This document appears to be a preliminary project schedule for the West Ottawa Community Pool Utility Relocation project. The schedule outlines the key tasks and timelines for the pre-construction, procurement, and construction phases of the project.

The pre-construction phase includes finalizing the bid package, a 10-day bidding period, bid due date, post-bid activities, board approval, and issuing subcontracts. The procurement phase covers the ordering of storm structures/piping, watermain, and dewatering equipment over a 20-day period. The 50-day construction phase includes mobilization, fencing/jobsite setup, utility relocation, dewatering implementation, site demolition, storm/watermain relocation, flushing/testing, and final restoration/cleanup. The project is scheduled to start on August 26, 2024 and be completed by December 13, 2024.

View the file

Other files

File Type Posted
Comm Pool Earthwork Advertisement.pdf PDF
04 Instructions-CMa Ed -WO Pool.pdf PDF
05.1 Site Logistics.pdf PDF
BP 01 - Addendum #1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Task Name Duration Start Finish Predecessors

1 PRE-CONSTRUCTION 20 days Mon 8/26/24 Fri 9/20/24

2 Finalize Bid Package 2 days Mon 8/26/24 Tue 8/27/24

3 Bidding 10 days Wed 8/28/24 Tue 9/10/24 2

4 Bids Due 1 day Wed 9/11/24 Wed 9/11/24 3

5 Post Bids 1 day Thu 9/12/24 Thu 9/12/24 4

6 Rec. to Award 1 day Thu 9/12/24 Thu 9/12/24 5SS

7 Board Approval 1 day Mon 9/16/24 Mon 9/16/24 6FS+1 day

8 Issue Subcontracts 4 days Tue 9/17/24 Fri 9/20/24 7

9 PROCUREMENT 20 days Mon 9/23/24 Fri 10/18/24

10 Storm Structures and Piping 3 wks Mon 9/23/24 Fri 10/11/24 8

11 Watermain 3 wks Mon 9/23/24 Fri 10/11/24 8

12 Dewatering Plan 4 wks Mon 9/23/24 Fri 10/18/24 8

13 CONSTRUCTION 50 days Mon 10/7/24 Fri 12/13/24

14 Mobilization 1 day Mon 10/7/24 Mon 10/7/24 12FS-2 wks

15 Fencing and Jobsite Setup 5 days Tue 10/8/24 Mon 10/14/24 14

16 Mis-Dig and SESC 2 days Tue 10/15/24 Wed 10/16/24 15

17 Owner Utility Relocation (Gas, Irrigation, Comm., Elec.)5 days Thu 10/17/24 Wed 10/23/24 16

18 Implement Dewatering 10 days Thu 10/24/24 Wed 11/6/24 17,12

19 Site Demo 5 days Thu 11/7/24 Wed 11/13/24 18

20 Storm and Watermain Relocation 3 wks Thu 11/14/24 Wed 12/4/24 19

21 Flushing and testing 2 days Thu 12/5/24 Fri 12/6/24 20

22 Restoration and Cleanup 5 days Mon 12/9/24 Fri 12/13/24 21

8/18 8/25 9/1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15

September October November December

West Ottawa Community Pool

BP 01 Utility Relocation - Preliminary Project Schedule

Wed 8/28/24 Page 1