02-MSD_Phasing_2024_06_25_v2.pdf

PDF 2 MB Posted

Attached to
171/26085. SAA; MI Schl for Deaf - New Dormitory
Solicitation number
RFP 171 260000002120 4
Issued by
Genesee County, Michigan

About this file

This document is a conceptual construction phasing plan for the Michigan School for the Deaf (MSD) Residence Hall project, prepared by the State of Michigan. The project involves the construction of a new residence hall and apartments on the existing MSD campus, with a phased approach designed to minimize disruption to campus operations. The project is scheduled to begin in July 2025 with the relocation of play areas and hazardous material abatement, followed by the razing of Gilbert Hall and relocation of utilities in December 2025. The main construction of the residence hall and apartments is planned from December 2025 through February 2027, with furniture installation and move-in occurring from March 2027 through July 2027. Additional work includes the razing of a portion of Stevens Hall from June 2027 through August 2027, followed by exterior repairs and site landscaping from August 2027 through September 2027.

The document provides a comprehensive visual and sequential overview of the site work, building massing, and construction timeline but does not contain specific information regarding pricing terms, contract awards, bid due dates, site visit requirements, or funding sources. The phasing strategy is designed to maintain the functionality of the Michigan School for the Deaf during the construction period while systematically addressing building demolition, new construction, and site improvements. The project encompasses demolition of existing structures, utility relocation, new residence and apartment construction, and site restoration activities across a multi-year timeline.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 5, 2023

State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall

SITE

BUILDING

tray Text Box Conceptual Construction Phasing Approach

MSD – Residence Hall | Existing Site Plan tray

Conceptual Building Massing and Site Location tray

Conceptual Building Massing and Site Location

MSD – Residence Hall | Project Phasing Strategy

Buildings to be affected

Conceptual Residence

Hall Overlay

MSD – Residence Hall | Project Schedule

July 2025

Relocate Play

Areas

Hazardous

Material

Abatement

December 2025

Raze Gilbert Hall

Relocate Utilities

Initial grading and sitework

December 2025 Thru

February 2027

Construct

Residence Hall and Apartments

March 2027 thru July 2027

Furniture and

Move-in

June 2027 thru

August 2027

Raze portion of

Stevens Hall

August 2027 thru

September 2027

Stevens Hall

Exterior Repairs

Site Landscaping and Plantings

MSD – Residence Hall | New Buildings tray

Conceptual Building Entry and Residence Wings

File details come from the government source that posted it. Updated .