This is an Advertisement for Bids (AFB) issued by the State of Colorado Department of Military and Veterans Affairs for bridge repair services at Fort Carson. The project, identified as Project No. 082517, involves repair of a pedestrian walkway bridge located at 8721 Frank Baldwin Road, Building 9121, Fort Carson, Colorado. The bridge has experienced repeated deterioration and maintenance issues, including deck replacement twice within the past ten years, with continued deficiencies such as separating, shifting, or misaligned portions due to deficient fastening systems and deterioration from pedestrian traffic and snow-removal activities. The estimated project cost is $250,000. A mandatory pre-bid conference and site tour will be held on September 8, 2026 at 11:00 AM at the project site. Clarification requests must be submitted by September 11, 2026 at 2:00 PM, with a final addendum anticipated by September 16, 2026 at 1:00 PM. Sealed bid submittals are due September 22, 2026 by 1:00 PM via Box.com, with a public bid opening at 1:05 PM the same day. Award notification is anticipated in October 2026, with contract approval also anticipated in October 2026. Construction is anticipated to start in November 2026 and finish in February 2027. The contractor shall provide all project supervision, construction coordination, scheduling, site logistics, safety, quality control, and warranty services throughout the project and warranty period.

Minimum bidder qualifications include: no prior termination by the State for non-performance; operation under the same business name for at least two years; demonstrated contracting experience on at least two projects each exceeding $250,000 in hard costs of similar scope and complexity; demonstrated bonding capacity up to $300,000; and attendance at the mandatory pre-bid conference. Per Colorado Revised Statutes 8-17-101, Colorado labor must be employed to perform at least 80% of the work, with preference given to Colorado resident bidders. For projects valued at $150,000 or more, the awarded contractor must provide payment and performance bonds of not less than 50% of the contract value, with bond costs included in the bid. A bid bond and power of attorney or proposal guaranty of not less than 5% of the total bid is required. Final settlement notice will be required per C.R.S. 38-26-107(1). All respondents must accept the contract terms outlined in Appendix F, including the sample Contractor's Design/Bid/Build Agreement and General Terms and Conditions, with any exceptions communicated formally in writing before the bid closing. Bidders must submit a cover letter addressing minimum requirements, completed bid form, bid bond, bid breakout form, and direct labor burden calculation.

View the file

Other files

File Type Posted
082517 ADDENDUM 1 QnA.pdf PDF
IFB 2027-0025 pre-bid sign in 082517.pdf PDF
082517 Design Addendum.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OSA-AFB-1 pg. 1

REV 7/2025

ADVERTISEMENT FOR BIDS

Design / Bid / Build State of Colorado

Department of Military and Veterans Affairs

Notice Number: IFB1 2027*0025 Project Number: 082517 Project Title: Bridge Repair at RTI Estimated Project Cost: $250,000.00

NOTICES

1. For all projects with a total dollar value above $150,000 Notice of Final Settlement is required by C.R.S. §38-26-107(1). Final Settlement, if required, will be advertised in the same location as the original solicitation.

2. For State Public Works C.R.S. §8-17-101 - Colorado labor shall be employed to perform at least 80% of the work. Colorado labor means any person who is a resident of the state of Colorado at the time of the Public Works project.

3. All respondents accept the conditions of this AFB, including but not limited to, the following:

a. All submittals shall become the property of the State of Colorado and will not be returned.

b. Late submittals shall not be evaluated.

c. The State reserves the right to reject any or all proposals on the basis of being unresponsive to this AFB or for failure to disclose requested information.

d. The State shall not be liable for any costs incurred by respondents in the preparation of submittals and proposals nor in costs related to any element of the selection and contract negotiation process.

4. The respondent has reviewed Appendix F and by responding has agreed that the terms and conditions of the sample Contractor’s Design/Bid/Build (D/B/B) Agreement (SC-6.21) and General Terms and Conditions of the Contractor’s Design/Bid/Build Agreement (SC- 6.23) are expressly workable without reservation. Any exceptions to the contract must be communicated formally in writing before the bid closes.

5. Preference shall be given to Colorado resident bidders and for Colorado labor, as provided by law.

OSA-AFB-1 pg. 2

6. Per C.R.S. §24-105-201 If the construction value is $50,000 or greater a Bid Bond and Power of Attorney or Proposal Guaranty is required in an amount not less than 5% of the total Bid.

PROJECT OVERVIEW

Introduction

The State of Colorado, Department of Military and Veterans Affairs (DMVA), is soliciting bids from qualified contractors to address existing deficiencies and recurring failures associated with the Pedestrian Walkway Bridge located at 8721 Frank Baldwin Road, Building 9121, Fort Carson, Colorado. The project is identified as Project No.

082517.

The pedestrian walkway bridge has experienced repeated deterioration and maintenance issues over its service life. The bridge decking has been replaced twice within approximately the last ten years; however, continued deficiencies have been observed. Portions of the bridge appear to be separating, shifting, or becoming misaligned, potentially due to loose, missing, or otherwise deficient fastening systems. The walking surface has also sustained deterioration associated with regular pedestrian traffic and snow-removal activities, contributing to a shortened service life of the decking system.

Scope of Services

Contractor shall provide services throughout construction, project closeout, and the warranty period. In addition to the work specifically identified in the drawings, specifications, and supporting exhibits, the Contractor, as the prime vendor to the State, shall provide all necessary project supervision, construction coordination, scheduling, site logistics, safety and access control, protection of existing facilities, coordination with DMVA, the Architect/Engineer and Fort Carson representatives, required submittals and RFIs, quality control, coordination of inspections and testing, progress meetings, documentation of existing and unforeseen conditions, daily site cleanup, protection of completed work, punch-list coordination, closeout documentation, warranties, and correction of warranty deficiencies. The Contractor shall coordinate all subcontractors, suppliers, deliveries, and construction activities necessary to maintain an orderly and safe project site while minimizing disruption to Fort Carson operations and shall comply with all Colorado National Guard, Department of Military and Veterans Affairs, and Fort Carson security, access, safety, and construction requirements. Bidders shall reference the drawings, specifications, and supporting documents contained in the Appendices for the detailed physical scope of construction.

The scope of services will include full Construction Contracting Services for the project specified during the process of construction and warranty period to the State as per the Advertisement for Bid. Specific tasks to be performed by the Contractor include those generally performed by the construction community where the Contractor is the prime vendor to the State. Bidders shall reference the drawings, OSA-AFB-1 pg. 3 specifications, and supporting documents in the Appendices for an understanding of the entire scope of the project.

Per C.R.S. §38-26-106, if a contract amounts to $150,000 or more, the awarded contractor shall provide payment and performance bonds not less than 50% of the value of the contract. The costs associated with this bond are to be included in the contractor’s bid.

MINIMUM REQUIREMENTS

Notice is hereby given to all interested parties that all firms will be required to meet all minimum requirements to be considered for this project. Interested bidders should be prepared to show evidence of the following to be considered as qualified, as a minimum:

1. Not previously terminated by the State for non-performance on a State Buildings contract or procurement.

2. The bidding contractor must have been in the same business, under the same name for the last two (2) years.

3. Demonstrated specific contracting experience in projects of similar scope and complexity for at least two (2) projects each in excess of $250,000.00 (hard cost), utilizing the expertise present in their Colorado Office; and

4. Demonstrated bonding capability up to $300,000.00 for an individual project coincidentally with current and anticipated workloads; provide letter from surety that affirms this capacity.

5. Attended and signed in at the Mandatory Pre-Bid Conference.

Firms meeting the minimum requirements may obtain the bidding documents on the directly from Jenny Randle at Engineering Studio Denver., at admin@esdenver.com.

Please verify your request by calling (720)612-7553.

MANDATORY PRE-BID CONFERENCE AND SITE TOUR

A mandatory Pre-Bid Meeting will be held at:

Building Address: 8721 Frank Baldwin Rd, Building 9121, Ft Carson, CO 80913 Room: Outside at project site (will have someone directing traffic off of Frank Baldwin Rd) Date/Time: September 8, 2026 at 11:00 AM

Visitor Access Requirements:

If you do not already have access to Fort Carson please allow extra time and go to the Fort Carson Visitor Center at 6012 Nelson Blvd, Fort Carson, CO 80913.

You will need a physical copy of your driver’s license, vehicle registration and proof of insurance. A sponsor is not required when applying for a pass but does require a mailto:admin@esdenver.com

OSA-AFB-1 pg. 4 valid purpose for visiting Fort Carson, such as Contractor Conference. If you wish to pre-register visitors can apply online for a pass from their computer or mobile device at https://pass.aie.army.mil

Please see https://maps.app.goo.gl/RHbkh4iAd3R4i8ez7

Please bring a business card that lists your email address.

SCHEDULE

The following is a tentative schedule of events for the Bid Submittal process and an outline of the schedule for the balance of the project. All dates are subject to change and changes in the schedule will be issued via addendum.

Advertisement for Bids Issued September 2, 2026 Mandatory Pre-Bid Conference and Site Tour September 8, 2026 at 11:00 AM Request for Clarifications Due September 11, 2026 by 2:00 PM Final Addendum Issued (anticipated) September 16, 2026 by 1:00 PM Bid Submittals Due (date and Time) September 22, 2026 by 1:00 PM Public Bid Opening September 22, 2026 by 1:05 PM Award Intent Notification (anticipated) October 2026 Contracting October 2026 Contract Approval (anticipated) October 2026 Anticipated Construction Start November 2026 Anticipated Construction Finish February 2027

The above schedule is tentative. Responding firms shall be notified of revisions in a timely manner by email or posted on ColoradoVSS website. Respondents may elect to verify times and dates by email, but no earlier than 36 hours before the scheduled date and time.

QUESTIONS, CLARIFICATIONS AND ADDENDA

Owner initiated changes to this AFB will be issued under numerically sequenced addenda.

Owner initiated changes to this AFB will be posted in the form of addenda on ColoradoVSS .

Questions and requests for clarifications regarding this project shall be submitted before the deadline listed in the above Schedule to Contracts Manager, Kimberlie Smith.

Communication regarding the project during the procurement, outside of this submission process or scheduled procurement milestones is not permitted.

https://pass.aie.army.mil/ https://maps.app.goo.gl/RHbkh4iAd3R4i8ez7 https://colorado.app.box.com/f/18031bc7518b489abf3e8d6055c39016 https://colorado.app.box.com/f/18031bc7518b489abf3e8d6055c39016

OSA-AFB-1 pg. 5

POINT OF CONTACT/CLARIFICATION

Name: Kimberlie Smith, Procurement Contracts Manager Email Address: kimberlie.smith@dmva.state.co.us Phone: 720-250-1542

Name: Arturo Altamirano, Project Manager Email Address: nestor.a.altamirano.nfg@army.mil Phone: 720-601-3931

Name: Domenick Scarimbolo, State Delegate Email Address: domenick.j.scarimbolo.nfg@army.mil Phone: 303-517-9468

BIDDING

Bids shall be submitted on the required bid form as indicated on the Information For Bidders document (SBP-6.12) in Appendix A.

An electronic copy of the sealed bid submittal is due September 22, 2026 and shall be received no later than 01:00 PM (MD/ST) and shall be submitted/accepted via Box.com at the following address. One .pdf is preferred, or a single zip file, as described in the Information for Bidders (SBP-6.12)

Submittal name format: CompanyName_IFB_Ft_Carson_RTI_Bridge_Repair https://colorado.app.box.com/f/0e93ccf968c444b7a42acd4a6a9f8cd4

Bid Forms and Appendices to be included with bid submittal:

1. Cover Letter that addresses Minimum Requirements 1-3

2. Bid Form (SBP-6.13)

3. Bid Bond (SBP-6.14)

4. Bid Breakout Form (Appendix B1)

5. Direct Labor Burden Calculation (SBP-6.18)

Late bid submittals will be rejected without consideration. The State of Colorado assume no responsibility for costs related to the preparation of bid submittals.

BID OPENING

Opening of the bid submittals will be a conference call public bid opening.

Conference line information will be issued in the first Addendum.

Virtual public bid opening will take place at the date and time identified in Schedule https://colorado.app.box.com/f/0e93ccf968c444b7a42acd4a6a9f8cd4 https://colorado.app.box.com/f/10abb996b4ec471fa8607d08d00499a0

NOTICES
PROJECT OVERVIEW
Introduction
Scope of Services
MINIMUM REQUIREMENTS
MANDATORY PRE-BID CONFERENCE AND SITE TOUR
SCHEDULE
QUESTIONS, CLARIFICATIONS AND ADDENDA
POINT OF CONTACT/CLARIFICATION
BIDDING
Bid Forms and Appendices to be included with bid submittal:

BID OPENING