02 - Project Specifications.pdf

PDF 355 KB Posted

Attached to
Site Support for AMARG Tension Fabric #3-6 Federal contract opportunity
Solicitation number
FA487720Q0015
Issued by
Department of the Air Force Air Combat Command

View the file

Other files for this federal contract opportunity

Other files attached to Site Support for AMARG Tension Fabric #3-6, newest first.
File Type Posted
AF Form 3052 (Blank) 14 May 20.xlsx XLSX spreadsheet
Solicitation Amendment FA487720Q00150001 SF 30 (3).pdf PDF
Signin sheet.pdf PDF
04 - Schedule of Items (Blank).docx DOCX document
08 - Tension Fabric Shelter New Site Photos.pdf PDF
03 - WD AZ20200018.docx DOCX document
06 - AF Form 3052 (Blank).xlsx XLSX spreadsheet
12 - Utilities Map.pdf PDF
05 - GFP Rock piles.pdf PDF
07 - Tension Fabric Shelter Existing Photos.pdf PDF
01 - Project Drawings.pdf PDF
06 - New Shelter Site(s) Aerial.png PNG image
11 - Solicitation Notes.docx DOCX document
Solicitation - FA487720Q0015.pdf PDF
09 - GFP Rock Stockpiles Photos.pdf PDF
10 - Canvas storage bldg.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

FOR

FBNV 20-0009

Site Support for AMARG Tension Fabric Structures #3 - 6

AT

DAVIS-MONTHAN AFB

ARIZONA

02 March 2020

02 Mar 2020 Table of Contents-1 FBNV 20-0009

TECHNICAL PROVISIONS OF SPECIFICATIONS

Project No. FBNV 20-0009

Contractor to furnish all labor, equipment, appliance and materials and perform all operations in connection with (Site Support for AMARG Tension Fabric Structures #3 -

6) at Davis-Monthan AFB, Arizona, in strict accordance with these specifications.

TABLE OF CONTENTS

SECTION AND TITLE

DIVISION 01 – GENERAL REQUIREMENTS

01010 Summary of Work AF Form 66 - Schedule of Material Submittals

DIVISION 03 – CONCRETE

03 30 00 Cast-In-Place Concrete

DIVISION 31 – EARTHWORK

31 00 00 Earthwork

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 11 20 Base Course for Rigid Paving

Davis-Monthan Air Force Base, Arizona FBNV 20-0009 Site Support for AMARG Tension Fabric Structures #3 - 6 02 March 2020

01010-1

SECTION 01010 – SUMMARY OF WORK

NOTE: The Davis-Monthan Air Force Base Design Compatibility Guideline requirements and those defined in the following section may directly affect the Contractor’s overhead for completing the scope of work.

Failure on the part of the Contractor to adequately review this section and identify/clarify any requirements herein will not constitute justification of Contractor claims for additional design and/or construction costs.

1. SUMMARY OF WORK

1.1 Work Included in this Contract: This request for proposal (RFP) calls for the construction of foundation pads at Davis-Monthan Air Force Base (Tucson), Arizona. Work will include but is not limited to excavation as well as embankment. The following descriptions are for general reference only, and shall not be construed as a complete list of all operations to be performed.

1.1.1. General Requirements.

1.1.1.1. Base utility information which may be provided for this RFP is the best information available and may be provided to assist the Contractor during this project. The Contractor is solely responsible for field verifying all information given, by potholing. The Contractor is also responsible for obtaining all information necessary to properly construct the project. Information gathering during construction shall be coordinated through the Contracting Officer. Any field surveying requiring the provision of utility locations, manhole inverts, verification of existing grades and features, etc., shall be the responsibility of the Contractor and shall be tied into the base surveying datum. Use of existing condition data provided by the Air Force does not relieve the Contractor of liability associated with performance of work.

1.1.1.2. The project shall conform to all applicable Federal, State and local laws, regulations and base-specific standards and applicable Unified Facilities Criteria (UFC). Where there is a conflict between the referenced standards the most stringent shall take precedence.

1.1.1.3. All construction work shall be accomplished between the hours of 0630—1630, Monday through Friday, unless otherwise approved in writing by the CO.

1.1.1.4. The construction site is within a controlled area and shall require the Contractor and subcontractors to have the requisite badging and identification to access this project site. The Contractor shall consider in the contract documents (e.g., the construction cost estimate) the reasonable costs and effects of daily, short delays in accessing the project site, as required by the restrictive access requirements or by local alert conditions.

1.1.2. Demolition Requirements

1.1.2.1. (Construct) Remove topsoil for the installation of four foundation pads.

1.1.2.2. See Civil Requirements (Paragraph 1.1.3.) for additional work.

1.1.3. Civil Requirements

1.1.3.1. The Contractor shall arrange for bluestaking of the site and any affected areas for the purposes of determining information applicable to, necessary for and pertinent to the construction of this project.

1.1.3.2. The Contractor shall perform a survey of the site and any affected areas for the purposes of determining information applicable to, necessary for and pertinent to this project.

1.1.3.3. (Construct) Grade site as shown in drawing sheet 2.

1.1.3.4. (Construct) Provide foundation pads as dimensioned on drawing sheet 2. Each shelter structure foundation shall be all one elevation.

1.1.3.5. (Construct) Provide a minimum of a 60-foot separation between each shelter structure, measured from the foundation edges, per UFC 3-600-01, Fire Protection Engineering for Facilities, with Change 2.

1.1.3.6. (Construct) Compact each site to 95 percent of laboratory maximum density.

1.1.3.7. (Construct) Catch existing grades, up or down, at a minimum 3:1 slope on all sides of the foundation pads.

01010-2

1.1.3.8. (Construct) Stockpile remaining excavation at a location, to be determined by the Contracting Officer, near the project site.

1.1.3.9. (Construct) Grade and prepare the subgrade of the two existing west entrances for a 20-foot wide concrete driveway, both exterior and interior to the shelter. Compact subgrade to 95 percent of laboratory maximum density.

1.1.3.10. (Construct) Provide and install 6-inch aggregate base course (ABC) at the driveway locations.

Compact ABC to 95 percent of laboratory maximum density.

1.1.3.11. (Construct) Install a 6-inch concrete driveway at each west entrance at a 2% slope away from the existing structures. Driveway shall be centered on existing door, 20-foot wide, and match existing elevations from the top of the concrete foundation to the bottom of the ramp. Concrete shall be 4,000 PSI, with 4x4 welded wire fabric (WWF).

1.1.3.12. (Repair) The contractor shall fill in all the erosion surrounding the two existing shelters. The final side slopes shall match the existing 5:1 slope. Cover the existing 12” vinyl shelter flap with 2” of dirt.

1.1.3.13. (Repair) Provide and install Gradation B, City of Tucson Standard Specifications Section 810 Erosion Control and Pollution Prevention, river rock within the first 4-feet of the shelter slopes. Existing 150-ton stockpile of river rock can be used.

1.1.3.14. (Repair) Provide and install Gradation A, City of Tucson Standard Specifications Section 810 Erosion Control and Pollution Prevention, river rock within the final 4-feet of the shelter slopes. Existing 150-ton stockpile of river rock can be used.

1.2 Salvage and Disposal: All salvageable and non-salvageable material obtained by removal of existing material shall be considered as having been included as a factor in the Contractor's bid price.

a. Salvageable material obtained from existing construction may be reused only if so stated elsewhere in the Contract Documents, and then only when the material is approved for reuse by the Contracting Officer.

b. Salvageable material shall remain the property of the Government only when specifically called out in the Contract Documents.

c. Salvageable material not reused or otherwise designated to remain the property of the Government shall become the property of the Contractor and shall be removed and disposed of off base in accordance with the environmental controls specified in this Section.

d. Non-salvageable material: Remove all non-salvageable material from the project site and dispose of it off base, in accordance with the environmental controls specified in this Section.

1.3 Base Outages and Digging Permits (AF Form 103, BCE Work Clearance Request):

a. Utility Outages: Accomplish all work required in connection with utility outages on weekends or off-duty hours, or as directed by the Contracting Officer. The Contractor shall be responsible for all work associated with the utility outages. Notify the Contracting Officer in writing 21 calendar days prior to the desired date for the utility outage.

b. Road Closures: If road closures are needed during the construction of any portion of the project, a traffic control plan shall be generated by the Contractor and submitted for approval by the Contracting Officer. Notify the Contracting Officer in writing 21 calendar days prior to the desired date for closure.

c. The Contractor is responsible for and shall process all digging permits and bluestake requirements through the 355 CES Customer Service Desk (Bldg 5315). The Contractor shall allow for approximately 21 calendar days for the construction areas to be properly marked. The Contractor is also responsible for contacting Arizona Blue Stake and independently marking and potholing for security camera conduit/wiring around the base; and vacuum and oxygen medical lines around the 355 Medical Group. Although the 355 CES Drawing Vault has drawings for security camera conduit/wiring and medical lines, it is not responsible for the bluestaking or actual location of these utilities. The Contractor must mark all areas that he wishes to have the Government bluestake with white paint PRIOR to the submission of the AF Form 103; and shall include a site drawing of the area to be bluestaked with the submission. Upon submission, the Contractor

01010-3 shall provide the Contracting Officer the tracking number in order for the Government to help the Contractor track its progress (if necessary). Once a construction site has been marked, it is the Contractor’s responsibility to maintain the markings with stakes or whiskers.

1.4 Submittal Procedures:

a. AF Form 66, Schedule of Material Submittals: An AF Form 66, listing the items of equipment and materials for which submittals are required by the specifications, shall be generated during the design by the Contractor for the Government’s approval. A draft of the base-standard AF Form 66 may be provided at the Contractor’s request, for the Contractor’s use. The Contractor shall complete the column “Required Submission Date” and submit to the Contracting Officer for approval within 10 calendar days after Notice to Proceed. The approved submittal register will become the scheduling document and will be used to control submittals throughout the life of the contract. During construction, it may be discovered that this list was not all-inclusive and that additional submittals may be required from and shall be submitted by the Contractor, as directed by the Contracting Officer.

b. AF Form 3000, Material Approval Submittal:

1. The AF Form 3000 shall be used for submitting both Government-approved and information-only submittals in accordance with the instructions on the reverse side of the form. The Contracting Officer shall furnish these forms to the Contractor. This form shall be properly completed by filling out the heading blanks and identifying each item submitted. Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the information submitted for each item(s).

2. The Contractor shall forward all material submittals required by the technical specifications using the AF Form 3000 as stated in paragraph b1 above. The Contractor provides the submittals in the number of copies as specified on the AF Form 66 and one original of the completed AF Form 3000 to the Contracting Officer no later than the required submission date specified on the AF Form 66 or 10 calendar days from the Notice to Proceed, whichever is later.

3. Identify each submittal by project, Contractor, drawing or detail number, and specification section number, as appropriate. Mark submittals to show the specific item(s) that will be furnished. Include intended use of the submittal and any other pertinent information necessary for a complete evaluation. If the Contractor provides a submittal which show variations from the contract documents, the Contractor shall completely describe such variations in writing clearly and separately from any other portion of the submittal. Highlighting or marking in any manner the proposed variations is not sufficient to comply with this requirement. This requirement applies irrespective of the provisions of any specification which follow this section and which may be particular to specific item(s).

c. Submit to the Contracting Officer complete information applicable to the item(s) of equipment and materials called for by the Contract Documents, for approval, prior to installing the relevant item(s) of equipment and material. If unapproved item(s) of equipment or material are installed, the Contracting Officer, at his sole discretion and option, may reject the installed equipment and material. If rejected, the Contracting Officer may then pursue, again in his sole discretion and option, remedies including but not limited to the removal and reinstallation of approved item(s) of equipment or material at the Contractor’s expense, extended warranties, and other remedies as may be deemed appropriate and applicable to that portion of the construction.

d. Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled.

e. Adequate time of 21 calendar days shall be allowed and shown on the register for distribution, review and approval by both or either the Project Inspector and Contracting Officer.

f. The Contractor, as part of the bid price, shall have a Government-approved, independent, commercial, testing laboratory perform all sampling and testing as called for in these specifications. Test reports shall be properly sealed by a professional engineer.

1.5 Construction Schedule and Progress Reports (AF Form 3064 and AF Form 3065):

01010-4

a. Following contract award, the Contractor shall prepare the construction completion schedule using the AF Form 3064, Contract Progress Schedule. The Contractor shall submit for government review and approval the AF Form 3064 no later than ten (10) calendar days following issuance of the Notice to Proceed.

b. Upon approval of the AF Form 3064 submit to the Contracting Officer, on a biweekly schedule, the construction progress using the AF Form 3065, Progress Report.

1.6 Quality Control:

a. Provide quality control over the entire project including but not limited to the items of equipment and materials intended for installation, necessary coordination and services to facilitate the performance of the work, site conditions, and the workmanship of the Contractor personnel and any subcontractors.

b. The Contractor shall become familiar with all the details of the work depicted in the Contract Documents and shall verify all field conditions related to the construction prior to commencement of the work. If conditions are discovered by the Contractor prior to commencement of the work which conflict with the Contract Documents, and which will substantially affect the construction as designed and depicted in the Contract Documents, identify and explain the condition(s) in writing to the Contracting Officer within 48 hours of discovery of the condition(s); and request clarification from the Contracting Officer before commencing work.

c. If site conditions are discovered by the Contractor during the construction which conflict with the Contract Documents, and which affect either a portion of the current construction, or which will substantially affect the construction as designed and depicted in the Contract Documents, identify and explain the condition(s) in writing to the Contracting Officer within 48 hours of discovery of the condition(s); and request clarification from the Contracting Officer before proceeding. All such requests for information shall completely address aspects of the condition, including but not limited to, engineering judgments and engineered solutions, possible costs or deductions, and time extensions.

d. If site conditions or defects are discovered during the construction, by the Contracting Officer or the Contracting Officer’s designated representative, which are the result of the Contractor’s inadequate quality control or substandard workmanship, whether by the Contractor or a subcontractor, which conflict with the Contract Documents, and which affect either a portion of the current construction, or which will substantially affect the construction as designed and depicted in the Contract Documents, the Contracting Officer may direct the Contractor to identify and explain the condition(s) or defect(s) in writing to the Contracting Officer within 48 hours of discovery of the condition(s). In all such instances, the Contractor shall present no less than three viable options to correct the condition or defect, completely addressing aspects of the condition, including but not limited to, engineering judgments and engineered solutions, possible costs or deductions, and time extensions. The Contracting Officer will then review and approve an option for use by the Contractor. The Contractor shall not proceed with the work until receiving the written permission from the Contracting Officer.

e. The Contractor shall comply fully with manufacturer's instructions, including each step in sequence.

If such instructions conflict with the Contract Documents, identify and explain the conflict in writing to the Contracting Officer within 48 hours of discovery of the conflict; and request clarification from the Contracting Officer before proceeding.

f. Testing: The Contractor shall provide samples and test results as required by the Contract Documents. Test reports shall be properly sealed by an independent professional engineer.

g. Cleanup: The Contractor shall keep the work area and surrounding surfaces clean and orderly.

Remove any Contractor-caused residue, dirt, or markings immediately upon completion of the work involved. Clean site daily.

h. Exterior surfaces including but not limited to Portland cement concrete, asphalt pavements, and gravel and interior surfaces including but not limited to carpet, tile, ceiling tiles, and gypsum board damaged by construction work or the Contractor’s operations, shall be replaced with materials consistent in quality and workmanship to match existing.

i. It is the Contractor’s responsibility to maintain any and all quality control records and have them available to the Government at all times.

01010-5

j. Record drawings shall be kept at the job site at all times, and shall be made available upon request by either or both the Project Inspector or the Contracting Officer. The record drawings shall be marked up on a daily basis to show actual “as-built” construction and conditions.

1.7 Experience Requirement:

a. The Contractor must have in the past been engaged in earthwork of this type for a minimum of five year(s). To complete a project of this nature during the short contract period, it is essential that the Contractor firm have the necessary background, supervision, and qualified personnel. Contractors proposing to submit a bid on this project must be prepared to submit notarized affidavits from Government agencies attesting to satisfactory performance of work of at least three project(s) of this nature during the previous five year period and to the qualifications both in terms of expertise and having proper and adequate equipment to accomplish the work. The affidavits will be reviewed for approval or disapproval. The notarized affidavits will be submitted within 3 calendar days after requested. If the Contractor firm for this project has previously submitted the required certification to the Contracting Officer under a previous contract requiring the same certification, re-submission is not required.

2. CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

2.1 Traffic Regulation:

a. Barriers: Contractor shall furnish all signs, barricades, and flagmen required to control traffic in the construction area.

1. All signs and barricades shall be in accordance with ANSI D6.1, Manual of Uniform Traffic Control Devices.

2. Minimize interference with the flow of traffic. At no time may access to any facility be prevented.

b. Haul routes: As directed by the Contracting Officer. The haul route shall enter and exit through the Swan Road gate, and travel to and from the project site by the most direct route.

1. Immediately clean up any material spilled along the haul route. This shall include clean-up of mud tracked on the road by the Contractor’s equipment.

2. For any spill of hazardous material on base, immediately notify the base fire department at 911.

The Contractor is responsible for all costs incurred by the Government in responding to or cleaning up any such spill.

c. Access: Contractor shall maintain access to the base work site at all times. The Contractor is to perform his work with a minimum of interference to the flow of traffic.

2.2 Safety:

a. Comply with the Corps of Engineers Manual on General Safety Requirements, EM 385-1-1;

Occupational Safety and Health Act (OSHA), Public Law 91-596; and AFI 91-301, Air Force Occupational Safety, Fire Prevention, and Health (AFOSH) Program.

b. Use of flammable adhesives or other similar flammable materials will be in strict accordance with manufacturer's instructions and the Contractor shall take all necessary safety and fire prevention steps to supervise and assure safe execution of work on the contract. This paragraph is applicable to adhesive materials or any other material involving flammable characteristics.

2.3 Blasting: No blasting will be permitted.

2.4 Grade Control: Grade site to drain to protect site from puddling or running water, or accumulation of standing water in excavations. The Contractor shall provide all surveying required to establish and maintain line and grade stakes necessary to complete the construction.

2.5 Environmental Control:

a. The Contractor shall be required to meet or exceed the requirements and procedures of the most current Davis-Monthan AFB (DMAFB) Contractor Environmental Guide in effect at the time of contract award. This guide will be provided to the Contractor within the request for proposal. The guide includes

01010-6 procedures to ensure compliance with the DMAFB environmental permit requirements and other regulations to include, but not limited to, training for the ISO 14001 Environmental Management System (EMS). To receive the initial EMS Awareness Training, the Contractor will be required to register and login to The Environmental Awareness Course Hub (TEACH): https://usaf.learningbuilder.com (must use Google Chrome). The detailed registration instructions are found in Appendix E of the DMAFB Contractor Environmental Guide.

b. Additionally, the Contractor shall be held responsible for complying with all federal, state, and local environmental regulations included as part of the processes in performing the work included in this project.

c. Hazardous material (HAZMAT) and/or regulated wastes may be encountered during construction -see Appendix A and Attachment(s) A-1 to A-3 of the Environmental Guide. These requirements shall be included as a submittal on the AF Form 66, Schedule of Material Submittals. Contractor shall plan and submit a HAZMAT worksheet (Attachment A-1), including the appropriate SDS and an estimated quantity to be used, to the gov’ts contract representative prior to construction. The Contracting Officer Representative will forward Attachment A-1 to Environmental for review and Environmental will return with Attachment A-2 determining if Attachment A-3 will be needed.

d. Obtain permits from the Pima County Department of Environmental Quality (PDEQ), Air Quality Division, for installation of new equipment or use of Contractor equipment which generate air pollution, for earth-moving activities related to new construction, and for asbestos removal or demolition. These permits shall be included as a submittal on the AF Form 66, Schedule of Material Submittals. Submit copies of permits to the Contracting Officer prior to beginning construction. All permit costs shall be considered as having been included as a factor in the Contractor's bid price.

e. The Contractor shall also submit a Construction and Demolition (C&D) Plan (Attch B-1, Contractor Environmental Guide) 3 weeks prior to starting construction. If the C&D Plan indicates potential regulated wastes or hazardous wastes, the contractor shall coordinate any disposal requirements through the contractor’s representative prior to disposal or manifesting – see Appendix C of the Contractor Environmental Guide. For projects involving asbestos abatement, complete the standard "Notification of Demolition or Renovation" forms and submit to PDEQ and other required agencies. These forms shall be included as a submittal on the AF Form 66, Schedule of Material Submittals. Submit copies of the forms to the Contracting Officer prior to beginning construction or demolition activities. The Contracting Officer Representative will forward the plan and forms to Environmental for review.

f. Contractors shall comply with all regulatory requirements/considerations if the project requires soil disturbance. These requirements may include Storm Water Pollution Prevention Plans (SWPPP), Air Activity Permits (see para d above), and Natural and Cultural Resource protections. Area disturbance requiring permits is set forth by Arizona Department of Environmental Quality (ADEQ) and PDEQ. Treat areas subject to dust producing activities with liquid palliatives which will not harm regrowth of vegetation, or other methods of dust control. Also, ensure methods to protect native plants, birds and wildlife are included in projects where required.

g. No open burning of trash, brush, or refuse will be permitted.

h. The Contractor shall be responsible for the proper management of both hazardous and non-hazardous waste and the required submittals IAW Section 3 and Appendix C of the Contractor Environmental Guide. The Contractor shall segregate hazardous or regulated materials and non-hazardous or non-regulated materials during demolition; and handle, transport, store, and dispose of these hazardous and non-hazardous materials in accordance with applicable federal, state, and local laws, ordinances, or other rulings having the effect of law, including but not limited to the items listed below. In addition, the Contractor shall obtain proper disposal manifests for both hazardous and regulated materials, and for non-hazardous or non-regulated materials, and submit these manifests to the Contracting Officer.

These manifests shall be included as a submittal on the AF Form 66, Schedule of Material Submittals. The Contracting Officer Representative will forward all manifests to Environmental for review. Submit original manifest—with original signature of the Contractor’s superintendent or authorized representative in block 14 attesting to the validity of the manifest—to the Contracting Officer within 3 calendar days of disposal.

For wastes regulated as PCBs or RCRA, the contractor must use DM’s EPA ID number in the Uniform Hazardous Waste Manifest (EPA Form 8700-22) and the manifest must be coordinated with and signed in

01010-7 block 15 by a designee in DM’s Environmental Management Office at the time of shipment. All handling, transporting, and disposal costs shall be considered as having been included as a factor in the Contractor's bid price. Any questions regarding proper handling or disposal of hazardous or non-hazardous materials may be directed through the Contracting Officer to the Installation Management Flight at 228-4840.

1. Resource Conservation and Recovery Act (42 USC 6901)

2. Clean Water Act (33 USC 1251)

3. Clean Air Act (42 USC 7401-7642)

4. Toxic Substances Control Act (15 USC 260)

5. National Environmental Policy Act (42 USC 4321-4347)

6. Hazard Communication (OSHA Std 29 CFR 1910.1200)

i. All radioactive material or equipment using radioactive material must be approved for use prior to bringing it on the base. The written request for approval, along with a copy of the permit for the source and a brief description of the intended activities, shall be submitted to the base Bioenvironmental Engineering Flight through the Contracting Officer 30 calendar days prior to the Contractor’s use. No work involving radioactive materials may proceed until receipt of the approved request. This requirement shall be included as a submittal on the AF Form 66, Schedule of Material Submittals.

j. Any items containing radioactive material, especially radio luminescent exit signs, discovered while performing maintenance, repair, alteration or renovation activities, shall be turned in by the Contractor through the Contracting Officer to 355 CES/CEO for proper disposal.

k. Liquid paints or coatings with lead shall be restricted to no more than 0.06 percent lead by weight of the non-volatile solids for use in or on all base facilities [Part 35 of 24 CFR].

2.6 Security:

a. For entry to the base, submit an entry authorization request letter for each individual requiring access to the project, at least 10 calendar days prior to beginning work. A copy of the format of this letter may be obtained from the Contracting Officer on or before the pre-performance conference. Valid identification with a photograph together with the base pass will be required for all individuals when entering the base.

b. All passes issued must be returned to the Contracting Officer upon termination of the employee or completion of the project, whichever is sooner.

c. This project is located in AMARG, a controlled area, and strict entry control is maintained.

1. To gain access to AMARG, at least 10 calendar days prior to beginning work, all Contractor personnel must be listed on an entry access letter (EAL). This list shall include the full name and social security number of the individual and the dates access will be required. The individuals will be issued a Contractor’s pass.

2. All passes issued must be returned to the Contracting Officer upon termination of the employee or completion of the project, whichever is sooner.

2.7 Project Identification Sign: Not used.

2.8. Project Progress Photographs: Submit to the Contracting Officer construction project progress digital photographs (minimum of twenty images files in JPG format, 450 -1000 KB, on Windows readable CD) taken on or about the first of every month, showing the general conditions of the work as viewed from the north, south, east, and west. Photographs are also required to document work phases such as rebar emplacement, concrete pours, sewer rough-in, etc., when the Government Project Inspector/Engineer is unable to view the site prior to that work being completed. Each image file shall be identified by the date of exposure (year-month-day), the project number and title, and description of content using the following format: Project Number - Project Title - Date - Project Item. This requirement shall be included as a submittal on the AF Form 66, Schedule of Material Submittals.

2.9. Fenced Contractor’s and Storage Yards: The Contractor shall install and maintain a temporary, fenced Contractor’s yard (in the base’s Contractor’s area) and a temporary, fenced storage yard (near the

01010-8 project site if approved) in locations designated by the Contracting Officer. The temporary fencing shall be of sufficient strength and height to minimize and restrict entry by unauthorized personnel. The temporary fencing shall be provided with visual screening for the full height and length, using tan-colored screening or a similar color selected and approved by the Contracting Officer. The temporary fencing and screening shall remain in place and be maintained for the life of this contract.

2.10. Material Handling and Storage:

a. Handle, store, and protect all products in accordance with manufacturer's instructions.

b. At the end of each work day, park and store all equipment and materials in the location designated by the Contracting Officer.

3. PROJECT CLOSE-OUT

3.1 Pre-Inspection Final Cleaning:

a. Clean all surfaces exposed to view.

b. Polish transparent and glossy surfaces.

c. Clean equipment and fixtures.

d. Clean debris from roofs, gutters, drainage systems, and site.

e. Remove temporary labels.

f. Properly dispose of all hazardous and non-hazardous materials off base in accordance with the environmental controls specified in this Section.

3.2 Record Disks, Documents, and Disks:

3.2.1. Provide design and construction deliverables as defined in the Design Compatibility Guidelines and in this Section the following paragraphs.

3.2.2. Prior to the Contracting Officer's final acceptance of and final payment for the completed project, submit for approval the record as-built drawings, disks, documents, and shop drawings as required in the following paragraphs, no later than 30 calendar days after the Final Inspection. These requirements shall be included as submittals on the AF Form 66, Schedule of Material Submittals.

a. Record As-built Drawings. Standard drafting practices shall be used to represent changes and shall include supplemental notes, legends, details and dimensions as required to show actual "as-built" construction. Submit to the Contracting Officer one full-size and one half-size sets of high-quality bond drawings, clearly and legibly marked “AS-BUILT DRAWINGS” in large print at the bottom right corner of each drawing sheet above the title block.

b. Record Disks. The Contractor shall submit two disks containing the following:

1. AutoCAD (dwg's) and Adobe Acrobat (pdf's) of the as-built drawings.

2. Scanned pdf's of the Operation and Maintenance (O&M) Manuals. (See also subparagraph 3.2.2.d below.)

3. Warranties and/or Guarantee Items in both Microsoft Word and pdf formats. (See also subparagraph 3.2.2.c.3 below.)

4. Scanned pdf's of the Government-approved, final version of the completed project AF Form 66, Schedule of Material Submittals, and all associated project submittals, including but not limited to, the AF Form 3000, Material Approval Submittal and the associated submittal(s) and resubmittal(s) and review(s) by the Government.

5. Scanned pdf's of the Government-reviewed and Contracting Officer-signed AF Form 3064, Contract Progress Schedule, and AF Forms 3065, Contract Progress Report.

c. Record Documents. Fourteen calendar days prior to the final inspection, complete the following record documents and submit to the Contracting Officer.

01010-9

1. DD Form 1354, Transfer and Acceptance of Military Real Property.

2. DD Form 1354 Checklist.

3. Contract/Roof Warranty and/or Guarantee Items.

4. DD Form 250, Material Inspection and Receiving Report

d. Operation and Maintenance Manuals. Submit operation and maintenance manuals for each major building system or item of equipment as per the contract specifications, including but not limited to all mechanical and electrical systems and equipment:

1. Reference information to be included, as applicable:

a. Table of contents.

b. Directory listing names, addresses, and telephone numbers of the architect/engineer, Contractor, subcontractors, and suppliers.

c. Significant design criteria.

d. Shop drawings and product data.

e. Air and water balance reports.

f. Certificates.

g. Copies of warranties.

2. Operation and maintenance information to be included, as applicable:

a. List of equipment.

b. Parts list for each component.

c. Operating instructions.

d. Maintenance and troubleshooting instructions.

e. Repair and assembly/disassembly instructions.

f. Calibration requirements.

3.3 Field Instructions: Prior to final inspection, provide competent instruction, using the manuals described above, to the Government in the operation and maintenance of the building systems and equipment, including but not limited to all mechanical and electrical systems and equipment.

End of Section 01010

PROJECT NUMBER : PROJECT TITLE: SOLICITATION/CONTRACT NO.:

NO. OF COPIES REQUIRED

Awarded:

Pre-Con:

NTP:

Const. Start:

Const. End:

Final:

APPROVED DISAPPROVED

AF Form 103 Job Order Sec 01010, Para 1.3c

AF Form 3064, Contract Progress Schedule Sec 01010, Para 1.5

(for projects > 59 calendar days)

Air Quality Activity Permit Sec 01010, Para 2.5d

7 Days after Reciept of Permit

AZPDES General Permit Sec 01010, Para 2.5d

2 Days Prior to Construction

SWPP Plan Sec 01010, Para 2.5f

Progress Photographs Sec 01010, Para 2.8

Preliminary As-Builts Sec 01010, Para 3.2.2.a

At Final Inspection

Record As-Builts Sec 01010, Para 3.2.2.a

Record Disks Sec 01010, Para 3.2.2.b

DD Form 1354 Sec 01010, Para 3.2.2.c.1

Warranty/Guarantee Items Sec 01010, Para 3.2.2.c.3

Reinforcing Steel Sec 03 30 00, Para 1.6.2.1

Joint Filler Sec 03 30 00, Para 2.4.2

Cementitious Materials Sec 03 30 00, Para 2.3.1

Concrete Curing Materials Sec 03 30 00, Para 2.4.1

1 1

Reinforcement Sec 03 30 00, Para 2.6

Admixtures Sec 03 30 00, Para 2.3.4

Biodeg. Form Release Agent Sec 03 30 00, Para 2.2.2

Concrete Mix Design Sec 03 30 00, Para 1.6.1.2 & 2.5

1 1

REMARKS

FI

NA

L

AP

PR

OV

AL

P re co n st ru ct io n

S u b m it ta ls

S h o p D ra w in g s

P ro d u ct

D at a

S am p le s

D es ig n D at e

T es t

R ep o rt s

C er ti fi ca te s

M an u fa ct u re r' s

In st ru ct io n s

M an u fa ct u re r' s

F ie ld R ep o rt s

RE

TU

RN

S

US

PE

NS

E

DA

TE

SU

BM

IT

TA

L

NU

MB

ER

S

DATE CONTRACTOR NOTIFIED

CO

NT

RA

CT

OR

R

ES

UB

MI

TT

AL

FBNV 20-0009 Site Support for AMARG Tension Fabric Structures #3 - 6SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

NE

N

UM

BE

R

ITEM OR DESCRIPTION OF ITEM, CONTRACT

REFERENCE, TYPE OF SUBMITTAL

RE

QU

IR

ED

S

UB

MI

SS

IO

N

DA

TE

DA

TE

R

EC

EI

VE

D

IN

C

ON

TR

AC

TI

NG

DA

TE

T O

CI

VI

L

EN

GI

NE

ER

IN

G

C lo se o u t S u b m it ta l

O p er at io n a n d

M ai n te n an ce M an u al s

AF FORM 66 (Computer Generated) PAGE 1 of 2

PROJECT NUMBER : PROJECT TITLE: SOLICITATION/CONTRACT NO.:

NO. OF COPIES REQUIRED

Awarded:

Pre-Con:

NTP:

Const. Start:

Const. End:

Final:

APPROVED DISAPPROVED

REMARKS

FI

NA

L

AP

PR

OV

AL

P re co n st ru ct io n

S u b m it ta ls

S h o p D ra w in g s

P ro d u ct

D at a

S am p le s

D es ig n D at e

T es t

R ep o rt s

C er ti fi ca te s

M an u fa ct u re r' s

In st ru ct io n s

M an u fa ct u re r' s

F ie ld R ep o rt s

RE

TU

RN

S

US

PE

NS

E

DA

TE

SU

BM

IT

TA

L

NU

MB

ER

S

DATE CONTRACTOR NOTIFIED

CO

NT

RA

CT

OR

R

ES

UB

MI

TT

AL

FBNV 20-0009 Site Support for AMARG Tension Fabric Structures #3 - 6SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

NE

N

UM

BE

R

ITEM OR DESCRIPTION OF ITEM, CONTRACT

REFERENCE, TYPE OF SUBMITTAL

RE

QU

IR

ED

S

UB

MI

SS

IO

N

DA

TE

DA

TE

R

EC

EI

VE

D

IN

C

ON

TR

AC

TI

NG

DA

TE

T O

CI

VI

L

EN

GI

NE

ER

IN

G

C lo se o u t S u b m it ta l

O p er at io n a n d

M ai n te n an ce M an u al s

Fly Ash & Pozzolan Sec 03 30 00, Para 1.6.4.1

Aggregates Sec 03 30 00, Para 1.6.4.2

Compressive Strength Tests Sec 03 30 00, Para 3.12.2.3

Air Content Sec 03 30 00, Para 3.14.2.4

Slump Tests Sec 03 30 00, Para 3.12.2.1

Water Sec 03 30 00, Para 2.3.2

Welder Qualifications Sec 03 30 00, Para 1.8

Safety Data Sheets Sec 03 30 00, Para 1.6.3.4

Testing Sec 31 00 00, Para 3.12

1 1

Contractor to add Submittals as required or requested.

AF FORM 66 (Computer Generated) PAGE 2 of 2

SECTION 03 30 00 Page 1

SECTION 03 30 00

CAST-IN-PLACE CONCRETE

02/19

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONCRETE INSTITUTE (ACI)

ACI 117 (2010; Errata 2011) Specifications for

Tolerances for Concrete Construction and Materials and Commentary

ACI 121R (2008) Guide for Concrete Construction

Quality Systems in Conformance with ISO

ACI 301 (2016) Specifications for Structural

Concrete

ACI 302.1R (2015) Guide for Concrete Floor and Slab

Construction

ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing

ACI 305R (2010) Guide to Hot Weather Concreting

ACI 306R (2016) Guide to Cold Weather Concreting

ACI 308.1 (2011) Specification for Curing Concrete

ACI 347R (2014; Errata 1 2017) Guide to Formwork for Concrete

ACI SP-2 (2007; Abstract: 10th Edition) ACI Manual of Concrete Inspection

ACI SP-15 (2011) Field Reference Manual: Standard

Specifications for Structural Concrete ACI 301-05 with Selected ACI References

AMERICAN HARDBOARD ASSOCIATION (AHA)

AHA A135.4 (1995; R 2004) Basic Hardboard AMERICAN

WELDING SOCIETY (AWS)

AWS D1.4/D1.4M (2011) Structural Welding Code -

Reinforcing Steel

ASTM INTERNATIONAL (ASTM)

ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

SECTION 03 30 00 Page 2

ASTM A615/A615M (2016) Standard Specification for

Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

ASTM A706/A706M (2016) Standard Specification for Low-

Alloy Steel Deformed and Plain Bars for Concrete Reinforcement

ASTM A780/A780M (2009; R 2015) Standard Practice for

Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings

ASTM A884/A884M (2019) Standard Specification for Epoxy-

Coated Steel Wire and Welded Wire Reinforcement

ASTM A934/A934M (2016) Standard Specification for Epoxy-

Coated Prefabricated Steel Reinforcing Bars

ASTM A1022/A1022M (2016b) Standard Specification for

Deformed and Plain Stainless Steel Wire and Welded Wire for Concrete Reinforcement

ASTM A1060/A1060M (2016b) Standard Specification for Zinc-

Coated (Galvanized) Steel Welded Wire Reinforcement, Plain and Deformed, for

ASTM A1064/A1064M (2017) Standard Specification for Carbon-

Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete

ASTM C31/C31M (2019) Standard Practice for Making and

Curing Concrete Test Specimens in the Field

ASTM C33/C33M (2018) Standard Specification for

Concrete Aggregates

ASTM C39/C39M (2018) Standard Test Method for

Compressive Strength of Cylindrical Concrete Specimens

ASTM C42/C42M (2018a) Standard Test Method for

Obtaining and Testing Drilled Cores and Sawed Beams of Concrete

ASTM C78/C78M (2018) Standard Test Method for Flexural

Strength of Concrete (Using Simple Beam with Third-Point Loading)

ASTM C94/C94M (2018) Standard Specification for Ready-

Mixed Concrete

ASTM C143/C143M (2015) Standard Test Method for Slump of

Hydraulic-Cement Concrete

ASTM C150/C150M (2018) Standard Specification for

SECTION 03 30 00 Page 3

Portland Cement

ASTM C172/C172M (2017) Standard Practice for Sampling

Freshly Mixed Concrete

ASTM C173/C173M (2016) Standard Test Method for Air

Content of Freshly Mixed Concrete by the Volumetric Method

ASTM C231/C231M (2017a) Standard Test Method for Air

Content of Freshly Mixed Concrete by the Pressure Method

ASTM C260/C260M (2010a; R 2016) Standard Specification for Air-Entraining Admixtures for

ASTM C311/C311M (2018) Standard Test Methods for Sampling and Testing Fly Ash or Natural Pozzolans for Use in Portland-Cement Concrete

ASTM C330/C330M (2017a) Standard Specification for

Lightweight Aggregates for Structural

ASTM C494/C494M (2017) Standard Specification for

Chemical Admixtures for Concrete

ASTM C595/C595M (2018) Standard Specification for Blended

Hydraulic Cements

ASTM C618 (2019) Standard Specification for Coal

Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete

ASTM C803/C803M (2018) Standard Test Method for

Penetration Resistance of Hardened

ASTM C845/C845M (2018) Standard Specification for

Expansive Hydraulic Cement

ASTM C873/C873M (2015) Standard Test Method for

Compressive Strength of Concrete Cylinders Cast in Place in Cylindrical Molds

ASTM C900 (2015) Standard Test Method for Pullout

Strength of Hardened Concrete

ASTM C989/C989M (2018a) Standard Specification for Slag

Cement for Use in Concrete and Mortars

ASTM C1012/C1012M (2018b) Standard Test Method for Length

Change of Hydraulic-Cement Mortars Exposed to a Sulfate Solution

ASTM C1017/C1017M (2013; E 2015) Standard Specification for

Chemical Admixtures for Use in Producing Flowing Concrete

SECTION 03 30 00 Page 4

ASTM C1074 (2011) Standard Practice for Estimating Concrete Strength by the Maturity Method

ASTM C1077 (2017) Standard Practice for Agencies

Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation

ASTM C1107/C1107M (2017) Standard Specification for

Packaged Dry, Hydraulic-Cement Grout (Nonshrink)

ASTM C1157/C1157M (2017) Standard Performance Specification for Hydraulic Cement

ASTM C1218/C1218M (2017) Standard Test Method for Water-

Soluble Chloride in Mortar and Concrete

ASTM C1240 (2014) Standard Specification for Silica

Fume Used in Cementitious Mixtures

ASTM C1260 (2014) Standard Test Method for Potential

Alkali Reactivity of Aggregates (Mortar- Bar Method)

ASTM C1293 (2008; R 2015) Standard Test Method for

Determination of Length Change of Concrete Due to Alkali-Silica Reaction

ASTM C1567 (2013) Standard Test Method for Potential

Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)

ASTM C1602/C1602M (2018) Standard Specification for Mixing

Water Used in Production of Hydraulic Cement Concrete

ASTM C1778 (2016) Standard Guide for Reducing the

Risk of Deleterious Alkali-Aggregate Reaction in Concrete

ASTM D1751 (2004; E 2013; R 2013) Standard

Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)

ASTM D3042 (2017) Standard Test Method for Insoluble

Residue in Carbonate Aggregates

ASTM D5759 (2012) Characterization of Coal Fly Ash and Clean Coal Combustion Fly Ash for Potential Uses

ASTM D6690 (2015) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements

ASTM E329 (2018) Standard Specification for

Agencies Engaged in Construction

SECTION 03 30 00 Page 5

Inspection, Testing, or Special Inspection

CONCRETE REINFORCING STEEL INSTITUTE (CRSI)

CRSI 10MSP (2009; 28th Ed; Errata) Manual of

Standard Practice

CRSI RB4.1 (2016) Supports for Reinforcement Used in

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)

NIST PS 1 (2009) DOC Voluntary Product Standard PS

1-07, Structural Plywood

1.2 DEFINITIONS

a. "Cementitious material" as used herein must include all portland cement, pozzolan, fly ash, slag cement, and silica fume.

b. "Exposed to public view" means situated so that it can be seen from eye level from a public location after completion of the building.

A public location is accessible to persons not responsible for operation or maintenance of the building.

c. "Chemical admixtures" are materials in the form of powder or fluids that are added to the concrete to give it certain characteristics not obtainable with plain concrete mixes.

d. "Supplementary cementing materials" (SCM) include coal fly ash, [silica fume, ]slag cement, natural or calcined pozzolans, and ultra-fine coal ash when used in such proportions to replace the portland cement that result in improvement to sustainability and durability and reduced cost.

e. "Design strength" (f'c) is the specified compressive strength of concrete at time(s) specified in this section to meet structural design criteria.

f. "Mass Concrete" is any concrete system that approaches a maximum temperature of 158 degrees F within the first 72 hours of placement.

In addition, it includes all concrete elements with a section thickness of 3 feet or more regardless of temperature.

g. "Mixture proportioning" is the process of designing concrete mixture proportions to enable it to meet the strength, service life and constructability requirements of the project while minimizing the initial and life-cycle cost.

h. "Mixture proportions" are the masses or volumes of individual ingredients used to make a unit measure (cubic meter or cubic yard) of concrete.

i. "Pozzolan" is a siliceous or siliceous and aluminous material, which in itself possesses little or no cementitious value but will, in finely divided form and in the presence of moisture, chemically react with calcium hydroxide at ordinary temperatures to form compounds possessing cementitious properties.

SECTION 03 30 00 Page 6

j. "Workability (or consistence)" is the ability of a fresh (plastic) concrete mix to fill the form/mould properly with the desired work (vibration) and without reducing the concrete's quality.

Workability depends on water content, chemical admixtures, aggregate (shape and size distribution), cementitious content and age (level of hydration).

1.3 SUBMITTALS

Government approval is required for all submittal items. The following shall be submitted in accordance with paragraph 1.4 of Section 01010, SUMMARY OF WORK:

SD-02 Shop Drawings

Reinforcing Steel

SD-03 Product Data

Joint Filler Cementitious Materials Concrete Curing Materials Reinforcement Admixtures Biodegradable Form Release Agent

SD-05 Design Data

Concrete Mix Design

SD-06 Test Reports

Concrete Mix Design Fly Ash Pozzolan Aggregates Compressive Strength Tests Air Content Slump Tests Water

SD-07 Certificates

Welder Qualifications Safety Data Sheets

SD-08 Manufacturer's Instructions

Curing Compound

1.4 MODIFICATION OF REFERENCES

Accomplish work in accordance with ACI publications except as modified herein. Consider the advisory or recommended provisions to be mandatory.

Interpret reference to the "Building Official," the "Structural Engineer," and the "Architect/Engineer" to mean the Contracting Officer.

1.5 DELIVERY, STORAGE, AND HANDLING

Follow ACI 301, ACI 304R and ASTM A934/A934M requirements and recommendations. Do not deliver concrete until vapor retarder, forms, SECTION 03 30 00 Page 7 reinforcement, embedded items, and chamfer strips are in place and ready for concrete placement. Do not store concrete curing compounds with materials that have a high capacity to adsorb volatile organic compound (VOC) emissions. Do not store concrete curing compounds in occupied spaces.

1.5.1 Reinforcement

Store reinforcement of different sizes and shapes in separate piles or racks raised above the ground to avoid excessive rusting. Protect from contaminants such as grease, oil, and dirt. Ensure bar sizes can be accurately identified after bundles are broken and tags removed.

1.6 QUALITY ASSURANCE

1.6.1 Design Data

1.6.1.1 Formwork Calculations

ACI 347R. Include design calculations indicating arrangement of forms, sizes and grades of supports (lumber), panels, and related components.

Furnish drawings and calculations of shoring and re-shoring methods proposed for floor and roof slabs, spandrel beams, and other horizontal concrete members. Calculations must indicate concrete pressure with both live and dead loads, along with material types.

1.6.1.2 Concrete Mix…