This is a conceptual construction phasing document for the Michigan School for the Deaf (MSD) Residence Hall project, prepared by the State of Michigan. The project involves the design and construction of new residential facilities at the MSD campus, including a new residence hall and apartments. The phased approach begins in July 2025 with the relocation of play areas and hazardous material abatement, followed by the razing of Gilbert Hall and relocation of utilities in December 2025. The primary construction phase for the residence hall and apartments runs from December 2025 through February 2027, with furniture installation and move-in scheduled for March 2027 through July 2027. A portion of Stevens Hall will be razed between June 2027 and August 2027, with exterior repairs to Stevens Hall and site landscaping occurring from August 2027 through September 2027. The document provides conceptual building massing, site location plans, and visual representations of the new residence wings and building entry design.

The document does not contain specific pricing information, contract terms, response deadlines, bid submission details, or funding amounts. This appears to be a preliminary planning and scheduling document rather than a bid solicitation or formal contract opportunity notice. No information is provided regarding set-asides, incumbent contractors, incumbent service providers, or specific funding sources for the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 5, 2023

State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall

SITE

BUILDING

tray Text Box Conceptual Construction Phasing Approach

MSD – Residence Hall | Existing Site Plan tray

Conceptual Building Massing and Site Location tray

Conceptual Building Massing and Site Location

MSD – Residence Hall | Project Phasing Strategy

Buildings to be affected

Conceptual Residence

Hall Overlay

MSD – Residence Hall | Project Schedule

July 2025

Relocate Play

Areas

Hazardous

Material

Abatement

December 2025

Raze Gilbert Hall

Relocate Utilities

Initial grading and sitework

December 2025 Thru

February 2027

Construct

Residence Hall and Apartments

March 2027 thru July 2027

Furniture and

Move-in

June 2027 thru

August 2027

Raze portion of

Stevens Hall

August 2027 thru

September 2027

Stevens Hall

Exterior Repairs

Site Landscaping and Plantings