This document is a Submittal Register that outlines the construction submittals required for the "Eleven Mile Canyon Road 96 Bridges and Guardrail Rehabilitation" project. The key details include:

The project involves the rehabilitation of five road bridges and the installation of approach guardrails. Required submittals include a Quality Control Plan, Hazardous Spill Plan, Erosion Control Plan, Construction Schedule, Traffic Control Plan, Bridge Jacking Plan, Painting Plan, Paint Samples, Certification of Weed-Free Material, Assay Retention Reports, Disposal Documentation, Shop Drawings for the bridge and approach rail, and various test results and material documentation. Submittals are generally required 14-28 days prior to the start of work. The project has a strict period of performance from September to October 2024, with a competitive range of $300,000 to $500,000.

View the file

Other files

File Type Posted
Rev2 Drawing Addendum_4.25.24.docx DOCX document
Rev2 CDOT_m-606-1-mgs-type3-w-beam-31-in.pdf PDF
co6 Park County Highway Wage Determination.txt TXT text file
02_Supplemental Specs_6.28.23.pdf PDF
Master Solicitation.pdf PDF
06_SOI_1.3.24 PDF.pdf PDF
07_Davis-Bacon Act WD_CO20240008.pdf PDF
04_Fire Control Plan.pdf PDF
01_Scope of Work.pdf PDF
03_Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal Register

CONSTRUCTION SUBMITTAL SCHEDULEProject Title:
ELEVEN MILE CANYON ROAD 96 BRIDGES AND GUARDRAIL REHABILITATION
TO BE COMPLETED BY CONTRACTORTO BE COMPLETED BY CONTRACT ADMINISTRATOR
SUBMITTAL ITEM NUMBERDESCRIPTION OF SUBMITTAL ITEMCONTRACT REFERENCETYPE OF SUBMITTAL (See Remarks)DATE REQUIRED BYDATE RESUBMITTAL RECEIVEDDATE CONTRACTOR NOTIFIEDREMARKS
SCHEDULEMANUFACTURER'S SPECIFICATIONSCERTIFICATION DOCUMENTATIONSHOP DRAWINGS/AS-BUILTSSAMPLESCOLOR SELECTIONPERMITS/NOTICESTEST RESULTS/MATERIAL MIXO & M MANUALS & INSTRUCTIONSWRITTEN PLANSOTHER DOCUMENTATION
SUBMITTAL RETURNED FOR RESUBMISSIONACCEPTANCE OR ACCEPTANCE WITH COMMENT(S)
1Equipment InspectionFSSS 171XPRIOR TO ENTERING WORK SITEVisual Equipment Inspection by COR. Make sure clean and weed free
2Quality Control PlanFP-14 153 & FSSS 153X14 DAYS PRIOR TO START OF WORK
3Hazardous Spill PlanFSSS 107X14 DAYS PRIOR TO START OF WORK
4Erosion Control PlanFSSS 157X14 DAYS PRIOR TO START OF WORK
5Construction ScheduleFSSS 155X28 DAYS PRIOR TO START OF WORKSchedule to include road closure dates for bearing pad replacement (if optional item 564(01) is awarded)
6Traffic Control PlanFSSS 156X14 DAYS PRIOR TO START OF WORK
7Bridge Jacking Plan (stamped by PE) & ScheduleFSSS 564XX14 DAYS PRIOR TO START OF WORKOnly required if optional item 564(01) is awarded
8Painting Plan & Competent Personnel CertificationsFP-14 563 & FSSS 563XX14 DAYS PRIOR TO START OF WORKExisting bridge rail paint is hazardous material (lead-based paint)
9Paint SampleFSSS 563X14 DAYS PRIOR TO START OF WORK
10Certification of Weed Free MaterialFSSS 105X7 DAYS PRIOR TO START OF WORKErosion Control materials
11Assay Retention Reports For The Approach Rail Posts and BlocksSHEET 5 OF DWGSXPRIOR TO INSTALLATION
12Disposal Agreements, Statements, and PermitsFP-14 203XPRIOR TO MATERIAL DISPOSALDocumentaion of Disposal Methods. Guardrail to be removed has hazardous material (lead-based paint)
13Bridge Rail Shop DrawingsFSSS 556XPRIOR TO FABRICATION
14Approach Rail Shop DrawingsSHEET 5 OF DWGSXPRIOR TO FABRICATION
15Elastomeric Bearing Pad DrawingsFP-14 564X14 DAYS PRIOR TO START OF WORK
NOTES:
CONTINUED SCHEDULE OF SUBMITTALSProject Title:Contract Number:Project Number:
ELEVEN MILE CANYON ROAD 96 BRIDGES AND GUARDRAIL REHABILITATION
TO BE COMPLETED BY DESIGNERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
SUBMITTAL ITEM NUMBERDESCRIPTION OF SUBMITTAL ITEMCONTRACT REFERENCETYPE OF SUBMITTAL (See Remarks)DATE REQUIRED BYDATE RESUBMITTAL RECEIVEDDATE CONTRACTOR NOTIFIEDREMARKS
SCHEDULEMANUFACTURER'S SPECIFICATIONSCERTIFICATION DOCUMENTATIONSHOP DRAWINGS/AS-BUILTSSAMPLES/COLORSCOLOR SELECTIONPERMITS/NOTICESTEST RESULTS/MATERIAL MIXO & M MANUALS & INSTRUCTIONSWRITTEN PLANSOTHER DOCUMENTATION
SUBMITTAL RETURNED FOR RESUBMISSIONACCEPTANCE OR ACCEPTANCE WITH COMMENT(S)
16As-Built DrawingsFSSS 104XPRIOR TO FINAL INSPECTION
17Structural Backfill: Optimum Moisture Content & Maximum Dry DensityFSSS 204X3 DAYS PRIOR TO COMPACTIONIncidental to Contracor Testing, Item 154(01)
18Structural Backfill: In-place Density & Moisture ContentFSSS 204X3 DAYS AFTER COMPACTIONIncidental to Contracor Testing, Item 154(01)
19Accident Prevention PlanFP-14 156X14 DAYS PRIOR TO START OF WORK
20
21
22
23
24
25
26
27
28
29
30
NOTES: