08-1N8804 Hot Mix Asphalt_ Imported borrow and Signal and Lighting System.pdf
PDF 810 KB Posted
- Solicitation number
- 08-1N8804, Fed #HSNHG-P062(047)
- Issued by
- Riverside County, California
About this file
This is a Notice to Bidders and Special Provisions document issued by the California Department of Transportation (Caltrans) District 8 for a highway construction project in Riverside County. The project involves hot mix asphalt paving, imported borrow material, and installation of signal and lighting systems on State Route 62 in Desert Hot Springs, extending from 0.3 mile south to 0.4 mile north of Pierson Boulevard (Post Mile R3.0/R3.7). The work is identified as Contract No. 08-1N8804, Federal-Aid Project HSNHG-P062(047), with a project ID of 0823000063. Bids are due electronically by 2:00 p.m. on Wednesday, December 2, 2026, via the Bid Express website. The contractor must hold either a Class A license or a combination of Class C licenses (C-10, C-12) constituting a majority of the work. The project includes 73 bid items ranging from lead compliance planning and traffic control systems to asphalt placement, drainage infrastructure, concrete work, pavement markings, and electrical systems. Work must be completed within 90 working days from notice of contract approval.
The estimated project cost is $3,530,000, with bids required on a unit price basis and bidder's security equal to at least 10 percent of the bid amount. Prevailing wages are required and must comply with the higher of California Department of Industrial Relations wage rates or federal minimum wage determinations. The project is subject to Buy America requirements for iron, steel, manufactured products, and construction materials, with a De Minimis Costs waiver available when non-compliant materials do not exceed the lesser of $1,000,000 or 5 percent of total applicable project costs. Environmental product declarations are required for hot mix asphalt and concrete materials supplied by plants providing specified minimum quantities. The contract includes extensive environmental stewardship requirements, including protection measures for desert tortoise, burrowing owls, Le Conte's thrasher, and other regulated species within Species Protection Areas. Traffic control restrictions apply with liquidated damages of $1,000 per 10-minute interval for closure violations. The project is funded as a federal-aid highway project and includes requirements for contractor-supplied biological monitoring, stormwater pollution prevention planning, and treated wood waste management.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bids open Wednesday, December 2, 2026 Dated October 19, 2026
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION
NOTICE TO BIDDERS
AND
SPECIAL PROVISIONS
FOR CONSTRUCTION ON STATE HIGHWAY IN RIVERSIDE COUNTY IN
DESERT HOT SPRINGS FROM 0.3 MILE SOUTH TO 0.4 MILE NORTH OF
PIERSON BOULEVARD
In District 08 On Route 62
Under Bid book dated October 19, 2026 Standard Specifications dated 2025
Project plans approved August 7, 2026 Standard Plans dated 2025
Identified by Contract No. 08-1N8804
08-Riv-62-R3.0/R3.7 Project ID 0823000063
Federal-Aid Project
HSNHG-P062(047)
SPECIAL NOTICES
• See sections 2 and 3 for contractors' registration requirements.
• The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.
• See section 2 for submittal requirements for DVBE quotes and Non–Small Business
Subcontractor Preference.
• For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).
• See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.
• The flagging and temporary traffic control requirements have been revised. See sections 7-
1.03, 7-1.04, and 12.
• See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.
• See section 14-11.14 for changes to the management of treated wood waste.
• See section 6-1.01 and 6-1.04 of these Special Provisions for the requirements of Buy
America/Build America for manufactured products.
• See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.
Contract No. 08-1N8804 i
TABLE OF CONTENTS
NOTICE TO BIDDERS
BID ITEM LIST
SPECIAL PROVISIONS
ORGANIZATION
DIVISION I GENERAL PROVISIONS
2 BIDDING
5 CONTROL OF WORK
6 CONTROL OF MATERIALS
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
8 PROSECUTION AND PROGRESS
9 PAYMENT
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
13 WATER POLLUTION CONTROL
14 ENVIRONMENTAL STEWARDSHIP
DIVISION III EARTHWORK AND LANDSCAPE
17 GENERAL
19 EARTHWORK
21 EROSION CONTROL
DIVISION V SURFACINGS AND PAVEMENTS
39 ASPHALT CONCRETE
DIVISION VIII MISCELLANEOUS CONSTRUCTION
73 CONCRETE CURBS AND SIDEWALKS
DIVISION IX TRAFFIC CONTROL DEVICES
81 MISCELLANEOUS TRAFFIC CONTROL DEVICES
84 MARKINGS
DIVISION X ELECTRICAL WORK
86 GENERAL
87 ELECTRICAL SYSTEMS
ii
STANDARD PLANS LIST
The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.
RSP A3A Abbreviations (Sheet 1 of 3)
RSP A3B Abbreviations (Sheet 2 of 3)
RSP A3C Abbreviations (Sheet 3 of 3)
A10A Legend - Lines and Symbols (Sheet 1 of 5)
A10B Legend - Lines and Symbols (Sheet 2 of 5)
A10C Legend - Lines and Symbols (Sheet 3 of 5)
A10D Legend - Lines and Symbols (Sheet 4 of 5)
A10E Legend - Lines and Symbols (Sheet 5 of 5)
A20A Pavement Markers and Traffic Lines - Typical Details
A20B Pavement Markers and Traffic Lines - Typical Details
A20C Pavement Markers and Traffic Lines - Typical Details
A20D Pavement Markers and Traffic Lines - Typical Details
A20E Traffic Lines - Typical Details for Contrast Striping
A24A Pavement Markings - Arrows
A24B Pavement Markings - Arrows and Symbols
A24D Pavement Markings - Words
A24F Pavement Markings - Crosswalks
A24G Pavement Markings - Yield Lines, Limit Lines, and Wrong Way Details
A62A Excavation and Backfill - Miscellaneous Details
A62F Excavation and Backfill - Metal and Plastic Culverts
A73B Markers
A73C Delineators, Channelizers and Barricades
A74 Survey Monuments
A84A Temporary Desert Tortoise Fence
A87A Curbs and Driveways
A87B Hot Mix Asphalt Dikes
P70 Hot Mix Asphalt Paving (Longitudinal Tapered Notched Wedge Joint)
P76 Pavement Edge Treatments - New Construction
D72B CIP Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D72C CIP Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D72F CIP Drainage Inlet Notes iii
D72G CIP Drainage Inlet Tables
D74 Drainage Inlet Details
D77B Grate Details No. 2
D78C Inlet Depressions - Hot Mix Asphalt Shoulders
D88 Construction Loads on Culverts
D94A Metal and Plastic Flared End Sections
D97A Corrugated Metal Pipe Coupling Details No. 1 - Annular Coupling Band, Bar and Strap, and Angle Connections
D97C Corrugated Metal Pipe Coupling Details No. 3 - Helical and Universal Couplers
D97D Corrugated Metal Pipe Coupling Details No. 4 - Hugger Coupling Bands
D97E Corrugated Metal Pipe Coupling Details No. 5 - Standard Joint
D97F Corrugated Metal Pipe Coupling Details No. 6 - Positive Joint
T1A Temporary Crash Cushion - Sand Filled (Unidirectional)
T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)
T1B Temporary Crash Cushion - Sand Filled (Bidirectional)
T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)
RSP T3A Temporary Railing (Type K)
T3B Temporary Railing (Type K)
T3C Temporary Barrier System (Cross Bolt)
T3D Temporary Barrier System (Cross Bolt)
T3E Temporary Barrier System (Cross Bolt)
T3F Temporary Barrier System (Cal F-23)
T3F2 Temporary Barrier System (Cal F-23)
T3G Temporary Barrier System (Staking or Anchoring)
T3G2 Temporary Barrier System (Staking or Anchoring)
RSP T5 Temporary Terminal Section (Type K)
T9 Traffic Control System Tables for Lane and Ramp Closures
T10 Traffic Control System for Lane Closure on Freeways and Expressways
RSP T11 Traffic Control System for Lane Closure on Multilane Conventional Highways
T11A Traffic Control System for Changeable Lane Closure on Multilane Conventional Highways and Expressways
T21 Traffic Control System - Construction Work Zone Speed Limit Reduction Twenty- Four Hours a Day 7 Days a Week (24/7)
T55 Temporary Water Pollution Control Details (Temporary Erosion Control Blanket)
T56 Temporary Water Pollution Control Details (Temporary Fiber Roll)
T58 Temporary Water Pollution Control Details (Temporary Construction Entrance)
T61 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection) iv
T62 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T63 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T64 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
RS1 Roadside Signs - Typical Installation Details No. 1
RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2
RS3 Roadside Signs - Laminated Wood Box Post - Typical Installation Details No. 3
RS4 Roadside Signs - Typical Installation Details No. 4
S93 Framing Details for Framed Single Sheet Aluminum Signs, Rectangular Shape
S94 Roadside Framed Single Sheet Aluminum Signs, Rectangular Shape
S95 Roadside Single Sheet Aluminum Signs, Diamond Shape
ES-1A Electrical Systems (Legend)
ES-1B Electrical Systems (Legend)
ES-1C Electrical Systems (Legend)
ES-2A Electrical Systems (Service Equipment)
ES-2F Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - C Series)
ES-3C1 Electrical Systems (Controller Cabinet Foundation and Pad Details)
ES-3C2 Electrical Systems (Controller Cabinet Foundation Details)
ES-3K Electrical Systems (Electronics Assembly Connection Diagram) (Battery Backup System)
ES-4A Electrical Systems (Signal Head Mounting)
ES-4B Electrical Systems (Pedestrian Signal Heads)
ES-4C Electrical Systems (Signal Heads and Mountings)
ES-4D Electrical Systems (Signal Head Mounting)
ES-4E Electrical Systems (Signal Heads)
ES-5B Electrical Systems (Detectors)
ES-5C Electrical Systems (Accessible Pedestrian Signal and Push Button Assemblies)
ES-5D Electrical Systems (Curb and Shoulder Termination, Trench, and Handhole Details)
ES-6G Electrical Systems (Lighting Standard, Type 32)
ES-7A Electrical Systems (Signal and Lighting Standard, Type TS, and Type 2 Post)
ES-7B Electrical Systems (Signal and Lighting Standard, Type 1 and Equipment Identification Characters)
ES-7C Electrical Systems (Signal and Lighting Standard, Case 1 Signal Mast Arm Loading, Wind Velocity = 100 mph and Signal Mast Arm Lengths 15' to 30')
ES-7E Electrical Systems (Signal and Lighting Standard, Case 3 Signal Mast Arm Loading, Wind Velocity = 100 mph and Signal Mast Arm Lengths 15' to 45')
ES-7F Electrical Systems (Signal and Lighting Standard, Case 4 Signal Mast Arm Loading, Wind Velocity = 100 mph and Signal Mast Arm Lengths 25' to 45')
ES-7J Electrical Systems (Flashing Beacon on a Type 1, Type 15-FBS, and Type 40 Standard) v
ES-7M Electrical Systems (Signal and Lighting Standard, Details No. 1)
ES-7N Electrical Systems (Signal and Lighting Standard, Details No. 2)
RSP ES-7O Electrical Systems (Signal and Lighting Standard, Details No. 3)
ES-7R Electrical Systems (Signal and Lighting Attachments)
ES-8A Electrical Systems (Non-Traffic Pull Box)
ES-8B Electrical Systems (Traffic Pull Box)
ES-13A Electrical Systems (Splice Insulation Methods Details)
ES-13B Electrical Systems (Kinking and Banding Detail)
ES-15D Electrical Systems (Lighting and Sign Illumination Control)
CANCELED STANDARD PLANS LIST
The 2025 standard plan sheets listed below are canceled and not applicable to this contract.
Plan No. Date Canceled Plan No. Date
Canceled Plan No. Date Canceled
P8 04-20-26
NOTICE TO BIDDERS
Bids open Wednesday, December 2, 2026
Dated October 19, 2026
General work description: Hot Mix Asphalt, imported borrow and signal and lighting system.
The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON
STATE HIGHWAY IN RIVERSIDE COUNTY IN DESERT HOT SPRINGS FROM 0.3 MILE SOUTH TO
0.4 MILE NORTH OF PIERSON BOULEVARD.
District-County-Route-Post Mile: 08-Riv-62-R3.0/R3.7
Contract No. 08-1N8804
The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-10, C-12.
Federal-aid project no.:
HSNHG-P062(047)
Bids must be on a unit price basis.
Complete the work within 90 working days.
The estimated cost of the project is $3,530,000.
The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.
The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.
For bid results go to:
https://ppmoe.dot.ca.gov/cc
Select Electronic Bidding under the Bidding tab.
District office addresses are provided in the Standard Specifications.
Present bidders' inquiries to the Department and view the Department's responses at:
https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries
Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.
Submit your bid with bidder's security equal to at least 10 percent of the bid.
Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.
The federal minimum wage rates for this Contract as determined by the United States Secretary of Labor are available at https://sam.gov/content/home.
If the minimum wage rates as determined by the United States Secretary of Labor differs from the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors must not pay less than the higher wage rate. The Department does not accept lower State wage rates not specifically included in the federal minimum wage determinations. This includes helper, or other classifications based on hours of experience, or any other classification not appearing in the federal wage determinations. Where federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors must not pay less than the federal minimum wage rate that most closely approximates the duties of the employees in question.
The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.
Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.
Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.
Department of Transportation
BID ITEM LIST
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM
0002 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 90
0003 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM
0004 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM
0005 120103 STATIONARY IMPACT ATTENUATOR VEHICLE DAY 70
0006 120159 TEMPORARY TRAFFIC STRIPE (PAINT) LF 2,600
0007 120165 CHANNELIZER (SURFACE MOUNTED) EA 48
0008 120300 TEMPORARY PAVEMENT MARKER EA 57
0009 120320 TEMPORARY BARRIER SYSTEM LF 3,280
0010 128651 PORTABLE CHANGEABLE MESSAGE SIGN (EA) EA 8
0011 129108 TEMPORARY CRASH CUSHION TL-3 EA 4
0012 129152 TEMPORARY RADAR SPEED FEEDBACK SIGN
SYSTEM
EA 2
0013 130100 JOB SITE MANAGEMENT LS LUMP SUM
0014 130301 STORMWATER POLLUTION PREVENTION PLAN LS LUMP SUM
0015 130312 PRE-STORM EVENT INSPECTION REPORT EA 9
0016 130323 DURING-AND POST-STORM EVENT INSPECTION
REPORT
DAY 4
0017 130331 STORMWATER ANNUAL REPORT EA 1
0018 130560 TEMPORARY SOIL BINDER SQYD 9,700
0019 130620 TEMPORARY DRAINAGE INLET PROTECTION EA 3
0020 130640 TEMPORARY FIBER ROLL LF 750
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0021 130710 TEMPORARY CONSTRUCTION ENTRANCE EA 1
0022 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM
0023 141120 TREATED WOOD WASTE LB 2,660
0024 146002 CONTRACTOR-SUPPLIED BIOLOGIST (LS) LS LUMP SUM
0025 170103 CLEARING AND GRUBBING (LS) LS LUMP SUM
0026 190101 ROADWAY EXCAVATION CY 610
0027 198010 IMPORTED BORROW (CY) CY 1,850
0028 210010 MOVE-IN/MOVE-OUT (EROSION CONTROL) EA 1
0029 210252 BONDED FIBER MATRIX (SQFT) SQFT 95,600
0030 260203 CLASS 2 AGGREGATE BASE (CY) CY 700
0031 390100 PRIME COAT TON 3.8
0032 390132 HOT MIX ASPHALT (TYPE A) TON 1,590
0033 394076 PLACE HOT MIX ASPHALT DIKE (TYPE E) LF 320
0034 397005 TACK COAT TON 1
0035 398000 REMOVE ASPHALT CONCRETE PAVEMENT (CY) CY 12
0036 510094 STRUCTURAL CONCRETE, DRAINAGE INLET CY 11
0037 510526 (F) - MINOR CONCRETE (BACKFILL) CY 11
0038 665018 18" CORRUGATED STEEL PIPE (.109" THICK) LF 69
0039 665024 24" CORRUGATED STEEL PIPE (.109" THICK) LF 190
0040 705315 24" ALTERNATIVE FLARED END SECTION EA 1
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0041 710132 REMOVE CULVERT (LF) LF 19
0042 710150 REMOVE INLET EA 1
0043 723095 ROCK SLOPE PROTECTION (20 LB, CLASS I,
METHOD B) (CY)
CY 2.7
0044 729011 ROCK SLOPE PROTECTION FABRIC (CLASS 8) SQYD 8
0045 730070 DETECTABLE WARNING SURFACE SQFT 60
0046 731504 MINOR CONCRETE (CURB AND GUTTER) CY 23
0047 731507 MINOR CONCRETE (GUTTER DEPRESSION) CY 3.2
0048 731521 MINOR CONCRETE (SIDEWALK) CY 1.1
0049 750001 MISCELLANEOUS IRON AND STEEL LB 1,200
0050 803210 TEMPORARY DESERT TORTOISE FENCE LF 5,790
0051 810120 REMOVE PAVEMENT MARKER EA 170
0052 810230 PAVEMENT MARKER (RETROREFLECTIVE) EA 570
0053 820112 MARKER (CULVERT) EA 4
0054 820113 TREATMENT BEST MANAGEMENT PRACTICE
MARKER
EA 4
0055 820250 REMOVE ROADSIDE SIGN EA 17
0056 820300 REMOVE ROADSIDE SIGN (STRAP AND SADDLE
BRACKET METHOD)
EA 1
0057 820750 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.063"-UNFRAMED)
SQFT 350
0058 820760 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.080"-UNFRAMED)
SQFT 140
0059 820780 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.063"-FRAMED)
SQFT 110
0060 820840 ROADSIDE SIGN - ONE POST EA 23
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0061 820850 ROADSIDE SIGN - TWO POST EA 6
0062 820860 INSTALL SIGN (STRAP AND SADDLE BRACKET
METHOD)
EA 1
0063 840516 THERMOPLASTIC PAVEMENT MARKING
(ENHANCED WET NIGHT VISIBILITY)
SQFT 2,090
0064 846007 6" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY)
LF 21,600
0065 846009 8" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY)
LF 400
0066 846013 12" THERMOPLASTIC TRAFFIC STRIPE
(ENHANCED WET NIGHT VISIBILITY)
LF 1,090
0067 846030 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 21,400
0068 846035 REMOVE THERMOPLASTIC PAVEMENT
MARKING
SQFT 730
0069 847218 6" TRAFFIC STRIPE TAPE WITH CONTRAST
(WARRANTY)
LF 1,250
0070 870200 LIGHTING SYSTEM LS LUMP SUM
0071 870400 SIGNAL AND LIGHTING SYSTEM LS LUMP SUM
0072 870700 FLASHING BEACON SYSTEM LS LUMP SUM
0073 999990 MOBILIZATION LS LUMP SUM
SPECIAL PROVISIONS
ORGANIZATION
Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.
Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.
Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.
DIVISION I GENERAL PROVISIONS
2 BIDDING
Add between the 1st and 2nd paragraphs of section 2-1.06B:
The Department makes the following supplemental project information available:
Supplemental Project Information Means Description
Included in the Information Handout 1. Materials Report
2. Warranty Bond (TOTE-1) Form
3. Survey Monument
Available as specified in the Standard Specifications
1. 08-1N8804 OG-Surface.xml
2. 08-1N8804 Design-Profile-AlignmentA1_LINE.xml
3. 08-1N8804 Design-Profile-AlignmentA2_LINE.xml
4. 08-1N8804 OG-Surface-AlignmentA_LINE.xml
5. 08-1N8804 OG-Surface-AlignmentB_LINE.xml
6. 08-1N8804 CrossSections-A1_LINE.pdf
7. 08-1N8804 CrossSections-A2_LINE.pdf
Delete section 2-1.20.
Delete section 2-1.33B(2)(b).
5 CONTROL OF WORK
Delete section 5-1.13B.
Replace section 5-1.13E with:
5-1.13E Prompt Payment Section 5-1.13E applies to all contracts.
Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.
Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:
1. Subcontractor’s or entity’s business name
2. Description of work performed
2.1. Bid item numbers or change order numbers
2.2. Written narrative of work performed
3. Value of work performed
4. Amount paid to subcontractor or entity
5. Withhold amount, if applicable
6. Explanation of withhold reasoning, if applicable
Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.
If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:
1. Value of the disputed work
2. Amount of the withhold being taken
3. Bid item numbers or change order numbers associated with the disputed work
4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated
5. Corrective actions to be taken for release of withheld amount
The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.
The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:
1. Withhold was not applied in good faith
2. Requested additional withhold documentation records were not provided
3. Payment information was not submitted through the prompt payment monitoring system
4. Required withhold notification was not provided
The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.
Add to the end of section 5-1.32:
Personal vehicles of your employees must not be parked on the traveled way or shoulders, including sections closed to traffic.
6 CONTROL OF MATERIALS
Add to end of section 6-1.01:
If you fail to submit the form for materials subject to Buy America, the Department may:
1. Withhold from the next progress payment
2. Reject your request for a De Minimis Costs waiver for non-compliant construction materials or manufactured products
Add to the beginning of section 6-1.02:
The Department furnishes you with:
1. Controller assemblies for traffic signals,
1.1. 2070 LX controller
1.2. Model 200
1.3. Model 222
1.4. Model 242L
2. Model 2070-7G Card (GPS)
3. Electronics assembly for battery backup systems as follows:
3.1. Inverter/charger unit
3.2. Power transfer relay
3.3. Manually-operated bypass switch
3.4. Battery harness
3.5. Utility interconnect wires
3.6. Battery temperature probe
3.7. Relay contact wires
The Department furnishes you with Model 342LX completely wired controller cabinets with auxiliary equipment but without controller unit at District 8 – Electrical Construction, 13970 Victoria Street, Fontana, CA 92336. At least 48 hours before you pick up the materials, inform the Engineer of what you will pick up and when you will pick it up.
Replace section 6-1.03B with:
6-1.03B Submittals 6-1.03B(1) General Not Used
6-1.03B(2) Work Plan For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:
1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).
2. Land use history of the local material location and surrounding property
3. Sampling protocol
4. Number of samples per volume of local material
5. QA and QC requirements and procedures
6. Qualifications of sampling personnel
7. Stockpile history
8. Name and address of the analytical laboratory that will perform the chemical analyses
9. Analyses that will be performed for lead and pH
10. Other analyses that will be performed for possible hazardous constituents based on:
10.1. Source property history
10.2. Land use adjacent to source property
10.3. Constituents of concern in the ground water basin where the job site is located
The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.
If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.
6-1.03B(3) Analytical Test Results At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:
1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.
2. Chain of custody of samples
3. Analytical results no older than 1 year
4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit
5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location
6-1.03B(4) Sample and Analysis Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:
1. Before bringing the local material to the job site
2. As described in the local material plan
3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)
The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.
Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:
Minimum Number of Samples and Analytical Tests for Local Material Maximum volume of imported borrow
(cu yd) Minimum number of samples and analytical tests
< 5,000 8
5,000–10,000 12 for the first 5,000 cu yd plus 1 for each additional 1,000 cu yd or portion thereof
10,000–20,000 17 for the first 10,000 cu yd plus 1 for each additional 2,500 cu yd or portion thereof
20,000-40,000 21 for the first 20,000 cu yd plus 1 for each additional 5,000 cu yd or portion thereof
40,000–80,000 25 for the first 40,000 cu yd plus 1 for each additional 10,000 cu yd or portion thereof
> 80,000 29 for the first 80,000 cu yd plus 1 for each additional 20,000 cu yd or portion thereof
Do not collect composite samples or mix individual samples to form a composite sample.
Analyze the samples using the US EPA's ProUCL software with a 95 percent upper confidence limit. All chemical analysis must be performed by a laboratory certified by the SWRCB's Environmental Laboratory Accreditation Program (ELAP).
The analytical test results must demonstrate that the local material:
1. Is not a hazardous waste
2. Has a pH above 5.0
3. Has an average total lead concentration, based upon the 95 percent upper confidence limit, at or below 80 mg/kg
4. Is free of possible contaminants identified in the local material plan
5. Complies with the RWQCB's basin plan for the job site location 6 Complies with the RWQCB's water quality objectives for the job site location
6-1.03C Local Material Management Do not place local material until authorized.
If the Engineer determines the appearance, odor, or texture of any delivered local material suggests possible contamination, sample and analyze the material. The sampling and analysis is change order work unless (1) hazardous waste is discovered or (2) the analytical test results indicate the material does not comply with section 6-1.03B(3).
Dispose of noncompliant local material at an appropriately permitted CA Class I, CA Class II or CA Class III facility. You are the generator of noncompliant local materials.
Replace section 6-1.04 with:
6-1.04 BUY AMERICA
6-1.04A General Buy America requirements do not apply to the following:
1. Tools and construction equipment used in performing the work.
2. Temporary work that is not incorporated into the finished project.
An article, material, or supply to be permanently incorporated in the project should only be classified into one of the following categories:
1. Iron or steel products
2. Manufactured products
3. Construction materials
4. Excluded materials
Excluded materials means cement and cementitious materials; aggregates such as stone, sand, or gravel; or aggregate binding agents or additives.
6-1.04B Crumb Rubber (Pub Res Code § 42703(d)) Furnish crumb rubber with a certificate of compliance. Crumb rubber must be:
1. Produced in the United States
2. Derived from waste tires taken from vehicles owned and operated in the United States
6-1.04C Iron or Steel Products Iron or steel products must be melted and manufactured in the United States except:
1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials
2. If the total combined cost of the materials produced outside the United States does not exceed the greater of 0.1 percent of the total bid or $2,500, the material may be used if authorized
Furnish iron or steel products to be incorporated into the work with certificates of compliance and certified mill test reports. Mill test reports must indicate where the steel and iron were melted and manufactured.
All melting and manufacturing processes for these materials, including an application of a coating, must occur in the United States. Coating includes all processes that protect or enhance the value of the material to which the coating is applied.
6-1.04D Manufactured Products Manufactured products mean articles, materials, or supplies that have been:
1. Processed into a specific form and shape; or
2. Combined with other articles, materials, or supplies to create a product with different properties than the individual articles, materials, or supplies
Per 23 CFR 635.410, these products must be manufactured in the United States.
Manufacturer, in the case of manufactured products, means the entity that performs the final manufacturing process by bringing individual elements together that produces a manufactured product.
If an item is classified as an iron or steel product, a construction material, or an excluded material under the definitions set forth under this Buy America section, then it is not a manufactured product. However, an article, material, or supply classified as a manufactured product under this Buy America section may include components that are construction materials, iron or steel products, or excluded materials.
Iron or steel used in precast concrete manufactured products or enclosures for Intelligent Transportation Systems (ITS) must meet the requirements of section 6-1.04C regardless of the amount used.
Iron or steel used in other manufactured products must meet the requirements of section 6-1.04C if the cost of steel and iron components is 50 percent or more of the total cost of the manufactured product.
Furnish manufactured products to be incorporated into the work with certificates of compliance with each project delivery. The manufacturer's certificate of compliance must identify where the manufacturing occurred and attest specifically to compliance with the 23 CFR 635.410 standard.
6-1.04E Construction Materials The following construction materials must be produced in the United States under standards in 2 CFR 184.6:
1. Non-ferrous metals
2. Plastic and polymer-based products such as:
2.1. Polyvinylchloride
2.2. Composite building materials
3. Glass
4. Fiber optic cable including drop cable
5. Optical fiber
6. Lumber
7. Engineered wood
8. Drywall
All manufacturing processes for these materials as defined in 2 CFR 184.6 must occur in the United States.
Furnish construction materials to be incorporated into the work with certificates of compliance with each project delivery. Manufacturer’s certificate of compliance must identify where the construction material was manufactured and attest specifically to compliance with the 2 CFR 184.6 standard.
Minor additions of articles, materials, supplies, or binding agents to these construction materials do not change the categorization of the construction material.
6-1.04F Buy America Waiver for the De Minimis Costs for Manufactured Products and Construction Materials A De Minimis Costs waiver can waive the application of FHWA's Buy America requirements for manufactured products and construction materials under a single project when the total cost of non-compliant manufactured products and construction materials is no more than the lesser of $1,000,000 or 5 percent of the total applicable costs for the project.
The percentage threshold is calculated based on the following formula:
X = NC / TA
where:
X = percent threshold NC = total cost of non-compliant construction materials and manufactured products TA = total applicable project costs (steel, iron, construction materials and manufactured products;
does not include excluded materials)
This threshold is based on the actual cost of the steel, iron, construction materials, and manufactured products, not the anticipated cost of those materials. The contractor must account for compliant and non-compliant Department-Furnished Materials for the project in the De Minimis Costs Waiver Worksheet calculation if provided by the Department as supplemental project information.
See further instructions for the De Minimis Costs waiver request in the Notice of Materials to be Used form.
Add to section 6-1:
6-1.08 ENVIRONMENTAL PRODUCT DECLARATIONS FOR HOT MIX ASPHALT AND CONCRETE
Section 6-1.08 includes specifications for environmental product declarations for hot mix asphalt and concrete materials and products.
See section 6-1.06B for definitions.
For projects with bid opening dates after February 1, 2025, with a total bid over $1 million and 175 or more original working days, materials or products specified in the following table require facility-specific, product stage, environmental product declarations as informational submittals:
Material or product Material specifications Hot mix asphalta Section 39-2, "Hot Mix Asphalt"
Excludes RHMA, OGFC, and BWC materials.
Concreteb Section 28-2, "Lean Concrete Bases," Section 28-3, "Rapid
Strength Concrete Base," Section 28-4, "Lean Concrete Base Rapid Setting," Section 28-5, "Concrete Base," Section 40, "Concrete Pavement," Section 47-5, "Type 6 Retaining Walls," Section 49-3, "Cast-In-Place Concrete Piling," Section 49-4, "Steel Soldier Piling," Section 51, "Concrete Structures," Section 58-2, "Masonry Block," Section 73, "Concrete Curbs and Sidewalks," Section 83, "Railings and Barriers," and Section 99, "Building Construction."
Excludes volumetric-proportioned rapid strength concrete and Section 90-4 PC concrete members.
aFor each hot mix asphalt plant providing 2,250 tons or more on the project by job mix formula.
bFor each concrete plant providing 250 cubic yards or more on the project by mix design.
The requirements in section 6-1.08 do not apply to seasonal plants operating fewer than 6 months per year.
The requirements in section 6-1.08 do not apply to informal-bid contracts.
For product category rules for hot mix asphalt or concrete, go to the METS website. Use the product category rule in effect on the date of bid opening unless otherwise authorized. An environmental product declaration for hot mix asphalt or concrete is not required for either of the following conditions:
1. Applicable product category rule has expired without replacement as of the bid opening date.
2. Applicable product category rule was issued less than 50 days before the bid opening date.
Immediately notify the Engineer if a program operator has determined their product category rule does not allow for development of a facility-specific environmental product declaration. Include written correspondence from the program operator with your notification to the Engineer. If the Engineer determines the development of a facility-specific environmental product declaration cannot be achieved, an environmental product declaration will not be required for that material or product.
You must register on the Department’s Data Interchange for Materials Engineering (DIME) at least 15 days before submitting environmental product declarations. Follow the registration process at:
https://dime.dot.ca.gov/
Within 30 days of initial placement of each applicable material or product, submit a facility-specific, product stage, environmental product declaration informational submittal to DIME and provide proof of submission in PDF file format to the Engineer. The DIME entry information must include intended use of materials and estimated quantities of materials to be used as represented by the environmental product declaration.
Failure to provide a required environmental product declaration informational submittal will result in a $6,000 performance failure withhold for each missing declaration. The Department returns the withhold within 30 days after receipt of the compliant declaration if submitted prior to Contract acceptance.
Withholds become permanent deductions if the declaration is not submitted before Contract acceptance.
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Replace Section 7-1.02K(6)(j)(iii) with:
7-1.02K(6)(j)(iii) Unregulated Earth Material Containing Lead Section 7-1.02K(6)(j)(iii) includes specifications for handling, removing, and disposing of unregulated earth material containing lead. Management of this material exposes workers to health hazards that must be addressed in your lead compliance plan. This material contains average lead concentrations below 80 mg/kg total lead and below 5 mg/L soluble lead and is not regulated by DTSC as a hazardous substance or a hazardous waste. This material does not require disposal at a permitted landfill or solid waste disposal facility. The RWQCB has jurisdiction over reuse of this material at locations outside the job site limits.
Unregulated earth material exists throughout the job site.
Lead is typically found within the top 2 feet of material within the highway. Reuse all of the excavated material on the right-of-way.Handle the material under all applicable laws, rules, and regulations, including those of the following agencies:
1. Cal/OSHA
2. CA RWQCB, Region 7 – Colorado River
8 PROSECUTION AND PROGRESS
Replace the row for DBE and DVBE in the table in the 2nd paragraph of section 8-1.03 with:
DVBE Final utilization reports
Replace the row for Schedule in the table in the 2nd paragraph of section 8-1.03 with:
Schedule Baseline schedule and weekly statement of working days report
Replace section 8-1.04C with:
8-1.04C Delayed Start Section 8-1.04B does not apply.
Start job site activities within 180 days after receiving notice that the Contract has been approved by the Attorney General or the attorney appointed and authorized to represent the Department.
Do not start job site activities until the Department authorizes or accepts your submittal for:
1. Contractor-supplied biologist
2. Biological resource information program
3. CPM baseline schedule
4. WPCP or SWPPP, whichever applies
5. Contingency plan for opening closures to traffic
If the submittals for Contractor-supplied biologist and biological resource information program are authorized, you may enter the job site only to measure controlling field dimensions and locate utilities.
Do not start other job site activities until all the submittals from the above list are authorized or accepted and the following information is received by the Engineer:
1. Notice of Materials To Be Used form.
2. Written statement from the vendor that the order for electrical material has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.
You may start job site activities before the 180th day after Contract approval if you:
1. Obtain specified authorization or acceptance for each submittal before the 180th day
2. Receive authorization to start
Submit a notice 72 hours before starting job site activities. If the project has more than 1 location of work, submit a separate notice for each location.
Replace the 4th and 5th paragraphs of section 8-1.05 with:
The Engineer issues a weekly statement of working days report by the end of the following week. If you disagree with a weekly statement of working days report, submit an RFI within 5 business days of receipt of the report.
The weekly statement of working days report shows:
1. Working days and non–working days during the reporting week
2. Time adjustments
3. Calculations of work completion dates, including working days remaining
4. Controlling activities
Delete the 6th paragraph of section 8-1.05.
9 PAYMENT
Replace the 1st paragraph of section 9-1.11D with:
For progress payments, the total work completed for the TRO bid item is the number of working days shown for the pay period on the weekly statement of working days report.
Replace item 2 in the list in the paragraph of section 9-1.16C with:
2. Material cost exceeds either of the following:
2.1. $50,000
2.2. $25,000 if the requestor is certified as one or more of the following:
2.2.1. DVBE
2.2.2. Small business as certified by Department of General Services, Office of Small
Business and Disabled Veteran Business Enterprise Services
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
Add to section 12-3.11B(5)(b):
Provide two C50D(CA) construction project funding identification signs.
Legend for the type of project must read as follows:
Highway Improvement
Legend for the year of completion on project funding sign must read as follows:
YEAR OF COMPLETION: 2027
Replace section 12-3.22 with:
12-3.22 TEMPORARY CRASH CUSHIONS
12-3.22A General 12-3.22A(1) Summary Section 12-3.22 includes specifications for installing, repairing, replacing, maintaining, and removing temporary crash cushions.
12-3.22A(2) Definitions Not Used
12-3.22A(3) Submittals At least 10 days before installation, submit as informational submittal for each temporary crash cushion model:
1. Certificate of compliance
2. Two copies of the following:
2.1. Manufacturer’s installation and maintenance manual
2.2 Department approved manufacturer’s drawings from the Department’s Division of Safety
Programs website
3. Record of training provided by manufacturer for each person installing the temporary crash cushion
12-3.22A(4) Quality Assurance 12-3.22A(4)(a) General Not Used
12-3.22A(4)(b) Quality Control Temporary crash cushion must be installed under the manufacturer's instructions by personnel trained by the manufacturer.
Keep a copy of the manufacturer’s drawings, and installation and maintenance manual for each temporary crash cushion model at the job site during installation.
12-3.22B Materials 12-3.22B(1) General Temporary crash cushion must:
1. Be on the Authorized Materials List for highway safety features
2. Comply with MASH:
2.1. Test Level 3 (TL-3) for a posted speed limit 45 mph or greater
2.2. Test Level 2 (TL-2) for a posted speed limit less than 45 mph
Water-filled temporary crash cushion must:
1. Include all components required for attachment to temporary barrier or protected obstacle
2. Comply with the manufacturer's drawings shown on the Department’s Division of Safety Programs website
Each sand-filled temporary crash cushion module must be:
1. Colored standard yellow with a black lid
2. Free from structural flaws and objectionable surface defects
Sand for filling module must:
1. Be commercial quality, washed concrete sand
2. Contain no more than 5 percent water under California Test 226
3. Be clean when placed in the module
12-3.22B(2) Temporary Crash Cushions TL-3 Temporary crash cushion TL-3 must:
1. Comply with MASH TL-3
2. Be one of the following:
2.1. Water-filled temporary crash cushion gating, non-redirective system
2.2. Sand-filled temporary crash cushion module array
12-3.22B(3) Temporary Crash Cushions TL-2 Temporary crash cushion TL-2 must:
1. Comply with MASH TL-2
2. Be one of the following:
2.1. Water-filled temporary crash cushion gating, non-redirective system
2.2. Sand-filled temporary crash cushion module array
12-3.22C Construction 12-3.22C(1) General When activities expose traffic to fixed obstacles, protect traffic from the obstacles with temporary crash cushions.
You may use NCHRP Report 350 compliant temporary crash cushions before December 31, 2026.
Install temporary crash cushions under the manufacturer's instructions before:
1. Starting activities requiring the crash cushions.
2. Opening to traffic lanes adjacent to the protected obstacles.
Temporary crash cushions must not impede the flow of traffic or encroach on the traveled way.
Attach a Type R or Type P marker panel to the front of temporary crash cushions if the closest point to the traveled way is within 12 feet of the traveled way. Fasten marker panels firmly to crash cushions with commercial quality hardware or by other authorized methods.
Maintain temporary crash cushions in place at each location, including when work is not in progress.
Keep the area behind the temporary crash cushions clear of obstructions.
Repair damaged temporary crash cushions immediately. Remove and replace temporary crash cushions damaged beyond repair. Repair and replacement of temporary crash cushions damaged by traffic is change order work.
12-3.22C(2) Water-Filled Temporary Crash Cushions Place temporary crash cushions and a minimum 20 feet of temporary barrier at a parallel 2-foot offset from edge of traveled way.
Install temporary crash cushions adjacent to a:
1. Barrier at an offset distance 1 to 2 feet or 7 feet or greater from the barrier
2. Dike or curb at an offset distance 0 to 4 feet or 7-1/2 feet or greater from the dike or curb
12-3.22C(3) Sand-Filled Temporary Crash Cushions Do not use sand-filled temporary crash cushions for permanent installations.
Use the same type of sand-filled modules for each array. Fill each sand-filled module with sand under the manufacturer's instructions.
Securely fasten the top edge of a seal to the wall of the sand-filled module with a continuous strip of heavy-duty tape, when a seal is required.
You may place sand-filled temporary crash cushion modules on movable pallets or frames complying with the dimensions shown. The pallets or frames must provide a full-bearing base beneath the modules. Do not move the modules and supporting pallets or frames by sliding or skidding along the pavement or bridge deck.
Attach a Type R marker panel such that the top of the panel is 1 inch below the module lid. Attach a Type P marker panel such that the bottom of the panel rests upon the roadway surface or pallet surface when used.
You may remove sand-filled modules during the work shift for access to the work area if the exposed fixed obstacle is 15 feet or more from the nearest lane carrying traffic. Reset the modules before the end of the work shift.
A lateral move of a temporary crash cushion module is change order work if ordered and the repositioning is not shown.
Remove sand-filled temporary crash cushion modules, including sand, pallets or frames, and marker panels, at Contract acceptance.
12-3.22D Payment The payment quantity does not include:
1. Temporary crash cushions placed for public safety
2. Modules placed in excess of the number described
Add to the beginning of section 12-3.32C:
Place PCMSs at the locations shown and in advance of the 1st warning sign for each:
1. Stationary lane closure
2. Shoulder closure
3. Speed reduction zone
For 5 days starting on the day of signal activation, place 1 PCMS in each direction of travel and display the following message in all caps: Signal Ahead -- Prepare To Stop.
Add between the 9th and 10th paragraphs of section 12-3.32C:
Start displaying the message on the sign 30 minutes before closing the lane or shoulder or when directed by the Engineer.
Replace the table in the definition of designated holidays in section 12-4.02A(2) with:
Designated Holidays
Holiday Date observed New Year's Day January 1st Memorial Day Last Monday in May Independence Day July 4th Labor Day 1st Monday in September Thanksgiving Day 4th Thursday in November Christmas Day December 25th
Add to section 12-4.02A(2):
special days: Martin Luther King Jr. Day, Washington’s Birthday, Cesar Chavez Day, Good Friday thru Easter Sunday, Veterans Day, Day after Thanksgiving, December 20 thru January 2.
Replace the last paragraph of section 12-4.02A(3)(b) with:
The Department notifies you through LCS of authorized and unauthorized closures and imposes conditions for authorization. Coordination for all closure per Section 5-1.20 is mandatory and must occur at the closure request level. Requests that are not in compliance with the specifications will be rejected.
Do not submit blanket closure requests. Blanket closure request are defined as requests that propose closures for multiple work zones without detailed, phased breakdowns that are tied to a 3-week look ahead schedule.
Coordinate your closures with other projects’ closures to resolve conflicts between closures. If no resolution is reached your closure request may be rejected. Delays as a result of rejections are inexcusable delays.
Replace the 3rd paragraph of section 12-4.02C(1) with:
Do not simultaneously close consecutive ramps (including connectors) in the same direction of travel servicing 2 consecutive local streets or highways, unless authorized.
Add between the 4th and 5th paragraphs of section 12-4.02C(1):
Concurrent stationary closures must be more than 5 miles apart. Closure spacing is the distance between the last cone of the…