07A3980.Addendum_2.pdf

PDF 155 KB Posted

Attached to
Decking System Installation Services in Los Angeles County
Solicitation number
07A3980
Issued by
Los Angeles County, California

About this file

This is Addendum No. 2 issued by the California Department of Transportation (Caltrans) Division of Procurement and Contracts for IFB No. 07A3980 for Decking System Installation Services, dated March 16, 2016. The addendum addresses installation specifications for decking systems at two bridge locations: Rio Hondo Bridge requiring 48,000 sq ft of decking over 14 months, and LA River Bridge requiring 80,000 sq ft of decking over 10 months.

The addendum clarifies the installation process for both locations, specifying that spans will be installed sequentially rather than simultaneously. For Rio Hondo, each span is approximately 12,000 sq ft and will be installed with 100% containment wrapping, with the second span beginning installation approximately 2 weeks before the first span's completion. A similar process applies to the LA River location, where each span is approximately 10,000 sq ft. The installation follows a "leap frog" pattern where the first span is removed after the second span is fully installed and contained, continuing this process for all remaining spans.

View the file

Other files

File Type Posted
07A3980.Addendum_1.pdf PDF
07A3980.Addendum_4.pdf PDF
07A3980.Addendum_3.pdf PDF
07A3980.Addendum_5.pdf PDF
IFB_Bid_Package_07A3980.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

“Provide as safe, sustainable, integrated and efficient transportation system to enhance California’s economy and livability”

STATE OF CALIFORNIA------- BUSINESS, TRANSPORTATION AND HOUSING AGENCY EDMUND G. BROWN Jr., Governor

DEPARTMENT OF TRANSPORTATION

ADMINISTRATION

DIVISION OF PROCUREMENT AND CONTRACTS

P.O. BOX 942873, MS-65

SACRAMENTO, CA 94273-0001

PHONE (916) 227-6124

FAX (916) 227-6007

TTY 711

www.dot.ca.gov

Serious drought.

Help save water!

March 16, 2016

ADDENDUM NO. 2

Invitation For Bid (IFB) NO. :07A3980

Decking System Installation Services

The addendum is to answer questions presented through e-mail:

Question 1:

Line item 1 – Refers to 14 months of rental for 48,000 sqft for Rio Hondo. Each span on the bridge is approximately 12,000 sqft. Typically on a project like this we will have (2) spans installed (24,000 sqft) and each span will be leap frogged for the duration of the project. Can you please clarify?

Answer 1:

Attachment 1, Bid Proposal, line item 1: First span approximately 12,000 sq. ft, is installed and wrapped for 100% containment, approximately 2 weeks before first span is completed, Supervisor notifies the

Contractor, Contractor comes out and starts building second span, once second span is completely installed, and wrapped for 100% containment, first span then is removed, same process with the remaining spans.

Question 2:

Line item 6 – Refers to 10 months of rental for 80,000 sq. ft for LA River. Each span on the bridge is approximately 10,000 sq. ft. Typically on a project like this we will have (2) spans installed (20,000 sq

ft) and each span will be leap frogged for the duration of the project. Can you please clarify?

Answer 2:

Attachment 1, Bid Proposal, line item 6: First span approximately 10,000 sq. ft, is installed and wrapped for 100% containment, approximately 2 weeks before first span is completed, Supervisor notifies the

Contractor, Contractor comes out and starts building second span, once second span is completely installed, and wrapped for 100% containment, first span then is removed, same process with the remaining spans.

All other terms and conditions for this Invitation for Bid, dated March 1, 2016, remain the same.

Kathleen Stonetakai

Contract Analyst