This is a Solicitation/Contract/Order for Commercial Products and Commercial Services (Standard Form 1449) issued by the Library of Congress for window treatment products and related services.
The Library seeks a single-award Indefinite Delivery/Indefinite Quantity (IDIQ) contract with a contract minimum of $1,000.00 and maximum of $1,186,000.00 over a five-year ordering period (January 4, 2027 through January 3, 2032). The contractor must provide commercial window treatments, window shades, custom draperies, theater curtains, wall-mounted acoustic upholstery products, and related services including installation, repair, cleaning, product specifications, shop drawings, and project management. All products must pass NFPA 701 vertical ignition tests and ASTM D6413 standards, with UL 2818 Greenguard Gold certification required for low chemical emissions. The contractor must maintain and provide access to commercially available price lists with fixed discount rates throughout the contract period; underlying product prices may fluctuate but contract discount rates remain fixed. Offerors must submit proposals electronically by December 8, 2026 at 2:00 PM EST to the Contracting Officer (David Leonard) and Contract Specialist (Melinda Dawson). Award is unrestricted with no set-asides designated. Evaluation will use a best-value trade-off methodology prioritizing technical approach, technical expertise, past performance, and price in descending order of importance, with non-price factors significantly outweighing price. The contract includes key personnel requirements (Project Manager, Lead Installer, Quality Control Manager), lifetime product warranty, 30-day free storage post-delivery, background investigation requirements for unescorted facility access, and compliance with Library security protocols for Capitol Hill campus deliveries.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment J1 - Price Worksheet.xlsx | XLSX spreadsheet | |
| Attachment J2 - Task Order 1 SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE 1 OF1. REQUISITION NO.
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 16. ADMINISTERED BY CODE
17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE
TELEPHONE NO. UEI: EFT:
PHONE: FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
See SCHEDULE
030ADV27R0013 11-20-2026
Leonard, David 12-08-2026
2:00 PM EST
Contracts and Grants Directorate Library of Congress
101 Independence Ave. SE LA 325 Washington DC 20540-9411
X
N/A
X
DELIVERY
See Sections D&F for delivery instructions.
Contracts & Grants Directorate Library of Congress
LA 325
101 Independence Av SE Washington DC 20540-9411
Submit Invoices through https://www.ipp.gov Washington DC 20540
See CONTINUATION Page
See CONTINUATION Page
X X
Leonard, David
030ADV27R0013
Table of Contents
SECTION A
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS
B.1 LC52.216-3 CONTRACT TYPE (JUN 2016)
B.2 PRICE/COST SCHEDULE
ITEM INFORMATION
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SECTION D - PACKAGING AND MARKING
D.1 LC52.211-1 DELIVERIES (APR 2015)
D.2 LC52.211-2 DELIVERIES TO THE LIBRARY OF CONGRESS, CAPITOL HILL CAMPUS (JUN 2021)
SECTION F - DELIVERIES OR PERFORMANCE
F.1 LC52.215-5 PLACE AND PERIOD OF PERFORMANCE (JAN 2019)
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 LC52.201-3 CONTRACT ADMINISTRATION (AUG 2015)
G.2 LC52.232-1 LIBRARY OF CONGRESS INVOICE INSTRUCTIONS (DEC 2022)
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1 LC52.201-1 CONTRACTING OFFICER'S REPRESENTATIVE (COR) APPOINTMENT AND AUTHORITY (JAN 2016)
H.2 LC52.203-1 CONTRACTOR PUBLICITY (OCT 2013)
H.3 LC52.204-1 COLLECTIONS SECURITY (DEC 2013)
H.4 LC52.204-2 CONDUCT ON LIBRARY PREMISES (JUL 2021)
H.7 LC52.237-1 KEY PERSONNEL (AUG 2014)
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
I.2 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE
ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAR 2026)
I.3 52.216-18 ORDERING (AUG 2020)
I.4 52.216-19 ORDER LIMITATIONS (OCT 1995)
I.5 52.216-22 INDEFINITE QUANTITY (OCT 1995)
I.6 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
I.7 LC52.212-4 CONTRACT TERMS AND CONDITIONS - COMMERCIAL ITEMS (DEV) (FEB 2016)
030ADV27R0013
I.8 LC52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE
ORDERS - COMMERCIAL ITEMS (DEV) (MAY 2015)
I.9 LC52.216-1 ORDER PLACEMENT – SINGLE AWARD INDEFINITE DELIVERY, INDEFINITE QUANTITY (FEB 2016)
I.10 LC52.216-1A ORDER PLACEMENT - ALTERNATIVE ORDERING PROCEDURES (FEB 2015)
I.11 LC52.232-25 PROMPT PAYMENT (DEV) (JUL 2013)
I.12 LC52.233-1 52.233-1 (DEV) DISPUTES (MAY 2014)
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION J - LIST OF ATTACHMENTS
PART IV - REPRESENTATIONS AND INSTRUCTIONS
SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS
K.1 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (OCT 2025)
SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
L.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
L.2 52.211-6 BRAND NAME OR EQUAL (AUG 1999)
L.3 LC52.215-1 PROPOSAL SUBMISSION INSTRUCTIONS - BEST VALUE TRADE-OFF (JUL 2016)
L.4 LC52.233-2 PROTESTS TO THE LIBRARY OF CONGRESS (DEC 2013)
SECTION M - EVALUATION FACTORS FOR AWARD
M.1 LC52.215-2 EVALUATION - BEST VALUE TRADE-OFF (FEB 2020)
M.2 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
030ADV27R0013 Section B
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS
B.1 LC52.216-3 CONTRACT TYPE (JUN 2016)
This is a single award Indefinite Delivery/Indefinite Quantity (IDIQ) contract. Orders issued under the IDIQ contract will be firm-fixed priced.
Contract Minimum: $1,000.00
Contract Maximum: $1,186,000.00
This IDIQ’s Period of Performance will be 5 years, consisting of a single, five-year ordering period.
Product Price List Maintenance: The Contractor shall maintain and provide access to commercially available price lists, for the Contractor's products, from which the order pricing will be calculated using the discount rates in this contract.
The Contractor may provide its GSA contract price list to meet the price list requirement; however, this is not a GSA Schedule based contract.
The Contractor may use GSA discounting percentages as a starting point on all products and then apply deeper than standard GSA discounts on certain product lines as indicated in this contract. For any non-GSA products that may be required over the course of the contract, the contractor shall use a similar product category on GSA and use the corresponding GSA discount. This contract will not be issued as an order under a GSA schedule, and offerors who do not have a GSA schedule may also provide their best discounts.
Given that multiple product lines may be offered and the contract pricing may be based on a mix of commercially available and GSA established pricing, the Contractor shall provide access to an online version of the price list to the Contracting Officer (CO) and the Contracting Officer’s Representative (COR). The price list shall indicate a date and time for the most recent change, update or refresh. While the underlying prices may change during the life of the contract the discount rates under this contract shall remain fixed for the life of the contract.
The firm-fixed price of each order shall remain unchanged through completion of each order, except as indicated via modification to the order.
(End of Clause)
B.2 PRICE/COST SCHEDULE
ITEM INFORMATION
BASE PERIOD POP: 01-04-2027 to 01-03-2032 Title: Total Items: 1 Base Period Period Total: _______________
ITEM TITLE QUANTITY UNIT UNIT PRICE TOTAL AMOUNT
030ADV27R0013 Section B
Window Treatment and Related Services 0.00 $_______________ $_______________00-0001
PERIOD OF PERFORMANCE: 01/04/2027 - 01/03/2032
PRICING ARRANGEMENT: Firm Fixed Price
TOTAL PRICE: $_______________
030ADV27R0013 Section C
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
BACKGROUND
1. SCOPE
The contractor shall provide a wide array of commercial window treatments, window shades, custom draperies, theater curtains, wall mounted acoustic upholstery products, & related services, including installation, repair services, and upholstery cleaning services. The contractor shall also provide product specifications, shop drawings, and project management services, and shall perform work at all Library of Congress buildings.
2. REQUIREMENTS
The contractor shall manage window treatment product, custom draperies, theater curtains, shades, and wall mounted acoustic upholstery products and services task orders, and provide, specify, and install a variety of hardware to support these products; The contractor also must provide repair and upholstery cleaning services. The contractor must ensure that at a minimum all products and services conform to specifications and standards stated in this contract.
The contractor shall also provide products and services for urgent requirements. Urgent requirements are time sensitive initiatives or purchases to fulfill a compelling need, which must be fulfilled within a period that is shorter than the standard lead-time. The schedule for such requirement(s) may require using quick ship products in lieu of longer-lead time manufacture or about a 50% accelerated installation schedule.
3. GENERAL
The contractor will need to ensure that their products include options that coordinate with all existing related products in the Library buildings.
Prior to start of a task order, the contractor must assess the existing site conditions and field measure all pertinent elements of the project. The Library campus consists of historical buildings which do not follow building standards.
All building elements may be slightly different in size from one another. The contractor shall notify the Contracting Officer’s Representative (COR) of any field conditions that need to be modified or addressed prior to the start of work.
Window treatments and drapery products must pass the following tests:
1. NFPA 701 Vertical Ignition Test – Test Method 1, Test Method 2 – Pass
2. ASTM D6413 Vertical Ignition Test – Pass
3. NFPA 701 Test Method #1, Small Scale -2010 Edition.
4. UL 2818 – 2013 Greenguard Certificate of Compliance for Low Chemical Emissions – Gold Standard.
4. PRODUCTS, SERVICES, AND SPECIFICATIONS
4.1 The contractor will provide, at a minimum, the following products:
4.1.1 Drapery (lined) and Sheers
4.1.1.1 Selection must include the following: 100% inherently fire-retardant yarns, Seamless or minimal seams, fully traversable sheer draperies; This is to fulfil the requirements for custom drapery/sheers options for a variety of spaces.
4.1.1.2 The contractor shall be prepared to perform off-site process for flame retardant treatment if the Library recommends it.
4.1.1.3 Problems with spray on flame retardant: uneven coverage, fabric damage, trouble cleaning fabric.
Please refer to NFPA 909 Handbook Section 16.3 Public Areas, 16.3.1 Drapes, Curtains, Props.
16.3.1.1 Fire-Retardant Treatments. 16.3.1.1.1. & 16.3.1.1.2.
4.1.1.4 Options may include – wand to open/close draperies/sheers; over-sized window sizes, for example 295” wide x 95” high. Tripple fullness with finger pinch pleating, Rolled hem over beaded chain weight, side hems 1 ½” double turned blind stitch.
4.1.1.5 Preference at window HVAC units, stop drapery/sheer length at HVAC units, do not extend to floor.
Avoid interaction between drapery/sheer length and electrical equipment, cords.
4.1.1.6 Typical approved sheer fabric or equal:
4.1.1.6.1 Manufacturer: Integra Fabrics; Pattern (woven not printed) – Rosen; Pattern Direction – Railroaded; Color – White; Style – Abstract, Contemporary, Stripe; Seamless Sheers; Content
– 100% FR polyester; Weight – 11.1 oz/yd; Width – 118”; Repeat – 2.28” H x 7.87” W;
Pattern – Railroaded; Weave – open 25.1 to 50 percent; Texture – smooth, twill; Drycleaning recommended. Flammability – meets NFPA 701.
4.1.1.6.2 Other Manufacturers’ products meeting the requirements specified and having similar characteristics will be acceptable.
4.1.2 Stage Curtains and Conference Room AV Curtains:
4.1.2.1 Selection must include the following: Traveler Curtains in 2 panels plus valance; 100% fullness;
Typical approved: 27-25 oz. Charisma Synthetic Velour, IFR that is Inherently Fire Retardant (IFR) with matte finish; fully lined in IFR black fabric.
4.1.2.2 Options may include box pleat, inverted box pleat, shirring, pinch pleat, knife pleat, ripple fold, etc;
side hems double fold and blind stitched; bottom hem has chain or hem tape; tracks and top finish hardware - provide options appropriate with weight, length, height, look, required manual or motorized operation; Optional back-packing – stacks from off stage pocket, not at opening.
4.1.3 Blinds – Horizontal, operable
4.1.3.1 Grade A: 2” & 1” wood or wood look blinds with plain matching valance, mounted to trim.
4.1.3.1.1 Options must include – cordless lift; tilt rod in matching finish; braided ladders and ladder tape; over-sized window sizes, for example 65” wide x 124” high. Provide increased slat count per foot or decreased pitch (rung spacing) appropriate to darken space and block glare when blinds are fully closed. Custom – tilt rod – provide length to windowsill. Custom – provide hold down brackets at blinds installed on doors.
4.1.3.1.2 Typical approved:
4.1.3.1.2.1 Manufacturer: Graber: Collection - Traditions Wood-Painted Program; Graber Color - Painted #1840 Pearl.
4.1.3.1.2.2 Manufacturer: Graber: Collections – Traditions Wood-Stained Program; Graber Color – Stained #1641 Dark Walnut.
4.1.3.1.2.3 Manufacturer: Graber: Collection - Traditions Wood Blinds, or equal with Benjamin Moore #819 ladder tape.
4.1.3.1.2.4 Other Manufacturer’ products meeting the requirements specified and having similar characteristics will be acceptable.
4.1.3.2 1” aluminum blinds with matching valance, mounted with matching hardware.
4.1.3.2.1 Options must include – cordless lift; tilt rod in matching finish; braided ladders in matching finish; over-sized window sizes, example: 58” wide x 106” high. Provide increased slat count per foot or decreased pitch (rung spacing) appropriate to darken space and block glare when blinds are fully closed. Custom – tilt rod – provide length to windowsill. Custom – provide hold down brackets at 1” blinds installed on doors.
4.1.3.2.2 Typical approved:
4.1.3.2.2.1 Manufacturer - SWF Contract; Classic 1” Cordless Aluminum Horizontal Blinds; Slats – 1” wide x .006” thick of 5000 series cold-rolled aluminum of corrosion-resistant flexible product, processed to be smooth. Tilt wand; Headrail – 1” high x 1-1/2” wide x ¼” thick U-shaped steel with finishes, color to match; Bottom rail – .025” thick, enclosed tubular shape, low to zero VOC finishes; Color – match existing James Madison Memorial Building window blinds - #62 Char Brown, or equal.
4.1.3.2.2.2 Other Manufacturer’s products meeting the requirements specified and having similar characteristics will be acceptable.
4.1.3.3 Shutter Blinds – Arch Fan Shutter (at half round inoperable windows). Grade A; 2” wood or wood look blinds custom mounting frame/trim.
4.1.3.3.1 Options must include – custom frame fitting window, full coverage to obscure light.
4.1.3.3.2 Typical approved:
4.1.3.3.2.1.1 Manufacturer: Graber: Collection - Traditions Wood-Painted Program; Graber Color - Painted #1840 Pearl.
4.1.3.3.2.1.2 Manufacturer: Graber: Collections – Traditions Wood-Stained Program; Graber Color – Stained #1641 Dark Walnut.
4.1.3.3.2.1.3 Other Manufacturer’ products meeting the requirements specified and having similar characteristics will be acceptable.
4.1.3.4 Roller Shades for light control and privacy
4.1.3.4.1 Options must include – both manually chain, or wand operated shades, (cordless lift) and electronically operated shades.
4.1.3.4.2 Typical approved: To match NAVCC exterior building window treatment.
4.1.3.4.2.1 Manufacturer: Mechoshade Systems, Inc. Both 1-layer shades and 2-layer shades.
4.1.3.4.2.1.1 Single shade Mechoshade Thermoveil vertical weave (color beige); light reduction = 50%. Valance covers entire roller assembly. Entire facility.
4.1.3.4.2.1.2 Double shade – Mechoshade, Black Out (color mid-grey); Light reduction 99%.
Side channels block light leaks 2-3% openness. Valance covers entire roller assembly. Mostly conference rooms.
4.1.3.4.2.2 Other Manufacturer’ products meeting the requirements specified and having similar characteristics will be acceptable.
4.1.3.5 Black-out Shades for light control at exhibits, etc.
4.1.3.5.1 Options must include - operable by hand. Oversized window sizes, example 65” wide x 124” high.
4.1.3.5.2 Typical approved: provide two color black-out shades; exterior face of shade to match adjacent window treatments on exterior of building; interior face of shade to match interior space décor.
4.1.3.5.2.1 Manufacturer: Draper – LightBloc FlexShade providing complete light blocking assembly - side channels, sill, channel fabric retention system.
4.1.3.5.2.2 Other Manufacturer’ products meeting the requirements specified and having similar characteristics will be acceptable.
4.1.3.6 Window Glass Film for privacy or decoration
4.1.3.6.1 Options – Product with the lowest minimum order required should be selected. Any overage will be stored by the Library.
4.1.3.6.2 Typical approved:
4.1.3.6.2.1 Manufacturer: 3M - Dusted Crystal White, 3.2 mil semi-private decorative film, #7725SE-314 or 3M Frosted Crystal White, 4.7 mil more private decorative film, #7725SE-324.
4.1.3.6.2.2 Manufacturer: SOLYX Glass Finishes – Dusted Crystal SX-3140, White, 2 mil cast vinyl, adhesive clear/pressure-sensitive, semi-private decorative film, meets ASTM E84, NFPA 101, Class A. zero VOC content.
4.1.3.6.2.3 Other Manufacturer’ products meeting the requirements specified and having similar characteristics will be acceptable.
4.1.3.7 Vertical Blinds
4.1.3.7.1 Options must include – operable by hand. Oversized storefront windows floor-to-ceiling.
4.1.3.7.2 Match existing product in color, dimensions, operations.
4.1.3.8 Hardware & Track Systems
4.1.3.8.1 Options:
4.1.3.8.1.1 Operational Method – one-way, two-way, multiple, non-cord operated, hand operated, motorized, remote control operated.
4.1.3.8.1.2 Cordless Lift System
4.1.3.8.1.3 Track – drapery track
4.1.3.8.1.4 Roller shade – motorized head rail, chains, and cords
4.1.3.8.1.5 Blackout fascia, side, top, and sill channels.
4.1.3.8.1.6 Traverse Rods – center draw single or single one-way draw.
4.1.3.8.2 Typical approved:
4.1.3.8.2.1 Manufacturer: Kirsch Drapery Hardware; Architrac Series 94003 Assembled set: Heavy duty ball bearing (for pleated) carriers; fully assembled with all necessary components;
wall or ceiling hung with support brackets @ 48” or less; steel baton (possible custom length) attached to lead master carriers; color – TBD, anodized or bronze; two-way draw for 40’ maximum track length; wheeled master carrier – prefer panels butt together at center; ball bearing wheeled carriers – 25 mm ball bearing carriers.
4.1.3.8.2.2 Other Manufacturer’ products meeting the requirements specified and having similar characteristics will be acceptable.
4.2 All components provided for in each order issued shall be of the same manufacturer and/or brand as to provide consistency and workability between those components such as hardware, mountings and fastenings.
4.3 Replacements: If replacement of an existing product with the same product is not possible, replace with like product matching existing materials, colors, specifications, hardware, etc. or provide appropriate alternative for review/approval.
4.4 The contractor shall identify a path of travel for installation from parking or the loading dock to the project site ensure that all products to be installed can fit in elevators, up/downstairs, or around sharp turns in the building.
The contractor will also work with the COR to identify where/if this path of travel interacts with the public and put in place appropriate safety measures.
4.5 Product shall be transported in a manner that prevents damage and distortion.
4.6 Products shipped to the Library shall be labeled with the manufacturer’s name or trademark, model number, description, and date (month and year) of manufacture legibly marked in dark ink, and Library Project number and Point of Contact (POC) on the product’s packaging.
4.7 Contractor shall deliver the products as specified in the order. Contractor must adhere to the dates and locations defined in the order. Contractor shall coordinate delivery dates with the COR. Contractor is responsible for verifying all procedures required for delivery prior to the date of delivery. Contractor shall verify delivery times, location(s), site restrictions, security restrictions, and contact requirements.
4.8 Contractor must provide free storage for thirty (30) days after the delivery date specified in the order.
4.9 If the Library notifies the contractor that it is unable to accept delivery at the location specified in the order, contractor shall deliver the product to an alternate address no more than sixty (60) miles from the original location in the order, provided the Library gives written notice within seventy-two (72) hours of the scheduled delivery date.
4.10 Fabrication
4.10.1 . Tolerances – Industry standard. Fabricate window treatments width ½” less than opening. For blinds and shades ensure the window treatment fills the opening.
4.11 Warranty – Lifetime warranty for all product materials, components, and working parts.
4.12 Fabricators and Manufacturers must have a minimum of 5 years of experience providing commercial drapery/window treatment fabrication.
5. REPAIR, CLEANING & INSTALLATION SERVICES
5.1. Cleaning: The contractor shall provide cleaning services for new and existing product in the Library’s Buildings.
5.1.1. Cleaning includes services to remove, transport, dry-clean or clean, deliver, reinstallation; providing all tools, equipment, material, and labor. Repair, cleaning, and installation services will be required during normal and after hours as well as off-site work.
5.1.2. In response to any Request for Quote (RFQ) from the Library, the contractor must provide any and all Safety Data Sheets, as applicable, for all window treatment chemicals they plan to use to in order to complete the work in the quote. The Library will review the Safety Data Sheets and inform the contractor if the products are approved for use in the Library and under what conditions within 30 days of receipt.
5.1.3. If, in reviewing the Safety Data Sheets, the contractor, COR, or the Library Safety Office find that the product requires additional ventilation, control, or will emit an odor that may cause a disruption, or poses any potential safety hazard, then the contractor shall perform the work at their off-site facility. This includes the use of cleaning products.
5.2. Repairs: The contractor shall provide repair services, on-site and/or off-site as required, for the following window treatment types:
5.2.1. Drapery & Sheers
5.2.2. Stage Curtains and Conference Room AV Curtains
5.2.3. Horizontal Blinds, shutter blinds
5.2.4. Roller Shades
5.2.5. Blackout Shades/Blinds
5.2.6. Vertical Blinds
5.2.7. Window Film - removal of glass films and glass coatings.
5.2.8. Hardware, including rods, tracks, controls, and motors.
5.3. Installation:
5.3.1. Prior to the start of a window treatment installation, the contractor must assess the existing site conditions and field measure every window as they may be slightly different in size. The contractor shall notify the COR of any field conditions that need to be modified or addressed prior to the start of work.
5.3.2. The contractor shall provide services during normal Library operating hours (Monday – Friday 8:30am to 4:30pm), and after hours and weekends as needed.
5.3.3. The contractor shall employ window treatment installation professionals with specific training in commercial window treatment installations.
5.3.4. The contractor shall use methods that meet all industry installation standards, safety standards, and best practices for occupied buildings, and shall comply with all standards in effect at the time of contract award, unless otherwise indicated.
5.3.4.1. All contractor’s responses to RFQ’s shall identify any specialized equipment required in order to complete the work requested (i.e. a scissor lift, scaffolding, bucket lift, etc.). Once order is awarded, the COR will obtain a WAP (Work Authorization Permit) and detail requirements necessary to complete the installation for the contractor. These requirements will be project specific but may include laydown of floor protection, elevator and floor max loads, and scheduling restrictions.
5.3.5. The contractor shall provide installation services for new and replacement product, and re-installation of existing product sent off-site for cleaning or repairs.
5.3.6. The contractor shall ensure all manufacturers’ instructions and guidelines are properly followed during the product’s installation.
5.3.7. The contractor must notify the COR when any products potentially classified as universal or hazardous waste are brought into and/or removed from the Library’s buildings.
5.3.8. The possibility of Asbestos Containing Material (ACM) may exist in the area to be worked. If there is ACM in the area, the contractor shall not use any mechanical means to remove the ACM. In the event during window treatment installation, it is discovered that the ACM must be removed, the Contractor must stop immediately and notify the Contracting Officer (CO). The Library will provide the Contractor at time of award, all known locations of ACM and Presumed Asbestos-Containing Materials (PACM).
5.3.9. Before installation begins, the contractor shall:
5.3.9.1. Verify installation area is clean and free of debris.
5.3.9.2. Comply with requirements before, during, and after installation as recommended by manufacturer's instructions.
5.3.10. During the installation, the project site shall be kept in a neat, orderly, and in safe condition at all times and all work areas shall be cleaned at the end of each workday.
5.3.10.1. The contractor shall not dispose of any trash or product in Government waste receptacles or leave any hazardous or universal waste at the job site.
5.3.11. Job Site Conditions – site survey and appropriate installation method.
5.3.11.1. The contractor must notify the COR one week or more in advance of any furniture or equipment that needs to be moved to install products.
5.3.12. Government Furnished Property (GFP)
5.3.12.1. Each order will specify GFP that will be the subject of repair, cleaning or installation services.
6. SPECIFICATION SERVICES
6.1. As specified in an order or modification to an existing order, contractor shall conduct site visits, make product recommendations, shop drawings, and estimates for product and services as indicated and necessary to support proposed new purchases and/or treatment installation and repair requests.
6.2. The contractor shall recommend and COR will approve:
6.2.1. Fabric – Manufacturer, Pattern, Color, width, pattern repeat size, sample, total yardage.
6.2.2. Lining – Manufacturer, color, width, sample, and purpose: to enhance draping qualities of fabric, increase energy performance, protection of drapery fabric from UV rays.
6.2.3. Drapery Measurement – width, stacking width, finished width, number of fabric widths, percentage of fullness, finished length, hems and headings, cutting length.
6.2.4. Hardware – type, dimensions, and operational method.
6.2.5. Hardware Installation Method
6.3. Samples: When a new non-standard product is to be specified, the contractor will provide recommendations and samples for approval. Sample size shall be minimum 12 inch by 12 inch, maximum 36 inch by 36 inch. If fabric has a large repeat pattern (over 12 inches) submit multiple pieces in sufficient quantity to provide representative look.
6.3.1. The contractor will provide the specified product in brand new quality, free of visual blemishes and other physical and manufacturing defects.
6.4. Field Measurements – The contractor is responsible for field measuring to verify all locations and conditions and coordinate fabrication of window treatments. If installation requires attachment to building, the contractor shall provide hardware specifications, shop drawings, and details for approval prior to ordering.
6.5. Prior to start of a window treatment procurement project, the contractor must assess the existing site conditions for variables.
6.6. The contractor must notify the COR when any products potentially classified as universal or hazardous waste is brought into and removed from the Library’s buildings.
7. PROJECT MANAGEMENT SERVICES
7.1. The contractor shall provide project management services for all orders under the contract. The contractor shall identify in the Key Personnel section of this contract an individual that will serve as the contractor’s Project Manager (PM) for each order. The contractor’s PM shall serve as the single point of contact for this contract. The contractor’s PM shall coordinate all services, deliveries, perform quality assurance, oversee contractor staff and all subcontractors, and participate in meetings. The contractor’s PM shall have the qualifications required as indicated in Section H.9, Key Personnel Qualifications and Requirements, of this contract.
7.2. At the request of the COR, the contractor’s PM will meet with the COR for a kick-off meeting to review the objectives, requirements, roles and responsibilities, and the anticipated schedules of an order.
7.3. The contractor’s PM shall maintain a record of pertinent communications, project details, current schedules, to ensure that the COR of this contract is fully informed of the status of orders under this contract.
7.4. The contractor’s PM shall coordinate all deliveries to the site with the COR designated in the order. The contractor’s PM shall provide advance notice of site deliveries and comply with all building access requirements and procedures.
7.5. The contractor’s PM shall provide two (2) weeks advance notice to the COR designated in the order to arrange deliveries, schedule installs, reserve dock or elevator if required, and ensure the deliveries are properly coordinated.
7.6. The contractor’s PM shall provide all badging requests to the COR thirty (30) business days prior to requirements in the applicable task order for on-site work to begin. Badging is required, but not limited to, the following situations:
7.6.1. Unescorted after-hours installations
7.6.2. Unescorted installations in areas where collections are stored and/or handled.
7.7. The contractor’s PM shall provide oversight to ensure the quality of work and installation crews are punctual and presentable.
8. DELIVERABLES
8.1. Estimates – The contractor shall generate estimates for all orders under the contract. The estimate should list all services and materials needed for the work including an itemized list of all components with part numbers, nomenclature, size, quantity, and finish. For product, the estimate should include the list price or manufacturer’s suggested retail price (MSRP), the discount given under the contract, and the final sell price. For services, the estimate should include the cost in the attached pricing table and the quantity of hours for service required.
8.2. Safety Data Sheets – At the time of estimate, the contractor must provide the Safety Data Sheets for all window treatment chemicals they plan to use to execute the work under this contract. The Library will review the Safety Data Sheets and inform the contractor if the products are approved for use in the Library and under what conditions they can be used, within 30 days of receipt.
8.3. Contractor’s PM must provide a monthly report to the COR no later than the 5th day of the month and must include the following information:
8.3.1. Active orders
8.3.2. Available balance of orders
8.3.3. Pending invoices
8.3.4.Status of orders
8.4. Submittals
8.4.1.Shop Drawings
8.4.1.1. If specified in the order, the contractor must provide an elevation and floor plan specifying location, operating controls for all window treatments and hardware.
8.5. Manufacturer’s specifications and installation instructions for hardware, digital copy.
8.6. Maintenance & Warranty Information, digital copy.
8.7. Test Reporting – provide certified test results or included with SDS, digital copy.
8.8. Below is a general deliverables schedule for the orders; the schedule will be adjusted to accommodate requirements specified in individual orders:
(Task Order) Project Management Deliverable Number of Days
Kick Off Meeting To Be Determined at Order Level
Meeting Minutes To Be Determined at Order Level
Project/Program Schedule To Be Determined at Order Level
Cost Estimate To Be Determined at Order Level
Installation Schedule (Within 5 days of Kickoff meeting) To Be Determined at Order Level
Punch List Two weeks after end of installation
8.9. Key Personnel Qualifications and Requirements
8.9.1. Contractor shall have full-time employees with qualifications, expertise, and experience in relevant disciplines to support the Library’s requirements. Contractor’s staff shall have the necessary training and experience for the performance of services under this contract. The following are designated as Key Personnel under this contract:
8.9.1.1. Contractor’s Project Manager
8.9.1.2. Lead Installer
8.9.1.3. Quality Control Manager
8.9.1.4. Staff Qualifications:
8.9.1.4.1. Contractor’s Project Manager (PM): The contractor’s PM must have a minimum of five
(5) years of window treatment product sales and installation experience and have the following:
8.9.1.4.1.1. The ability to communicate effectively orally and in writing
8.9.1.4.1.2. Experience in preparing written reports, correspondence, and briefing clients and management personnel
8.9.1.4.1.3. Excellent problem solving skills
8.9.1.4.2. Lead Installer: The Lead Installer must be product-certified and have five (5) years’ experience installing all products indicated in this contract.
8.9.1.4.3. Quality Control (QC) Manager: The QC Manager shall provide the services of a Quality Control Manager (QCM) for this contract. The QCM shall have at least five (5) years of experience in quality control for products and services provided under this contract and must be knowledgeable in applicable trade codes, criteria, standards, and guidelines for commercial window treatments products and services. The PM may also serve as the QCM.
(Task Order) Installation Deliverable Number of Days
Warranty Information To Be Determined at Order Level
Installation Drawings To Be Determined at Order Level
Installation Instructions To Be Determined at Order Level
Installation Schedule To Be Determined at Order Level
Post Installation orientation/training To Be Determined at Order Level
8.9.1.5. Replacement of Key Personnel: Replacement of a Key Personnel member must include a minimum seven (7) day transition period between the departing employee and the newly arriving employee to ensure a smooth, seamless transition, unless otherwise determined by the CO. The dates of this transition period shall be made known to the Library. The Library shall incur no additional costs associated with the replacement and transition of contractor employees. There shall be no delay in the project delivery schedule as a result of the contractor changing any employees.
8.9.1.6. Transition Plan: In the event the contractor is required to transition the services identified in this contract due to contract expiration or termination, the contractor shall provide a transition plan to the CO for approval. The contractor shall support the transition plan within the timeline agreed upon by the contractor and the CO. This transition plan shall identify how the contractor will coordinate with the incoming contractor and with Library personnel to transfer knowledge regarding the status and schedule for all outstanding actions to include orders, invoices, pending orders, and inventory.
030ADV27R0013 Section D
SECTION D - PACKAGING AND MARKING
D.1 LC52.211-1 DELIVERIES (APR 2015)
All deliveries submitted to the CO or the COR or other Library personnel designated to receive deliverables shall clearly indicate the following information:
a. Agency/Requiring Library Service Unit and MAIL STOP/Room Number
b. Description of information/data being submitted
c. Contract Number
d. Contractor Name and Address
(End of Clause)
D.2 LC52.211-2 DELIVERIES TO THE LIBRARY OF CONGRESS, CAPITOL HILL CAMPUS (JUN
2021)
(a) SAFETY. Trucks making deliveries to the Library of Congress must meet the following minimum clearances: 13 ft high, 9 ft wide and 20 ft long. Contractor vehicles exceeding that limitation shall not be permitted access to the Loading Dock area. The Contractor shall ensure that ceiling; doors or walls are not disturbed or damaged. The Contractor shall be held responsible for all costs of repairs to ceiling, doors, etc. and any secondary damage resulting from that damage. The maximum ceiling height inside the loading dock is 14′-8″.
(b) SECURITY. The contractor must adhere to all Library of Congress and U.S. Capitol Police physical security protocols and offsite screening procedures. These requirements may change during the course of the contract and it is the responsibility of the contractor to stay in compliance with current regulations. The most current procedures for accessing only the Madison Loading Dock are as follows:
(c) SCREENING PROCESS FOR ALL VEHICLES COMING TO LIBRARY OF CONGRESS LOADING DOCKS & JEFFERSON EAST
PARKING LOT FREIGHT ELEVATOR
Process includes all trucks, cars and vans coming to the LC Capitol Hill campus. All contractors are now required to notify the Off-Site Delivery Center (OSDC) no later than 24 HOURS PRIOR TO ARRIVAL (48-72 hours if possible)
Contractors are required to have a letter on file with the U.S. Capitol Police. The letter must be on company letterhead accompanied by signature of the owner, president or manager and sent directly to the OSDC email:
OSDCAdmin@USCP.GOV and the COR. The letter shall be protected with a password, and the password shall be sent separately. Requests for access must be renewed every year and should contain the following information:
1. Company Name,
2. Drivers/Employee Names requiring access,
3. Social Security Number for each Driver/Employee,
4. Date of Birth for each Drive Employee,
5. Driver License Number,
6. Vehicle make, model, tag number,
7. Building(s) to be accessed,
8. COR’s name and phone number,
9. Contract number
030ADV27R0013 Section D
All deliveries must include a Bill of Lading and designate a Library Point of Contact (POC) name and telephone number for deliveries. If making more than one delivery on the Hill, make the Library of Congress your last stop. If you do not, you will have to go through the screening process again after leaving the Library.
Vehicles leaving the Library are not resealed.
(d) DELIVERIES BEFORE 3:00 P.M. – OFF-SITE DELIVERY CENTER (OSDC)
The OSDC is open Mon-Fri. 4:30 a.m. to 3:00 p.m. at 4700 Shepherd Parkway S.W. for screening by the U.S. Capitol Police. Once cleared, proceed to D Street and Delaware Avenue S.W. (open Mon-Fri.4:45 am – 3:00 pm) to gain access to Capitol Hill. The OSDC phone number is (202)224-0202.
When a vehicle enters the OSDC:
1. Drivers information is checked.
2. Truck unloaded and material X-rayed and screened.
3. Material is replaced and the vehicle is sealed.
4. Vehicle proceeds to Delaware Avenue, seal is verified, and truck is cleared to first destination.
5. If multiple deliveries on the Hill the vehicle will be resealed upon departure from each delivery location – except the Library of Congress.
6. Vehicle arrives at the Library of Congress. The seal is verified and removed by the police.
(e) DELIVERIE S AFTER 3:00 P.M. Weekdays or Saturday – ALL DELIVERIES / WITH COORDINATION WITH USCP LIBRARY DIVISION (Exception basis for same day delivery only)
Provide all information as above and copy the Library Division at police_support@loc.gov (underscore between police and support) and a fax to (202) 707-1030 and include the estimated arrival time. The inspection location is the 600 block of New Jersey Ave. S.E., and C St NW near the power plant. Call the Library Division at (202) 707-1000 who will arrange for the vehicle to be swept. The vehicle will then be escorted to the Library. All containers have a designated placement location and the Contractor shall not leave any container in any area except those identified in this contract. This expressly designates Independence Avenue, C Street, 1st, 2nd, 3rd Streets and East Capitol Street, SE as areas off limits for staging of containers. All delivery vehicles shall have clearly identified company signage. Driver and all onsite staff shall wear distinguishable company uniform and/or company ID. The Contractor shall not travel beyond the dock area of the Madison Loading Dock. The Contractor shall comply with the Library security procedures. Contractor will be briefed by the COR on Library’s security procedures currently in effect. The security procedures vary periodically.
(End of Clause)
030ADV27R0013 Section F
SECTION F - DELIVERIES OR PERFORMANCE
FAR Number Title Date
52.242-15 STOP-WORK ORDER AUG 1989
52.242-17 GOVERNMENT DELAY OF WORK APR 1984
52.247-34 F.O.B. DESTINATION NOV 1991
F.1 LC52.215-5 PLACE AND PERIOD OF PERFORMANCE (JAN 2019)
Place of Performance:
The Library currently has the following places of performance:
1. Library of Congress Capitol Hill Campus (James Madison Building, John Adams Building, and Thomas Jefferson Building, St. Cecelia's Special Facility Services Center) - 101 Independence Ave SE Washington, DC 20540
2. Library of Congress Cabin Branch Warehouses - 1505 Cabin Branch Dr. Landover, MD 20785
3. Library of Congress The National Audiovisual Conservation Center - 18053 Mt. Pony Road Culpeper, VA 22701
4. Library of Congress Ft. Meade - 100 Montgomery Meigs Rd, Fort Meade, MD 20755
The overall period of performance shall be as stated in section B.
The contractor is responsible for determining its hours of operation in fulfilling the requirements of this contract. The Library’s standard operating hours are from 8:30 AM through 5:30 PM, Monday through Friday, excluding Federal holidays. The contractor shall coordinate with the COR for any work to be conducted at Library facilities.
030ADV27R0013 Section G
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 LC52.201-3 CONTRACT ADMINISTRATION (AUG 2015)
This contract will be administered by:
Library Contracting Officer: Leonard, David
Address: Contracts & Grants Directorate
Library of Congress
LA 325
Washington DC 20540-9411
Phone:
Email: dleonard@loc.gov
Library Contract Specialist: Dawson, Melinda
Address: Contracts & Grants Directorate
Library of Congress
LA 325
Washington DC 20540-9411
Phone:
Email: mdawson@loc.gov
Library Contracting Officer Representative:
Address: Provided at time of award
Phone:
Email:
030ADV27R0013 Section G
Contractor Contract Administrator: Provided at time of award
Address: Provided at time of award
Provided at time of award
Provided at time of award
Provided at time of award
Phone:
Email:
G.2 LC52.232-1 LIBRARY OF CONGRESS INVOICE INSTRUCTIONS (DEC 2022)
The Contractor must prepare and submit invoices electronically to: https://www.ipp.gov. The Contractor may submit payment requests using other than electronic means only when alternate procedures are authorized by the contracting officer in writing. Assistance is available via the IPP Help Desk via email at: ippcustomersupport@fiscal.treasury.gov or by commercial telephone at (866) 973-3131. Invoices shall contain the information required in FAR 52.212-4, paragraph (g).
030ADV27R0013 Section H
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1 LC52.201-1 CONTRACTING OFFICER'S REPRESENTATIVE (COR) APPOINTMENT AND
AUTHORITY (JAN 2016)
(a) Performance of work under this contract is subject to the technical direction of the COR. The term “technical direction” includes, without limitation, direction to the contractor that directs or redirects the labor effort, shifts the work between work areas or locations, and/or fills in details and otherwise serves to ensure that tasks outlined in the contract are accomplished satisfactorily.
(b) Technical direction must be within the scope of the contract specification(s)/work statement. The COR does not have authority to issue technical direction that:
(1) Constitutes additional work outside the contract specification(s)/work statement;
(2) Constitutes a change as defined in the “Changes” clause of this contract;
(3) Causes an increase or decrease in the contract price, or the time required for contract performance;
(4) Changes any of the terms, conditions, or specification(s)/work statement of the contract;
(5) Interferes with the contractor's right to perform under the terms and conditions of the contract; or
(6) Directs, supervises or otherwise controls the actions of the contractor's employees.
(c) Technical direction may be oral or in writing. The COR must confirm oral direction in writing within five workdays, with a copy to the Contracting Officer.
(d) The Contractor shall proceed promptly with performance resulting from the technical direction issued by the COR.
If, in the opinion of the contractor, any direction of the COR or the designated representative falls within the limitations of (b) above, the contractor shall immediately notify the Contracting Officer no later than the beginning of the next Government work day.
(e) Failure of the Contractor and the Contracting Officer to agree that technical direction is within the scope of the contract shall be subject to the terms of the “Disputes” clause of this contract.
(End of Clause)
H.2 LC52.203-1 CONTRACTOR PUBLICITY (OCT 2013)
The Contractor, or any entity or representative acting on behalf of the Contractor, may not refer to the equipment or services furnished pursuant to the provisions of this contract in any news release or commercial advertising, or in connection with any news release or commercial advertising, without first obtaining explicit written consent to do so from the Contracting Officer. Should any reference to such equipment or services appear in any news release or commercial advertising issued by or on behalf of the Contractor without the required consent, the Government will consider institution of all remedies available under applicable law.
H.3 LC52.204-1 COLLECTIONS SECURITY (DEC 2013)
(1) The Library is a public institution responsible for making its resources (collections and staff) available to the Congress and the American people. To achieve a balance between access and security, the Library requires everyone (staff, visitors, interns, contractors, etc.), to always use due diligence and protect its assets during use.
(2) Physical access to Library collections is limited to staff and/or determined by the host office. In addition, established requesting processes in the various readings rooms must be followed.
(3) Loan Privileges. Contractor employees may obtain loans of Library property for internal use and Library work-related purposes.
i. Loan of Library Property. All loans of Library property must be approved and documented by the host Library Services office. Contractor staff shall obtain a Library “General Pass” (Form LW 12/54 (rev2/88)) for each loan.
ii. Liability – Loss or Damage of Library Property. Use or loan of all Library property and signature on this contract means that the contractor acknowledges and agrees to:
(a) ensure the return all Library property issued in the same condition as borrowed;
(b) accept responsibility and liability for the negligent loss or damage of issued or borrowed Library property; and
(c) ensure that the loaned property is used for Library purposes and not loaned to any other person.
(End of Clause)
H.4 LC52.204-2 CONDUCT ON LIBRARY PREMISES (JUL 2021)
1. Access to Library buildings and grounds is governed by 36 C.F.R. part 702 - Conduct on Library Premises. Contractor staff must comply with these requirements and restrictions and related Library of Congress Regulations and Directives.
2. The Library is committed to preventing and addressing all forms of discriminatory harassment and to ensuring that Equal Employment Opportunity (EEO) principles are fundamental to Library culture. Everyone — employees, interns, volunteers, contractors, researchers, and visitors — is expected to help make the Library a respectful environment free from offensive behavior.
a. Library of Congress employees, contractors, interns, volunteers, researchers, patrons, and other visitors have a right to Library facilities that are free from discrimination based on their race, color, national origin, religion, sex, sexual orientation, gender identity, age (40 and over), disability, genetic information, union affiliation, political affiliation, or marital status.
b. The Library does not tolerate discrimination – including sexual harassment, other forms of harassment, or a hostile work environment – based on these factors. The Library does not tolerate retaliation against anyone who engages in any form of protected EEO activity.
c. Contractor (including subcontractor) staff alleged to have engaged in discrimination or retaliation in the performance of this contract may be prohibited from entering Library facilities to perform work under their contracts.
Contractors are required to promptly respond to all Library inquiries into allegations of discrimination, and must, in good faith, cooperate with Library investigations. Good faith cooperation includes, but is not limited to, making contractor staff available for:
1. Formal and informal interviews by Library agents investigating allegations of…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .