About this file

This is a Specifications document for an Invitation for Bid (IFB) issued by Williamson County, Texas for construction services. The project involves the construction of CR 258 turn bays and overlay of the existing roadway, including grading, drainage structures, erosion control, pavement markings, traffic signals, and signing. The contract has an initial term of 127 calendar days, with substantial completion required within 97 calendar days and final completion within 127 calendar days. An optional pre-solicitation conference is scheduled for Wednesday, January 4, 2026, at 10:00 AM at 100 Wilco Way P104, Georgetown, Texas 78626.

The estimated contract amount is $1,500,000.00. Liquidated damages are set at $968 per day. Contractors must provide a Performance Bond, Payment Bond, Warranty Bond (2-year term), and Bid Bond (5% of bid amount). No set-asides, incumbent information, or specific funding source details are provided in this specifications document.

View the file

Other files

File Type Posted
2-01-CR258-BidForm.xlsx XLSX spreadsheet
5-05-CR258-Bid Affidavit.pdf PDF
6-06-CR258-AddAcknowledge.pdf PDF
10-Virtual Bid Opening Link.docx DOCX document
9-02R-CR258-PCM.pdf PDF
7-07-CR258-FormCIQ.pdf PDF
3-03-CR258-Plans.pdf PDF
4-04-CR258-BidderReference.pdf PDF
8-08-CR258-AntiBoycottStatement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications

GENERAL INFORMATION:

Williamson County is seeking qualified contractors for the construction of the CR 258 turn bays and overlay of the existing roadway including grading, drainage structures, erosion control, pavement markings, traffic signals and signing.

ESTIMATED CONTRACT AMOUNT:

$1,500,000.00

INITIAL CONTRACT TERM:

127 Calendar Days

SUBSTANTIAL COMPLETION (DAYS):

97 Calendar Days

FINAL COMPLETION (DAYS):

127 Calendar Days

LIQUIDATED DAMAGES:

$968 / Day

BONDS REQUIRED:

Performance Bond Payment Bond Warranty Bond (2 year) Bid Bond (5% of Bid Amount)

OPTIONAL PRE-SOLICITATION CONFERENCE

Wednesday, January 4, 2026, at 10:00 AM 100 Wilco Way P104, Georgetown, Texas 78626 image1.jpeg