This is a conceptual construction phasing document for the State of Michigan's Michigan School for the Deaf (MSD) Residence Hall project. The document outlines a multi-phase construction strategy for developing a new residence hall and apartments on the MSD campus. The project encompasses hazardous material abatement, demolition of existing structures (Gilbert Hall and a portion of Stevens Hall), utility relocation, new construction, and site improvements including landscaping. The phasing schedule begins in July 2025 with relocation of play areas and hazardous material abatement, progresses through December 2025 with the razing of Gilbert Hall and initial sitework, and continues with residence hall and apartment construction from December 2025 through February 2027. Furniture installation and occupancy are scheduled for March 2027 through July 2027, with final demolition and exterior repairs to Stevens Hall occurring from June 2027 through September 2027.
The document provides a conceptual framework for the project's sequencing and site logistics, including building massing overlays, existing site plans, and conceptual renderings of the new residence hall entries and wings. No specific pricing, budget allocation, or contract award information is included in this phasing document. This appears to be a planning and design phase document intended to communicate the overall construction sequence and timeline to stakeholders and potential bidders for the dormitory construction project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 5, 2023
State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall
SITE
BUILDING
tray Text Box Conceptual Construction Phasing Approach
MSD – Residence Hall | Existing Site Plan tray
Conceptual Building Massing and Site Location tray
Conceptual Building Massing and Site Location
MSD – Residence Hall | Project Phasing Strategy
Buildings to be affected
Conceptual Residence
Hall Overlay
MSD – Residence Hall | Project Schedule
July 2025
Relocate Play
Areas
Hazardous
Material
Abatement
December 2025
Raze Gilbert Hall
Relocate Utilities
Initial grading and sitework
December 2025 Thru
February 2027
Construct
Residence Hall and Apartments
March 2027 thru July 2027
Furniture and
Move-in
June 2027 thru
August 2027
Raze portion of
Stevens Hall
August 2027 thru
September 2027
Stevens Hall
Exterior Repairs
Site Landscaping and Plantings