This document is a conceptual construction phasing plan for the Michigan School for the Deaf (MSD) Residence Hall project in Michigan. The project encompasses the construction of a new residence hall and apartments on the existing MSD campus, with a phased approach to minimize disruption to ongoing operations. The project timeline spans from July 2025 through September 2027, beginning with the relocation of play areas and hazardous material abatement in July 2025, followed by the razing of Gilbert Hall and utility relocation in December 2025. The primary construction phase for the residence hall and apartments is scheduled from December 2025 through February 2027, with furniture installation and move-in occurring from March 2027 through July 2027. The final phases include the razing of a portion of Stevens Hall from June 2027 through August 2027, followed by exterior repairs to Stevens Hall and site landscaping from August 2027 through September 2027.
The document presents the site building and massing strategy, illustrating the conceptual placement of the new residence hall on the existing campus with detailed overlays showing building entries and residence wings. The phasing strategy is designed to address existing buildings affected by the project, including the demolition of Gilbert Hall and partial demolition of Stevens Hall, while maintaining campus operations throughout construction. No specific pricing, funding sources, contract award dates, or procurement response deadlines are identified in this planning document, which serves as a visual and scheduling reference for the proposed residential construction project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 5, 2023
State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall
SITE
BUILDING
tray Text Box Conceptual Construction Phasing Approach
MSD – Residence Hall | Existing Site Plan tray
Conceptual Building Massing and Site Location tray
Conceptual Building Massing and Site Location
MSD – Residence Hall | Project Phasing Strategy
Buildings to be affected
Conceptual Residence
Hall Overlay
MSD – Residence Hall | Project Schedule
July 2025
Relocate Play
Areas
Hazardous
Material
Abatement
December 2025
Raze Gilbert Hall
Relocate Utilities
Initial grading and sitework
December 2025 Thru
February 2027
Construct
Residence Hall and Apartments
March 2027 thru July 2027
Furniture and
Move-in
June 2027 thru
August 2027
Raze portion of
Stevens Hall
August 2027 thru
September 2027
Stevens Hall
Exterior Repairs
Site Landscaping and Plantings
MSD – Residence Hall | New Buildings tray
Conceptual Building Entry and Residence Wings