08_SOW_-_Quivira_C1_Bridge_(Repair)_-_V3_Redacted.pdf
PDF 161 KB Posted
- Solicitation number
- 140FGA25Q0014
About this file
This Statement of Work (SOW) outlines design services for the rehabilitation of the C1 Bridge at Quivira National Wildlife Refuge in Stafford, Kansas. The project involves a full-depth repair of Cell #3 of a three-barrel box culvert constructed in 1964, which serves as both a two-lane bridge and a water control structure. The contractor will be responsible for structural repair drawings signed by a Kansas-licensed Professional Engineer, and must perform specific repair tasks including removing 1-foot of fill, replacing the top slab of cell 3, cleaning and reusing viable reinforcing steel, and doweling new reinforcing into concrete slab faces.
Key project requirements include completing the work within 180 days of the Notice to Proceed, obtaining all necessary permits and licenses, and adhering to strict environmental protection guidelines. The contractor must coordinate with the Contracting Officer, provide detailed submittals for approval, and follow specific safety, pollution control, and site restoration protocols. The project involves working at the Quivira National Wildlife Refuge, with typical working hours from 7:30 am to 4:00 pm Monday through Friday, and no work authorized on weekends or holidays without prior approval. The Contracting Officer is Shanen Fox from the U.S. Fish and Wildlife Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Title_I_Investigation_and_Pics.pdf | ||
| B08_Wage_Determinations.pdf | ||
| 08_Specifications_V2_Redacted.pdf | ||
| 06_Quote_Schedule_V2.pdf | ||
| Sol_140FGA25Q0014.pdf | ||
| 03_Submittals.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q u i v i r a N W R C 1 B r i d g e P a g e 1 | 10
STATEMENT OF WORK
Design Services
Quivira National Wildlife Refuge Rehabilitation of C1 Bridge
I. PROJECT SCOPE
A. General The Contractor shall provide structural repair drawings signed and sealed by a
Professional Engineer licensed to practice in the State of Kansas, material, equipment, and labor required for the rehabilitation of a bridge / water control structure (WCS)/ asset at the Quivira National Wildlife Refuge, located in Stafford, Kansas.
II. GENERAL CONDITIONS
A. The Contractor shall provide all material, equipment, and labor required to perform a full depth repair Cell #3 and provide upstream protection of the repaired structure.
B. C1 Bridge/WCS is a three-barrel box culvert constructed in 1964 and owned by USFWS. The construction material is cast-in-place concrete with a gravel wearing surface. The two-lane bridge carries two-way traffic and provides the primary access for FWS and the public between the Headquarters, at the south end, and the remainder of the refuge. The bridge also serves as a water control structure.
An engineering report completed in 2024 (See Attachment) determined that a full depth repair of Cell #3 & concrete repair of Cell #3 is needed to prolong the life of this WCS.
Fish and Wildlife Staff will complete the Concrete Repairs for Cell #3.
C. The Contractor shall be responsible for installing all materials described in Section IX Project Requirements.
D. The Prime Contractor shall have all permits, certificates and licenses required by law for the execution of the work, and shall comply with all Federal, State, or local laws, ordinances, rules, regulations, and codes relating to performance of the work.
E. The Prime Contractor shall provide a list and contact information for any subcontractors.
F. Typical working hours are 7:30 am to 4:00 pm Monday through Friday. Any work that deviates from this schedule or during a holiday requires Contracting Officer approval. These times can be negotiable during the pre-construction meeting.
G. Any conflict or overlap of State of Kansas, EPA, OSHA, and other applicable Federal, State, and local regulations, the Contractor shall follow the most stringent
Q u i v i r a N W R C 1 B r i d g e P a g e 2 | 10 provision.
H. Safety
1. The Contractor shall assume full responsibility and liability for compliance with all applicable Federal, State, and local regulations pertaining to the protection of workers, visitors to the site, and persons occupying areas adjacent to the site, including the provisions of 29 CFR 1910 and 29 CFR 1926 of the Code of Federal Regulations. The Contractor shall hold harmless the Government for failure to comply with any applicable safety or health regulations on the part of himself, his employees, or his subcontractors.
2. Every Contractor employee shall be responsible for complying with applicable safety requirements, wearing prescribed safety equipment, and preventing avoidable accidents and property damage.
3. The Contractor shall provide and maintain a basic first aid kit for use of the workers. The kit shall contain first aid supplies in type and quantity commensurate with type and size of project and the work force, with items necessary for first aid treatment of all injuries. The Contractor shall advise all workers of the location of first aid supplies.
4. The Contractor shall post the telephone numbers of nearest hospital, ambulance service, and fire station in a conspicuous location. The Contractor shall advise all workers of the location of telephone numbers.
Communication devices shall be made available and be ready at the work site to alert others in case of emergencies.
5. The Contractor shall provide at least one nonfreezing type fire extinguisher in each field office, workshop, work site, and storage shed at the work site. These fire extinguishers shall be placed in locations readily accessible by workers.
III. PROJECT REQUIREMENTS
A. The full-depth repair of Cell #3 will consist of the following:
1. Closing the road for an extended period of time.
2. Removing the 1-foot of fill over the top of the box.
3. Removing and replacing the full depth of the top slab of cell 3 of the box.
4. Any reinforcing steel in this area that is still viable, shall be cleaned and used in-place with the placement of new concrete.
Q u i v i r a N W R C 1 B r i d g e P a g e 3 | 10
5. New reinforcing shall be doweled into the faces of the concrete slab and new concrete would be placed, closing the top of the box.
B. Any removal of materials not outlined in this project shall be placed in a condition the same, or better, prior to the start of the project.
C. The Contractor shall provide labor, materials, tools, equipment, and any other work to complete all items in the construction documents.
D. Requirements may be changed based on field conditions. The changes shall be approved by the COR prior to commencing these changes.
E. All materials in contact with water must be rated NSF. All requirements shall meet or exceed ANSI, AWWA, or ASTM. Materials shall be marked with the NSF label.WORK SITE CONDITIONS
IV. WORK SITE CONDITIONS
A. The site of the work is the Quivira NWR, which is located near the town of Stafford, Kansas, it lies mostly in northeastern Stafford County, but small parts extend into southwestern Rice and northwestern Reno Counties. The address is 1434 NE 80th St, Stafford, KS 67578. Attached is a site location map, with photos.
B. Construction activity around the Bridge / WCS must be planned and conducted carefully, so as not to significantly impact the surrounding environment. The Contractor shall provide 48 hours notice to the Government prior to working in the vicinity of the Bridge / WCS.
C. Protection Environmental
1. Pollution Control
a. The Contractor shall abate and control all environmental pollution arising from construction activities by complying with all applicable Federal, State, and local laws and regulations concerning environmental pollution control and abatement, as well as the specified requirements in this contract. The Refuge Manager, or his designee, will inspect the site regularly for compliance.
b. Compliance with this requirement by any and all subcontractors shall be the responsibility of the Contractor.
Q u i v i r a N W R C 1 B r i d g e P a g e 4 | 10
2. Prevention of Water Pollution
a. During construction the Contractor shall comply with all applicable Federal, State, and local laws and regulations concerning the control and abatement of water pollution.
b. The Contractor is responsible for implementing the terms and requirements of the Kansas storm water discharge permit, as issued to the State under the National Pollution Discharge Elimination System (NPDES) by the Environmental Protection Agency (EPA). The Contractor shall apply for and execute all permits as required by the State of (insert state) regarding storm water discharge from the construction site. The Contractor shall submit to the Contracting Officer a copy of all permit applications and a copy of all approvals from the State. Allow the Government 10 days for review of the application package prior to submission. The Contractor's construction activities shall be performed by methods that will prevent entrance or accidental spillage of solid and/or liquid matter, contaminants, debris, and other objectionable pollutants and wastes into streams, flowing or dry watercourses, lakes, ponds, and underground water sources. Such pollutants and wastes include, but are not limited to, refuse, garbage, cement, concrete, sanitary waste, industrial waste, radioactive substances, oil and other petroleum products, aggregate processing tailings, mineral salts, and thermal pollution. The Contractor shall provide a Water Pollution Prevention Plan.
c. At the completion of construction, the Contractor shall remove and dispose of all pollutants, wastes, and objectionable material at a site located off the Government property.
d. The Contractor is responsible for the proper disposal of such materials in accordance with applicable local, State, and Federal regulations.
3. Noise Pollution
a. The Contractor shall comply with all applicable Federal, State and local laws, temporary use permit, orders, and regulations concerning the prevention, control, and abatement of excessive noise.
4. Solid Waste
a. The Contractor shall dispose all non-hazardous waste in an EPA approved landfill.
Q u i v i r a N W R C 1 B r i d g e P a g e 5 | 10
b. The Contractor shall remove any dust, dirt, and debris caused during the construction process.
5. Hazardous Waste
a. The Contractor shall comply with applicable Federal, State, and local laws and regulations concerning the abatement, handling, removal, and disposal of hazardous waste.
b. The Contractor’s abatement activities shall be performed by methods that will prevent accidental spillage of solid material, contaminants, debris, and other objectionable pollutants and wastes into streams flowing or dry water-courses, lakes, ponds, and underground water sources.
D. Environmental Litigation
1. Time lost due to work stoppage because of failure of the Contractor to comply with these requirements may not be the subject of a claim for extension of time or for costs or damages.
E. Fossils and Cultural Materials:
1. Should the Contractor discover any fossils or cultural materials during construction operations, such objects shall become the property of the Government. The contractor shall cease construction operations in the area of the "find," and immediately notify the station manager of such discovery. Construction operations may proceed in other areas not affected by this clause. Care shall be exercised by the Contractor not to damage or collect fossils or cultural materials uncovered during excavation operations.
2. Failure to comply with this requirement may be considered a violation of the Archeological Resources Protection Act of 1979 as amended. Destruction of historic and prehistoric sites and/or unauthorized collection of cultural materials can result in criminal and/or civil penalties. Penalties can include fines, prison sentences, and/or confiscation of equipment.
V. TEMPORARY FACILITIES AND CONTROLS
A. Temporary Utilities
1. The site does not have access to electricity. The contractor shall supply a porta-john.
Coordination with the station is required for potable water.
Q u i v i r a N W R C 1 B r i d g e P a g e 6 | 10
2. The Contractor shall be responsible for the removal and disposal of all debris from demolition and construction activities.
B. Site access and equipment storage areas
1. All Contractor operations (including storage of materials) upon Government premises shall be confined to areas authorized or approved by the Refuge Manager, or his designee.
2. The Contractor shall restore all work and storage areas and areas disturbed by construction to their original condition, or as approved by the Refuge Manager, or his designee, upon completion of the work.
3. The Contractor shall observe all laws and regulations of the local, county, and State authorities in the use of all public roads and highways for the transportation of materials and equipment in connection with work on the project.
4. The Contractor shall observe all overhead obstructions such as bridges, cables, ect.
The Contractor shall repair damage to roads, highways, overhead obstructions, and similar items, resulting from operations performed in connection with this project.
C. Protection and Restoration:
1. The Contractor shall protect all structures and vegetation during the progress of the work and remove all debris and unused materials from the site.
2. Upon completion of the work, the Contractor shall restore, at their expense, all vegetation to its original condition, including the replacement any facility or landscaping which has been damaged.
3. The Contractor shall limit removal of any vegetation to that which interferes with the construction and shall seed any disturbed soil with native grass. The Contractor shall obtain the seed mix from the Refuge Manager.
D. Traffic Regulation
1. If traffic regulation is required at the jobsite, the Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient flasher lights, flagmen, danger signals and signs, and shall take all necessary precautions for the protection of the work and the safety of the public.
Q u i v i r a N W R C 1 B r i d g e P a g e 7 | 10
2. Roads closed to traffic shall be protected by effective barricades on which shall be placed acceptable warning signs.
a. All barricades and obstructions shall be illuminated at night and all lights shall be kept burning from sunset until sunrise.
3. Install appropriate traffic signs at crossroads and approaches to site as needed to direct all affected traffic. Specific sign and barricade requirements are detailed in ANSI D61, "Manual on Uniform Traffic Control Devices."
E. Delivery and Storage: Material shall be delivered to the site in a dry and undamaged condition and stored out of contact with the ground. Materials shall be covered with weather tight covering and kept dry. Storage accommodations shall provide good air circulation and protection from surface staining, when appropriate.
VI. MEANS AND METHODS
A. The Contractor will complete all required local, state, and federal permits associated with construction activities.
B. Means and methods of construction shall be such as the Contractor or subcontractors may choose; subject, however, to the Contracting Officer's right to reject means and methods proposed which:
1. Constitute a hazard to the work, persons, or property.
2. Will not produce finished work according to the terms of the contract.
3. Are contrary to specified means or methods included in the contract.
C. The right to reject means and methods of the Contractor or subcontractor shall not be construed or interpreted as acceptance of control of means and methods by the Contracting Officer.
D. The Contracting Officer's approval of means and methods or failure to exercise right to reject means and methods shall not relieve the Contractor of the obligation to complete the work required by the contract.
E. Total responsibility for control of all means and methods lies with the Contractor for all work.
F. Final Inspection
Q u i v i r a N W R C 1 B r i d g e P a g e 8 | 10
1. The Contractor shall request a final inspection in writing at least ten (10) days prior to the anticipated date of completion.
2. Work will not be considered READY FOR FINAL INSPECTION until all the work has been completed and the Contractor has certified that all items are properly operating and in strict compliance with all contract terms and conditions.
3. The Contractor and/or his project supervisor shall be at the job site during the final inspection.
G. Final Cleanup: The Contractor shall clean the site and remove from the site all construction debris.
H. Payment: The Contractor shall submit a schedule of values. Other requirements may be required based on when the payment is requested. All components in the payment shall be in working condition, unless otherwise agreed upon.
I. Progress Payment: The Contractor may submit a progress payment as agreed upon during the pre-construction meeting.
J. Final Payment: The Contractor shall submit the following prior to final payment:
evidence of completion, guarantees, warranties, O&M manual, certificates, certified payrolls, and as-builts.
VII. CONTRACTOR QUALIFICATIONS
A. The Contractor and all subcontractors shall have all Federal, State, and local licenses, and/or certifications, etc., necessary to perform work in at the station. All licenses and/or certificates must be current from start to finish of the project.
VIII. SUBMITTALS
A. See attached submittal list for required submittal items.
B. The Contractor shall provide copies of all required permits, clearance, and licenses obtained to perform this work to the Contracting Office.
Q u i v i r a N W R C 1 B r i d g e P a g e 9 | 10
C. If alternatives to the means and materials described in these specifications are offered, the submittal must contain a written description of the proposed means and materials comparing all features, options, and codes (if any), in detail. A detailed explanation of why the proposed alternative should be accepted must also be submitted.
D. The Contractor shall submit manufacturer's warranties, guarantees, and certificates for all installed equipment listed on the Project Submittal List.
E. Timing of Submittals/Unapproved Work: As specified above, the Contractor shall submit all deliverables, copies of all required permits, and all product data sheets to the Contracting Officer for review. These submittals must be approved PRIOR to the installation of any purchased or fabricated components. THE PURCHASE AND/OR
INSTALLATION OF ANY UNAPPROVED COMPONENTS SHALL BE AT THE
CONTRACTOR’S RISK. Contract performance time shall not be extended due to delays caused either directly or indirectly by the purchase and/or installation of unapproved components.
F. All items in Section I Project Scope shall be submitted for approval.
G. The attached submittal form shall be used.
IX. PERFORMACE
A. All materials shall be installed according to the manufacturer’s instructions.
B. The Contractor shall coordinate the construction start date with the Contracting Officer.
The project shall be completed within 180 days from the date the Notice to Proceed (NTP) is issued. Additional time will be allowed, if needed, to obtain permits and lead times for materials. Construction will not continue on Saturdays, Sundays, or Federal Government holidays without prior permission of the Contracting Officer.
C. During the performance period of the contract, the Contractor shall be available for conference calls as needed with the Contracting Officer, the Contracting Officer’s Representative (COR), and the Government On-Site Inspector to discuss project progress and/or problems.
D. The Contractor shall obtain all permits and licenses, pay all fees and taxes, and give the notices necessary to perform the services of the contract. The Contractor shall submit all permits and licenses, and receipts for all fees and taxes paid.
Q u i v i r a N W R C 1 B r i d g e P a g e 10 | 10
E. The Contractor shall be liable for damages to roads, utilities, structures, and property, due to any act, omission, neglect, or misconduct during the period of performance of the services of this contract, unless the Government provided that portion of work that directly damaged one of these items.
F. The Contractor is responsible for completing the job to the specifications outlined in this document. The presence of an inspection does not preclude the Contractor from following this document and the specifications outlined.
G. Work on weekends and holidays is not authorized. Prior approval by the Contracting Officer may approve work during these days.
X. POINTS OF CONTACT
A. Quivira National Wildlife Refuge:
B. Contracting Officer
1. Shanen Fox . shanen_fox@fws.gov
C. Contracting Officer Representative / Engineer
XI. ATTACHMENTS
A. Division I Specifications B. C1 WCS/Bridge Title I Investigation
END OF STATEMENT OF WORK