08 SOW - 2272 Carpet-Paint PDPG242858.pdf

PDF 168 KB Posted

Attached to
163rd Carpet and Paint building 2272
Solicitation number
W50S74-24-R-A015
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to replace carpet tile and paint interiors in Building 2272 to support the 163rd Attack Wing of the California Air National Guard at March Air Reserve Base.

The SOW outlines the specific requirements, including replacing approximately 4,000 square feet of carpet tile and 800 linear feet of rubber base, as well as painting approximately 14,500 square feet of interior walls. The contractor shall complete the work within 60 days from the Notice to Proceed. The contract will be a firm-fixed-price with options for the rubber base, painting offices, and painting corridors. Key submittals required include a project schedule, schedule of values, activity hazard analysis, accident prevention plan, and construction quality control plan. The contractor must comply with various base access, security, and safety requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CARPET & PAINT

Building 2272 Page 1 of 3 March Air Reserve Base California

STATEMENT OF WORK

CARPET & PAINT

BUILDING 2272

PDPG242858

163 CES CALIFORNIA AIR NATIONAL GUARD

MARCH AIR RESERVE BASE CA

29 MAY 2024

1 SPECIFIC REQUIREMENTS

1.1 PURPOSE

Replace carpet tile and paint interiors in Building 2272 to support the 163 ATKW CA ANG at March

ARB.

1.2 SCOPE

A Replace ~4,000 sf carpet tile and 800 lf rubber base.

B Paint ~14,500 sf interior walls.

C Work is shown on the drawings.

1.3 COST LINE ITEMS

A BASE BID CARPET TILE

B OPTION 1 RUBBER BASE

C OPTION 2 PAINT OFFICES

D OPTION 3 PAINT CORRIDOR

1.4 PERIOD OF PERFORMANCE

The contractor shall complete work 60 days from the Notice to Proceed.

1.5 SUBMITTALS

Submit Government provided AF3000 with Submittal attached in PDF Portfolio to COR for review and approval.

1 Submittal 1 – Administrative

1 Project Schedule 2 Schedule of Values (SOV) 3 Activity Hazard Analysis (AHA) 4 Accident Prevention Plan (APA) 5 Construction Quality Control (CQC)

2 Submittal 2 – Material

1 Product Data 2 Material Samples

3 Submittal 3 – Contract Closeout

1 Warrantee

1.6 PAYMENTS

Submit Government provided AF3065 with SOV attached in PDF Portfolio to COR for review and approval. Once approved submit pay request in WAWF.

Building 2272 Page 2 of 3 March Air Reserve Base California

2 GENERAL REQUIREMENTS

2.1 CHANGES

All work shall be completed in a workmanlike manner according to generally accepted standard practices. Any alteration, or deviation from the drawings/specifications or contract involving extra costs or credits will be executed as mutually agreed upon and be verified by written change order.

2.2 TESTS & INSPECTIONS

Provide all required tests and inspections required by code.

2.3 WARRANTY

Guarantee the material and workmanship for a minimum of one (1) year following the date of substantial completion.

2.4 STAGING AND SITE ACCESS

Materials and Equipment shall be staged in adjacent parking lots. Contractor and Government shall establish schedule of use.

2.5 DEMOLITION

Dispose per industry standards and regulations to approved off-base location.

2.6 PROJECT CLEANUP

Construction debris will be removed on a daily basis. Prior to final acceptance, contractor shall remove all waste materials and debris arising from construction and shall present all construction areas in a broom clean condition.

2.7 HOURS OF OPERATION

Construction shall be performed during normal duty hours which are 0700-1600, Tuesdays through Fridays, excluding federal holidays, unless otherwise required in the contract or approved by the COR. There may be situations that require the contractor to work at times other than normal working hours. When the Contractor’s work schedule conflicts with an Air Force mission requirement, the COR reschedule the work to minimize disruption.

2.8 RECOGNIZED HOLIDAYS

Contractor is not required to provide service on federal holidays, except in emergency situations.

When a federal holiday falls on Saturday, the preceding Friday will be observed. If these holidays fall on Sunday, the following Monday will be observed. If a holiday falls on a scheduled service day, the Contractor will be responsible for rescheduling services for the first day post the holiday observance.

2.9 BASE CLOSURES

Work scheduled but not accomplished because of base closure due to weather, exercises, or actual alert, will be accomplished as soon as possible after reopening the base.

2.10 CONTRACTOR IDENTIFICATION BADGES

March Air Reserve Base is a DOD installation. All badging and security checks will be done in accordance with DOD, Air Force and base Security Forces requirements.

A Badges or temporary base passes will be issued. All commercial vehicles will be inspected each time they enter the base.

B Badges will be issued by the 452d Security Forces Squadron (SFS) to the contractor through the 163d Civil Engineering Squadron (CES) Construction Inspector. Badges shall be issued, tracked, and collected in accordance with instructions from Security Forces.

C The following are the requirements and procedures for the contractor:

1 Contractors and sub-contractors working on the installation for 30 calendar days or more must be issued contractor identification badges. Contractors must submit a list of

Building 2272 Page 3 of 3 March Air Reserve Base California all workers using government provided form which will be routed through 452 SFS for approval. Once approved, passes will be picked up at the visitor center.

2 Contractors working in Controlled or Restricted areas or any area on the flight line must be issued a specific contractor identification badge or be escorted.

2.11 AT LEVEL 1 TRAINING

Prior to start of construction Contractor’s Onsite Manager shall complete Antiterrorism Awareness Level 1 Training via https://jkodirect.jten.mil selecting Non-CAC user. Onsite Manager shall review requirements with all workers and keep onsite the updated government provided form.

2.12 PERFORMANCE OF SERVICE DURING CRISIS OR HEIGHTENED SECURITY

In the event of crisis or heightened security caused by a national emergency, natural disaster, or other cause, continue performance as required in support of the Air Force mission. The Contract price and delivery schedule may be adjusted to reflect any change of work that may be directed. This service is not determined to be essential for performance during crisis according to DODI 3020.37.

2.13 SPECIAL QUALIFICATIONS

Contractor shall provide the name and telephone number of the Contractor’s on-site contract manager and alternate. The Contractor’s on-site manager and alternate must both be able to speak and write in the English language. Wither the on-site manager or alternate must be present on site at all times to provide quality control and oversite of project operations.

2.14 INTERFACES

Do not unduly interfere with regularly scheduled Government operational activities in the performance of contract requirements. In the event a Government supervisor so requests, temporarily cease work in the area and report the instructions, to include name of the Government person involved, to the COR immediately by the most expedient means. Notify the COR verbally of disputes with customers or other base contractors and follow-up in writing.

2.15 WORK CLEARANCE/DIG PERMIT REQUESTS

Contractor shall obtain an approved Work Clearance Request, AF Form 103, for all work which involves excavation including minor digging. Blank digging permits are available from the 163d CES Operations Section and must be routed through the 452d CES and other on- base parties as listed on the form. The approval process takes roughly two weeks to complete.

2.16 SAFETY REQUIREMENTS AND REPORTS

Contractor shall perform work in a safe manner as required by OSHA Safety and Health Requirements. Provide a verbal report to the COR as soon as possible of each occurrence of damage to Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of required Accident Investigation Reports to the COR within five calendar days of each occurrence.

2.17 PARTNERING AGREEMENT

COR may require a partnering agreement between the Government and Contractor to facilitate joint cooperation and a sound partnership of all parties involved in the execution of this contract.

Partnering is the creation of a Government-Contractor relationship that promotes achievement of mutually beneficial goals. It involves an agreement in principal to share the risk involved in completing the project and to establish and promote a nurturing partnership environment.

Representatives from each organization are encouraged to participate in developing a partnering agreement. The partnering agreement that results may be formal or informal. If formal, it should be reduced to writing and signed by the parties involved.

STAGING

PARKING

CACTUS AVE

VISITOR

CENTER

2339 2315

PROJECT

MEYER DR

GRAEBER ST

CALIFORNIA AIR NATIONAL GUARD

163 CIVIL ENGINEERIN SQUADRON

MARCH AIR RESERVE BASE

N

AREA PLANS 129 MAY 2024

CARPET & PAINT

BUILDING 2272 PDPG242858

AutoCAD SHX Text G

AutoCAD SHX Text "4"

NOTES

1. MOVE FURNITURE AS REQUIRED

2. DEMO CARPET TILE. REMOVE TACKTILES. PROTECT IN PLACE VAPOR BARRIER MEMBRANE,

3.25" TIGHTLOCK CARPET BASE & CORRIDOR TRANSITIONS

3. DEMO 4" COVED RUBBER BASE AT CORRIDORS & VESTIBULES

4. CLIMATIZE ALL MATERIAL IN BUILDING FOR 1 WEEK PRIOR TO INSTALL

5. PROVIDE CARPET TILE USING TACTILES ONLY

~3,880 SF OFFICE AREA: INTERFACE CUBIC 6393 HEIGHT, NO EQ

~200 SF VESTIBULES: INTERFACE SR799 ONYX, NO EQ

6. PROVIDE RUBBER BASE AT RUBBER TILE CORRIDORS

~750 LF - TARKETT TIGHTLOCK RESILENT 4.375" - 82 BLACK PEARL, NO EQ.

6. PROVIDE RUBBER BASE AT CARPET TILE VESTIBULES

~60 LF - TARKETT TIGHTLOCK CARPET 4.25" - 82 BLACK PEARL, NO EQ.

7. PROVIDE TRANSITION AT VESTIBULES & BREAKROOM - TARKETT SLT-XX-A BLACK OR EQ

16'8'

CALIFORNIA AIR NATIONAL GUARD

163 CIVIL ENGINEERIN SQUADRON

MARCH AIR RESERVE BASE

N

CARPET PLAN 229 MAY 2024

BUILDING 2272 PDPG242858

NOTES

1. MOVE FURNITURE AS REQD

2. PROTECT EXISTING

3. CARPET TO BE REPLACED

4. RUBBER FLOOR IN CORRIDORS TO REMAIN

5. RUBBER BASE IN OFFICES TO REMAIN

6. RUBBER BASE IN CORRIDORS & VESTIBULES TO BE REMOVED BY FLOORING CTR

7. PATCH HOLES & TEXTURE EXISTING & NEW PATCHED HOLES TO MATCH & PREP WALLS

8. EXISTING WALLS ARE HALF WHITE HALF TAN

9. PAINT WALLS & WOOD WINDOW SILLS BEHR 75 POLAR BEAR EGGSHELL OR EQ

OFFICES ~800 LF X 9'H = ~7,200 SF LESS DOORS & WINDOWS

CORRIDORS ~800 LF X 9'H = ~7,200 SF LESS DOORS & WINDOWS

16'8'

CALIFORNIA AIR NATIONAL GUARD

163 CIVIL ENGINEERIN SQUADRON

MARCH AIR RESERVE BASE

N

PAINT PLAN 329 MAY 2024

BUILDING 2272 PDPG242858

File details come from the government source that posted it. Updated .