02-MSD_Phasing_2024_06_25_v2.pdf
PDF 2 MB Posted
- Solicitation number
- RFI 171 260000000011 1
- Issued by
- Michigan
About this file
This is a conceptual construction phasing document for the Michigan School for the Deaf (MSD) Residence Hall project, prepared by the State of Michigan. The project involves the design and construction of new residential facilities at the MSD campus, including a new residence hall and apartments. The phased approach begins in July 2025 with the relocation of play areas and hazardous material abatement, followed by the razing of Gilbert Hall and relocation of utilities in December 2025. The primary construction phase for the residence hall and apartments runs from December 2025 through February 2027, with furniture installation and move-in scheduled for March 2027 through July 2027. A portion of Stevens Hall will be razed between June 2027 and August 2027, with exterior repairs to Stevens Hall and site landscaping occurring from August 2027 through September 2027. The document provides conceptual building massing, site location plans, and visual representations of the new residence wings and building entry design.
The document does not contain specific pricing information, contract terms, response deadlines, bid submission details, or funding amounts. This appears to be a preliminary planning and scheduling document rather than a bid solicitation or formal contract opportunity notice. No information is provided regarding set-asides, incumbent contractors, incumbent service providers, or specific funding sources for the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 5, 2023
State of Michigan | Michigan School for the Deaf (MSD) – Residence Hall
SITE
BUILDING
tray Text Box Conceptual Construction Phasing Approach
MSD – Residence Hall | Existing Site Plan tray
Conceptual Building Massing and Site Location tray
Conceptual Building Massing and Site Location
MSD – Residence Hall | Project Phasing Strategy
Buildings to be affected
Conceptual Residence
Hall Overlay
MSD – Residence Hall | Project Schedule
July 2025
Relocate Play
Areas
Hazardous
Material
Abatement
December 2025
Raze Gilbert Hall
Relocate Utilities
Initial grading and sitework
December 2025 Thru
February 2027
Construct
Residence Hall and Apartments
March 2027 thru July 2027
Furniture and
Move-in
June 2027 thru
August 2027
Raze portion of
Stevens Hall
August 2027 thru
September 2027
Stevens Hall
Exterior Repairs
Site Landscaping and Plantings
MSD – Residence Hall | New Buildings tray
Conceptual Building Entry and Residence Wings