05. SFC Project Specifications.pdf
PDF 484 KB Posted
- Solicitation number
- 89503421BWA000023
About this file
This project specification document outlines the requirements for a federal construction contract to build a Sioux Falls Operations and Maintenance Service Center and Garage in South Dakota. The project involves constructing a single-story pre-engineered steel building approximately 62 feet wide by 116 feet long with four vehicle storage bays and one drive-through bay. Additional requirements include site work covering 2.25 acres, a septic system, concrete work, mechanical and plumbing systems, fire protection, electrical work, interior finishes, and an access control system. The specification provides bidding schedule items for the various construction divisions and details submittal requirements, construction schedules, material and utility provisions, and correspondence protocols. The Western Area Power Administration is the contracting agency, and the work must be completed per their standards and the specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 05. SFC Project Drawings.pdf | ||
| 05. SFC Appendix A - Technical Specifications.pdf | ||
| 12. General Decision Number.docx | DOCX document | |
| 22. 89503421BWA000023 (1).pdf | ||
| 05. SFC Appendix B - Geotechnical Evaluation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SIOUX FALLS O&M SERVICE CENTER
MAINTENANCE OFFICE AND GARAGE
Solicitation No. 89503421BWA000023 Spec. No. 21WC139216-1015
SECTION C
DESCRIPTION/SPECIFICATIONS
SOUTH DAKOTA
SECTION C
DESCRIPTION/SPECIFICATIONS
SIOUX FALLS O&M SERVICE CENTER
MAINTENANCE OFFICE AND GARAGE
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
B. DESCRIPTION OF WORK:
1. Approximately 2.25 acres of site improvements
2. Four (4) vehicle storage bays and (1) drive-thru vehicle bay
3. Four (4) personnel doors, (2) on east side, and (2) on west side of the building
4. Equipment to be stored in building
5. Under floor hydronic (electric) boiler heating system in the vehicle bays
6. Air conditioning and ventilation systems in the office and work area spaces
7. Mechanical plumbing for kitchen, break area, bathrooms, and water closets
8. Break area millwork
9. Interior walls, doors, ceiling, carpeting, tile, painting, and finish
10. Water and storm drain systems
11. Lighting, communication, access control, and electrical systems
12. Fire protection system as shown on drawings
13. Floor trench drain system with water oil separator
14. Water “bibs” for hosing off vehicles and floor
15. Concrete aprons on East and West sides of building for parking
16. Grading, drainage, roadways, and stormwater requirements as shown on drawings
17. Sanitary septic system
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work”
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK:
2. SUBMITTAL APPROVAL TIME:
3. CONSTRUCTION SCHEDULE RESTRICTIONS:
4. TYPICAL FOUNDATIONS FOR BUILDING FOUNDATION:
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME:
F. MATERIAL:
1. Furnish all material for completing the work
G. RIGHTS-OF-WAY:
1. GENERAL:
H. GEOLOGIC INVESTIGATIONS:
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
J. WATER FOR CONSTRUCTION PURPOSES:
K. EXPLOSIVES AND BLASTING:
L. BURIED UTILITIES:
M. EMPLOYEE REQUIREMENTS:
N. ELECTRICAL MINIMUM APPROACH DISTANCES:
O. SUBMITTALS AND CORRESPONDENCE:
1. GENERAL:
2. TRANSMITTALS:
3. PHYSICAL SAMPLE SUBMITTALS:
4. SUBMITTAL RESPONSE:
5. APPROVAL TIME:
6. PROJECT PROTOCOL:
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Civil Site Preparation”
2. Bidding Schedule item “Complete Septic System”
DIVISION 3 – CONCRETE
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Concrete”
2. Bidding Schedule item “Outdoor Concrete”
DIVISION 11 – SERVICE BUILDING
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Pre-engineered Building”
2. Bidding Schedule item “Mechanical and Plumbing”
3. Bidding Schedule item “Fire Protection”
4. Bidding Schedule item “Electrical”
5. Bidding Schedule item “Interior Finishes”
6. Bidding Schedule item “Provide New Physical Access Control System”
7. Bidding Schedule item “Provide Security Key Pads at Three New Doors”
SECTION C
DESCRIPTIONS/SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
Construct and complete Sioux Falls O&M Service Center, Maintenance Office and Garage, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; Western Area Power Administration’s (WAPA) Construction Standards, including Standard 1 – General Requirements (September 2016), Standard 2 – Sitework (September 2016), Standard 3 – Concrete (September 2016), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (September 2016), Standard 5 – Transmission Line Steel Pole Structures (September 2016), Standard 6 – Light Duty Steel Pole Structures (September 2016), Standard 7 – Wood Poles (September 2016), Standard 8 – Glued Laminated Structures (September 2016), Standard 9 – Substation – Electrical (September 2016), Standard 10 – Transmission Line – Electrical (September 2016), Standard 12 – Painting (September 2016), Standard 13 – Environmental Quality Protection (September 2016), Standard 14 – Communication Facilities (September 2016), Standard 15 – Drawings (September 2016); Standard Drawings; and these Project Specifications and Drawings.
If a conf lict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.
WAPA’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.
WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.
All applicable city, county, and state permits shall be adhered to.
B. DESCRIPTION OF WORK:
The project consists of a single-story office and vehicle garage facility. The building structure is nominally 62 f t wide x 116 f t long pre-engineered steel building with the drive thru bay portion of the building being 82 ft in width. The major attributes of this project include the following:
1. Approximately 2.25 acres of site improvements.
2. Four (4) vehicle storage bays and (1) drive-thru vehicle bay. The (4) vehicle storage bays will have 12 f t wide x 14 ft high overhead doors.
3. Four (4) personnel doors, (2) on east side, and (2) on west side of the building. Each door to be provided with entry pads and ramps.
4. Equipment to be stored in building includes semi-tractors with trailers, man-lifts, cranes, wire reel trailers, etc.
5. Under f loor hydronic (electric) boiler heating system in the vehicle bays.
6. Air conditioning and ventilation systems in the office and work area spaces.
7. Mechanical plumbing for kitchen, break area, bathrooms, and water closets. Includes complete bathroom and break area fixtures and accessories.
https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx
8. Break area millwork.
9. Interior walls, doors, ceiling, carpeting, tile, painting, and finish.
10. Water and storm drain systems including connections to main utilities as shown on drawings.
11. Lighting, communication, access control, and electrical systems including transformer and connections to main power source as shown on drawings.
12. Fire protection system as shown on drawings.
13. Floor trench drain system with water oil separator.
14. Water “bibs” for hosing off vehicles and floor.
15. Concrete aprons on East and West sides of building for parking.
16. Grading, drainage, roadways, and stormwater requirements as shown on drawings.
17. Sanitary septic system.
The summary of “Bidding Schedule Items” are more fully described in the following divisions in the specification and in the Construction Standards listed in Division 1, Section A above.
The work is located in Minnehaha County, Sioux Falls, South Dakota.
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
a. Performing mobilization and preparatory work in accordance with Sections H and M of the contract clauses.
b. Preparing and submitting a Construction Schedule and furnishing a Safety and Health
Program.
c. Complying with DOE O 442.2, Differing Professional Opinions for Technical Issues Involving Environment Safety and Health.
d. Complying with applicable Environmental Standards.
e. Providing jobsite office trailer and the items listed below. Prior to any jobsite work, the Contractor shall provide the office trailer for the exclusive use of WAPA.
1. Relocation: If the Contractor changes the location of his office during the term of the contract, then the Contractor shall also move the mobile office trailer provided for WAPA, simultaneously with the transportation of his own unit.
a. Installation: Install anchors and tie-downs for the trailer complying with local, State and Federal regulations. The office trailer shall be grounded. Entry points to the trailer shall be provided with stairways complying with OSHA (29 CFR 1926.1052).
b. Of f ice Space Requirements:
i. Size and Arrangement: At least 250-square feet (minimum) consisting of two separate rooms (one office and one larger workroom).
ii. Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling.
iii. Lighting and Electrical: Adequate lighting and 120 V electrical outlets.
iv. Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power, and heating and cooling energy.
v. Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the of fice and shall be maintained.
2. Emergency Equipment: Provide and maintain the following emergency equipment:
a. First aid kit that meets or exceeds ANSI Z308.1 (latest version) Class B, Type IV.
Mount to the wall inside the workroom.
b. Dry chemical f ire extinguishers, classified 4-A:60-B:C, one to be located inside each entrance to the trailer.
3. Window Coverings: Provide adjustable mini-blinds.
4. Of f ice Furniture: Provide good quality, fully functional, office furniture as follows:
Quantity Description
5 Folding Office Chairs.
1 Of f ice desk (30” x 60” minimum).
2 Of f ice tables (30” x 60” minimum).
1 Five-drawer f ile cabinet.
1 Bookcase (30” x 13” x 48”).
12 “Plan Hold” binders No. 1CB-24 (including one plan rack).
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK: See FAR 52.211- 10 in Section F of the solicitation/contract.
2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 30-calendar days for review of drawings or data submitted for approval.
3. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:
a. The Contractor shall not work more than 12 hours per day and not more than 60-hours in one continuous period without approval from the COR.
4. TYPICAL FOUNDATIONS FOR BUILDING FOUNDATION: Typical foundations are shown on drawings. Regarding foundations noted as “design not firm”: The engineer-of-record will design these foundations after receipt and f inal approval of pre-engineered steel building manufacturer’s f inal shop drawings and calculations from the Contractor.
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 10 calendar days after date of Notice to Proceed.
F. MATERIAL:
1. Furnish all material for completing the work.
G. RIGHTS-OF-WAY:
1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way and within Government property lines or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired by the Contractor shall have prior COR approval. During the contract period, WAPA reserves the right to use Contractor-obtained access.
H. GEOLOGIC INVESTIGATIONS:
The Geotechnical Engineering Report prepared by FMG Engineering, Report No. 200903, dated October 8, 2020 is incorporated into these Project Specifications as a requirement for design and construction of this project. The report is included as Appendix B.
The geologic logs of subsurface explorations included in the Geotechnical Engineering Report constitute the information and records of geologic investigations for the work. Locations of subsurface investigations are shown in the same report.
Samples and cores of recovered material were not retained. Bidders shall obtain their own samples and perform tests on the material to evaluate properties, which they believe to be significant. WAPA does not guarantee that the geologic information and records show the conditions that will be encountered in performing the work, but only that the geologic information and records show conditions encountered at the particular point and time the information and records were obtained.
The geologic information may not indicate variations, such as those caused by seasonal fluctuations in rainfall and other factors, which may af fect the water level. The Contractor shall determine the nature of material to be excavated, the difficulties of making and maintaining required.
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
Electric power up to a maximum of approximately 25-kVA for construction purposes will be available without cost. Source of supply is located in the receptacles throughout the substation. Power made available by WAPA will be delivered as single-phase, 60 Hz, AC, at approximately 120-240 V. Co-ordinate with the COR for establishing electric power service.
Until permanent power is available, provide temporary power to the building to serve all building loads including heating & lighting, Provide temporary heating prior to beginning f inish work, sufficient to keep the interior of the building at a minimum of 70 degrees Fahrenheit for 24-hours a day, until permanent heating is available.
The Contractor may furnish power for his operations by other means at no additional cost to WAPA.
Provide necessary transmission lines, distribution circuits, transformers, and other electrical equipment for distributing the power to the places of use. At contract completion, remove temporary electrical equipment and distribution lines.
J. WATER FOR CONSTRUCTION PURPOSES:
Furnish water for construction purposes. Make arrangements for obtaining the water and provide for conveying the water to the points of use.
K. EXPLOSIVES AND BLASTING:
Explosives shall not be used.
L. BURIED UTILITIES:
Prior to excavation, examine the area and determine the location of buried utilities. Utilities shall be identified with a marker denoting the type of service.
M. EMPLOYEE REQUIREMENTS:
In addition to the requirements listed in WAPA Construction Standard 1.4.3 all employees are restricted f rom wearing a headset, headphone, or other listening device, other than a hearing aid or instrument for the improvement of defective human hearing, hearing protection worn as the hazard exists, or for communication purposes while on a WAPA jobsite.
N. ELECTRICAL MINIMUM APPROACH DISTANCES:
In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances established by OSHA 1926.958(b), “Materials, Handling, and Storage”. The less stringent equipment clearance distances established by OSHA 1926.960, “Working On or Near Exposed Energized Parts”, Table V-5 and Table V-6, may only be used af ter the Contractor has completed and submitted WAPA’s Electrical Clearance Variance form and has received the signed form in return f rom the COR.
O. SUBMITTALS AND CORRESPONDENCE:
1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements:
a. Submittals shall be in standard PDF, Microsoft Word (.doc/.docx), Microsoft Excel
(.xls/.xlsx), or Electronic CAD (.dwg) (AutoCAD 2010 or 2014) formats. All submittals in .dwg format shall also be submitted in .pdf format.
b. All submittals shall include the WAPA Contract number, Specification number, WAPA project title, Bidding Schedule Contract Line Item Number (CLIN) and applicable division number.
c. Multiple CLIN’s on a single submittal are not permitted.
d. A cover transmittal letter in Microsoft Word or PDF format shall be included with each email submittal.
2. TRANSMITTALS:
a. The Contractor shall transmit all submittals to the Construction Office:
Email: UGP-CS-B5600@WAPA.GOV mailto:UGP-CS-B5600@WAPA.GOV
b. The Contractor shall transmit all inquiries regarding contract changes or modifications to:
Email: dittmer@wapa.gov or richter@wapa.gov
3. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e. brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlining the physical sample submittal prior to sending the sample (including tracking data when applicable) and shall deliver physical specimens to:
Burns & McDonnell Attn: Philip Voegtle, PE, SE 9785 Maroon Circle, Suite 400 Centennial, CO 80112 pjvoegtle@burnsmcd.com
A courtesy copy of the submittal letter shall be emailed to the Construction office at the above address.
4. SUBMITTAL RESPONSE: WAPA will respond to submittals electronically with an “Accepted” or
“Not Accepted” status with comments as appropriate in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph to the email address where the submittals originated.
5. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecutions, and Completion of Work” paragraph.
6. PROJECT PROTOCOL:
a. Submittals – Electronic Correspondence:
SUBJECT LINE IN EMAIL -- SUBMITTAL FORMAT
CLIN + Submittal Name – Applicable Division Number or Drawing Number – Project Title – Specification Number – Contract Number Example: 0011 Concrete Mix Design – 3.A.1 – Sioux Falls O&M Service Center, Maintenance Off ice and Garage, SD– 21WC139216-1015 – 89503421CWA0000XX
b. Payment Requests:
SUBJECT LINE IN EMAIL -- PAYMENT REQUEST FORMAT
Invoice Number – Project Title – Specification Number – Contract Number Example: Invoice 01 – Sioux Falls O&M Service Center, Maintenance Office and Garage, SD–
21WC139216-1015 – 89503421CWA0000XX
c. Certif ied Payrolls – Prime and Sub-Contractors:
SUBJECT LINE IN EMAIL -- CERTIFIED PAYROLL FORMAT
Certif ied Payroll (CP) – Contractor Name – Week Ending (WE) – Project Title – Specification Number – Contract Number Example: CP – Bob’s Asphalt Repair – WE 08/13/16 & 08/20/16 – Sioux Falls O&M Service Center, Maintenance Office and Garage, SD– 21WC139216-1015 – 89503421CWA0000XX mailto:dittmer@wapa.gov mailto:richter@wapa.gov mailto:pjvoegtle@burnsmcd.com
d. Request for Information:
SUBJECT LINE IN EMAIL -- REQUEST FOR INFORMATION (RFI) FORMAT
RFI Number – Subject – Project Title – Specification Number – Contract Number Example: RFI 003 – Labeling Info – Sioux Falls O&M Service Center, Maintenance Office and Garage, SD– 21WC139216-1015 – 89503421CWA0000XX
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Civil Site Preparation” includes providing and meeting all the sitework requirements and specifications listed on the Drawings and in Appendix A and B.
This item includes: clearing, grubbing, demolition, disposal, underground utilities, sewer, manholes, storm drains, culverts, oil/water separator, duct bank, trenching, backfill, traffic control, signage, surveying, staking, laydown areas, construction trailers, temporary utilities, erosion control, and miscellaneous sitework.
2. Bidding Schedule item “Complete Septic System” includes providing and meeting all the septic system requirements and specifications listed on the Drawings and in Appendixes A and B.
DIVISION 3 – CONCRETE
1. Bidding Schedule item “Concrete” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B.
This item includes: foundations; grade beams; indoor slabs on grade; trench drains; pipe bollards;
anchor bolts; and associated excavation, backfill, and structural fill for these structures.
2. Bidding Schedule item “Outdoor Concrete” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B.
This item includes: outdoor slabs on grade; ramps; curb, gutter, and sidewalks; and associated excavation, backfill, and subgrade materials.
DIVISION 11 – SERVICE BUILDING
1. Bidding Schedule item “Pre-engineered Building” includes providing and meeting all the
This item includes: materials, fabrication, delivery, offloading, storage, erection, walk-through doors, overhead doors, door operators, windows, gutters, downspouts, insulation, f lashing, sealing, framed openings, and miscellaneous steel.
2. Bidding Schedule item “Mechanical and Plumbing” includes providing and meeting all the
This item includes: hydronic heating system, boilers, pumps, eye wash stations, air handlers, fans, ductwork, louvers, hose bib stations, valves, meters, and local controls necessary for a complete mechanical and plumbing systems.
3. Bidding Schedule item “Fire Protection” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B.
This item includes: alarms, detection, wiring, notification, and programming necessary for a complete fire protection system.
4. Bidding Schedule item “Electrical” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B.
This item includes: light poles, grounding systems, lightning protection systems, lighting fixtures, lighting controls, exit signs, receptacles, conduit, cabling, terminations, panelboards, breakers, transformers, communication vaults, controls necessary for a complete electrical and communication system.
5. Bidding Schedule item “Interior Finishes” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B.
This item includes: walls, furring, carpet, tile, paint, millwork, interior doors, wall base, trim, sinks, mirrors, and fixtures necessary for a complete finished interior.
6. Bidding Schedule item “Provide New Physical Access Control System” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B.
7. Bidding Schedule item “Provide Security Key Pads at Three New Doors” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B.
Message from the Administrator
At Western Area Power Administration (WAPA), we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to WAPA. In performing work for WAPA, all contractors must make the right decisions to ensure that the work environment is as safe as possible.
Our safety program is based on four points:
Safety procedures or common sense must be applied by each
Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.
Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.
Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.
Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.
By integrating these principles into every task we take, together we can ensure WAPA is a safe place to work.
Mark A. Gabriel Administrator and CEO
| SECTION C |
| DESCRIPTION/SPECIFICATIONS |
| SIOUX FALLS O&M SERVICE CENTER |
| MAINTENANCE OFFICE AND GARAGE |
| DIVISION 1 – GENERAL REQUIREMENTS |
| A. CONTRACT REQUIREMENT: |
| B. DESCRIPTION OF WORK: |
| 1. Approximately 2.25 acres of site improvements. |
| 2. Four (4) vehicle storage bays and (1) drive-thru vehicle bay. The (4) vehicle storage bays will have 12 ft wide x 14 ft high overhead doors. |
| 3. Four (4) personnel doors, (2) on east side, and (2) on west side of the building. Each door to be provided with entry pads and ramps. |
| 4. Equipment to be stored in building includes semi-tractors with trailers, man-lifts, cranes, wire reel trailers, etc. |
| 5. Under floor hydronic (electric) boiler heating system in the vehicle bays. |
| 6. Air conditioning and ventilation systems in the office and work area spaces. |
| 7. Mechanical plumbing for kitchen, break area, bathrooms, and water closets. Includes complete bathroom and break area fixtures and accessories. |
| 8. Break area millwork. |
| 9. Interior walls, doors, ceiling, carpeting, tile, painting, and finish. |
| 10. Water and storm drain systems including connections to main utilities as shown on drawings. |
| 11. Lighting, communication, access control, and electrical systems including transformer and connections to main power source as shown on drawings. |
| 12. Fire protection system as shown on drawings. |
| 13. Floor trench drain system with water oil separator. |
| 14. Water “bibs” for hosing off vehicles and floor. |
| 15. Concrete aprons on East and West sides of building for parking. |
| 16. Grading, drainage, roadways, and stormwater requirements as shown on drawings. |
| 17. Sanitary septic system. |
| C. DESCRIPTION OF BIDDING SCHEDULE ITEM: |
| 1. Bidding Schedule item “Mobilization and preparatory work” includes the following: |
| D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: |
| 1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK: See FAR 52.211-10 in Section F of the solicitation/contract. |
| 2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 30-calendar days for review of drawings or data submitted for approval. |
| 3. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply: |
| 4. TYPICAL FOUNDATIONS FOR BUILDING FOUNDATION: Typical foundations are shown on drawings. Regarding foundations noted as “design not firm”: The engineer-of-record will design these foundations after receipt and final approval of pre-engineered ste... |
| E. CONSTRUCTION SCHEDULE: |
| 1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 10 calendar days after date of Notice to Proceed. |
| F. MATERIAL: |
| 1. Furnish all material for completing the work. |
| G. RIGHTS-OF-WAY: |
| 1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way and within Government property lines or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired ... |
| H. GEOLOGIC INVESTIGATIONS: |
| I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES: |
| J. WATER FOR CONSTRUCTION PURPOSES: |
| K. EXPLOSIVES AND BLASTING: |
| L. BURIED UTILITIES: |
| M. EMPLOYEE REQUIREMENTS: |
| In addition to the requirements listed in WAPA Construction Standard 1.4.3 all employees are restricted from wearing a headset, headphone, or other listening device, other than a hearing aid or instrument for the improvement of defective human hearing... |
| N. ELECTRICAL MINIMUM APPROACH DISTANCES: |
| In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances e... |
| O. SUBMITTALS AND CORRESPONDENCE: |
| 1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements: |
| 2. TRANSMITTALS: |
| 3. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e. brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlinin... |
| A courtesy copy of the submittal letter shall be emailed to the Construction office at the above address. |
| 4. SUBMITTAL RESPONSE: WAPA will respond to submittals electronically with an “Accepted” or “Not Accepted” status with comments as appropriate in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph to the email address w... |
| 5. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecutions, and Completion of Work” paragraph. |
| 6. PROJECT PROTOCOL: |
| DIVISION 2 – SITEWORK |
| A. DESCRIPTION OF BIDDING SCHEDULE ITEMS: |
| 1. Bidding Schedule item “Civil Site Preparation” includes providing and meeting all the sitework requirements and specifications listed on the Drawings and in Appendix A and B. |
| This item includes: clearing, grubbing, demolition, disposal, underground utilities, sewer, manholes, storm drains, culverts, oil/water separator, duct bank, trenching, backfill, traffic control, signage, surveying, staking, laydown areas, constructio... |
| 2. Bidding Schedule item “Complete Septic System” includes providing and meeting all the septic system requirements and specifications listed on the Drawings and in Appendixes A and B. |
| DIVISION 3 – CONCRETE |
| A. DESCRIPTION OF BIDDING SCHEDULE ITEMS: |
| 1. Bidding Schedule item “Concrete” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |
| This item includes: foundations; grade beams; indoor slabs on grade; trench drains; pipe bollards; anchor bolts; and associated excavation, backfill, and structural fill for these structures. |
| 2. Bidding Schedule item “Outdoor Concrete” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |
| This item includes: outdoor slabs on grade; ramps; curb, gutter, and sidewalks; and associated excavation, backfill, and subgrade materials. |
| DIVISION 11 – SERVICE BUILDING |
| A. DESCRIPTION OF BIDDING SCHEDULE ITEMS: |
| 1. Bidding Schedule item “Pre-engineered Building” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |
| This item includes: materials, fabrication, delivery, offloading, storage, erection, walk-through doors, overhead doors, door operators, windows, gutters, downspouts, insulation, flashing, sealing, framed openings, and miscellaneous steel. |
| 2. Bidding Schedule item “Mechanical and Plumbing” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |
| This item includes: hydronic heating system, boilers, pumps, eye wash stations, air handlers, fans, ductwork, louvers, hose bib stations, valves, meters, and local controls necessary for a complete mechanical and plumbing systems. |
| 3. Bidding Schedule item “Fire Protection” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |
| This item includes: alarms, detection, wiring, notification, and programming necessary for a complete fire protection system. |
| 4. Bidding Schedule item “Electrical” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |
| This item includes: light poles, grounding systems, lightning protection systems, lighting fixtures, lighting controls, exit signs, receptacles, conduit, cabling, terminations, panelboards, breakers, transformers, communication vaults, controls necess... |
| 5. Bidding Schedule item “Interior Finishes” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |
| This item includes: walls, furring, carpet, tile, paint, millwork, interior doors, wall base, trim, sinks, mirrors, and fixtures necessary for a complete finished interior. |
| 6. Bidding Schedule item “Provide New Physical Access Control System” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |
| 7. Bidding Schedule item “Provide Security Key Pads at Three New Doors” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendixes A and B. |