05 Schedule.pdf
PDF 80 KB Posted
- Attached to
- Community Pool - Site, Earthwork & Utilities
- Solicitation number
- RFP-WOP-240000003020-3
- Issued by
- Saginaw County, Michigan
About this file
This document appears to be a preliminary project schedule for the West Ottawa Community Pool Utility Relocation project. The schedule outlines the key tasks and timelines for the pre-construction, procurement, and construction phases of the project.
The pre-construction phase includes finalizing the bid package, a 10-day bidding period, bid due date, post-bid activities, board approval, and issuing subcontracts. The procurement phase covers the ordering of storm structures/piping, watermain, and dewatering equipment over a 20-day period. The 50-day construction phase includes mobilization, fencing/jobsite setup, utility relocation, dewatering implementation, site demolition, storm/watermain relocation, flushing/testing, and final restoration/cleanup. The project is scheduled to start on August 26, 2024 and be completed by December 13, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Comm Pool Earthwork Advertisement.pdf | ||
| 04 Instructions-CMa Ed -WO Pool.pdf | ||
| 05.1 Site Logistics.pdf | ||
| BP 01 - Addendum #1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Duration Start Finish Predecessors
1 PRE-CONSTRUCTION 20 days Mon 8/26/24 Fri 9/20/24
2 Finalize Bid Package 2 days Mon 8/26/24 Tue 8/27/24
3 Bidding 10 days Wed 8/28/24 Tue 9/10/24 2
4 Bids Due 1 day Wed 9/11/24 Wed 9/11/24 3
5 Post Bids 1 day Thu 9/12/24 Thu 9/12/24 4
6 Rec. to Award 1 day Thu 9/12/24 Thu 9/12/24 5SS
7 Board Approval 1 day Mon 9/16/24 Mon 9/16/24 6FS+1 day
8 Issue Subcontracts 4 days Tue 9/17/24 Fri 9/20/24 7
9 PROCUREMENT 20 days Mon 9/23/24 Fri 10/18/24
10 Storm Structures and Piping 3 wks Mon 9/23/24 Fri 10/11/24 8
11 Watermain 3 wks Mon 9/23/24 Fri 10/11/24 8
12 Dewatering Plan 4 wks Mon 9/23/24 Fri 10/18/24 8
13 CONSTRUCTION 50 days Mon 10/7/24 Fri 12/13/24
14 Mobilization 1 day Mon 10/7/24 Mon 10/7/24 12FS-2 wks
15 Fencing and Jobsite Setup 5 days Tue 10/8/24 Mon 10/14/24 14
16 Mis-Dig and SESC 2 days Tue 10/15/24 Wed 10/16/24 15
17 Owner Utility Relocation (Gas, Irrigation, Comm., Elec.)5 days Thu 10/17/24 Wed 10/23/24 16
18 Implement Dewatering 10 days Thu 10/24/24 Wed 11/6/24 17,12
19 Site Demo 5 days Thu 11/7/24 Wed 11/13/24 18
20 Storm and Watermain Relocation 3 wks Thu 11/14/24 Wed 12/4/24 19
21 Flushing and testing 2 days Thu 12/5/24 Fri 12/6/24 20
22 Restoration and Cleanup 5 days Mon 12/9/24 Fri 12/13/24 21
8/18 8/25 9/1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15
September October November December
West Ottawa Community Pool
BP 01 Utility Relocation - Preliminary Project Schedule
Wed 8/28/24 Page 1
File details come from the government source that posted it. Updated .