02-MSD_Phasing_2024_06_25_v2.pdf
PDF 2 MB Posted
- Solicitation number
- RFI 171 260000000011 2
- Issued by
- Genesee County, Michigan
About this file
This is a project phasing and conceptual construction document for the Michigan School for the Deaf (MSD) Residence Hall project in Michigan. The document outlines a comprehensive multi-phase construction approach for a new residence hall and apartments facility, with associated site improvements and demolition activities. The project involves relocation of play areas, hazardous material abatement, demolition of Gilbert Hall, utility relocation, initial grading and sitework, construction of the residence hall and apartments, furniture installation and move-in, partial demolition of Stevens Hall, exterior repairs to Stevens Hall, and site landscaping. The project schedule spans from July 2025 through September 2027, with major construction activities scheduled from December 2025 through February 2027, followed by furniture and move-in from March 2027 through July 2027.
The document does not contain information regarding pricing terms, budget allocations, funding sources, set-asides, incumbent contractors, response deadlines, bid submission dates, or contract award details. The material presented is conceptual in nature, depicting site plans, building massing, phasing strategy diagrams, and a project schedule. No specific contract terms, renewal options, or financial requirements are identified in this document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 5, 2023
State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall
SITE
BUILDING
tray Text Box Conceptual Construction Phasing Approach
MSD – Residence Hall | Existing Site Plan tray
Conceptual Building Massing and Site Location tray
Conceptual Building Massing and Site Location
MSD – Residence Hall | Project Phasing Strategy
Buildings to be affected
Conceptual Residence
Hall Overlay
MSD – Residence Hall | Project Schedule
July 2025
Relocate Play
Areas
Hazardous
Material
Abatement
December 2025
Raze Gilbert Hall
Relocate Utilities
Initial grading and sitework
December 2025 Thru
February 2027
Construct
Residence Hall and Apartments
March 2027 thru July 2027
Furniture and
Move-in
June 2027 thru
August 2027
Raze portion of
Stevens Hall
August 2027 thru
September 2027
Stevens Hall
Exterior Repairs
Site Landscaping and Plantings
MSD – Residence Hall | New Buildings tray
Conceptual Building Entry and Residence Wings
File details come from the government source that posted it. Updated .