This document is a Statement of Work (SOW) for a pipe fencing project at the Catahoula Ranger District. The contractor will be responsible for constructing 400 feet of pipe fencing, including 5-foot tall upright supports placed every 10 feet and a welded top rail. The work is to be performed between September 2024 and May 2025.
The related federal contract opportunity is an RFQ issued by the USDA Forest Service for the construction and installation of the pipe fence. This RFQ is limited to current MATOC contract holders under contract numbers 127K1120D0013 through 127K1120D0018. Quotes are due by September 13, 2024 at 11am CDT, and the Forest Service intends to award one firm-fixed price MATOC task order based on this RFQ. All terms and conditions of the parent MATOC contract will apply.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Catahoula Ranger District Fish Creek Pipe Fencing
FY24 TASK ORDER INFORMATION
Dated August 23, 2024
BRIEF DESCRIPTION OF PROJECT:
Pipe fencing to be constructed in the following manner. Use drill stem to construct 400 feet of fencing at one location (see map). Upright supports made of same pipe (drill stem) to be placed every 10 feet unless obstacle is restricting placement. Then the next unobstructed place is to be used. Supports will be 5 feet tall with 2 ½ feet cemented in the ground and 2 ½ feet above ground. Two bags of cement must be used on each support. Saddles will be cut on top of upright post to accommodate top rail of fencing. Rail fencing will be welded to upright supports. An example in the field can be viewed before construction. Careful coordination with the US Forest Service will be necessary during the installation for correct placement.
Location: In the woods approximately 1000ft down a wood’s road. (see map)
Period of Performance:
Contract time begins on the effective date of the Notice to Proceed (NTP) and runs until the appropriate number of calendar day’s elapse. Estimated time to start work is Sept. 2024, to May 2025.
Reference IDIQ contract for all other terms and conditions.