This document is the Instructions to Bidders for the City of Gunnison, Colorado's Cape, Crack & Slurry Seal Project (Project ID 25-07), prepared using the EJCDC® C-200 standard construction contract template. The project involves road maintenance work including crack seal, slurry seal, cape seal, and asphalt patching, with electronic bids to be submitted through the Rocky Mountain E-Purchasing System (RMEPS) by Tuesday, May 20, 2025, at 2:00 pm Mountain Time. Bidders must obtain complete bidding documents from the website https://www.bidnetdirect.com/colorado, and all questions must be submitted to the City Clerk by Tuesday, May 13, 2025, at 5:00 pm Mountain Time. No pre-bid conference will be conducted, and bidders are responsible for examining the project site and documentation.

The contract will be awarded on a unit price basis, with bidders required to submit prices for each work item listed in the Bid Form. A Bid Bond is required, ranging from 5% to 10% of the estimated project cost depending on the total project value. The City of Gunnison is exempt from Colorado state sales and use taxes on materials and equipment to be incorporated into the work (Exemption No. 09806327). The Owner reserves the right to reject any or all bids and will award the contract to the responsible bidder submitting the lowest responsive bid. Successful bidders must execute the contract within 15 days of the Notice of Award and will receive fully executed contract documents within 10 days thereafter.

View the file

Other files for this state and local contract opportunity

Other files attached to Cape, Crack & Slurry Seal Project, newest first.
File Type Posted
05 25-07 Exhibit B Slurry Cape Seal Project Manual Final.pdf PDF
06 25-07 Exhibit C 2025 Street Improvement Project Map.pdf PDF
04 25-07 Exhibit A Scope of Work.pdf PDF
07 25-07 Sample Agreement.pdf PDF
01 25-07 Advertisement.pdf PDF
03 25-07 Bid Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (5/24/2023).

CITY OF GUNNISON, COLORADO

CAPE, CRACK & SLURRY SEAL PROJECT

(PROJECT ID. 25-07)

INSTRUCTIONS TO BIDDERS

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated below:

A. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents.

B. Agreement – The written instrument, executed by Owner and Contractor, that sets forth the Contract Price and Contract Times, identifies the parties and the Engineer (if applicable), and designates the specific items that are Contract Documents.

C. Bid—The offer of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed.

D. Bidder—An individual or entity that submits a Bid to Owner.

E. Bidding Documents—The Bidding Requirements, the proposed Contract Documents, and all Addenda.

F. Bidding Documents Website—Rocky Mountain E-Purchasing System (“RMEPS”) website where electronic Bidding Documents are available, plan holders are registered on behalf of the Issuing Office, and contains questions posed by prospective Bidders and the Owner’s responses to those questions. https://www.bidnetdirect.com/colorado.

G. Bidding Requirements—The Advertisement or invitation to bid, Instructions to Bidders, Bid Bond or other Bid security, if any, the Bid Form, and the Bid with any attachments.

H. Contract—The entire and integrated written contract between Owner and Contractor concerning the Work.

I. Contractor – The individual or entity with which Owner has contracted for performance of the Work.

J. Domestic Preference - The Build America, Buy America Act (BABAA) requirements under Title IX of the Infrastructure Investment and Jobs Act (IIJA), Pub. L. 117-58, §§ 70901-70953.

K. Owner—The individual or entity with which Contractor has contracted regarding the Work, and which has agreed to pay Contractor for the performance of the Work, pursuant to the terms of the Contract.

L. Project—The total undertaking to be accomplished for Owner by engineers, contractors, and others, including planning, study, design, construction, testing, commissioning, and start-up, and of which the Work to be performed under the Contract Documents is a part.

M. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work.

https://www.bidnetdirect.com/colorado

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (5/24/2023).

N. Successful Bidder—The Bidder to which the Owner makes an award of contract.

O. Work—The entire project or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction;

furnishing, installing, and incorporating all materials and equipment into such construction;

and may include related services such as testing, start-up, and commissioning, all as required by the Contract Documents.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents) from the Bidding Documents Website, https://www.bidnetdirect.com/colorado. See the Agreement for a List of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Bidding Documents Website and obtain a complete set of the Bidding Documents from such website.

Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner through the Bidding Documents Website.

2.04 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader. It is the intent of the Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner cannot and does not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (5/24/2023).

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.05.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

A. Bidder shall be authorized to do business in the state of Colorado or shall obtain such authority prior to the Effective Date of the Contract.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A pre-bid conference will not be conducted for this Project.

ARTICLE 5—EXAMINATION OF SITE; OWNER’S SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site Visit and Testing by Bidders

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Owner’s Safety Program – not used.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Contract

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (5/24/2023).

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents in writing via email. Contact information and submittal procedures for such questions are as follows:

A. Email all questions ONLY to the City Clerk at cityclerk@gunnisonco.gov. Questions must be submitted by Tuesday, May 13, 2025, at 5:00:00 pm Mountain Time.

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda will be reported on https://www.bidnetdirect.com/colorado. It shall be each Bidder’s responsibility to make inquiry as to Addenda that have been issued. All Addenda shall become part of this RFP, and all Bidders shall be bound by such Addenda, whether or not received by the Bidder.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—SUBSTITUTE AND “OR EQUAL” ITEMS

8.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders.

Bidders cannot rely upon approvals made in any other manner.

8.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as mailto:cityclerk@gunnisonco.gov

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (5/24/2023).

supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 9—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

9.01 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for all portions of the Work within five days after Bid opening.

ARTICLE 10—PREPARATION OF BID

10.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

10.02 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

10.03 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign.

The official address of the partnership must be shown.

10.04 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

10.05 A Bid by an individual must show the Bidder’s name and official address.

10.06 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

10.07 All names must be printed in ink below the signatures.

10.08 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

10.09 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

10.10 The Bid must contain evidence of Bidder’s authority to do business in the state of Colorado or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (5/24/2023).

ARTICLE 11—BASIS OF BID

11.01 Unit Price

A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form, C-410.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

ARTICLE 12—SUBMITTAL OF BID

Bids for the construction of the Project will be received electronically at the Rocky Mountain E-Purchasing System (“RMEPS”): portal at https://www.bidnetdirect.com/colorado. Submittals must be received in the RMEPS submission portal on or before Tuesday, May 20, 2025, at 2:00:00 pm Mountain Time. Hardcopy submittals will not be accepted. It is the Respondent’s sole responsibility to ensure all required documents

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (5/24/2023).

are submitted through RMEPS by the submission deadline. RMEPS does not allow for uploading of documents after the submittal due date and time has closed.

12.01 Bids (as hereinafter defined) received after the above specified due date and time, or which are not prepared and filed in accordance with the terms and conditions of this Request for Bids (“RFB”), may not be considered for evaluation.

ARTICLE 13—MODIFICATION AND WITHDRAWAL OF BID

13.01 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified herein and submit a new Bid prior to the date and time for the opening of Bids.

ARTICLE 14—OPENING OF BIDS

14.01 Bids will be opened electronically via Bidding Documents Website at the time and place indicated in the advertisement or invitation to bid.

ARTICLE 15—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

15.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 16—EVALUATION OF BIDS AND AWARD OF CONTRACT

16.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

16.02 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner then Owner will reject the Bid as nonresponsive.

16.03 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

16.04 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

16.05 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (5/24/2023).

proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

16.06 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 17—BONDS AND INSURANCE

Bid Bond at an amount equal to 5% of the estimated project cost when project cost is between $100,000

- $500,000; at an amount equal to 10% of the estimated project cost when project cost is greater than $500,000. Reference the Contract for performance bond and payment bond requirements.

ARTICLE 18—SIGNING OF AGREEMENT

18.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Contract and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Contract to Successful Bidder, together with printed and electronic copies of the Contract Documents.

ARTICLE 19—SALES AND USE TAXES

19.01 Owner is exempt from State of Colorado state sales and use taxes on materials and equipment to be incorporated in the Work. (Exemption No. 09806327). Said taxes must not be included in the Bid.

Article 1— DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated below:
A. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents.
B. Agreement – The written instrument, executed by Owner and Contractor, that sets forth the Contract Price and Contract Times, identifies the parties and the Engineer (if applicable), and designates the specific items that are Contract Documents.
C. Bid—The offer of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed.
D. Bidder—An individual or entity that submits a Bid to Owner.
E. Bidding Documents—The Bidding Requirements, the proposed Contract Documents, and all Addenda.
F. Bidding Documents Website—Rocky Mountain E-Purchasing System (“RMEPS”) website where electronic Bidding Documents are available, plan holders are registered on behalf of the Issuing Office, and contains questions posed by prospective Bidders and th...
G. Bidding Requirements—The Advertisement or invitation to bid, Instructions to Bidders, Bid Bond or other Bid security, if any, the Bid Form, and the Bid with any attachments.
H. Contract—The entire and integrated written contract between Owner and Contractor concerning the Work.
I. Contractor – The individual or entity with which Owner has contracted for performance of the Work.
J. Domestic Preference - The Build America, Buy America Act (BABAA) requirements under Title IX of the Infrastructure Investment and Jobs Act (IIJA), Pub. L. 117-58, §§ 70901-70953.
K. Owner—The individual or entity with which Contractor has contracted regarding the Work, and which has agreed to pay Contractor for the performance of the Work, pursuant to the terms of the Contract.
L. Project—The total undertaking to be accomplished for Owner by engineers, contractors, and others, including planning, study, design, construction, testing, commissioning, and start-up, and of which the Work to be performed under the Contract Docume...
M. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work.
N. Successful Bidder—The Bidder to which the Owner makes an award of contract.
O. Work—The entire project or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produc...
Article 2— Bidding Documents
2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents) from the Bidding Documents Website, https://www.bidnetdirect.com/colorado. See the Agreement for a List of the Contract D...
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any o...
2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Bidding Documents Website and obtain a complete set of the Bidding Documents...
2.04 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.
1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader. It is the intent of the Owner that such Electronic Documents are to be exactly representative of the paper copies of the doc...

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.05.A above. However, Bidder assumes all risks associated with differences ar...

Article 3— Qualifications of Bidders
A. Bidder
A. shall be authorized to do business in the state of Colorado or shall obtain such authority prior to the Effective Date of the Contract.
Article 1—
Article 4— PRE-BID CONFERENCE
4.01 A pre-bid conference will not be conducted for this Project.
Article 5— Examination of Site; Owner’s Safety Program; Other Work at the Site
5.01 Site Visit and Testing by Bidders
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, const...

5.02 Owner’s Safety Program – not used.

Article 1—
Article 6— Bidder’s Representations and Certifications
6.01 Express Representations and Certifications in Bid Form, Contract
A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection wi...
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
Article 7— Interpretations and Addenda
7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.
7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents in writing via email. Contact information and submittal procedures for such questions are as follows:
A. Email all questions ONLY to the City Clerk at cityclerk@gunnisonco.gov. Questions must be submitted by Tuesday, May 13, 2025, at 5:00:00 pm Mountain Time.
7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda will be reported on https://www.bidnetdirect.com/colorado. It shall be each Bidder’s responsibility to make inquiry as to A...
7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly m...
Article 8— Substitute and “Or Equal” Items
8.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the s...
8.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding th...
Article 9— Subcontractors, Suppliers, and Others
9.01 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for all portions of the Work within five days after Bid opening.
Article 10— Preparation of Bid
10.01 The Bid Form is included with the Bidding Documents.
A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment...
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”
10.02 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
10.03 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.
10.04 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must b...
10.05 A Bid by an individual must show the Bidder’s name and official address.
10.06 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address...
10.07 All names must be printed in ink below the signatures.
10.08 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
10.09 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.
10.10 The Bid must contain evidence of Bidder’s authority to do business in the state of Colorado or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
Article 11— BASIS OF BID
11.01 Unit Price
A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form, C-410.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Uni...
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the co...
Article 12— Submittal of Bid
Bids for the construction of the Project will be received electronically at the Rocky Mountain E-Purchasing System (“RMEPS”): portal at https://www.bidnetdirect.com/colorado. Submittals must be received in the RMEPS submission portal on or before Tues...
12.01 Bids (as hereinafter defined) received after the above specified due date and time, or which are not prepared and filed in accordance with the terms and conditions of this Request for Bids (“RFB”), may not be considered for evaluation.
Article 13— Modification and Withdrawal of Bid
13.01 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified herein and submit a new Bid prior to the date and time for the opening of Bids.
Article 14— Opening of Bids
14.01 Bids will be opened electronically via Bidding Documents Website at the time and place indicated in the advertisement or invitation to bid.
Article 15— Bids to Remain Subject to Acceptance
15.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
Article 16— Evaluation of Bids and Award of Contract
16.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or cha...
Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.
16.02 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate ...
16.03 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.
16.04 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.
16.05 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity...
16.06 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
Article 17— Bonds and Insurance
Bid Bond at an amount equal to 5% of the estimated project cost when project cost is between $100,000 - $500,000; at an amount equal to 10% of the estimated project cost when project cost is greater than $500,000. Reference the Contract for performan...
Article 18— Signing of AGREEMENT
18.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bi...
Article 19— Sales and Use Taxes
19.01 Owner is exempt from State of Colorado state sales and use taxes on materials and equipment to be incorporated in the Work. (Exemption No. 09806327). Said taxes must not be included in the Bid.