About this file
This attachment details the Build America Buy America (BABA) Act compliance requirements mandated by the Bipartisan Infrastructure Law (P.L. 117-58) for the Hollywood Reactor Tank Maintenance project in Pennsylvania. The document establishes procurement preferences requiring that all iron, steel, manufactured products, and construction materials used in infrastructure projects funded through federal financial assistance programs must be produced in the United States, effective May 14, 2022. For manufactured products, domestic content must comprise at least 55 percent of the total component costs unless an alternative standard applies. The BABA preference applies only to articles, materials, and supplies that are consumed, incorporated, or affixed to the infrastructure project itself, excluding temporary tools, equipment, and portable furnishings. The Department of the Interior may grant waivers from these requirements under three circumstances: non-availability of domestically produced materials in sufficient quantities or satisfactory quality, unreasonable cost increases exceeding 25 percent of the overall project cost, or public interest considerations.
Waiver requests must be submitted in writing to the financial assistance awarding officer and must include specific information including the type of waiver, requesting entity details, the federal award identification number, project description and location, itemized lists of materials seeking waiver status with origins and costs, certification of good faith bidding efforts, and documentation of efforts to avoid waiver necessity. Waiver requests are subject to public comment periods of at least 15 days and review by the Made in America Office before approval determination. Additionally, the contract is subject to Davis Bacon prevailing minimum wage requirements, and organizations receiving funding may be eligible for additional support through Pennsylvania's Commonwealth Workforce Transformation Fund under Executive Order 2023-17.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT C
BUILD AMERICA BUY AMERICA (“BABA”) DOMESTIC PROCUREMENT
PREFERENCE
Contractor must comply with the federal “Build American Buy American Act” P.L. 117-58
(also known as the Bipartisan Infrastructure Law or Infrastructure Investment and Jobs Act) regarding any work performed on or after May 14, 2022.
As required by Section 70914 of the Bipartisan Infrastructure Law (also known as the
Infrastructure Investment and Jobs Act), P.L. 117-58, on or after May 14, 2022, none of the funds under a federal award that are part of Federal financial assistance program for infrastructure may be obligated for a project unless all of the iron, steel, manufactured products, and construction materials used in the project are produced in the United States, unless subject to an approved waiver. The requirements of this section must be included in all subawards, including all contracts and purchase orders for work or products under this program. In the event of any conflict between this section’s requirements and those described in DEP’s 2016 General Conditions for Construction, including but not limited to Subsections
4.10.K.16 and 5.14.B.3, this section’s requirements are controlling.
Recipients of an award of Federal financial assistance are hereby notified that none of the funds provided under this award may be used for a project for infrastructure unless:
1. all iron and steel used in the project are produced in the United States--this means all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States;
2. all manufactured products used in the project are produced in the United States— this means the manufactured product was manufactured in the United States; and the cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product, unless another standard for determining the minimum amount of domestic content of the manufactured product has been established under applicable law or regulation; and
3. all construction materials are manufactured in the United States—this means that all manufacturing processes for the construction material occurred in the United States.
The BABA preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a BABA preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project but are not an integral part of the structure or permanently affixed to the infrastructure project.
For further information on the BABA preference, please visit www.doi.gov/grants/BuyAmerica. Additional information can also be found at the White
House Made in America Office website: www.whitehouse.gov/omb/management/made-in-america/.
Waivers
When necessary, with the approval of the Department of Environmental Protection, recipients may apply for, and the Department of the Interior (DOI) may grant, a waiver from these requirements, subject to review by the Made in America Office. The DOI may waive the application of the domestic content procurement preference in any case in which it is determined that one of the below circumstances applies:
1. Non-availability Waiver: the types of iron, steel, manufactured products, or construction materials are not produced in the United States in sufficient and reasonably available quantities or of a satisfactory quality;
2. Unreasonable Cost Waiver: the inclusion of iron, steel, manufactured products, or construction materials produced in the United States will increase the cost of the overall project by more than 25 percent; or
3. Public Interest Waiver: applying the domestic content procurement preference would be inconsistent with the public interest.
There may be instances where an award qualifies, in whole or in part, for an existing DOI general applicability waiver as described at:
www.doi.gov/grants/BuyAmerica/GeneralApplicabilityWaivers. If the specific financial assistance agreement, infrastructure project, or non-domestic materials meets the criteria of an existing general applicability waiver within the limitations defined within the waiver, the recipient is not required to request a separate waiver for non-domestic materials.
If a general applicability waiver does not already apply, and a recipient believes that one of the above circumstances applies to an award, a request to waive the application of the domestic content procurement preference may be submitted to the financial assistance awarding officer in writing. Waiver requests shall include the below information. The waiver shall not include any Privacy Act information, sensitive data, or proprietary information within their waiver request. Waiver requests will be posted to www.doi.gov/grants/buyamerica and are subject to public comment periods of no less than
15 days. Waiver requests will also be reviewed by the Made in America Office.
1. Type of waiver requested (non-availability, unreasonable cost, or public interest).
2. Requesting entity and Unique Entity Identifier (UEI) submitting the request.
3. Department of Interior Bureau or Office who issued the award.
4. Federal financial assistance listing name and number (reference block 2 on DOI
Notice of Award)
5. Financial assistance title of project (reference block 8 on DOI Notice of Award).
http://www.whitehouse.gov/omb/management/made-in-america/ http://www.whitehouse.gov/omb/management/made-in-america/ http://www.doi.gov/grants/BuyAmerica/GeneralApplicabilityWaivers http://www.doi.gov/grants/buyamerica
6. Federal Award Identification Number (FAIN).
7. Federal funding amount (reference block 11.m. on DO Notice of Award).
8. Total cost of Infrastructure expenditures (includes federal and non-federal funds to the extent known).
9. Infrastructure project description(s) and location(s) (to the extent known).
10. List of iron or steel item(s), manufactured goods, and construction material(s) the recipient seeks to waive from Buy America requirements. Include the name, cost, countries of origin (if known), and relevant PSC or NAICS code for each.
11. A certification that the recipient made a good faith effort to solicit bids for domestic products supported by terms included in requests for proposals, contracts, and nonproprietary communications with the prime contractor.
12. A statement of waiver justification, including a description of efforts made (e.g., market research, industry outreach) by the recipient, in an attempt to avoid the need for a waiver. Such a justification may cite, if applicable, the absence of any Buy
America-compliant bids received in response to a solicitation.
13. Anticipated impact if no waiver is issued.
Approved waivers will be posted at www.doi.gov/grants/BuyAmerica/ApprovedWaivers;
recipients requesting a waiver will be notified of their waiver request determination by an awarding officer.
Questions pertaining to waivers should be directed to the financial assistance awarding officer.
Definitions
“Construction materials” includes an article, material, or supply that is or consists primarily of:
• non-ferrous metals;
• plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables);
• glass (including optic glass);
• lumber; or
• drywall.
“Construction Materials” does not include cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives.
“Domestic content procurement preference’’ means all iron and steel used in the project are produced in the United States; the manufactured products used in the project are produced in the United States; or the construction materials used in the project are produced in the
United States.
“Infrastructure” includes, at a minimum, the structures, facilities, and equipment for, in the
United States, roads, highways, and bridges; public transportation; dams, ports, harbors, and other maritime facilities; intercity passenger and freight railroads; freight and intermodal http://www.doi.gov/grants/BuyAmerica/ApprovedWaivers facilities; airports; water systems, including drinking water and wastewater systems;
electrical transmission facilities and systems; utilities; broadband infrastructure; and buildings and real property. Infrastructure includes facilities that generate, transport, and distribute energy.
‘‘Project’’ means the construction, alteration, maintenance, or repair of infrastructure in the
United States.
IMPLEMENTATION OF EXECUTIVE ORDER 2023-17, COMMONWEALTH
WORKFORCE TRANSFORMATON PROGRAM
Pursuant to Executive Order 2023-17, Commonwealth Workforce Transformation Program
(July 31, 2023), awards under this solicitation have been funded by the Infrastructure
Investment and Jobs Act (IIJA) of 2021 and/or the Inflation Reduction Act (IRA) of 2022.
Should you receive funding as a result of your submission, your organization may be eligible for additional funding from the Commonwealth Workforce Transformation Fund (CWTF).
For more information, visit www.pa.gov/newjobs or email newjobs@pa.gov.
DAVIS BACON PREVAILING MINIMUM WAGE:
Davis Bacon Prevailing Minimum Wages rates apply.
http://www.pa.gov/newjobs mailto:newjobs@pa.gov