06_Quote_Schedule_V2.pdf
PDF 82 KB Posted
- Solicitation number
- 140FGA25Q0014
About this file
This document is a Bidding Schedule for the C1 Bridge Repair project (Project No. 25-005) located at Quivira National Wildlife Refuge in Stafford, Kansas. The project involves repairing a three-barrel box culvert constructed in 1964, which serves as a critical two-lane bridge providing primary access for Fish and Wildlife Service (FWS) personnel and the public between the Headquarters and the remainder of the refuge. The specific scope includes a full depth repair of the top slab of Cell #3, with the structure being constructed of cast-in-place concrete and featuring a gravel wearing surface.
The Bidding Schedule provides a cost breakdown framework organized by division, including General Requirements (mobilization, demobilization, and bonding), Existing Conditions, Concrete, and Earthwork. While the specific dollar amounts are not filled in, the document is structured to allow contractors to detail their proposed costs across these key project divisions. The bridge/water control structure is owned by USFWS and plays a dual role of providing transportation access and serving as a water management infrastructure component for the wildlife refuge.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIDDING SCHEDULE
C1 Bridge Repair - 25-005
Quivira NWR
Stafford, KS
PROJECT DESCRIPTION:
A. GENERAL CONDITIONS:
Division 1: General Requirements
Mobilization and demobilization $ Bond $
Division 1 Total $ -
B. SUMMARY OF COST BREAKDOWN FOR MATERIALS, LABOR AND EQUIPMENT
Div. 2 Existing Conditions $
Div. 3 Concrete $
Div. 31 Earthwork $
BASE TOTAL $ -
TOTAL $ -
C1 Bridge/WCS is a three-barrel box culvert constructed in 1964 and owned by USFWS. The construction material is cast-in-place concrete with a gravel wearing surface. The two-lane bridge carries two-way traffic and provides the primary access for FWS and the public between the Headquarters, at the south end, and the remainder of the refuge. The bridge also serves as a water control structure. A full depth repair of top slab of Cell #3.
BIDDING SCHEDULE
C1 Bridge Repair - 25-005
Quivira NWR
Stafford, KS
06 - Bid Schedule