06 FBNV 240017 DB Period of Performance.pdf
PDF 144 KB Posted
- Solicitation number
- FA487724QA029
About this file
This document is a Government Period of Performance for the FBNV240017 Upgrade PGS Fire Suppression Project. It outlines the projected and actual dates for various design and construction tasks over a 225-calendar day period of performance. The project calls for the design, plans, specifications, and installation of a new fire suppression system in a power generation shelter at Davis-Monthan Air Force Base in Tucson, Arizona.
The related federal contract opportunity is a pre-solicitation for a Firm Fixed Price contract under NAICS code 236220 (Commercial and Institutional Building Construction), with a small business size standard of $45,000,000. This is a 100% Women-Owned Small Business set-aside with the award based primarily on price and past performance. The solicitation is expected to be issued around July 13, 2024, with bids due by the closing date specified in the solicitation package. A site visit is tentatively scheduled for August 1, 2024 and a bid bond will be required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Government Period of Performance 225
240017 Upgrade PGS Fire Suppression Project Number FBNV240017
Projected Date Projected Duration
Actual Date Submitted
Actual Duration
Task Order Award 6/7/2022 0 -44719 Kick-off Meeting 6/8/2022 1 0 Notice to Proceed 6/22/2022 14 0
Dig Permit (AF Form 103) 6/22/2022 0 0 Investigation 6/24/2022 2 0 Charrette Submittal 7/15/2022 21 0 Charrette Meeting 7/16/2022 1 0 35% Design Submittal 7/16/2022 0 0 Government Review 7/16/2022 0 0 35% Design Review Meeting 7/16/2022 0 0 65% Design Submittal 8/6/2022 21 0 Government Review 8/27/2022 21 0 65% Design Review Meeting 8/28/2022 1 0 95% Design Submittal 9/18/2022 21 0 Government Review 10/9/2022 21 0 95% Design Review Meeting 10/10/2022 1 0 Final Contract Documents Submittal 10/24/2022 14 0 Government Review 11/14/2022 21 0
Total Design Performance Period 160 0
Div 02 Demolition 11/27/2022 13 0 Div 03 Concrete 11/27/2022 0 0 Div 04 Masonry 11/27/2022 0 0 Div 05 Metals 11/27/2022 0 0 Div 06 Wood, Plastics, and Composites 11/27/2022 0 0
Div 07 Thermal and Moisture Protection 11/27/2022 0 0 Div 08 Openings 11/27/2022 0 0 Div 09 Finishes 11/27/2022 0 0 Div 10 Specialties 11/27/2022 0 0 Div 21 Fire Suppression 1/26/2023 60 0 Div 22 Plumbing 1/26/2023 0 0
Design Phase
Construction Phase
Div 23 HVAC 1/26/2023 0 0 Div 26 Electrical 1/31/2023 5 0 Div 27 Communications 1/31/2023 0 0 Div 31 Earthwork 1/31/2023 0 0 Div 32 Exterior Improvements 1/31/2023 0 0 Div 33 Utilities 1/31/2023 0 0 Div 34 Transportation 1/31/2023 0 0
Total Construction Performance Period 65 0
Total Performance Period 225 0
Comments
Performance of period (PoP) is an estimate. The project will begin once the Award & notice to proceed is given by the Contracting Squadron (Contract Adminitrator).
Sheet1