05 BAILEY BARCO (WPC 154) DD FQ4 JMD 25R0.pdf
PDF 3 MB Posted
- Attached to
- DRYDOCK: USCGC BAILEY BARCO DD FY25
- Solicitation number
- 70Z08025QPBPL0012
About this file
This file contains detailed technical specifications for a FY2025 drydock maintenance availability for the USCGC BAILEY BARCO, with work to be performed at the contractor's facility between August 12 - December 9, 2025. The work items include inspections and repairs of hull plating, watertight closures, propulsion shafting systems, electrical systems, machinery ventilation, HVAC ducts, rudder assemblies, stabilizing fins, bow thruster, stern launch door, sewage/grey water systems, and bilge surfaces.
Key requirements include preserving/resealing various deck coverings, renewing carpeting in multiple compartments, performing thermographic inspections of electrical distribution systems, cleaning ventilation systems, and conducting comprehensive testing of all affected systems during sea trials. The contractor must provide temporary services including office space, berthing for duty personnel, electrical power, water supply, and hazardous waste disposal. Government-furnished property includes specific replacement parts like propeller shafts, rudders, fin blades, and various hydraulic components. The work requires close coordination with Coast Guard personnel who will operate shipboard machinery and equipment during testing. Critical inspection reporting is required within the first 25% of the contract period for several key work items.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC BAILEY BARCO (WPC 1122)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2025
Developed By: Jason Devin
(Rev-0, 06 December 2024)
USCGC BAILEY BARCO (WPC-154) DRYDOCK AVAILABILITY FY2025
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics ............................................................................................................................. xii General Requirements WORK ITEM 1: Hull Plating, Inspect WORK ITEM 2: Watertight Closures, Assess WORK ITEM 3: Louver Assembly, Overhaul WORK ITEM 4: Louvers and Covers, Moisture Eliminator, Preserve WORK ITEM 5: Propulsion Shafting System, Inspect and Repair WORK ITEM 6: ASW/Firemain System Components, Renew/Overhaul WORK ITEM 7: Ship Service Diesel Generator(s), Clean & Inspect WORK ITEM 8: Electrical Power Distribution System, Thermographic Inspection (450 VAC And
Below) WORK ITEM 9: Machinery Ventilation System, Clean WORK ITEM 10: HVAC Duct System, Clean WORK ITEM 11: Rudder Assemblies, Inspect and Repair WORK ITEM 12: Stabilizing Fins, Inspect and Repair WORK ITEM 13: Bow Thruster Propeller and Tunnel, Inspect and Repair WORK ITEM 14: Stern Launch Door, Inspect and Preserve WORK ITEM 15: Sewage and Grey Water System, Clean and Inspect WORK ITEM 16: Bilge Surface, Clean and Inspect WORK ITEM 17: Forward Void, Float Coat, Renew WORK ITEM 18: Freeboard, Preserve WORK ITEM 19: Weatherdecks, Preserve WORK ITEM 20: U/W Body, Preserve WORK ITEM 21: Impressed Current Cathodic Protection (ICCP) and Anti-Fouling System, Inspect and
Maintain WORK ITEM 22: Interior Wet Deck Coverings, Reseal WORK ITEM 23: Interior Deck Covering (Carpeting), Renew WORK ITEM 24: Drydocking WORK ITEM 25: Temporary Services, Provide - Cutter WORK ITEM 26: Sea Trial Performance, Support, Provide WORK ITEM 27: Grey Water Tank, Preserve (Opt) iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 154 WPC 079-900, Rev D, Stability and Loading Data Booklet Coast Guard Drawing 154 WPC 079-902, Rev -, Curves of Form Hydrostatic Analysis Coast Guard Drawing 154 WPC 085-201, Rev A, Propulsion System, SSDG, EDG Installation Drawings Coast Guard Drawing 154 WPC 085-301, Rev B, Hull Lines and Offsets Coast Guard Drawing 154 WPC 111-301, Rev B, Shell Expansion Coast Guard Drawing 154 WPC 127-302, Rev C, Potable Water & Sewage Tank Fabrication Details Coast Guard Drawing 154 WPC 131-301, Rev D, Scantlings Main Deck Coast Guard Drawing 154 WPC 161-301, Rev C, Skegs and Stern Tubes Support Structures Coast Guard Drawing 154 WPC 163-201, Rev C, Sea Chest A&D Coast Guard Drawing 154 WPC 167-201, Rev E, Schedule of Doors, Manholes, and Hatches Coast Guard Drawing 154 WPC 168-201, Rev F, Louvers and Covers A&D Coast Guard Drawing 154 WPC 169-201, Rev C, Structural Closure Stern Gate Coast Guard Drawing 154 WPC 171-201, Rev D, Mast A&D Coast Guard Drawing 154 WPC 171-601, Rev D, Mast Prefab Coast Guard Drawing 154 WPC 204-301, Rev F, Equipment Removal Plan Coast Guard Drawing 154 WPC 243-201, Rev D, Main Propulsion Shafting A&D Coast Guard Drawing 154 WPC 245-304, Rev B, Propeller Plans and Data Six Blade Propeller Coast Guard Drawing 154 WPC 251-301, Rev D, Combustion Air Diagram Coast Guard Drawing 154 WPC 256-301, Rev D, Main and Auxiliary Cooling System Diagram Coast Guard Drawing 154 WPC 320-301, Rev E, 450V System Deck Plan Coast Guard Drawing 154 WPC 324-301, Rev C, Generator and Switchboard Drawing Coast Guard Drawing 154 WPC 324-304, Rev D, Generator & Switchboard Drawing (COED) Coast Guard Drawing 154 WPC 330-301, Rev G, 120V System Deck Plan Coast Guard Drawing 154 WPC 405-201, Rev D, Antenna A&D Coast Guard Drawing 154 WPC 405-202, Rev A, Antenna Arrangement and Installation Coast Guard Drawing 154 WPC 406-301, Rev G, Schedule of Bonding and Grounding Coast Guard Drawing 154 WPC 422-301, Rev F, Electrical Navigational Aids Coast Guard Drawing 154 WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows Coast Guard Drawing 154 WPC 506-301, Rev -, Fills, Vents, Sounds, Overflows Diagram v (Rev-0)
Coast Guard Drawing 154 WPC 512-201, Rev -, HVAC Arrangement Coast Guard Drawing 154 WPC 512-301, Rev B, HVAC System Diagram Coast Guard Drawing 154 WPC 512-305, Rev -, HVAC Equipment List Coast Guard Drawing 154 WPC 513-201, Rev C, Machinery Ventilation Arrangement Coast Guard Drawing 154 WPC 513-301, Rev C, Machinery Ventilation Diagram Coast Guard Drawing 154 WPC 528-301, Rev B, Grey Water System Diagram Coast Guard Drawing 154 WPC 529-301, Rev -, Bilge System Diagram Coast Guard Drawing 154 WPC 533-201, Rev C, Potable Water System Arrangement Coast Guard Drawing 154 WPC 533-301, Rev H, Potable Water System Diagram Coast Guard Drawing 154 WPC 556-202, Rev D, Fin Stabilizer Hydraulic System A&D Coast Guard Drawing 154 WPC 556-302, Rev C, Fin Stabilizer Hydraulic System Diagram Coast Guard Drawing 154 WPC 561-202, Rev C, Steering Arrangement & Details Coast Guard Drawing 154 WPC 562-201, Rev A, Rudder Details Coast Guard Drawing 154 WPC 562-202, Rev C, Rudder Arrangement & Details Coast Guard Drawing 154 WPC 565-201, Rev -, Fin Stabilizer System A&D Coast Guard Drawing 154 WPC 565-301, Rev A, Fin Stabilizer Control System Coast Guard Drawing 154 WPC 565-302, Rev C, Fin Stabilizer Control System COED Coast Guard Drawing 154 WPC 568-201, Rev B, Bow Thruster System A&D Coast Guard Drawing 154 WPC 593-201, Rev F, Sewage System Arrangement Coast Guard Drawing 154 WPC 593-301, Rev C, Sewage System Diagram Coast Guard Drawing 154 WPC 593-303, Rev A, Sewage Control System Coast Guard Drawing 154 WPC 601-302, Rev D, General Arrangement Coast Guard Drawing 154 WPC 602-305, Rev D, Visual Identification and Draft Marks Plan Coast Guard Drawing 154 WPC 631-301, Rev A, Paint and Preservation Schedule Coast Guard Drawing 154 WPC 633-301, Rev C, Cathodic Protection System Coast Guard Drawing 154 WPC 634-301, Rev B, Deck Covering Schedule Coast Guard Drawing 154 WPC 995-900, Rev -, FRC Docking Assembly Details & Construction Coast Guard Drawing 154 WPC 997-002, Rev -, Alternate Docking Plan Mobile Lift Option Coast Guard Drawing 154 WPC 997-004, Rev -, Steel Block Towers for Alternate Docking Plan Coast Guard Drawing 154 WPC 997-302, Rev -, Docking Plan (Supersedes DWGS 154-WPC-997-1, 997-301) Coast Guard Drawing 154B WPC 111-301, Rev A, Shell Expansion Coast Guard Drawing 154B WPC 131-301, Rev B, Scantlings Main Deck Coast Guard Drawing 154B WPC 161-301, Rev -, Skegs and Stern Tubes Support Structures Coast Guard Drawing 154B WPC 167-201, Rev -, Schedule of Doors, Manholes, and Hatches Coast Guard Drawing 154B WPC 169-201, Rev -, Structural Closure Stern Gate Coast Guard Drawing 154B WPC 171-201, Rev A, Mast A&D Coast Guard Drawing 154B WPC 204-301, Rev -, Equipment Removal Plans Coast Guard Drawing 154B WPC 243-201, Rev A, Main Propulsion Shafting A&D Coast Guard Drawing 154B WPC 245-301, Rev -, Propeller Plans and Data Six Blade Propeller Coast Guard Drawing 154B WPC 251-301, Rev -, Combustion Air Diagram Coast Guard Drawing 154B WPC 256-301, Rev A, Main and Auxiliary Cooling System Diagram vi (Rev-0)
Coast Guard Drawing 154B WPC 320-301, Rev -, 450V System Deck Plan Coast Guard Drawing 154B WPC 330-301, Rev B, 120V System Deck Plan Coast Guard Drawing 154B WPC 405-201, Rev -, Antenna A&D Coast Guard Drawing 154B WPC 405-202, Rev -, Antenna Arrangement and Installation Coast Guard Drawing 154B WPC 406-301, Rev C, Schedule of Bonding and Grounding Coast Guard Drawing 154B WPC 422-301, Rev -, Electrical Navigational Aids Coast Guard Drawing 154B WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows Coast Guard Drawing 154B WPC 512-201, Rev A, HVAC Arrangement Coast Guard Drawing 154B WPC 512-301, Rev -, HVAC System Diagram Coast Guard Drawing 154B WPC 512-305, Rev -, HVAC Equipment List Coast Guard Drawing 154B WPC 513-201, Rev B, Machinery Ventilation Arrangement Coast Guard Drawing 154B WPC 513-301, Rev -, Machinery Ventilation Diagram Coast Guard Drawing 154B WPC 533-201, Rev -, Potable Water System Arrangement Coast Guard Drawing 154B WPC 556-202, Rev -, Fin Stabilizer Hydraulic System A&D Coast Guard Drawing 154B WPC 562-201, Rev -, Rudder Details Coast Guard Drawing 154B WPC 562-202, Rev -, Rudder Arrangement & Details Coast Guard Drawing 154B WPC 565-301, Rev -, Fin Stabilizer Control System Coast Guard Drawing 154B WPC 565-302, Rev -, Fin Stabilizer Control System COED Coast Guard Drawing 154B WPC 568-201, Rev -, Bow Thruster System A&D Coast Guard Drawing 154B WPC 593-201, Rev A, Sewage System Arrangement Coast Guard Drawing 154B WPC 593-301, Rev -, Sewage System Diagram Coast Guard Drawing 154B WPC 601-302, Rev -, General Arrangement Coast Guard Drawing 154B WPC 602-305, Rev B, Visual Identification and Draft Marks Plan If your particular vessel doesn’t have these either submit a CSMP (the work to add them will be written into this work item by SES) or have the KTR install via CR (in conjunction with the inspection/CFR requested in 3.1.8 below).
Vessels have been delivered w/out the main deck cement epoxy fairings shown on SECTION/PLAN 39 A/C on 634-301.
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual Coast Guard Technical Publication (TP) 8000, SWBS 256, Apr 2015, Main Engine Seawater Strainer, 10
Inch Duplex Basket Strainer Coast Guard Technical Publication (TP) 8001B, SWBS 633, Sep 2018, Cathodic Protection System –
Model CA44227 Coast Guard Technical Publication (TP) 8010B, SWBS 565, May 2019, Fin Stabilizer System – Model
QC-1500 with MPU20 Hydraulic System Coast Guard Technical Publication (TP) 8051, March 2012, SSDG QSM11-DM Manual Coast Guard Technical Publication (TP) 8081A, SWBS 243, Apr 2018, Stern Tube Seal with Emergency
Packing Gland Coast Guard Technical Publication (TP) 8096B, SWBS 252, Aug 2018, Bowthruster – Model 60 LK with
Operator Panel and Motor Drive – Installation, Service, and Operation Manual Coast Guard Technical Publication (TP) 8105, SWBS 533, Apr 2018, Watermaker/Brominator Reverse
Osmosis – Model FRC-B 1600 vii (Rev-0)
Coast Guard Technical Publication (TP) 8123, SEP 2019, Preliminary - Heating, Ventilation, and Air Conditioning System - Frc-514-P1
Coast Guard Technical Publication (TP) 8153A, SWBS 562, Apr 2019, Rudderstock Seal Assembly, Type EL + IS, Model H 78525-01
Coast Guard Technical Publication (TP) 8216, Jun 2019, Digital Excitation Control System - Model
DECS-250
Coast Guard Technical Publication (TP) 8911B, SWBS 086, Apr 2020, Technical Repair Standard for Use on FRC - Fin Stabilizer System Model QC-1500
Coast Guard Technical Publication (TP) 8912A, Mar 2020, Technical Repair Standard for Use on FRC - Ship Service Diesel Generator Unit Model - QSM11-DM and HCM434E
Coast Guard Technical Publication (TP) 8913A, SWBS 086, Mar 2020, Technical Repair Standard for Propellers
Coast Guard Technical Publication (TP) 8916, SWBS 086, 28 JUL 2020, TECHNICAL REPAIR
STANDARD FOR USE ON FRC - FLOW ADAPTIVE RUDDER AND EL + IS RUDDERSTOCK
SEAL MODEL - H 78525-01 (HULLS 1118, 1139 AND ON) 154' WPC (A) AND (B) CLASS
CUTTERS
Coast Guard Technical Publications (TP) 6632, SWBS 6633, Jul 2015, Reduction Gear – Model ZF 280-1 Fire Prevention and Response Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC
Electrical Motors Surface Forces Logistics Center Standard Specification 3100 (SFLC Std Spec 3100), 2022, Inspect, Test and Recondition AC Synchronous Machines In-Place Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary
Machine Systems Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean
Shipboard Ventilation Systems Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior
Deck Covering Systems Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary
Services
OTHER REFERENCES
American Bureau of Shipbuilding (ABS) Rules for Survey After Construction, Part 7 American Society for Nondestructive Testing, SNT-TC-1A: Personnel Qualification and Certification in
Nondestructive Testing, 2016 American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and
Welding End viii (Rev-0)
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component
Adhesives (An) ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates Coast Guard Maintenance Procedure Card (MPC) B10017.D, CONVERSION B/T ANODE BOLT (1
Time, 01-32) Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment Commercial Item Descriptions (CID) A-A-59316, Nov 2003; Abrasive Materials for Blasting DOD-STD-2003, Dec 1990, Electric Plant Installations, Standard Methods for Surface Ships and
Submarines (Cable), Figures 1B5, 3B19, 3B20, 3B21 Federal Specification (Fed Spec) DDD-C-95, Mar 1972, Carpets and Rugs, Wool, Nylon, Acrylic, Modacrylic Federal Standard (FED-STD) 595, 2008, Colors Used In Government Procurement Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves MIL-C-16173, Jan 1993, Corrosive Preventative Compound, Solvent Cutback, Cold Application MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application MIL-PRF-24635, 2009, Coating Systems, Weather-Resistant, Exterior Use MIL-PRF-24667, Jun 2005, Coating system, Non-Skid, for Roll or Spray Application MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure QPL-24667, May 2006, Qualified Product List of Products Qualified under Performance Specification
MIL-PRF-24667, Coating system, Non-Skid, for Roll or Spray Application Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE No.2 2004, Near White Blast
Cleaning) ix (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
5 Y **Propeller Shaft NSN: 2010-01-605-7516 2 ea. 103,000 5 Y **LH Propeller NSN: 2010-01-628-0276 PN:
531915 1 ea. 190,000
5 Y **RH Propeller NSN: 2010-01-627-9761 531914
1 ea. 190,000
5 N **Stave Kit (each kit contains 8 reg. Romor staves, 2 rubber locking staves, 2 Romor staves w/keeper slot)
NSN: 3120-01-605-7400 P/N:
80920203000003
4 kt 2430
5 N **FWD Bearing Split External Retaining Ring
Kit (each kit contains 1ea retaining ring, 10ea socket head cap screws)
NSN: 3120-01-605-7345 P/N:
80920203000004
2 kt 1970
5 N **AFT Bearing Split External Retaining Ring
Kit (each kit contains 1ea retaining ring, 10ea socket head cap screws)
NSN: 3120-01-605-7510 P/N:
80920203000005
2 kt 2575
5 N **Kit, Installation Part- Replacement (see note
4.1 for kit contents)
NSN: 2010-01-629-4693 P/N:
950700
2 kt 1900
5 Y *Kit, Propeller - Removal/Installation Tools and Equipment (see note 4.2 for kit contents)
NSN: 2010-01-632-2198/ P/N:
999120
1 kt 22,970
5 N **Shaft Seal Overhaul Kit (see table 7-4 of TP-
8081, pg 7-8, Service Kit B)
NSN:5330-01-618-5248 P/N:
H76214-6
2 kt 5650.93
5 N **Shaft Seal Overhaul Kit (see table 7-5 of TP-
8081, pg 7-9, Service Kit C)
NSN: 5330-01-618-5276 P/N:
H76214-8
2 kt 4896
5 N Anodes, Zinc (stern tube)
NIIN: 01-644-5483 P/N:
Z0020202H3
16 ea. 50
5 N CAD Model of LH & RH propellers for use in propeller scans and analysis
N/A 1 ea. 1 x (Rev-0)
11 Y **Port Rudder NSN: 2040-01-690-5509 1 ea. 30,000 11 Y **Stbd Rudder NSN: 2040-01-690-5507 1 ea. 30,000 11 N Shaft Seal Overhaul Kit
(Service Kit A from TP- 8153, pg 7-5, Table 7-2)
NSN: 5330-01-595-4647 PN:
H785252-01-6
2 kt 9722.00
11 N Shaft Seal Overhaul Kit (Service Kit B from TP- 8153, pg 7-5, Table 7-3)
NSN: 5330- 01-596-7760 PN:
H78525-01-7
2 kt 6,170.00
11 N Locknut PC5 154WPC 562-002
NSN: 5310-33-201-6431 PN:
KM32
4 ea. 100.00
11 N Lock Washer PC6
154WPC 562-002
NSN: 5310-33-201-5247 PN:
MB 32
2 ea. 150.00
11 N Upper Roller Bearing
PC7 154WPC 562-002
NSN: 3110-01-597-3537 PN:
23032 CC/C2W33
2 ea. 502.11
11 N Oil Seal PC8 154WPC 562-002
NSN: 5330-01-618-5091 PN:
CR70028 CRWH1R
2 ea. 60.00
11 N Lower Bearing PC9
154WPC 562-002
NSN: 3120-01-631-4104 2 ea. 1,162.00
12 Y **Fin Blade NSN: 2040-01-598-8181 PN:
601-15-020S02-00-00-A
2 ea. 22,254.38
12 N **Hydraulic Cylinder NSN: 9999-01-682-3497 PN:
304-07-070040-00-01-ABS_C
4 ea. 5,723.55
12 Y Shaft, Shouldered NSN: 3040-01-659-0358 PN:
601-15-S00001-00-05_F
2 ea. 12,076.58
13 N **Set of bevel gears 19:28, Mfr: Schottel
NSN: 3020-01-618-1133 PN:
1088301
1st. 10,378.13
13 Y **Propeller, Mfr:
Schottel
NSN: PN: 1161329 1ea. 20,000.00
15 N **Sewage Tank Zinc Anode
NIIN: 014474686 2 142.19
15 N Tank, Accumulator NIIN: 251632044 PN:
012101232
1 6,259.51
20 Y **Depth Sounder Transducer
NSN: 5845-01-586-7921, P/N:
SS164-20-10-F
1 ea. $10,000.00
20 Y **Speed log transducer NSN: 6605-99-839-3629 1 ea. $10,000.00 20 N Parts Kit, Gate Valve
(Doppler Speed Log)
NSN: 4820-99-374-5925 P/N:
81702-0410-00 1 ea. $1,000.00
20 N Zinc Anodes NIIN: 01-647-6179 P/N: GA-4 4 ea. $50.00 21 N **Anode, Corrosion, Elliptical
NSN: 5340-99-400-2561 PN:
PPEC1202-MM50
2 ea. 1,900.00
21 N **Silver/Silver Chloride Reference
Electrode Cell
NSN: 6630-99-553-5405 PN:
PPR100019
2 ea. 1,625.00
21 N Copper Anode, Anti- Fouling
NSN: 5342-99-133-5325 PN:
PAAZRRY037FT
3 ea. 436.69
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C5IT Service Center xi (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
1 Hull Plating, Inspect
5 Propulsion Shafting System, Inspect and Repair
6 ASW/Firemain System Components, Renew/Overhaul
11 Rudder Assemblies, Inspect and Repair
12 Stabilizing Fins, Inspect and Repair
13 Bow Thruster Propeller and Tunnel, Inspect and Repair
14 Stern Launch Door, Inspect and Preserve
15 Sewage and Grey Water System, Clean and Inspect
18 Freeboard, Preserve
19 Weatherdecks, Preserve
20 U/W Body, Preserve
21 Impressed Current Cathodic Protection (ICCP) and Anti-Fouling System, Inspect and Maintain
26 Sea Trial Performance, Support, Provide xii (Rev-0)
PRINCIPAL CHARACTERISTICS
154' WPC (SENTINEL CLASS)
PHYSICAL
Anchor ROCNA, anchor, 150 KG/ 331 LB, Stainless Steel Bulkheads (7), Watertight Bulkheads located below the Main Deck Displacement, delivery, light ship 302 Metric Tons Draft, full load 2.58 Meters (8.46 Feet) End of service life displacement 353 Metric Tons Framing Longitudinal Full load displacement 353 Metric Tons Height of highest projection 17.22 Meters (56.5 Feet) Length overall (loa) 46.80 Meters (153.5 Feet) Maximum beam 7.75 Meters (25.43 Feet) Minimum operating displacement 314 Metric Tons Waterline length (lwl) 44.35 Meters (145.5 Feet)
HULL
Hull/main weatherdeck material AH-36 Steel Superstructure 5456-H1111 Aluminum
MACHINERY
Bow thruster Schottel STT 60 LK Diameter of propeller 1900 mm Emergency service generator (edg) Cummins 6BTA5.9-DM Diesel with Stanford 93KW Generator Fin stabilizer (2), Quantum QC1500 Main propulsion (2), MTU 20V4000 M93L, Sequential Turbo-Charged Diesels Number of blades 6 Number of propellers (2) Michigan Wheel Marine Propeller pitch capability Fixed Propulsion shafts (2), Electralloy Nitronic 50HS (9430mm) Shafts Reduction gears (2), ZF 23560C/D Series Rudders (2), 316L Stainless Steel Shaft rotations per minute 478 Shaft(s) bearing, aft (2), Duramax Bearings Shaft(s) bearing, intermediate (2), Duramax Bearings Shaft(s) diameter 8 Inches Shaft(s) Seal (2), Wartsila Mechanical Seals Ship service generators (2), Cummins QSM11-DM Diesels with Stanford 317KW Generator
TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)
Fresh water tank, port (3-38-2-w) 708 gal Fresh water tank, stbd (3-38-1-w) 756 gal Fuel oil edg day tank (1-10-1-f) 134 gal Fuel oil gen. ovrflw tnk, ctr. (3-40-0-f) 1,159 gal Fuel oil overflow tank, center (3-10-0-f)
616 gal
Fuel oil service tank, #1 port (3-17-2-f)
1,750 gal
Fuel oil service tank, #1 stbd (3-17-1-f)
1,750 gal xiii (Rev-0)
Fuel oil service tank, #2 port (3-40-2-f)
890 gal
Fuel oil service tank, #2 stbd (3-40-1-f)
890 gal
Fuel oil storage tank, #1 center (3-11- 0-f)
5,040 gal
Fuel oil storage tank, #2 center (3-23- 0-f)
5,350 gal
TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)
Grey water tank, (3-17-0-w) 2,668 gal.
Lube oil storage tank, (2-35-2-f) 146 gal.
Oily water tank, (3-34-1-w) 336 gal.
Sewage collection tank, (3-6-0-w) 429 gal.
Waste oil tank, (3-34-2-f) 336 gal.
1 (Rev-0)
00000_0824_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure
2 (Rev-0)
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.1.1.3 SFLC-PBPL Availabilities (87 WPB, 110 WPB, & 154 WPC). The Contractor must conform to SFLC Std Spec 5550 with the following amendments and supplements:
• For contracts executed at a Contractor’s facility, submit (pre-award) the facility’s Fire Safety Plan document described in 29 CFR 1915.502 – “Fire Safety Plan”. For planning assume that Coast Guard personnel will not be available to fight a fire. All welding requires isolation of the installed fire detection system and other electronic systems throughout the ship.
• For all contracts at all facilities, submit the following information pre-award, taking into consideration how the maintenance/repairs specified in the work items will affect uninterrupted operation of the subject systems; make all necessary amendments to this submission after discussions with the COR at the arrival conference and during contract execution as emerging conditions warrant:
o Describe all anticipated needs for fire detection/alarm, fire-fighting, and shipboard lighting and communication systems supplementation (see below) and a description of the proposed remedies/solutions (include pricing for maintaining capability in pre-award quote).
o Describe how any required temporary/supplemental fire detection/alarm systems will notify fire responders.
o Describe all anticipated breaches of the cutter’s Fire Protection Boundaries and the proposed temporary solutions that will minimize impact on the Fire Protection Boundary’s proper function (e.g. removal of cables/hoses/etc. at the end of work day or installation of quick disconnects, installation of temporary fire curtains, etc.).
• Whenever maintenance/repairs described in work items or Change Requests necessitate securing, or making inoperable, all or part of the vessel’s fire detection or fire alarm system, submit a proposal to the COR/KO describing an equivalent method(s) for temporarily maintaining all lost functionality of the system(s). Select the most economical option(s) available (i.e. for extended loss of service (more than 8 hours) of the entire system the temporary fire detection/alarm system described in SFLC Std Spec 5550 may be the best option, for shorter durations (less than 8 hours) temporary watch standers may be more economical, etc.). After the COR has agreed to the proposal, maintain the capability of these systems for the duration of the contract to the greatest practicable extent.
3 (Rev-0)
• Whenever maintenance/repairs described in work items or Change Requests necessitate securing, or making inoperable, all or part of the vessel’s firefighting (e.g. fire main system, P100 and other dewatering systems, halon systems, portable fire extinguishers, etc.), lighting, and communications systems, submit a proposal to the COR/KO describing equivalent method(s) for temporarily maintaining all lost functionality of the system(s). Select the most economical option(s) available.
After the COR has agreed to the proposal, maintain fire detection/alarm/fighting and lighting/communications capability for the duration of the contract to the greatest practicable extent.
• All Fire Protection Boundaries must be left intact and functional at all times to the greatest practicable extent. Notify the COR in writing whenever a breached Fire Protection Boundary will be left unattended outside of normal working hours (e.g. a door/hatch is made un-closable/un-securable due to repair work, an access cut is made into deck/bhd that is part of a Fire Protection Boundary, etc.).
When a Fire Protection Boundary must be breached to facilitate contract work, minimize the impact using industry-standard methods (e.g. fire curtains, quick-disconnect fittings, etc.).
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1500, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70
4 (Rev-0) microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Unit is small quantity.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of
5 (Rev-0) regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage) if work is being performed at a USCG Facility.
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
6 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK
ITEM #
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
7 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL # WORK
ITEM # WORK ITEM TITLE
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER
COAT, BARRIER COAT, TOP
COAT, ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFAC
E
AMBIEN
T
ΔT
| DP -
SURFACE |
8 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /
TIME
9 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT
QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
10 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK
ITEM #
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
COATING MFG PRODUCT NAME BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-0)
4.2 Tank and Void Assessment form.
13 (Rev-0)
11100_JLW_0523_154
WORK ITEM 1: Hull Plating, Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to conduct an inspection of the hull shell plate and inaccessible voids and to perform the designated hulls scans as specified below.
TABLE 1 – ELEVATED INSPECTION SCANS
INCLUDED SCAN TYPE
NO
Conduct an automated crawler ultrasonic inspection scanning (i.e. SIDESCAN) of underwater hull plating and entire freeboard, up to the main deck edge to detect all metal corrosion and deterioration. See paragraph 3.6.1 for requirements.
YES
Conduct a 3D laser scan of the cutter’s exterior hull shell, deck and dock floor locations/deformations and provide results in 3D CAD format. See paragraph 3.6.2 for requirements
If “YES” appears in the left-column cell then the corresponding scan work is required, must be quoted on, and executed during the contract performance period. If “NO” appears in the cell then the corresponding scan work is NOT required, must NOT be quoted on, nor executed during the contract performance period.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 154 WPC 085-301, Rev B, Hull Lines and Offsets Coast Guard Drawing 154 WPC 111-301, Rev B, Shell Expansion Coast Guard Drawing 154B WPC 111-301, Rev A, Shell Expansion Coast Guard Drawing 154 WPC 997-302, Rev -, Docking Plan (Supersedes DWGS 154-WPC-
997-1, 997-301)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
OTHER REFERENCES
ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-
Component Adhesives (An)
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
• 3.4 Initial inspection/test report submission.
3.1.2 Tech Rep. None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.1.5 Refer to Coast Guard Drawings listed in Section 2 (References) for guidance.
3.2 Inspect hull shell plate. In the presence of the Coast Guard Inspector, the Contractor must visually inspect all hull freeboard and underwater body shell plate (water boundary) to identify all discrepancies (e.g. pitting, rust, significant deformation, cracks, obvious reduced shell plate thickness, etc.). If "Yes" is specified in Table 1 above for either of the elevated inspections, then perform those inspections as well.
If "No" is specified in Table 1 above, then the corresponding elevated inspection is not…
This is the start of the file's text. The full file is on GovTribe.