This document is a Summary of Work section for a USPS Main Post Office roof replacement project in Myrtle Beach, SC, with project number K35886, dated 10/06/2025. The comprehensive roof replacement project covers multiple roof areas (A, B, C, F, G, H, and K) and includes detailed specifications for roof removal, substrate preparation, insulation installation, and roofing membrane application. Key requirements include removing existing roof systems down to the structural deck, performing necessary deck repairs, installing polyisocyanurate insulation with varying slopes (1/8-inch to 1/4-inch per foot), adding a gypsum cover board, and applying a fully-adhered 60-mil PVC roof system meeting ASTM D4434, Type III standards.
Additional project work encompasses replacing 11 roof drain assemblies, with an allowance for 6,400 square feet of steel deck replacement and 20,354 square feet of steel deck brushing and priming. The contractor must provide an alternate price for a 20-Year "Total System Warranty" for the roof system. The project requires compliance with all applicable codes and local regulations, with the more stringent standards applied in case of any conflicts between contract documents, project manual, or project drawings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Coupa Supplier Registration Form.docx | DOCX document | |
| COUPA Supplier Registration Quick Reference Guide.pdf | ||
| Event management for suppliers - Coupa.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
011000-1
USPS – Main Post Office Date: 10/06/2025 SUMMARY OF WORK Roof Replacement Myrtle Beach, SC USPS Project No. K35886
SECTION 011000
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SCOPE
A. The Contractor must provide all material, labor, tools, supplies, equipment, transportation, superintendence, temporary construction of every nature, and all other services and facilities necessary to complete the specified work, including all incidental work described in the contract documents. For purposes of this construction project, the terms “Offeror” and “Contractor” are interchangeable and refer to the party whose proposal is accepted by the Postal Service. It is the Owner’s sole responsibility to clarify design and construction responsibilities among the Owner’s designers, contractors and other agents.
B. The scope of work is listed within Articles 1.2 and 1.3 of this Section.
C. All work shall be in accordance with applicable codes and local regulations that may apply. In case of conflict in or between the Contract Documents and a governing code or ordinance, the more stringent standard shall apply.
D. In case of conflict between the Project Manual and Project Drawings, the more stringent requirement shall apply.
1.2 SUMMARY OF ROOF REPLACEMENT WORK – AREAS A, B, C, F, G, H AND K
A. Asbestos laboratory analysis report: Refer to Section 022623 for information relating to the location of ACM, if applicable, within project areas. If positive refer to Sections 013543 and 028233 for procedures and requirements related to the removal and disposal of non-friable asbestos related to this project.
B. Roof removal and substrate preparation: Remove existing roof system down to the structural deck, including roof membrane(s), and underlying insulation, underlayments, and additional roof membranes. Inspect the existing structural deck and inform the Owner immediately of observed damage and or deterioration. Temporarily displace rooftop equipment as necessary to complete the specified work. Refer to Section 024100.
C. Provide an alternate price for complete refastening of existing structural decks; provide a unit price for areas of existing structural deck that require refastening. Note that refastening of perimeter wood blocking is required. Refer to Sections 053123 and 061516 for re-fastening requirements.
D. After roof removal and inspection of the existing structural deck and perimeter wood blocking, perform repairs to the structural deck, as determined necessary by the Owner. Refer to Sections 053123 and 061516.
E. Provide required wood blocking where indicated on the project drawings. Refer to Section 061053.
F. Area K: Provide an underlayment consisting of red rosin paper, mechanically-attached to the existing structural deck. Refer to Section 072215 for product and installation requirements.
011000-2
Roof Replacement
G. Area A: Provide two layers of 2-1/2 inch polyisocyanurate insulation (5-inches total). If indicated on the project drawings, provide insulation saddles and crickets where shown. Refer to Section 072223 for additional insulation product and installation requirements.
H. Areas H and K: Provide a tapered polyisocyanurate insulation system with an insulation system slope of 1/8-inch per foot, and a starting thickness of 1/2-inch over a base layer of 2-1/2 inch polyisocyanurate insulation. If indicated on the project drawings, provide insulation saddles and crickets where shown. Refer to Sections 072222 and 072223 for additional insulation product and installation requirements.
I. Area G: Provide a tapered polyisocyanurate insulation system with an insulation system slope of 1/4-inch per foot, and a starting thickness of 1/2-inch over a base layer of 2-1/2 inch polyisocyanurate insulation. If indicated on the project drawings, provide insulation saddles and crickets where shown. Refer to Section 072223 for additional insulation product and installation requirements.
J. Areas B and C: Provide a tapered polyisocyanurate insulation system with an insulation system slope of 1/8-inch per foot, and a starting thickness of 1-inch, minimum. If indicated on the project drawings, provide insulation saddles and crickets where shown. Refer to Section 072223 for additional insulation product and installation requirements.
K. Area F: Provide a tapered polyisocyanurate insulation system with an insulation system slope of 1/4-inch per foot, and a starting thickness of 1-inch, minimum. If indicated on the project drawings, provide insulation saddles and crickets where shown. Refer to Section 072223 for additional insulation product and installation requirements.
L. Provide a 1/2-inch gypsum-based cover board over the underlying insulation. Refer to Sections 072222 and 072223 for additional product and installation requirements.
M. Provide a fully-adhered, minimum 60-mil PVC roof system meeting ASTM D4434, Type III. After installation of specified insulation and cover board, install the PVC roofing membrane in bonding adhesive. Provide PVC and sheet metal flashings as specified. Provide an alternate price for a 20-Year, “Total System Warranty” for the roof system. Refer to Sections 075419 and 076207 for product and installation requirements.
N. Provide sealants at locations indicated on the project drawings. Refer to Section 079201.
1.3 SUMMARY OF ADDITIONAL PROJECT WORK
A. Provide new roof drain assemblies at all existing roof drain locations within these roof areas (11 total locations). Refer to Section 024100 for product and installation requirements. Include the cost for this work in the Base Proposal Price; unit prices shall be used to adjust the total number of drain assemblies replaced, if necessary.
B. Within the Base Proposal Price, provide an allowance for 6,400 square feet of steel deck replacement. Replacement location to be determined by field conditions encountered, and the allowance amount shall be adjusted (increase or decrease) per the square foot unit price provided. Refer to Section 053123 for product and installation requirements.
C. Within the Base Proposal Price, provide an allowance for 20,354 square feet of brushing and priming of steel deck. Repair location to be determined by field conditions encountered, and the allowance amount shall be adjusted (increase or decrease) per the square foot unit price provided. Refer to Section 053123 for product and installation requirements.
011000-3
Roof Replacement
PART 2 – PRODUCTS
NOT USED
PART 3 – EXECUTION
NOT USED
END OF SECTION
USPS Master Specifications, issued: 10/1/2017 Last revised: 12/13/2017