032_Attachment_4-Past_Performance_Questionnaire.pdf
PDF 361 KB Posted
- Solicitation number
- 1333MK26Q0011
About this file
This is a Past Performance Questionnaire used to evaluate a contractor's performance across four key dimensions: Quality of Service, Schedule, Cost Control, and Management. The document is associated with Solicitation 1333MK26Q0011 and is to be completed by Isaac Bright at NOAA, with a submission deadline of 01/02/2026 at 1600 PST.
The questionnaire provides a structured rating system with five performance levels (Exceptional, Very Good, Satisfactory, Marginal, Unsatisfactory) for each evaluation area. For each dimension, the ratings assess different aspects such as adherence to contract requirements, timeliness, problem-solving effectiveness, corrective action implementation, and overall government benefit. The form includes space for comments and requires the rater's name, signature, and date at the conclusion. The document is marked as Source Selection Information, indicating its sensitivity and restricted use in the procurement process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 020_140802-26-0077_Brand_Name_Justification_Redacted.pdf | ||
| Sol_1333MK26Q0011.pdf | ||
| 002_140802-26-0077_Statement_of_Need.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 4:
PAST PERFORMANCE
QUESTIONNAIRE
SOLICITATION
Source Selection Information
PAST PERFORMANCE QUESTIONNAIRE
CONTRACTOR BEING REVIEWED:
PERSON COMPLETING QUESTIONNAIRE:
REFERENCE CONTRACT #:
BRIEF DESCRIPTION:
Send Completed Questionnaire to at no later than
1. QUALITY OF SERVICE
Assess the contractor’s performance to contract requirements, specifications, and standards of good workmanship (e.g. commonly accepted technical, professional, or environmental standards).
(Check the appropriate rating box.)
RATING ADJECTIVAL
RATING
DEFINITION
EXCEPTIONAL
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.
VERY GOOD
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.
SATISFACTORY
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.
MARGINAL
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
UNSATISFACTORY
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.
Comments:
1333MK26Q0011
01/02/2026
Isaac Bright isaac.bright@noaa.gov @1600pst
Isaac.Bright Inserted Text 10+6
Source Selection Information
2. SCHEDULE
Assess the timeliness of the contractor against the completion of the contract, task orders, milestones, delivery schedules, and administrative requirements (e.g. efforts that contribute to or affect the schedule variance).
(Check the appropriate rating box.)
RATING ADJECTIVAL
RATING
DEFINITION
EXCEPTIONAL
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.
VERY GOOD
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.
SATISFACTORY
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.
MARGINAL
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
UNSATISFACTORY
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.
Comments:
3. COST CONTROL
Assess the contractor’s effectiveness in forecasting, managing, and controlling cost.
(Check the appropriate rating box.)
RATING ADJECTIVAL
RATING
DEFINITION
EXCEPTIONAL
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.
VERY GOOD
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.
SATISFACTORY
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.
MARGINAL
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
UNSATISFACTORY
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the
4. MANAGEMENT
Assess the integration and coordination of all activities needed to execute the contract, specifically the timeliness, completeness and quality of problem identification, corrective action plans, proposal submittals, the contractor’s history of reasonable and cooperative behavior, and customer satisfaction.
(Check the appropriate rating box.)
RATING ADJECTIVAL
RATING
DEFINITION
EXCEPTIONAL
Performance meets contractual requirements and exceeds many to the Government’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.
VERY GOOD
Performance meets contractual requirements and exceeds some to the Government’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.
SATISFACTORY
Performance meets contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.
MARGINAL
Performance does not meet some contractual requirements. The element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions.
UNSATISFACTORY
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the
ADDITIONAL COMMENTS, IF ANY:
Rater’s Name: ___________________________
Rater’s Signature: ________________________
Date: ____________________________________