02-MSD_Phasing_2024_06_25_v2.pdf

PDF 2 MB Posted

Attached to
171/26085. SAA; Michigan School for the Deaf- New Dormitory
Solicitation number
RFP 171 260000001490 3
Issued by
Genesee County, Michigan

About this file

This document is a conceptual construction phasing plan for the Michigan School for the Deaf (MSD) Residence Hall project in Michigan. The project encompasses the construction of a new residence hall and apartments on the existing MSD campus, with a phased approach to minimize disruption to ongoing operations. The project timeline spans from July 2025 through September 2027, beginning with the relocation of play areas and hazardous material abatement in July 2025, followed by the razing of Gilbert Hall and utility relocation in December 2025. The primary construction phase for the residence hall and apartments is scheduled from December 2025 through February 2027, with furniture installation and move-in occurring from March 2027 through July 2027. The final phases include the razing of a portion of Stevens Hall from June 2027 through August 2027, followed by exterior repairs to Stevens Hall and site landscaping from August 2027 through September 2027.

The document presents the site building and massing strategy, illustrating the conceptual placement of the new residence hall on the existing campus with detailed overlays showing building entries and residence wings. The phasing strategy is designed to address existing buildings affected by the project, including the demolition of Gilbert Hall and partial demolition of Stevens Hall, while maintaining campus operations throughout construction. No specific pricing, funding sources, contract award dates, or procurement response deadlines are identified in this planning document, which serves as a visual and scheduling reference for the proposed residential construction project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 5, 2023

State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall

SITE

BUILDING

tray Text Box Conceptual Construction Phasing Approach

MSD – Residence Hall | Existing Site Plan tray

Conceptual Building Massing and Site Location tray

Conceptual Building Massing and Site Location

MSD – Residence Hall | Project Phasing Strategy

Buildings to be affected

Conceptual Residence

Hall Overlay

MSD – Residence Hall | Project Schedule

July 2025

Relocate Play

Areas

Hazardous

Material

Abatement

December 2025

Raze Gilbert Hall

Relocate Utilities

Initial grading and sitework

December 2025 Thru

February 2027

Construct

Residence Hall and Apartments

March 2027 thru July 2027

Furniture and

Move-in

June 2027 thru

August 2027

Raze portion of

Stevens Hall

August 2027 thru

September 2027

Stevens Hall

Exterior Repairs

Site Landscaping and Plantings

MSD – Residence Hall | New Buildings tray

Conceptual Building Entry and Residence Wings