receiving notices shall be shown.

13.06 A Bid by an individual shall show the Bidder’s name and address for receiving notices.

13.07 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture’s address for receiving notices shall be shown.

13.08 All names shall be printed in ink below the signatures.

13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

13.10 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.

13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 7 of 9

ARTICLE 14 – BASIS OF BID

14.01 Base Bid with Alternates

A. Bidders shall submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form.

The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.

B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.

14.02 Unit Price

A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

ARTICLE 15 – SUBMITTAL OF BID

15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 7 of the Bid Form.

15.02 A Bid shall be received no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED, DO NOT OPEN ENVELOP UNTIL BID OPENING.” A mailed Bid shall be addressed to:

Westtown Township, 1039 Wilmington Pike, West Chester, PA 19382

15.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 8 of 9

16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.

16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

ARTICLE 17 – OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.

19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.

19.03 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form. To determine the Bid prices for purposes of comparison, Owner shall announce to all bidders a “Base Bid plus alternates” budget after receiving all Bids, but prior to opening them. For comparison purposes alternates will be accepted, following the order of priority established in the Bid Form, until doing so would cause the budget to be exceeded. After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its base Bid and any combination of its additive alternate Bids for which Owner determines funds will be available at the time of award.

19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 9 of 9 proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 20 – BONDS AND INSURANCE

20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the Agreement (executed by Successful Bidder) to Owner, it shall be accompanied by required bonds and insurance documentation.

ARTICLE 21 – SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner. Within ten days thereafter, Owner shall deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

+ + END OF INSTRUCTION TO BIDDERS + +

EJCDC® C-410, 2013 Bid Form for Construction Contracts Page 00410-i Cedarville Engineering Group, LLC 0236-25-0228

BID FORM

Westtown Township 2026 Road Program Improvements to West Pleasant Grove Road

Westtown Township, Chester County, PA

TABLE OF CONTENTS

Page

Article 1 – Bid Recipient

Article 2 – Bidder’s Acknowledgements

Article 3 – Bidder’s Representations

Article 4 – Bidder’s Certification

Article 5 – Basis of Bid

Article 6 – Time of Completion

Article 7 – Attachments to this Bid

Article 8 – Defined Terms

Article 9 – Bid Submittal

EJCDC® C-410, 2013 Bid Form for Construction Contracts Page 00410-1

ARTICLE 1 – BID RECIPIENT

1.01 This Bid is submitted to:

Westtown Township 1039 Wilmington Pike, West Chester, PA 19382

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS

2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, unless award is delayed by a required approval from a government agency, the sale of bonds, or the award of a grant, in which event, the Bids shall remain open for a period of one hundred twenty (120) calendar days from the date of bid opening. The Owner will either award the contract within the applicable time period or reject all Bids, returning the Bid Security to the Bidders. A thirty (30) day time extension of the date for the award may be made by the mutual written consent of the Owner and the lowest responsible, responsive Bidder.

2.02 Bidder will sign and submit the Agreement along with the Bonds and other documents requires by the Bidding Requirement within the time period indicated in the Notice of Award.

ARTICLE 3 – BIDDER’S REPRESENTATIONS

3.01 In submitting this Bid, Bidder represents that:

A. Bidder has examined and carefully studied the Bidding Documents, and any data and reference items identified in the Bidding Documents, and hereby acknowledges receipt of the following Addenda:

Addendum No. Addendum, Date

B. Bidder has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfied itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

C. Bidder is familiar with and has satisfied itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work.

D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if

EJCDC® C-410, 2013 Bid Form for Construction Contracts Page 00410-2 any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings.

E. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and any Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs.

F. Bidder agrees, based on the information and observations referred to in the preceding paragraph, that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents.

G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and confirms that the written resolution thereof by Engineer is acceptable to Bidder.

I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work.

J. The submission of this Bid constitutes an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, and that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

ARTICLE 4 – BIDDER’S CERTIFICATION

4.01 Bidder certifies that:

A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;

B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and

D. Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner, and

E. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.E:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at

EJCDC® C-410, 2013 Bid Form for Construction Contracts Page 00410-3 artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

ARTICLE 5 – BASIS OF BID

5.01 Bidder will complete the Work in accordance with the Contract Documents for the following Lump Sum and Unit Price(s):

EJCDC® C-410, 2013 Bid Form for Construction Contracts Page 00410-4

SCHEDULE OF PRICES

Construction Item Description Units

Est. Unit Total

Quantity Cost Cost

BASE BID

GENERAL CONDITIONS

1 Mobilization/Demobilization/General Conditions LS

2 Maintenance and Traffic Control LS

DEMOLITION

3 PAVEMENT MARKING REMOVAL LF

SAWCUTTING AND MILLING OF ASPHALT PAVEMENT

SURFACE, 1 ½” DEPTH, MILLED MATERIAL RETAINED BY

CONTRACTOR SY

5 REMOVE EXISTING CULVERT HEADWALL EA

6 FULL DEPTH PAVEMENT REMOVAL SF

7 REMOVE EXISTING STORM PIPE LF

8 REMOVE STORM INLET EA

9 REMOVE TREE STUMPS, INCLUDING MULCH EA

10 SITE CLEARING AND GRUBBING LS

EROSION & SEDIMENT CONTROLS

11 INLET SEDIMENT PROTECTION EA

12 EROSION CONTROL BLANKET SY

13 12" COMPOST FILTER SOCK LF

14 TEMPORARY SEEDS & MULCH SY

EARTHWORK

15 TOPSOIL-STRIP/STOCKPILE/RESPREAD LS

16 EARTHWORK CY

SITE IMPROVEMENTS

WEARING COURSE, 0.3 TO < 3 MILLION, 9.5 MM MIX, 1

1/2" DEPTH SY

BASE COURSE,0.3 TO < 3 MILLION, 25.0 MM MIX, 4

1/2" DEPTH SY

19 AGGREGATE BASE, PENNDOT 2A 6" DEPTH SY

20 ASPHALT TACK COAT SY

SCRATCH/LEVELING COURSE, 0.3 to 3 MILLION ESALS,

9.5 MM MIX, 1/2" to 3/4" DEPTH SY

22 SUBBASE UNDERCUT, PENNDOT 2A 6" DEPTH SY

23 4" WHITE WATERBORNE PAVEMENT MARKINGS LF

24 4" YELLOW WATERBORNE PAVEMENT MARKINGS LF

25 24" WHITE WATERBORNE PAVEMENT MARKINGS LF

26 RUBBERIZED JOINT SEALANT SY

27 MAILBOX RELOCATION EA

29 GUIDERAIL LF

30 GUIDERAIL END TREATMENT EA

31 PERMANENT SEEDS & MULCH SY

STORM DRAINAGE

33 TYPE D-W ENDWALL EA

34 TYPE M INLET W/ BICYCLE SAFE GRATE EA

35 6” SDR 35 PVC PIPE LF

EJCDC® C-410, 2013 Bid Form for Construction Contracts Page 00410-5

36 6” DUCTILE IRON PIPE LF

37 8” DUCTILE IRON PIPE LF

38 15" REINFORCED CONCRETE PIPE LF

BID OPTION

DEMOLITION

39 FULL DEPTH PAVEMENT REMOVAL SY

SITE IMPROVEMENTS

40 FULL DEPTH PAVEMENT INSTALLATION SY

The following items of Work are EXTRA items. They are not part of the scope of work for this project as described on the plans and specifications. They shall only be provided by the Contractor and paid the Owner if so directed in writing by the Engineer. The EXTRA Work items are not included in the Total Bid Price.

Construction Item Description Units Quantity

Unit Cost

Extra unclassified excavation below subgrade, where ordered by Engineer. CY 1

Extra Structural Fill, PennDOT No. 2A compacted in place as ordered by Engineer CY 1

3 Tree stump removal over indicated quantity. EA 1

4 Tree removal up to 15” caliper EA 1

5 Tree removal over 15” caliper LF 1

Total of All Lump Sum and Unit Price Items 1 through 38 $

Total of Bid Option Unit Price Items 39 through 40 $

Total Bid Price $

Total Amount of Bid Written Words

The Contract will be awarded to the responsive Bidder with the lowest Total Bid Price of all Lump Sum and Unit Price bid items.

Bidder acknowledges that (1) each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and (2) estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all unit price Bid items will be based on actual quantities, determined as provided in the Contract Documents.

The use of the word “complete” or “in place” in the Schedule of Prices shall be understood to mean the item of Work includes all labor, materials, tools, equipment, excavation (regardless of material encountered), backfill, restoration, reseeding and incidental work necessary to complete the item.

All specified cash allowances are included in the price(s) set forth above and have been computed in accordance with Paragraph 13.02 of the General Conditions.

EJCDC® C-410, 2013 Bid Form for Construction Contracts Page 00410-6

ARTICLE 6 – TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 7 – ATTACHMENTS TO THIS BID

7.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security; if Bid Bond use only the two page form included with the Bidding Documents;

B. Noncolllusion Affidavit;

C. Required Bidder Qualification Statement with supporting data; and

D. Public Works Verification Form – Act 127

E. Current PennDOT Pre-qualification Documentation.

ARTICLE 8 – DEFINED TERMS

8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

EJCDC® C-410, 2013 Bid Form for Construction Contracts Page 00410-7

ARTICLE 9 – BID SUBMITTAL

BIDDER: [Indicate correct name of bidding entity]

By:

[Signature]

[Printed name]

(If Bidder is a corporation, a limited liability company, a partnership, or a joint venture, attach evidence of authority to sign.)

Attest:

[Signature]

[Printed name]

Title:

Submittal Date:

Address for giving notices:

Telephone Number:

Fax Number:

Contact Name and e-mail address:

Bidder’s License No.:

(where applicable)

++ END OF BID FORM ++

PENAL SUM FORM

EJCDC® C-430, Bid Bond (Penal Sum Form). Published 2013.

Prepared by the Engineers Joint Contract Documents Committee.

BID BOND

Any singular reference to Bidder, Surety, Owner or other party shall be considered plural where applicable.

BIDDER (Name and Address):

SURETY (Name, and Address of Principal Place of Business):

OWNER (Name and Address):

Westtown Township 1039 Wilmington Pike West Chester, PA 19382

BID

Bid Due Date: Date Description Westtown Township 2026 Road Program:

BOND

Bond Number:

Date:

Penal sum $ (Words) (Figures) Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

BIDDER SURETY

(Seal) (Seal) Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (Attach Power of Attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

Title Title Note: Addresses are to be used for giving any required notice.

Provide execution by any additional parties, such as joint venturers, if necessary.

PENAL SUM FORM

EJCDC® C-430, Bid Bond (Penal Sum Form). Published 2013.

Prepared by the Engineers Joint Contract Documents Committee.

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond shall be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation shall be null and void if:

3.1 Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2 All Bids are rejected by Owner, or

3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from the Bid due date without Surety’s written consent.

6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after the Bid due date.

7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .