Draft Timeline, to be finalized at time of award

I Married a Witch Digital Restoration Time line

Picture Restoration Audio Restoration

Contract Award

Kickoff Meeting Within 10 days after Picture contract award Contract Award

Receipt of DPX Files from the Library 15-20 days after Picture contract award Kickoff Meeting 10 days after audio contract award Reference frame accurate QT for audio conform Delivery to audio contractor 45 days after Picture contract award Receipt of source material from the Library Receipt of QT from Pic Restoration Contractor 15-30 days after audio contract award DPX 10-bit 4K Restoration Card for approval 100 days after Picture contract award

Completed image restoration DCP files w/timecode to the library for approval (prior to grading) Broadcast Wave file of restored track to 110 days after Picture contract award Deliver Library for approval 130 days after contract award

Receive Restored sound track from Audio Contractor 130-140 days after contract award

Completed grading and sound track insertion DCP files w/timecode to the library for approval 160 days after contract award

2 DCPs and Pro-res of final restored version 180 days after contract award

Delivery of Raw sound track files and restored 35mm optical track negative 180 days after audio contract award