06-Exhibit_B-1_Rate_Sheet._(Protected).xlsx

XLSX spreadsheet 50 KB Posted

Attached to
C5612488-D Concrete Cutting and Demolition services
Solicitation number
0000033458
Issued by
California

About this file

This is a Rate Sheet (Exhibit B-1) from the California Department of Corrections and Rehabilitation (CDCR) for concrete cutting and demolition services across multiple correctional facilities, divided into three groups: Group 1 (CMF-SOL), Group 2 (SAC-FSP-CHCF-MCSP-SCC), and Group 3 (SQRC). The services include various types of concrete cutting work including gas flat saw cutting, electric flat saw cutting, core drilling, wall saw cutting, wire saw cutting, GPR scanning, and X-ray services. The work schedule is primarily during standard hours (6:30 AM - 2:30 PM Monday - Friday) with provisions for non-standard hours. Each group requires separate work scope assessments and work plan submissions.

The pricing structure is based on hourly rates and estimated quantities for each service type, with bidders required to complete all items within their chosen group(s). CDCR reserves the right to augment the Master Agreement amount by 25-100% of the total bid amount. Contractors may offer a minimum 1% discount on invoices (minimum $50) for 30-day payment terms. The contract includes preferences for California companies and requirements for listing subcontractors who will perform work exceeding 0.5% of the total bid. DVBE subcontractor participation is required, and all rates must include fees and taxes.

View the file

Other files

File Type Posted
IFB_Package.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CMF-SOL

CONCRETE CUTTING AND DEMOLITION SERVICES

INMATE/WARD LABOR PROGRAM

CALIFORNIA STATE PRISON, SOLANO

CALIFORNIA MEDICAL FACILITY

Electronic bid packages include an Excel version of this Public Works Rate Sheet (Exhibit B-1) in addition to the PDF file in order to assist bidders in computing accurate totals. Bidders should download the Excel version and complete all highlighted cells.
Quantities listed on Exhibit B-1, Public Works Rate Sheet are the State's estimates only and are offered as a basis for comparison of bids. The State does not expressly or by implication agree that the actual amount of work will correspond therewith and reserves the right to increase/omit portions of the work as may be deemed necessary or advisable by the State.
NOTE: Bidders may bid on one (1) or more Institution groups. Bidders are not required to bid on all groups. However, if bidding on a group, your bid shall be for all locations within each group. Each item within the selected group you are bidding, must be completed. Failure to indicate a dollar amount (BLANK CELL) in any item may be grounds for rejection. A zero dollar ($0.00 or $-) listed for any and/or all items shall be interpreted and understood by the State to mean that the bidder shall perform any such services at NO COST to the State. Rates must include all fees and taxes.
The "Basis of Award" for each Group is strictly used for bidding purposes only to determine the lowest responsive bidder. The CDCR reserves the right to augment this Master Agreement dollar amount by 25 - 100% of the total bid amount.
All prices and notations must be printed in ink or typewritten. All prices must be in U. S. currency.
Group 1
PHASE 1
DESCRIPTIONCOST PER VISITXESTIMATED NUMBER OF VISITS=TOTAL
Work Scope Assessment$ - 0X10=$ - 0
PHASE 2
DESCRIPTIONCOST PER WORK PLANXESTIMATED AMOUNT OF WORK PLAN SUBMISSION AND APPROVAL=TOTAL
Work Plan/Construction Schedule, Submission and Approval$ - 0X10=$ - 0
PHASE 3- CONCRETE CUTTING AND DEMOLITION
STANDARD WORKING HOURS
(6:30 AM - 2:30 PM MONDAY - FRIDAY)HOURLY RATEXESTIMATED NUMBER OF HOURS

tc={0D67544A-B826-416D-85AB-6BBE4D5ECF04}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

I was just making sure the hours are accurate as they appear the same as sheet 2 with 5 institutions.=TOTAL
Gas Flat Saw Cutting (Depth 0"-12")$ - 0X100=$ - 0
Gas Flat Saw Cutting (Depth 13"-18")$ - 0X50=$ - 0
Gas Flat Saw Cutting (Depth 19"-24")$ - 0X50=$ - 0
Electric Flat Saw Cutting (Depth 0"-14")$ - 0X100=$ - 0
Core Drill (Diameter of 0"- 15")$ - 0X25=$ - 0
Core Drill (Diameter of 16"-28")$ - 0X50=$ - 0
Core Drill (Diameter of 29"-36")$ - 0X50=$ - 0
Wall Saw Cutting (Depth 0"-24")$ - 0X100=$ - 0
Wire Saw Cutting$ - 0X25=$ - 0
Laborer$ - 0X100=$ - 0
GPR Scanning$ - 0X100=$ - 0
X-Ray (2 Person Crew)$ - 0X50=$ - 0
GPR Scan/X-Ray Report$ - 0X50=$ - 0
Slurry (Per Barrel)$ - 0X25=$ - 0
TOTAL STANDARD WORKING HOURS=$ - 0
NON-STANDARD WORKING HOURS (AS SPECIFIED IN EXHIBIT A, SCOPE OF WORK)HOURLY RATEESTIMATED NUMBER OF HOURS=TOTAL
Stand By Time$ - 0X100=$ - 0
OT (Overtime)$ - 0X15=$ - 0
Sunday$ - 0X16=$ - 0
Starting Work After 5:00 PM Monday through Friday$ - 0X40=$ - 0
TOTAL NON-STANDARD WORKING HOURS=$ - 0
TOTAL AMOUNT OF PHASE 1 + PHASE 2 + PHASE 3=$ - 0
Basis For Award
The total amount of Phase 1 + Phase 2 + Phase 3 shall be used for determining the Basis for Award.
If awarded the contract, the Contractor agrees to sign the contract and to furnish the applicable bonds and certificates of insurance as required and start the work when notified.
Pursuant to Public Contract Code Section 6107, in awarding contracts for construction, a State agency shall grant a California company a reciprocal preference against a nonresident contractor with the lowest responsive bid, except where the resident contractor is eligible for a California small business preference, in which case the preference applied shall be the greater of the two, but not both.
NOTE: THIS RECIPROCAL PREFERENCE IS AVAILABLE ONLY TO BIDDERS WHO CERTIFY, UNDER PENALTY OF PERJURY, THAT THEY QUALIFY AS CALIFORNIA COMPANIES.

In order to qualify as a "California company" under California Public Contract Code Section 6107, a business entity must be a licensed California contractor at the time of the bid opening and must meet one of the following requirements:

1. Has its principal place of business in California.

2. Has its principal place of business in a state in which there is no local contractor preference on construction contracts.

3. Has its principal place of business in a state in which there is no local contractor preference on construction contracts, but the bidder has paid not less than Five Thousand Dollars ($5,000) in sales or use taxes to California for construction related activity for each of the five years immediately preceding the submission of the bid.

Does bidder certify, under penalty of perjury, that the bidder qualifies as a California company?
Yes ____ No ____

Nonresident bidder must disclose any and all bid preferences provided to the nonresident bidder by the state or country in which the nonresident bidder has its principal place of business at the time of bid submission. Therefore, if the bidder has answered “No” above, use this space to disclose any such preference. (If none, indicate):

Preference given:

By signing the Bidder Acknowledgement/Certification (OBS 300), the bidder certifies under penalty of perjury the correctness of this statement. Bidders are cautioned that making false certification may result in rejection of the bid or legal action or both.

The bidder shall set forth in the bid:

1. The name and business address of each subcontractor who will perform work or labor or render service in an amount in excess of one-half of one percent of the general contractor's total bid; and

2. The portion of work to be performed by each subcontractor. (See California Public Contract Code Sections 4100 through 4108, inclusive.)

3. In addition, effective January 1,1994, pursuant to the California Public Contract Code Section 10115 et seq., prime contractors MUST list on their Bid Proposal all certified DVBE subcontractors who will perform work or labor or render service to the prime contractor in connection with the performance of the contract and who will be used by the prime contractor to fulfill DVBE participation goals. The prime contractor shall list only one subcontractor for each portion as is defined by the prime contractor in his/her bid.

LIST OF PROPOSED SUBCONTRACTORS

Listed hereinafter is the name and address of each subcontractor who will be employed and the kind of work which each will perform in carrying out the aforementioned project. I understand that under California Public Contract Code Sections 4100 through 4108, I MUST clearly set forth the name and address of each subcontractor who will perform work or labor or render service to me in or about the site of the work and that as to any work in which I fail to do, I agree to perform that portion myself or be subjected to penalty under the Subletting and Subcontracting Fair Practices Act.

If further space is required for the list of proposed subcontractors, additional sheets showing the required information, in the format outlined below, shall be attached hereto and made a part of the Bid Proposal.

NOTE: Percentage of work to be performed refers to the percentage of the overall Scope of Work that the subcontractor will be performing. Total should not exceed 100%.

Kind of Work Percentage of work to be performed in relation to overall bid amount Type of License and Number Subcontractor Name and Address

Subcontractor NameSubcontractor Dollar AmountTotal Bid AmountPercentage Subcontractor Usage
$0.000.00%
$0.000.00%
$0.000.00%

Contractor may offer a discount to the amount paid on invoices received and accepted by the CDCR in order for the invoices to be paid within thirty (30) days of receipt. Discount offered on invoices must be at least one percent of the invoice amount and a minimum of $50.00.

Discount offered on invoices to be paid within 30 days of receipt = %

* In the event of a tie, absent other determining factors, the lowest responsible bid with the highest discount shall prevail. IF the highest discounts' also tie, the awarded bidder shall be determined by a public coin toss. Refer to the Notice to Prospective Bidders, Bid Submission Requirements.

&"Arial,Regular"&12TBB California Department of Corrections and Rehabilitation (CDCR) Public Works Rate Sheet &"Arial,Regular"&12Bid Number C5612488-D Exhibit B-1

&"Arial,Regular"&12Page &P of &N

SAC-FSP-CHCF-MCSP-SCC

CONCRETE CUTTING AND DEMOLITION SERVICES

INMATE/WARD LABOR PROGRAM

CALIFORNIA STATE PRISON, SACRAMENTO

FOLSOM STATE PRISON

CALIFORNIA HEALTH CARE FACILITY, STOCKTON

MULE CREEK STATE PRISON

SIERRA CONSERVATION CENTER

Electronic bid packages include an Excel version of this Public Works Rate Sheet (Exhibit B-1) in addition to the PDF file in order to assist bidders in computing accurate totals. Bidders should download the Excel version and complete all highlighted cells.
Quantities listed on Exhibit B-1, Public Works Rate Sheet are the State's estimates only and are offered as a basis for comparison of bids. The State does not expressly or by implication agree that the actual amount of work will correspond therewith and reserves the right to increase/omit portions of the work as may be deemed necessary or advisable by the State.
NOTE: Bidders may bid on one (1) or more Institution groups. Bidders are not required to bid on all groups. However, if bidding on a group, your bid shall be for all locations within each group. Each item within the selected group you are bidding, must be completed. Failure to indicate a dollar amount (BLANK CELL) in any item may be grounds for rejection. A zero dollar ($0.00 or $-) listed for any and/or all items shall be interpreted and understood by the State to mean that the bidder shall perform any such services at NO COST to the State. Rates must include all fees and taxes.
The "Basis of Award" for each Group is strictly used for bidding purposes only to determine the lowest responsive bidder. The CDCR reserves the right to augment this Master Agreement dollar amount by 25 - 100% of the total bid amount.
All prices and notations must be printed in ink or typewritten. All prices must be in U. S. currency.
Group 2
PHASE 1
DESCRIPTIONCOST PER VISITXESTIMATED NUMBER OF VISITS=TOTAL
Work Scope Assessment$ - 0X78=$ - 0
PHASE 2
DESCRIPTIONCOST PER WORK PLANXESTIMATED AMOUNT OF WORK PLAN SUBMISSION AND APPROVAL=TOTAL
Work Plan/Construction Schedule, Submission and Approval$ - 0X78=$ - 0
PHASE 3- CONCRETE CUTTING AND DEMOLITION
STANDARD WORKING HOURS
(6:30 AM - 2:30 PM MONDAY - FRIDAY)HOURLY RATEXESTIMATED NUMBER OF HOURS

tc={16877B25-81FD-4681-B71C-651ABE40AFEC}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

I was just making sure the hours are accurate as they appear the same as sheet 2 with 5 institutions.=TOTAL
Gas Flat Saw Cutting (Depth 0"-12")$ - 0X100=$ - 0
Gas Flat Saw Cutting (Depth 13"-18")$ - 0X100=$ - 0
Gas Flat Saw Cutting (Depth 19"-24")$ - 0X100=$ - 0
Electric Flat Saw Cutting (Depth 0"-14")$ - 0X300=$ - 0
Core Drill (Diameter of 0"- 15")$ - 0X100=$ - 0
Core Drill (Diameter of 16"-28")$ - 0X100=$ - 0
Core Drill (Diameter of 29"-36")$ - 0X100=$ - 0
Wall Saw Cutting (Depth 0"-24")$ - 0X300=$ - 0
Wire Saw Cutting$ - 0X100=$ - 0
Laborer$ - 0X300=$ - 0
GPR Scanning$ - 0X200=$ - 0
X-Ray (2 Person Crew)$ - 0X100=$ - 0
GPR Scan/X-Ray Report$ - 0X100=$ - 0
Slurry (Per Barrel)$ - 0X100=$ - 0
TOTAL STANDARD WORKING HOURS=$ - 0
NON-STANDARD WORKING HOURS (AS SPECIFIED IN EXHIBIT A, SCOPE OF WORK)HOURLY RATEXESTIMATED NUMBER OF HOURS=TOTAL
Stand By Time$ - 0X300=$ - 0
OT (Overtime)$ - 0X50=$ - 0
Sunday$ - 0X50=$ - 0
Starting Work After 5:00 PM Monday through Friday$ - 0X100=$ - 0
TOTAL NON-STANDARD WORKING HOURS=$ - 0
TOTAL AMOUNT OF PHASE 1 + PHASE 2 + PHASE 3=$ - 0
Basis For Award
The total amount of Phase 1 + Phase 2 + Phase 3 shall be used for determining the Basis for Award.
If awarded the contract, the Contractor agrees to sign the contract and to furnish the applicable bonds and certificates of insurance as required and start the work when notified.
Pursuant to Public Contract Code Section 6107, in awarding contracts for construction, a State agency shall grant a California company a reciprocal preference against a nonresident contractor with the lowest responsive bid, except where the resident contractor is eligible for a California small business preference, in which case the preference applied shall be the greater of the two, but not both.
NOTE: THIS RECIPROCAL PREFERENCE IS AVAILABLE ONLY TO BIDDERS WHO CERTIFY, UNDER PENALTY OF PERJURY, THAT THEY QUALIFY AS CALIFORNIA COMPANIES.

In order to qualify as a "California company" under California Public Contract Code Section 6107, a business entity must be a licensed California contractor at the time of the bid opening and must meet one of the following requirements:

1. Has its principal place of business in California.

2. Has its principal place of business in a state in which there is no local contractor preference on construction contracts.

3. Has its principal place of business in a state in which there is no local contractor preference on construction contracts, but the bidder has paid not less than Five Thousand Dollars ($5,000) in sales or use taxes to California for construction related activity for each of the five years immediately preceding the submission of the bid.

Does bidder certify, under penalty of perjury, that the bidder qualifies as a California company?
Yes ____ No ____

Nonresident bidder must disclose any and all bid preferences provided to the nonresident bidder by the state or country in which the nonresident bidder has its principal place of business at the time of bid submission. Therefore, if the bidder has answered “No” above, use this space to disclose any such preference. (If none, indicate):

Preference given:

By signing the Bidder Acknowledgement/Certification (OBS 300), the bidder certifies under penalty of perjury the correctness of this statement. Bidders are cautioned that making false certification may result in rejection of the bid or legal action or both.

The bidder shall set forth in the bid:

1. The name and business address of each subcontractor who will perform work or labor or render service in an amount in excess of one-half of one percent of the general contractor's total bid; and

2. The portion of work to be performed by each subcontractor. (See California Public Contract Code Sections 4100 through 4108, inclusive.)

3. In addition, effective January 1,1994, pursuant to the California Public Contract Code Section 10115 et seq., prime contractors MUST list on their Bid Proposal all certified DVBE subcontractors who will perform work or labor or render service to the prime contractor in connection with the performance of the contract and who will be used by the prime contractor to fulfill DVBE participation goals. The prime contractor shall list only one subcontractor for each portion as is defined by the prime contractor in his/her bid.

LIST OF PROPOSED SUBCONTRACTORS

Listed hereinafter is the name and address of each subcontractor who will be employed and the kind of work which each will perform in carrying out the aforementioned project. I understand that under California Public Contract Code Sections 4100 through 4108, I MUST clearly set forth the name and address of each subcontractor who will perform work or labor or render service to me in or about the site of the work and that as to any work in which I fail to do, I agree to perform that portion myself or be subjected to penalty under the Subletting and Subcontracting Fair Practices Act.

If further space is required for the list of proposed subcontractors, additional sheets showing the required information, in the format outlined below, shall be attached hereto and made a part of the Bid Proposal.

NOTE: Percentage of work to be performed refers to the percentage of the overall Scope of Work that the subcontractor will be performing. Total should not exceed 100%.

Kind of Work Percentage of work to be performed in relation to overall bid amount Type of License and Number Subcontractor Name and Address

Subcontractor NameSubcontractor Dollar AmountTotal Bid AmountPercentage Subcontractor Usage
$0.000.00%
$0.000.00%
$0.000.00%

Contractor may offer a discount to the amount paid on invoices received and accepted by the CDCR in order for the invoices to be paid within thirty (30) days of receipt. Discount offered on invoices must be at least one percent of the invoice amount and a minimum of $50.00.

Discount offered on invoices to be paid within 30 days of receipt = %

* In the event of a tie, absent other determining factors, the lowest responsible bid with the highest discount shall prevail. IF the highest discounts' also tie, the awarded bidder shall be determined by a public coin toss. Refer to the Notice to Prospective Bidders, Bid Submission Requirements.

Public Works Rate Sheet &"Arial,Regular"&12Bid Number C5612488-D

&"Arial,Regular"&12Page &P of &N

SQRC

CONCRETE CUTTING AND DEMOLITION SERVICES

INMATE/WARD LABOR PROGRAM

SAN QUENTIN REHABILITATION CENTER

Electronic bid packages include an Excel version of this Public Works Rate Sheet (Exhibit B-1) in addition to the PDF file in order to assist bidders in computing accurate totals. Bidders should download the Excel version and complete all highlighted cells.
Quantities listed on Exhibit B-1, Public Works Rate Sheet are the State's estimates only and are offered as a basis for comparison of bids. The State does not expressly or by implication agree that the actual amount of work will correspond therewith and reserves the right to increase/omit portions of the work as may be deemed necessary or advisable by the State.
NOTE: Bidders may bid on one (1) or more Institution groups. Bidders are not required to bid on all groups. However, if bidding on a group, your bid shall be for all locations within each group. Each item within the selected group you are bidding, must be completed. Failure to indicate a dollar amount (BLANK CELL) in any item may be grounds for rejection. A zero dollar ($0.00 or $-) listed for any and/or all items shall be interpreted and understood by the State to mean that the bidder shall perform any such services at NO COST to the State. Rates must include all fees and taxes.
The "Basis of Award" for each Group is strictly used for bidding purposes only to determine the lowest responsive bidder. The CDCR reserves the right to augment this Master Agreement dollar amount by 25 - 100% of the total bid amount.
All prices and notations must be printed in ink or typewritten. All prices must be in U. S. currency.
Group 3
PHASE 1
DESCRIPTIONCOST PER VISITXESTIMATED NUMBER OF VISITS=TOTAL
Work Scope Assessment$ - 0X30=$ - 0
PHASE 2
DESCRIPTIONCOST PER WORK PLANXESTIMATED AMOUNT OF WORK PLAN SUBMISSION AND APPROVAL=TOTAL
Work Plan/Construction Schedule, Submission and Approval$ - 0X30=$ - 0
PHASE 3- CONCRETE CUTTING AND DEMOLITION
STANDARD WORKING HOURS
(6:30 AM - 2:30 PM MONDAY - FRIDAY)HOURLY RATEXESTIMATED NUMBER OF HOURS

tc={D2C04CBD-08B0-40E6-9131-33C9D6AD8127}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

I was just making sure the hours are accurate as they appear the same as sheet 2 with 5 institutions.=TOTAL
Gas Flat Saw Cutting (Depth 0"-12")$ - 0X100=$ - 0
Gas Flat Saw Cutting (Depth 13"-18")$ - 0X50=$ - 0
Gas Flat Saw Cutting (Depth 19"-24")$ - 0X50=$ - 0
Electric Flat Saw Cutting (Depth 0"-14")$ - 0X50=$ - 0
Core Drill (Diameter of 0"- 15")$ - 0X100=$ - 0
Core Drill (Diameter of 16"-28")$ - 0X50=$ - 0
Core Drill (Diameter of 29"-36")$ - 0X50=$ - 0
Wall Saw Cutting (Depth 0"-24")$ - 0X100=$ - 0
Wire Saw Cutting$ - 0X100=$ - 0
Laborer$ - 0X500=$ - 0
GPR Scanning$ - 0X50=$ - 0
X-Ray (2 Person Crew)$ - 0X50=$ - 0
GPR Scan/X-Ray Report$ - 0X50=$ - 0
Slurry (Per Barrel)$ - 0X250=$ - 0
TOTAL STANDARD WORKING HOURS=$ - 0
NON-STANDARD WORKING HOURS (AS SPECIFIED IN EXHIBIT A, SCOPE OF WORK)HOURLY RATEESTIMATED NUMBER OF HOURS=TOTAL
Stand By Time$ - 0X50=$ - 0
OT (Overtime)$ - 0X20=$ - 0
Sunday$ - 0X20=$ - 0
Starting Work After 5:00 PM Monday through Friday$ - 0X20=$ - 0
TOTAL STANDARD WORKING HOURS=$ - 0
TOTAL AMOUNT OF PHASE 1 + PHASE 2 + PHASE 3=$ - 0
Basis For Award
The total amount of Phase 1 + Phase 2 + Phase 3 shall be used for determining the Basis for Award.
If awarded the contract, the Contractor agrees to sign the contract and to furnish the applicable bonds and certificates of insurance as required and start the work when notified.
Pursuant to Public Contract Code Section 6107, in awarding contracts for construction, a State agency shall grant a California company a reciprocal preference against a nonresident contractor with the lowest responsive bid, except where the resident contractor is eligible for a California small business preference, in which case the preference applied shall be the greater of the two, but not both.
NOTE: THIS RECIPROCAL PREFERENCE IS AVAILABLE ONLY TO BIDDERS WHO CERTIFY, UNDER PENALTY OF PERJURY, THAT THEY QUALIFY AS CALIFORNIA COMPANIES.

In order to qualify as a "California company" under California Public Contract Code Section 6107, a business entity must be a licensed California contractor at the time of the bid opening and must meet one of the following requirements:

1. Has its principal place of business in California.

2. Has its principal place of business in a state in which there is no local contractor preference on construction contracts.

3. Has its principal place of business in a state in which there is no local contractor preference on construction contracts, but the bidder has paid not less than Five Thousand Dollars ($5,000) in sales or use taxes to California for construction related activity for each of the five years immediately preceding the submission of the bid.

Does bidder certify, under penalty of perjury, that the bidder qualifies as a California company?
Yes ____ No ____

Nonresident bidder must disclose any and all bid preferences provided to the nonresident bidder by the state or country in which the nonresident bidder has its principal place of business at the time of bid submission. Therefore, if the bidder has answered “No” above, use this space to disclose any such preference. (If none, indicate):

Preference given:

By signing the Bidder Acknowledgement/Certification (OBS 300), the bidder certifies under penalty of perjury the correctness of this statement. Bidders are cautioned that making false certification may result in rejection of the bid or legal action or both.

The bidder shall set forth in the bid:

1. The name and business address of each subcontractor who will perform work or labor or render service in an amount in excess of one-half of one percent of the general contractor's total bid; and

2. The portion of work to be performed by each subcontractor. (See California Public Contract Code Sections 4100 through 4108, inclusive.)

3. In addition, effective January 1,1994, pursuant to the California Public Contract Code Section 10115 et seq., prime contractors MUST list on their Bid Proposal all certified DVBE subcontractors who will perform work or labor or render service to the prime contractor in connection with the performance of the contract and who will be used by the prime contractor to fulfill DVBE participation goals. The prime contractor shall list only one subcontractor for each portion as is defined by the prime contractor in his/her bid.

LIST OF PROPOSED SUBCONTRACTORS

Listed hereinafter is the name and address of each subcontractor who will be employed and the kind of work which each will perform in carrying out the aforementioned project. I understand that under California Public Contract Code Sections 4100 through 4108, I MUST clearly set forth the name and address of each subcontractor who will perform work or labor or render service to me in or about the site of the work and that as to any work in which I fail to do, I agree to perform that portion myself or be subjected to penalty under the Subletting and Subcontracting Fair Practices Act.

If further space is required for the list of proposed subcontractors, additional sheets showing the required information, in the format outlined below, shall be attached hereto and made a part of the Bid Proposal.

NOTE: Percentage of work to be performed refers to the percentage of the overall Scope of Work that the subcontractor will be performing. Total should not exceed 100%.

Kind of Work Percentage of work to be performed in relation to overall bid amount Type of License and Number Subcontractor Name and Address

Subcontractor NameSubcontractor Dollar AmountTotal Bid AmountPercentage Subcontractor Usage
$0.000.00%
$0.000.00%
$0.000.00%

Contractor may offer a discount to the amount paid on invoices received and accepted by the CDCR in order for the invoices to be paid within thirty (30) days of receipt. Discount offered on invoices must be at least one percent of the invoice amount and a minimum of $50.00.

Discount offered on invoices to be paid within 30 days of receipt = %

* In the event of a tie, absent other determining factors, the lowest responsible bid with the highest discount shall prevail. IF the highest discounts' also tie, the awarded bidder shall be determined by a public coin toss. Refer to the Notice to Prospective Bidders, Bid Submission Requirements.

Public Works Rate Sheet &"Arial,Regular"&12Bid Number C5612488-D

&"Arial,Regular"&12Page &P of &N

File details come from the government source that posted it. Updated .