03_1 Attachment I Specifications 09Jul26.pdf

PDF 236 KB Posted

Attached to
Repair Transformer station 9 at Range 301, USAG Bavaria, Grafenwoehr Military Community - Tower Barracks
Solicitation number
W912P26BA010
Issued by

About this file

This is a specification and performance work statement for the repair and reconstruction of Transformer Station 9 at Range 301, USAG Bavaria, Grafenwöhr Military Community, dated July 9, 2026.

The project encompasses complete demolition of the existing transformer station building and installation of a new prefabricated reinforced concrete structure measuring approximately 4.2m x 3.3m with a cable cellar. Major electrical work includes disconnection and removal of the existing 100 kVA oil transformer and medium/low-voltage switchgear, followed by installation of new equipment: a 20 kV, 100 kVA oil transformer with DGPT2 protection; a 24 kV medium-voltage switchgear consisting of four panels (transformer control, two cable outlet panels, and one reserve panel) manufactured by Driescher with 630A rated busbar current and 500 MVA short-circuit capacity; a low-voltage distribution board with 400A rated current featuring a 160A circuit breaker, 6 fused switch disconnectors at 63A, and supporting equipment; and a lightning protection system compliant with VDE 0185. Site work includes soil excavation, grounding system installation with stainless steel ring earth electrode, cable relocation from the existing station, and creation of a gravel surface. The scope requires compliance with German construction standards (VOB Part C, DIN 18 382), VDE regulations (VDE 0100, 0101), and German accident prevention laws (Baustellenverordnung). Deliverables include as-built drawings in CAD (Microstation V8 DGN format), test and metering protocols, lightning protection system inspection reports, and training of operating personnel. The contractor is responsible for obtaining all necessary German work permits, licenses, and authorizations; waste disposal per German regulations; and coordination with COR (Contracting Officer's Representative) for cable disconnection/reconnection activities requiring 48-hour advance notice.

View the file

Other files

File Type Posted
03 Solicitation - W912PB26BA010.pdf PDF
3_4 Attachment V Price Schedule KTR TOOL ONLY.xlsx XLSX spreadsheet
03_2 Attachment II Pictures.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 60 Pages Seite 1 von 60 Seiten

- 1 -

ATTACHMENT # I

DEPARTMENT OF THE ARMY

UNITED STATES ARMY GARRISON BAVARIA

DIRECTORATE OF PUBLIC WORKS

UNIT 28130

APO AE 09114-8130

Project No. 42A-01014-1P

09 July 2026

Repair Work Reparaturarbeit

S P E C I F I C A T I O N

Repair Transformer station 9 at Range 301, USAG Bavaria, Grafenwoehr Military Community - Tower Barracks

L E I S T U N G S B E S C H R E I B U N G

Reperatur der Transformerstation 9 in Range 301, USAG Bavaria, Grafenwoehr Military Community - Tower Barracks

In the event of a disagreement between the English text and the courtesy translation of this specification the English text shall govern.

Im Falle einer Unstimmigkeit zwischen dem englischen Text der Leistungsbeschreibung und der Gefälligkeitsübersetzung ist der englische Text maßgebend.

Project No. 42A-01014-1P

- 2 -

TABLE OF CONTENTS

INHALTSANGABE

SUBJECT PAGE

TITEL SEITE

Cover Sheet Deckblatt 1

Table of Contents Inhaltsangabe 2

General Description Allgemeine Beschreibung 3 - 4

General Preamble Allgemeine Vorbemerkungen 5 - 31

Technical Specification Leistungsbeschreibung 32 - 61

- 3 -

GENERAL DESCRIPTION

This project specifies the following work:

The construction project is located within the Grafenwöhr military training area.

- Dismantling of the existing medium-voltage and low-voltage built-in devices in the old transformer station 9, Range 301, consisting of:

1 existing 100 kVA oil transformer, 1 existing medium-voltage switchgear consisting of 3 MV cells, 1 existing low-voltage switchgear, approx. LxHxD = 0.6 m x 2.0 m x 0.6, 1 antenna system (reinstallation in new transformer station), Dismantle all existing medium-voltage cables and low-voltage cables or transfer them to the new station.

Dismantle all ceiling lights and switches.

Dismantle all existing metal structures.

- Demolition of the existing transformer building, LxHxD = 3.15 m x 3,2 m x 2.75 m, building # 30141.

- Construction of a new transformer building with cable cellar and pent roof, roof pitch 7 degrees.

Building dimensions: approx. 4.2 m x 3.3 m, clear height 2.60 m.

Dimensions of reinforced concrete cable cellar approx. 0.8 m high.

- Installation of a 24 kV medium-voltage switchgear consisting of:

1 x 24 kV transformer switch panel 2 x 24 kV fused cable outlet 1 x 24 kV reserve panel 1 x 24 kV high-voltage/voltage transformer panel 1 separate 24 kV earth terminal in the transformer room 1 20 kV oil transformer 100 kVA with DGPT2 full transformer protection

- Installation of a low-voltage switchgear consisting of:

1 circuit breaker 160 A 1 busbar system 400 A 5 fuse switch disconnectors 63 A 1 energy multimeter with LED display,

- Transfer of all medium-voltage and low-voltage cables from the old transformer station 9 to the new transformer station 9.

- Creation of a walkable gravel surface for the new transformer station.

- 4 -

ALLGEMEINE BESCHREIBUNG

Dieses Projekt umfasst folgende Arbeiten:

Das Bauvorhaben liegt innerhalb des Truppenübungsplatzes Grafenwöhr.

- Demontage der vorhandenen Mittelspannungs- und Niederspannungs-Einbaugeräte in der alten Transformatorstation 9, Range 301, bestehend aus:

1 Stck vorhandenem Öltransformator 100 kVA, 1 Stck vorhandener Mittelspannungs-Schaltanlage bestehend aus 3 Stck MS-Zellen, 1 Stck vorhandener Niederspannungs-Schaltanlage, ca. LxHxT = 0.6 m x 2.0 m x 0.6, 1 Stck Antennenanlage (Wiederanbau neue Trafostation), Alle vorhandene Mittelspannungskabel, Niederspannungskabel demontieren bzw. in die neue Station umlegen Alle Deckenleuchten und Schalter demontieren.

Alle vorhandenen Metallkonstruktionen demontieren.

- Abbruch des bestehenden Transformatorgebäudes, LxHxT = 3.15 m x 3.2 m x 2.75 m Gebäude # 30141.

- Erstellen eines neuen Transformatorgebäudes mit Kabelkeller und Pultdach, Dachneigung 7 Grad.

Abmessungen Gebäude: ca. 4.2 m x 3.3 m, lichte Höhe 2.60 m Abmessungen Kabelkeller aus Stahlbeton ca. 0.8 m hoch

- Einbau einer Mittelspannungs-Schaltanlage 24 kV bestehend aus:

1 Stck 24 kV Trafoschaltfelder 2 Stck 24 kV gesicherter Kabelabgang 1 Stck 24 kV Reservefeld 1 Stck 24 kV Hochführungs-/Spannungswandlerfeld 1 Stck separater 24 kV Erder im Traforaum 1 Stck 20 kV Öltransformator 100 kVA mit DGPT2 Trafovollschutz

- Einbau einer Niederspannungs-Schaltanlage bestehend aus:

1 Stck Leistungsschalter 160 A

1 Stck Sammelschienensystem 400 A 5 Stck Sicherungslasttrennleisten 63 A 1 Stck Energiemultimeter mit LED-Anzeige,

- Umlegen aller Mittelspannungs- und Niederspannungskabel von der alten Trafostation 9 in die neue Trafostation 9.

- Erstellen einer begehbaren Schotterfläche für die neue Transformatorstation.

- 5 -

General Preamble to Project No. 42A-01014-1P Allgemeine Vorbemerkungen zu Projekt Nr. 42A-01014-1P

1. Regulations

The work to be accomplished and material to be furnished shall be in accordance with the following standards and regulations:

a. DIN standards (German Industry Standards) of German Construction Contract Procedures (VOB), Part C, identified below are governing:

DIN 18 299 General Regulations for all kinds of Construction Work DIN 18 300 Earth Work DIN 18 303 Sheathing Work DIN 18 320 Landscape Construction Work DIN 18 322 Civil Engineering Works for Cable Placement DIN 18 336 Sealing Work DIN 18 382 Low and Medium Voltage Systems with Nominal Voltage up to 36 kV DIN 18 384 Lightning Protection Systems

b. Other regulations:

VDE Regulation No. 0100 Erection of power installations, with rated voltages up to 1000 V

VDE Regulation No. 0101 Power installations exceeding 1 kV

Pertinent accident prevention regulations of the employer's liability insurance association.

1. Vorschriften

Die auszuführenden Arbeiten und zu liefernden Materialien müssen den folgenden Bestimmungen und Vorschriften entsprechen:

a. DIN Bestimmungen der VOB, Teil C, wie nachfolgend aufgeführt, sind gültig:

DIN 18 299 Allgemeine Regelungen für Bauarbeiten jeder Art DIN 18 300 Erdarbeiten DIN 18 303 Verbauarbeiten DIN 18 320 Landschaftsbauarbeiten DIN 18 322 Kabelleitungstiefbauarbeiten DIN 18 336 Abdichtungsarbeiten DIN 18 382 Nieder- und Mittelspannungsanlagen mit Nennspannungen bis 36 kV DIN 18 384 Blitzschutzanlagen

b. Sonstige Bestimmungen:

VDE Bestimmung Nr. 0100 Bestimmungen für das Errichten von Starkstromanlagen mit Nennspannungen bis 1000 V

VDE Bestimmung Nr. 0101 Starkstromanlagen mit Nennwechselspannungen über 1 kV

Einschlägige Unfallverhütungsvorschriften der Berufsgenossenschaft

- 6 -

2. Drawings

The work to be performed will include but is not limited to the items specified in the drawing(s). The drawing(s) is/are a part of this specification:

Number of drawings: 1

Date of drawing(s): 18 March 2026

2. Pläne

Die auszuführenden Arbeiten beinhalten unter anderem die in den Plänen angegebenen Objekte. Die Pläne sind Bestandteil dieser Leistungsbeschreibung:

Anzahl der Pläne: 1

Datum der Pläne: 18. März 2026

3. Authorization to Perform Work in Germany

a. Contractors performing work in the Federal Republic of Germany (FRG) shall comply with German law. The Contractor shall determine whether performance requires registration with German authorities or authorization to do business in Germany and, if so, shall comply with all requirements. Whether or not registration or authorization to do business is required, the contractor also shall determine what documents or authorization its employees and any subcontractor employees shall possess to work in Germany. The contractor shall ensure affirmatively that its employees and subcontractor employees possess such documents or authorizations.

b. Contractor employees who:

(1) are not nationals of Germany or other European Union countries, and

(2) are not members of the force, the civilian component or their dependents, and

(3) do not have assimilated status under Articles 71, 72, or 73 of the

Supplementary Agreement to the NATO SOFA shall possess work and residence permits.

c. The contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable laws, codes, and regulations applicable to the performance of the work.

d. By acceptance of and performance under this contract and any task orders or delivery orders issued hereunder, the contractor affirms that it has complied with the requirements above. Compliance with this clause and German law is a material contract requirement. Noncompliance by the contractor or subcontractor at any tier shall be grounds for issuing a negative performance evaluation and terminating this contract, task order, or delivery order for default.

- 7 -

3. Befugnis in Deutschland zu arbeiten

a. Auftragnehmer, die in der Bundesrepublik Deutschland (BRD) Arbeitsleistungen erbringen, müssen deutsches Recht befolgen. Der Auftragnehmer muss ermitteln, ob die Ausführung der Arbeiten die Registrierung bei deutschen Behörden erfordert oder ob eine Genehmigung, Geschäfte zu tätigen, eingeholt werden muss, und - wenn dies der Fall ist - allen Anforderungen entsprechen. Gleichgültig, ob eine Registrierung oder die Genehmigung, Geschäfte zu tätigen, erforderlich ist, oder nicht, muss der Auftragnehmer ermitteln, welche Dokumente oder Autorisierungen seine eigenen Arbeitnehmer sowie sämtliche Arbeitnehmer von Subunternehmern besitzen müssen, um in Deutschland arbeiten zu dürfen. Der Auftragnehmer muss unbedingt sicherstellen, dass seine eigenen Arbeitnehmer und die Arbeitnehmer der Subunternehmer derartige Dokumente oder Autorisierungen besitzen.

b. Arbeitnehmer von Auftragnehmern, die:

(1) keine deutschen Staatsbürger oder keine Staatsbürger anderer Staaten der Europäischen Union sind, und

(2) keine Mitglieder der Streitkräfte, Zivilisten oder deren Familienangehörige sind, und

(3) über keinen gleichgestellten Rechtsstatus gemäß Artikel 71, 72, oder 73 der Zusatzvereinbarung zum NATO Truppenstatut verfügen (SOFA = Status of Forces Agreement), müssen Arbeits- und Aufenthaltsgenehmigungen besitzen.

c. Der Auftragnehmer ist, ohne dass zusätzliche Kosten für den Auftraggeber entstehen, dafür verantwortlich, jegliche Erlaubnis einzuholen und sämtliche notwendige Genehmigungen zu besorgen, und sich an sämtliche, für die Arbeitsdurchführung maßgeblichen Gesetze, Vorschriften und Bestimmungen zu halten.

d. Mit der Zustimmung zu diesem Vertrag und der Ausführung von Leistungen im Rahmen dieses Vertrages und sämtlicher hierunter erteilten Arbeits- oder Lieferaufträge, versichert der Auftragnehmer die Erfüllung der obigen Anforderungen. Die Einhaltung dieser Klausel und des deutschen Rechts ist eine wesentliche Vertragsbedingung. Eine Zuwiderhandlung seitens des Auftragnehmers oder Subunternehmers, gleich auf welcher Ebene, hat die Erteilung einer negativen Arbeitsbeurteilung und die Beendigung dieses Vertrages, Arbeitsauftrages oder Lieferauftrages wegen Nichterfüllung zur Folge.

4. German Accident Prevention Laws and Regulations

The contractor shall comply with FAR 52.236-13, Accident Prevention, the references contained therein (e.g. EM 385-1-1), and applicable Host Nation Safety Laws and Regulations. The requirements under FAR 52.236-13 and specifically of the EM 385- 1-1 include, but are not limited to the following:

a. Before initiation of work at the job site, an accident prevention plan, written by the contractor for the specific work and hazards of the contract and implementing in detail the pertinent requirements of EM 385-1-1, will be approved by designated Government personnel. Specific requirements for development of the accident prevention plan are found in 01.A and Appendix A of EM 385-1-1. EM 385-1- 1 is available online at www.usace.army.mil.

- 8 -

b. Before beginning any work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work, an activity hazard analysis (AHA) shall be prepared by the contractor (see paragraph 01.a.09 of EM 385-1-1).

c. The contractor shall require subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work.

d. The contractor shall discuss the plans in conferences convened by the contracting officer prior to starting work on each major phase of operation. Plans shall include all pertinent information such as layout of haul roads, access roads, storage areas, electrical distribution lines, methods of providing minimum exposure to overhead loads, and methods of access to work areas. The plan for accomplishing the initial work phase shall be submitted within 15 calendar days after award of the contract. Plans for subsequent major phases of work shall be submitted no later than 15 calendar days prior to initiation of work on each major phase.

e. In all areas where construction, demolition, alteration, building, or similar related activities take place, the contractor shall have the following minimum personal protective clothing and equipment requirements in place for any person working on or visiting the site:

(1) Short sleeve shirt.

(2) Long trousers.

(3) Steel-toed safety boots.

(4) Hard hat.

f. In addition to other requirements for accident prevention specified in this contract, the contractor is responsible for compliance with all Federal and State requirements governing safety and health protection on construction sites and other applicable occupational safety codes. In particular, within the requirements of the German Safety and Health Protection Regulation for Construction Sites, Baustellenverordnung (BaustellV), dated 10 June 1998, the contractor is responsible for coordination of all work at the site, including development of plans and providing advance notices. The contractor shall indicate its plan for compliance considering conditions of the work described by the design, technical proposal, operational activities of the Government or others in the area of the work, identification of the coordinator, and implementation of all other accident prevention provisions of this contract. For the compliance with host nation laws and regulations, the contractor shall assure that it complies with the non-exclusive list of duties described in this clause. If the contractor determines that additional activities are required to fully comply, the contractor shall assure that compliance with the laws is complete. The duties include:

(1) Conditions of construction and operational activities to be considered include but are not limited construction activities meeting the following criteria:

(a) The work is scheduled to last longer than 30 working days and on which more than 20 workers are occupied simultaneously, or

- 9 -

(b) The volume of work is scheduled to exceed 500 person days, or the work presents particularly hazardous tasks (e.g. excavations deeper than 5 meters, falls from a height of greater than 7 meters, exposures to hazardous chemical or biological substances, work at less than 5 meters from high voltage lines, underground earth works or tunnels, danger of drowning, diving, use of compressed air, work with ionizing radiation, explosives, or work involving assembly or dismantling of heavy prefabricated components (10 tons or greater)).

(2) If the contractor determines that the BaustellV, dated 10 June 1998, applies, the contractor shall prepare a Safety and Health Protection Plan (SIGE) as required under that regulation. The SIGE shall be submitted two weeks prior to mobilization. In addition, the contractor shall appoint a qualified Safety Coordinator who will ensure that safety measures are implemented during construction. The Safety Coordinator shall meet minimum training and experience requirements required under Host Nation laws.

(a) The SIGE shall be written in a comprehensive form and explained in language the workers understand and shall contain the following minimum information:

(i) Maintenance of tools and equipment.

(ii) Provisions for the storage and disposal of materials and waste, particular hazardous materials and substances.

(iii) Modifying performance periods for such work, taking into consideration the site conditions.

(iv) Organizing cooperation between different employers and contractors without employees.

(v) Interaction between work at the site and other operational activities in the area, on which or near which the first identified work will be performed, and taking into consideration the instructions and advice of the coordinator as well as safety and health plans.

(b) The contractor is responsible for completing and providing any safety notifications required by host nation authorities and shall provide proof to the contracting officer that such notifications were made.

4. Deutsche Unfallverhütungsgesetze und -vorschriften

Der Auftragnehmer muss die FAR 52.236-13, Federal Acquisition Regulation, (Beschaffungsverordnung der US-Bundesbehörden) zur Unfallverhütung befolgen, sowie die darin enthaltenen Dienstvorschriften (zum Beispiel EM 385-1-1, Engineers Manual = Ingenieursdienstvorschrift) und die maßgeblichen Sicherheitsgesetze und Vorschriften des Gastgeberstaates. FAR 52.236-13 und besonders die Dienstvorschrift EM 385-1-1 umfassen unter anderem die nachfolgenden Anforderungen:

a. Noch vor Arbeitsbeginn auf der Baustelle, wird ein vom Auftragnehmer verfasster Unfallverhütungsplan für die spezielle Arbeit und die Gefahren des Vertrages, unter genauer Einhaltung der einschlägigen Anforderungen der Dienstvorschrift EM 385-1-1, von designiertem Regierungspersonal genehmigt. Die genauen Anforderungen für die Entwicklung des Unfallverhütungsplanes sind im Abschnitt 01.A und Anhang A der Dienstvorschrift EM 385-1-1 zu finden. Die Dienstvorschrift EM 385-1-1 ist online unter dem Link: www.usace.army.mil.

verfügbar.

- 10 -

b. Noch vor Beginn jeglicher Arbeiten, die Gefahren darstellen, welche in vorherigen Projektabläufen noch nicht vorkamen oder bei der ein neues Team oder Subunternehmer Arbeiten durchführen müssen, hat der mit der Tätigkeit betraute Auftragnehmer eine Tätigkeits-Gefahrenanalyse (AHA - activity hazard analysis) zu erstellen. (Siehe Paragraph 01.a.09 der EM 385-1-1)

c. Der Auftragnehmer hat seine Subunternehmer zu verpflichten, eine Arbeitsablaufsplanung vorzulegen, die die beabsichtigten Maßnahmen für die Durchführung wichtiger Arbeitsphasen aufzeigt.

d. Noch bevor mit den Arbeiten für jede größere Arbeitsphase begonnen wird, muss der Auftragnehmer in vom Contracting Officer einberufenen Konferenzen seine Pläne besprechen. Die Pläne müssen alle relevanten Informationen enthalten, wie zum Beispiel Lagepläne für Transportstraßen, Zugangsstraßen, Ablagerungsflächen, elektrische Verteilungsleitungen, die Maßnahmen, die eine Gefährdung durch Überkopf-Lasten auf ein Minimum beschränken und die Art und Weise, wie die Arbeitsstätten erreicht werden können. Der Plan zur Verwirklichung der Arbeiten in der Anfangsphase muss innerhalb von 15 Kalendertagen nach Auftragsvergabe vorliegen. Pläne für größere, darauffolgende Arbeitsphasen müssen spätestens 15 Kalendertage vor dem Arbeitsbeginn jeder größeren Phase vorliegen.

e. In allen Bereichen, in denen Bau-, Abbruch- und Änderungsarbeiten durchgeführt, Bauwerke erstellt oder ähnliche, damit in Verbindung stehende Aktivitäten stattfinden, muss der Auftragnehmer als Mindesterfordernis für jeden Arbeiter oder Besucher die im Folgenden beschriebene, persönliche Schutzkleidung und Ausrüstungsteile zur Verfügung stellen:

(1) Kurzärmeliges Hemd

(2) Lange Hose

(3) Sicherheitsschuhe mit Stahlkappen

(4) Schutzhelm

f. Zusätzlich zu weiteren Anforderungen an die in diesem Vertrag aufgeführten Unfallverhütungsmaßnahmen, ist der Auftragnehmer für die Einhaltung aller Bundes-und Staatsvorgaben, die für den Sicherheits- und Gesundheitsschutz auf Baustellen maßgeblich sind, sowie anderer zutreffender berufsbezogener Sicherheitsvorschriften, verantwortlich. Im Besonderen innerhalb der Anforderungen der deutschen Verordnung über Sicherheit und Gesundheitsschutz auf Baustellen (Baustellenverordnung - BaustellV), vom 10 Juni 1998, ist der Auftragnehmer für die Koordination aller Arbeiten auf der Baustelle, sowie für die Planentwicklung und die Erbringung von Vorabmitteilungen verantwortlich. Der Auftragnehmer muss seinen Plan zur Einhaltung anzeigen unter Berücksichtigung der Arbeiten, welche im Design und im technischen Angebot beschrieben sind, der operativen Aufgaben der Regierung oder anderer im Arbeitsbereich, die Bestimmung des Koordinators und die Anwendung aller Unfallverhütungsmaßnahmen dieses Vertrages. Zur Einhaltung der Gesetze und Vorschriften des Gastgeberstaates stellt der Auftragnehmer sicher, dass er die nicht-exklusive Liste der in dieser Klausel beschriebenen Verpflichtungen befolgt.

Wenn der Auftragnehmer feststellt, dass zusätzliche Maßnahmen zur vollständigen Einhaltung notwendig sind, muss er sicherstellen, dass die Gesetze eingehalten werden. Die Verpflichtungen beinhalten:

(1) Die einzuhaltenden Konditionen für bauliche und betriebliche Tätigkeiten beinhalten - unter anderem - Baumaßnahmen, die folgende Kriterien erfüllen:

- 11 -

(a) Die voraussichtliche Dauer der Arbeiten beträgt mehr als 30 Arbeitstage und es werden mehr als 20 Arbeiter gleichzeitig beschäftigt, oder

(b) Der Umfang der Arbeiten übersteigt 500 Personentage, oder die

Arbeit beinhaltet besonders gefährliche Tätigkeiten (z.B. Erdaushub in einer Tiefe von mehr als 5 Metern, Arbeiten in einer Höhe von über 7 Meter, Umgang mit gefährlichen chemischen oder biologischen Substanzen, Arbeiten in einem Abstand von weniger als 5 Meter von Hochspannungsleitungen, Tiefbau- oder Tunnelarbeiten, Gefahr zu ertrinken, Arbeiten mit Tauchgeräten, Arbeiten mit Druckluft, Arbeiten mit ionisierender Strahlung, Sprengstoff oder Arbeiten die den Aufbau bzw. Abbau von schweren Fertigbauteilen beinhalten (10 Tonnen oder mehr)).

(2) Stellt der Auftragnehmer fest, dass die BaustellV vom 10 June 1998, zutreffend ist, muss er gemäß dieser Verordnung einen Sicherheits- und Gesundheitsschutzplan (SIGE) erstellen. Der „SIGE“ muss zwei Wochen vor der Baustelleneinrichtung eingereicht werden. Außerdem muss der Auftragnehmer einen qualifizierten Sicherheitsbeauftragten bestimmen, der sicherstellt, dass alle Sicherheitsmaßnahmen während der Baumaßnahme umgesetzt werden. In Übereinstimmung mit der Rechtsordnung des Gastgeberstaates muss der Sicherheitsbeauftragte ein Mindestmaß an Training und die notwendigen Erfahrungen aufweisen.

(a) SIGE wird in umfassender Form geschrieben und in einer von den

Arbeitern verständlichen Sprache erklärt und soll mindestens folgende Informationen enthalten:

(i) Instandhaltung der Arbeitsmittel.

(ii) Vorkehrungen zur Lagerung und Entsorgung der Arbeitsstoffe und Abfälle, insbesondere umweltgefährdende Materialien und Gefahrstoffe.

(iii)Anpassen der Ausführungszeiten für die Arbeiten unter Berücksichtigung der Gegebenheiten auf der Baustelle.

(iv) Zusammenarbeit zwischen verschiedenen Arbeitgebern und Auftragnehmern ohne Beschäftigte.

(v) Wechselwirkungen zwischen den Arbeiten auf der Baustelle und anderen betrieblichen Tätigkeiten auf dem Gelände, auf dem oder in dessen Umgebung die erstgenannten Arbeiten ausgeführt werden.

Dabei sind die Anweisungen und Empfehlungen des Koordinators sowie der Sicherheits- und Gesundheitsschutzplan zu berücksichtigen.

(b) Der Auftragnehmer ist verantwortlich für die Erstellung und

Bereitstellung jeglicher, von der zuständigen Behörde des Gastgeberlandes geforderten, Sicherheitsbekanntmachungen und muss dem Contracting Officer einen Nachweis darüber liefern.

5. Instructions for Contractor's Quality Control Plan

a. The contractor shall coordinate with the COR (or receiving activity, if no COR has been appointed) to establish a contractor's Quality Control Plan (CQCP).

b. The contractor shall provide a copy of the CQCP annotated with the contract number to the COR at least one week after contract start date. The COR shall submit an approved copy to the contracting officer at the below listed address not later than three weeks after contract start date:

Regional Contracting Office Bavaria

- 12 -

Building 542, Lager 92655 Grafenwöhr

c. In addition to any requirements in the specification or statement of work, the contractor's quality control plan shall have as a minimum:

(1) Identification and clearly defined authority of key personnel under the contractor's organization.

(2) A quality inspection system covering all general and specific tasks included in the contract scope of work. It should specify tasks or areas to be inspected on either a scheduled or unscheduled basis, and the manner in which inspections are to be conducted.

(3) The names of firms or individuals tasked to perform inspections and the extent of their authority. This may be in the form of an organization chart or other form approved by the contracting officer's representative (COR).

(4) Proposed test methods, including names of technicians or qualified testing laboratories to be used, if applicable. Tests shall be specified.

(5) A method of identifying deficiencies in the quality of services or construction performed before the level of performance becomes unacceptable.

(6) A method of documenting and enforcing quality control operations of both prime and subcontractor work, including inspection and testing.

(7) Key control, internal control or security procedures, if applicable.

(8) Any winterization plans and procedures for outdoor and exposed contractor and Government furnished equipment, if applicable.

(9) A method of identifying deficiencies in the quality of manufacturing, services, or construction performed before the level of performance becomes unacceptable.

(10) Detailed information specifying the types of action the contractor shall take to correct deficiencies and prevent their recurrence.

(11) Detailed information on the inspection methods used and proposed test methods, including names of technicians or qualified testing laboratories to be used, if applicable. Tests shall be specified.

5. Qualitätskontrollplan des Auftragnehmers

a. Der Auftragnehmer muss in Abstimmung mit dem COR (oder, falls kein COR ernannt wurde, mit dem Leistungsempfänger) einen annehmbaren Fertigungs- /Gütekontrollplan (CQCP) erstellen.

b. Eine Kopie des genehmigten Fertigungs-/Gütekontrollplans, unter Angabe der Vertragsnummer, muss spätestens eine Woche nach Vertragsbeginn beim Vertreter des Contracting Officers (COR) vorliegen. Der Vertreter des Contracting Officers hat den genehmigten Fertigungs-/Gütekontrollplans dem Contracting Officer spätestens drei Wochen nach Vertragsbeginn unter folgender Adresse einzureichen.

Regional Contracting Office Bavaria Building 542, Lager 92655 Grafenwöhr

c. Außer den Anforderungen des Leistungsverzeichnisses bzw. der Arbeitsbeschreibung, muss der Fertigungs-/Gütekontrollplan mindestens folgendes beinhalten:

(1) Benennung des verantwortlichen Schlüsselpersonals (Bauleiter etc.) und dessen Befugnisse innerhalb der Organisation des Vertragsnehmers.

- 13 -

(2) Alle speziellen Erfordernisse, die den Umfang der Arbeit ausmachen, müssen durch das Fertigungs-/Gütekontrollsystem abgedeckt sein. Die Art der Kontrolle/Inspektion, planmäßig oder außerplanmäßig, sowie die Arbeit/Arbeitsbereiche selber müssen genau dargelegt werden.

(3) Die Namen der Firmen oder Einzelpersonen, die damit beauftragt wurden, die Fertigungs-/Gütekontrollen durchzuführen und deren klare Befugnisse. Dies kann in der Form einer Organisationsübersicht oder eines anderen, vom Vertreter des Contracting Officers (COR) genehmigten Vorschlages erfolgen.

(4) Die beabsichtigten Prüfungsmethoden, unter Angabe der Namen der Techniker bzw. der Testlaboratorien, die dafür vorgesehen sind (falls zutreffend). Die Tests müssen ausführlich beschrieben werden.

(5) Eine Methode zur Feststellung von Mängeln im Arbeits-/ Leistungsablauf, die eine Nichtabnahme/-annahme seitens des Auftraggebers vorbeugend verhindert.

(6) Ein Nachweis- bzw. Ausführungsverfahren der Fertigungs-/ Gütekontrollmethoden von Leistungen des Hauptunternehmers als auch aller Subunternehmer, einschließlich der vorgesehenen Inspektionen und Tests.

(7) Alle wesentlichen und innerbetrieblichen Kontrollen sowie alle Sicherheitsmaßnahmen (falls zutreffend).

(8) Alle Pläne und Verfahren zur Winterfestmachung von ungeschützten Ausrüstungsgegenständen des Vertragsnehmers oder -gebers.

(9) Eine Methode zur Feststellung von Qualitätsmängeln in der Produktion, im Dienstleistungsbetrieb oder bei den Bauarbeiten, die eine Nichtabnahme/-annahme seitens des Auftraggebers vorbeugend verhindert.

(10) Ausführliche Informationen welche Maßnahmen der Auftragnehmer ergreifen wird um Mängel zu korrigieren und ihre Wiederholung zu verhindern.

(11) Ausführliche Informationen über die angewandten Inspektionsmethoden und die beabsichtigten Testmethoden, unter Angabe der Namen der Techniker bzw. der Testlaboratorien, die dafür vorgesehen sind (falls zutreffend). Die Tests müssen ausführlich beschrieben werden.

6. Disposal of Debris

a. The Sanitary Landfill Grafenwöhr will not accept material, such as asphalt, concrete, wood, construction debris, metal, branches, rootstocks, cardboard, hazardous waste (cleaning agents, paints etc.), dismantled material (cables, pipes, installation material etc.) or soil excavation. This material becomes property of the contractor and shall be disposed of in accordance with German laws and regulations (for example Closed Cycle and Waste Management Act, Ordinance of Waste Wood Management, Guideline 3.4/1 of the Bavarian Water Board for tar debris, etc.).

If applicable, the contractor shall commission a certified laboratory to analyze representative samples for classification. Sampling and chemical analysis of the excavated soil shall be executed according to LAGA PN 98 (German Interstate Working Party on Waste Processing - Ordinance for the procedure for physical, chemical and biological analyses in connection with recycling/removal of waste). If the sample analysis shows contamination classifications not included in any of the specification items, an appropriate contract modification will be issued.

b. Waste wood resulting from demolition work shall be disassembled individually and stored separate from other debris. The disposal shall be in compliance with the German Ordinance on the Management of Waste wood ("Altholzverordnung"). Waste wood shall be categorized and disposed of based on the Ordinance on the Management of Waste wood.

c. A copy of the waste consignment document shall be provided to the COR.

- 14 -

d. The dismantled material shall be stored in water-tight covered containers until removal and shall be disposed of at least once a week.

e. Within USAG Bavaria, Grafenwöhr Military Community there is a separate sewer system for rain water and waste water. Therefore, accumulated waste water shall be disposed of via waste water duct in coordination with the COR.

6. Bauschuttabfuhr

a. Material, wie Teeraufbruch, Beton, Holz, Bauschutt, Metall, Äste, Wurzelstöcke, Kartonagen, Sondermüll (Reiniger, Farben, etc.), ausgebaute Materialien (Kabel, Rohre, Installationsmaterialien, etc.) oder Erdaushub werden nicht an der Mülldeponie im Lager Grafenwöhr angenommen. Diese Materialien werden Eigentum des Auftragnehmers und sind gemäß deutschen Gesetzen und Vorschriften (zum Beispiel Kreislaufwirtschaftsgesetz, Altholzverordnung, Merkblatt 3.4/1 des Bayerischen Landesamt für Wasserwirtschaft für Teeraufbruch, etc.) zu entsorgen.

Gegebenenfalls muss der Auftragnehmer ein zertifiziertes Labor beauftragen, repräsentative Proben zu untersuchen und entsprechend einzustufen. Die Probenahme und Analytik des Bodenaushubs muss nach der Richtlinie LAGA PN 98 (Länderarbeitsgemeinschaft Abfall - Richtlinie für das Vorgehen bei physikalischen, chemischen und biologischen Untersuchungen im Zusammenhang mit der Verwertung / Beseitigung von Abfällen) erfolgen. Falls die Probeuntersuchung eine Einstufung der Kontamination aufweist, die nicht in irgendeiner Position der Leistungsbeschreibung beinhaltet ist, wird eine entsprechende Vertragsmodifikation erstellt.

b. Fallen im Zuge der Abbrucharbeiten Holzabfälle an, sind diese separat zurück zu bauen und von den übrigen Abfällen getrennt zur Entsorgung bereit zu stellen.

Die Entsorgung ist in der Altholzverordnung geregelt. Der anfallende Holzabfall ist gemäß den Kategorien der Altholzverordnung einzuteilen und zu entsorgen.

c. Eine Kopie des jeweiligen Entsorgungsnachweises muss dem COR ausgehändigt werden.

d. Bauabfälle sind bis zur Abfuhr in wasserdicht abgedeckten Containern zu lagern und mindestens einmal pro Woche abzufahren.

e. Im Bereich der USAG Bavaria, Grafenwöhr Military Community besteht ein Trennsystem für Regenwasser und Schmutzwasser. Anfallendes Schmutzwasser muss deshalb nach Angabe des COR über den Schmutzwasserkanal entsorgt werden.

7. Job Site Equipment and Storage

The contractor shall be responsible for the safe storage of materials and equipment. Upon approval from the COR and at their own risk the contractor may be authorized to erect containers for personnel and construction equipment/materials according to current German workplace ordinance. These containers shall be a minimum of 25 meters away from any building occupied by 10 or more personnel.

Construction materials and other equipment shall not be stored in U.S. buildings.

Upon completion of work the contractor shall clean up the storage area and return it to its original condition.

- 15 -

7. Baustelleneinrichtung und Materiallagerung

Der Auftragnehmer ist für eine sichere Lagerung der Materialien und Geräte selbst verantwortlich. Er darf mit Genehmigung des COR und auf eigene Gefahr Container für Personal und Baugeräte/Material gemäß der Arbeitsstättenverordnung aufstellen.

Diese Container müssen mindestens 25 m von allen Gebäuden entfernt sein, in denen sich zehn oder mehr Personen aufhalten. Baumaterial und sonstige Gegenstände dürfen nicht in U.S. Gebäuden gelagert werden. Nach Beendigung der Arbeiten ist der Lagerplatz zu reinigen und wieder in den ursprünglichen Zustand zu versetzen.

8. Electromagnetic Compatibility Directive (Germany)

The contractor certifies that all electrical and electronic equipment and appliances furnished are in compliance with the Electromagnetic Compatibility Directive 2014/30/EU. For radio transmitting and telecommunication devices furnished in the Federal Republic of Germany, the contractor certifies that all such items have been approved by the Bundesamt für Zulassungen. Any penalties for noncompliance imposed by the Government of the European country where the equipment or appliances are delivered or product liability claims caused by interference generated by furnished appliances or equipment are solely the responsibility of the contractor.

8. Elektromagnetische Verträglichkeit (Deutschland)

Der Auftragnehmer bescheinigt, dass alle gelieferten elektrischen und elektronischen Betriebsmittel und Geräte mit der Richtlinie über die elektromagnetische Verträglichkeit 2014/30/EU übereinstimmen. Für Funkgeräte und Fernmeldeeinrichtungen, die in der Bundesrepublik Deutschland verwendet werden, bescheinigt der Auftragnehmer, dass diese vom Bundesamt für Zulassungen genehmigt wurden. Alle Strafen für die Nichteinhaltung dieser Bestimmungen, welche von Behörden des europäischen Landes erlassen werden, in die die Betriebsmittel oder Geräte geliefert wurden oder Produkthaftungsansprüche wegen Störungen, die durch die gelieferten Geräte oder Betriebsmittel verursacht wurden, gehen allein zu Lasten des Auftragnehmers.

9. Water and Electrical Power Supply

Water and electrical power are not available at job sites located in peripheral areas. If required, water and electrical power shall be provided by the contractor

(e. g. emergency power generator, water containers).

9. Wasser- und Baustromversorgung

Wasser und Baustrom sind an den im Außenbereich liegenden Baustellen nicht vorhanden. Falls erforderlich, muss beides vom Auftragnehmer gestellt werden

(z. B. Notstromaggregat, Wasserbehälter).

- 16 -

10. Behavior on Ranges and their Danger Zones

Prior to start of work, the contractor's personnel working on this project shall attend a briefing concerning the behavior on ranges and their danger zones. The briefing shall be attended upon coordination with the COR and will be certified in writing. Interruptions caused by training operations are to be expected.

10. Verhalten auf Schießbahnen und deren Gefahrenbereiche

Vor Baubeginn haben sich die an diesem Projekt beteiligten Personen des Auftragnehmers einer Belehrung über das Verhalten auf Schießbahnen und deren Gefahrenbereiche zu unterziehen. Die Belehrung muss nach Rücksprache mit dem COR absolviert werden und wird schriftlich bestätigt. Mit Stillstandszeiten, bedingt durch Trainingsbetrieb, ist zu rechnen.

11. Driving on Tank Roads

Driving on tank roads is only allowed with a permit. At the pre-construction conference the COR will provide a request for this permit to the contractor. The contractor shall complete this request and have the COR sign it. Then the contractor shall submit the completed signed request to "Range Control" in building # 3015, Grafenwöhr Tower Barracks. After issuance of the permit the contractor can pick up the permit at "Range Control".

11. Fahren auf der Panzerstraße

Fahren auf der Panzerstraße ist nur mit Erlaubnisschein zulässig. Ein Antrag hierfür wird dem Auftragnehmer bei der Bauvorbesprechung vom COR übergeben. Dieser ist vom Auftragnehmer auszufüllen und vom COR unterschreiben zu lassen. Den ausgefüllten Antrag muss der Auftragnehmer bei "Range Control" im Gebäude # 3015, Grafenwöhr Tower Barracks, einreichen. Nach Ausstellung des Erlaubnisscheins kann dieser vom Auftragnehmer bei "Range Control" abgeholt werden.

12. As-built Drawings

a. For the scope of work described in the specification, as-built drawings shall be delivered in the format of CAD Software Microstation, version 8 (DGN-file).

b. The COR will provide the contractor with existing U.S. Government drawing documents on compact disk in the above referenced format. The contractor shall provide the data media required for this purpose. The assignment of the individual drawing levels shall be coordinated with the COR. The as-built drawings shall be provided on compact disk in both the German and English languages.

12. Bestandspläne

a. Für den im Leistungsverzeichnis beschriebenen Leistungsumfang sind Bestandspläne im Format der CAD-Software Microstation, Version 8 (DGN-Datei), zu liefern.

- 17 -

b. Der COR stellt dem Auftragnehmer die vorhandenen Planunterlagen der U.S.

Regierung auf CD’s im oben aufgeführten Format zur Verfügung. Die hierfür erforderlichen Datenträger sind vom Auftragnehmer zu stellen. Die Belegung der einzelnen Zeichnungsebenen ist mit dem COR abzustimmen. Die Bestandspläne sind in deutscher und englischer Sprache auf CD’s zu liefern.

13. Protection of trees, existing plants and planted areas at construction measures according to DIN 18 920

a. Protection of planted areas In order to avoid damage, planted areas shall be surrounded with a fence which is at least 1.8 meter (m) high, lateral fence distance 1.5 m.

b. Protection of trees against mechanical damage Trees within the construction site shall be protected against mechanical damage caused by vehicles, construction machines or any other construction processes by means of a fence as described in the previous paragraph "a". The fence shall enclose the entire root area. Root area means the ground surface underneath the tree crown plus 1.5 m (in case of columnar trees add 5 m).

c. Soil excavation shall not be performed in the root area.

d. Trenches, depressions or construction pits shall not be created in root areas. If excavation in this area is unavoidable in special cases, the excavation shall only be performed manually and only up to a distance of 2.5 m to the bottom end of the tree.

e. When excavating trenches, roots with a diameter greater than 3 cm shall not be cut. Damages to roots shall be avoided and shall be treated if necessary.

f. Roots shall be separated by cutting and cut surfaces shall be smoothed.

Root ends with a diameter less than 2 cm shall be treated with growth-stimulating substances and root ends with a diameter greater than 2 cm with substances for wound treatment. Roots shall be protected against drying-out and frost.

13. Schutz von Bäumen, Pflanzenbeständen und Vegetationsflächen bei Baumaßnahmen nach DIN 18 920

a. Schutz von Vegetationsflächen Zur Verhinderung von Schäden sind Vegetationsflächen mit einem mindestens 1.8 m hohen Zaun zu umgeben, seitlicher Zaunabstand 1.5 m.

b. Schutz von Bäumen gegen mechanische Schäden Zum Schutz gegen mechanische Schäden durch Fahrzeuge, Baumaschinen und sonstige Bauvorgänge sind Bäume im Baubereich durch einen Zaun zu schützen, wie im vorhergehenden Paragraph "a" beschrieben. Der Zaun soll den gesamten Wurzelbereich umschließen. Als Wurzelbereich gilt die Bodenfläche unter der Krone von Bäumen (Kronentraufe) zuzüglich 1.5 m (bei Säulenform zuzüglich 5 m).

c. Im Wurzelbereich darf kein Boden abgetragen werden.

- 18 -

d. Im Wurzelbereich dürfen keine Gräben, Mulden oder Baugruben hergestellt werden. Ist dies im Einzelfall nicht zu vermeiden, darf die Herstellung nur in Handarbeit erfolgen und nicht näher als 2.5 m an den Stammfuß herangeführt werden.

e. Beim Aushub von Gräben dürfen Wurzeln mit einem Durchmesser größer als 3 cm nicht durchtrennt werden. Verletzungen sollen vermieden werden und sind gegebenenfalls zu behandeln.

f. Wurzeln sind schneidend zu durchtrennen und die Schnittstellen zu glätten.

Wurzelenden mit einem Durchmesser von weniger als 2 cm sind mit wachstumsfördernden Stoffen, Wurzelenden mit einem Durchmesser größer als 2 cm mit Wundbehandlungsstoffen zu behandeln. Die Wurzeln sind gegen Austrocknung und Frosteinwirkung zu schützen.

14. Spill reporting procedures for contractors working within the Training Area/Tower Barracks and Rose Barracks

a. Applicability: In accordance with USAG Bavaria’s Environmental Management System (EMS) the following procedures shall be followed in the event of a spill of hazardous substances caused by vehicles or equipment of contractors working within the Training Area/Tower Barracks or Rose Barracks

b. Hazards for humans and environment:

- Release of hazardous substances during accidents (mainly Petroleum, Oil and

Lubricant (POL)products);

- Release of hazardous substances caused by equipment failure (mainly POL products)

- Release of hazardous substances during transportation of hazardous materials/waste (excluding Class 1, explosives).

c. Protective Measures and Procedures: The following requirements shall be met when operating a vehicle within the Training Area/Tower Barracks or Rose Barracks.

- Valid driving license appropriate for the vehicle;

- Valid hazardous cargo driver’s license for the transportation of hazardous material/hazardous waste;

- Follow the Road Traffic Regulation:

- Road Traffic Law (Straßenverkehrsgesetz - StVG);

- Road Traffic Regulation (Straßenverkehrsordnung - StVO)Federal Motor Vehicle

Safety Standards (Straßenverkehrs-Zulassungs-Ordnung - StVZO);

- European Agreement concerning the international carriage of dangerous goods by road (Accord europeen relatif au transport international des marchandises Dangereuses par Route - ADR);

- Load safety according to VDI 2700 and ADR

- Spill equipment shall be kept on hand (e.g. absorbent, absorbent pads etc.).

- 19 -

d. The following procedures shall be followed should hazardous situations arise:

- Immediately notify the COR and the local US Fire Department under the following number: 09641 – 83 8303 if hazardous substances (diesel, hydraulic fluid etc.), including hazardous waste, are released due to failure of vehicles or construction equipment;

- The contractor shall take immediate protective measures to prevent spilled material from spreading;

- The necessary spill clean-up shall be performed by the contractor or their subcontractors.

e. Emergency Procedures – First Aid:

- Secure scene of the accident;

- Inform the COR and the local U.S. Fire Department at 09641-83-8303 (emergency number: 09641-83-112);

- Provide first aid to injured individuals

f. Refueling, Maintenance, Disposal:

- To avoid impacting the environment, appropriate precautionary measures shall be taken during refueling of construction vehicles / equipment;

- Maintenance of vehicles and equipment shall only be conducted on paved surfaces connected to an oil/water separator (such as maintenance hardstands/refueling pads);

- The contractor is responsible for the disposal of hazardous substances and contaminated soil caused by accidents or failure of vehicles/equipment. Proof of proper disposal shall be provided to the COR within 14 days after receipt of the documentation (Entsorgungsnachweis).

14. Verhaltensregeln für Auftragnehmer bei Freisetzung von Gefahrstoffen auf dem Truppenübungsplatz/Tower Barracks (Grafenwöhr) bzw. Rose Barracks (Vilseck)

a. Geltungsbereich: Gemäß dem Umweltmanagementsystem (Environmental Management System – EMS) von USAG Bavaria, wird im Folgenden das Verhalten bei Freisetzung von Gefahrstoffen während des Betriebs von Baufahrzeugen von auf dem Truppenübungsplatz/Tower Barracks bzw. in der Rose Barracks tätigen Auftragnehmern beschrieben.

b. Gefahren für Mensch und Umwelt:

- Freisetzen von Gefahrstoffen bei Unfällen (in der Regel Mineralöle).

- Freisetzen von Gefahrstoffen durch defekte Maschinen (in der Regel Mineralöle).

- Freisetzen von Gefahrstoffen bei Gefahrstofftransporten/Sondermülltransporten

(ausgenommen Klasse 1, Sprengstoffe)

c. Schutzmaßnahmen und Verhaltensregeln: Voraussetzung für das Führen eines Fahrzeuges auf dem Truppenübungsplatz/Tower Barracks bzw. in der Rose Barracks:

- Gültige Fahrerlaubnis für das entsprechende Fahrzeug.

- Gültiger Gefahrgutführerschein beim Transport von Gefahrgut/Sondermüll.

- Einhalten der Vorschriften des Straßenverkehrsrechts:

- Straßenverkehrsgesetz (StVG)

- 20 -

- Straßenverkehrsverordnung (StVO)

- Straßenverkehrs-Zulassungs-Ordnung (StVZO)

- Europäisches Abkommen zum internationalen Transport von Gefahrgütern auf

Straßen (Accord europeen relatif au transport international des marchandises Dangereuses par Route - ADR).

- Ladungssicherung entsprechend VDI 2700 und ADR

- Ausrüstung zur Bekämpfung von Ölunfällen ist für den Notfall bereitzuhalten

(z.B. Bindemittel, Ölbindematten etc.).

d. Verhalten bei Störungen und im Gefahrfall:

- Bei Freisetzen von Gefahrstoffen (auch Sondermüll) oder Betriebsmitteln

(Hydrauliköl, Diesel usw.) durch Defekte an Fahrzeugen bzw. Baumaschinen sind sofort der COR und die Standortfeuerwehr unter der Telefonnummer 09641-83-8303 zu verständigen.

- Der Auftragnehmer hat dafür zu sorgen, dass geeignete Sofortmaßnahmen getroffen werden um ein Ausbreiten zu verhindern.

- Die anfallenden Reinigungsarbeiten sind vom Auftragnehmer bzw. Subunternehmer durchzuführen.

e. Verhalten bei Unfällen - Erste Hilfe:

- Unfallstelle sichern.

- COR und Standortfeuerwehr unter 09641-83-8303 (Notruf: 09641-83-112) verständigen.

- Verletzte versorgen.

f. Betanken, Instandhaltung, Entsorgung:

- Beim Betanken von Baustellenfahrzeugen / Baumaschinen sind geeignete

Vorsichtsmaßnahmen zu treffen, um Umweltschäden zu vermeiden.

- Instandhaltungsarbeiten an Fahrzeugen und Baumaschinen sind grundsätzlich nur auf befestigtem Untergrund mit Anschluss an einen Ölabscheider durchzuführen (z.B. Wartungs- und Betankungsflächen).

- Die Entsorgung von ausgelaufenen Substanzen oder von verunreinigtem Boden als Folge von Unfällen oder durch defekte Fahrzeuge/Baumaschinen ist vom Auftragnehmer selbst durchzuführen. Ein Nachweis über die ordnungsgemäße Entsorgung ist dem COR innerhalb von 14 Tagen nach Erhalt der Dokumentation (Entsorgungsnachweis) vorzulegen.

15. Time extensions for unusually severe weather

a. The following specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the contract clause FAR 52.249-10, DEFAULT (FIXED PRICE CONSTRUCTION). In order for the contracting officer to award a time extension under this clause, the following conditions shall be met:

(1) The weather experienced at the project site during the contract period shall be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

- 21 -

(2) The unusually severe weather shall actually cause a delay to the completion of the project. The delay shall be beyond the control and without the fault or negligence of the contractor.

b. The following schedule of monthly anticipated adverse weather delays for the project location will constitute the base line for monthly weather time evaluations. The contractor’s performance schedule shall reflect these anticipated adverse weather delays in all weather dependent activities.

Monthly Anticipated Adverse Weather Calendar Days

| JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC |

| 2 | 2 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 |

c. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor shall record on its inspection records, the occurrence of adverse weather and resultant impact to normally scheduled work.

Actual adverse weather delay days shall prevent work on critical activities for 50 percent or more of the contractor’s scheduled work day.

d. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b above, the contracting officer will approve the exceeding calendar days and issue a modification for time in accordance with contract clause FAR 52.249-10.

15. Zeitverlängerungen im Falle extrem schlechten Wetters

a. Im Folgenden wird der Verfahrensablauf zur Gewährung von Zeitverlängerungen bei extrem schlechtem Wetter gemäß der Vertragsklausel FAR 52.249-10, NICHTEINHALTUNG (FESTPREISBAUVERTRAG) beschrieben.