5-Contract Sections G No. REC-36.pdf

PDF 685 KB Posted

Attached to
HAVERFORD COMMUNITY RECREATION AND ENVIRONMENTAL CENTER DECK REPLACEMENT
Solicitation number
US.216089
Issued by
Delaware County, Harveys Lake Borough, Pennsylvania

View the file

Other files

File Type Posted
6-Addendum No 1 2026-01-09.pdf PDF
4-Prevailing Wage.pdf PDF
1-REC-36 Contract Drawings.pdf PDF
3-Contract Sections K-M No. REC-36.pdf PDF
2-Contract No. REC-36.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HAVTT 305022

01001-1 SPECIAL PROVISIONS

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01001 - Special Provisions.doc

SECTION 01001

SPECIAL PROVISIONS

PART 1 GENERAL

1.1 WORK INCLUDES

A. The project involves the removal and replacement of the existing 1,620-square-foot elevated exterior deck on the north side of the building at the Township’s

Community Environmental and Recreation Center (CREC).

1.2 CONTRACTORS LICENSE

A. The Contractor, and any subcontractors performing work on this project must have a current valid Contractor’s License from the Township of Haverford. In addition, the Contractor must apply for a building permit with the Township

Codes Department. Questions regarding this process should be directed to the

Township Codes Department.

1.3 PROXIMITY OF USERS TO WORK AREA

A. The Township’s Community Recreation and Environmental Center (CREC) is within the Haverford Reserve recreational complex. The Contractor must be fully aware that residents and user groups use the various amenities of the building and within the adjacent park, including the fields and trails adjacent to the building.

Throughout the duration of the work, the Contractor must be fully aware of the activities within and adjacent to the building, and throughout the fields to ensure that their work does not in any manner jeopardize the safety of anyone using these facilities.

B. The Contractor must ensure that all staging areas, equipment and deliveries do not interfere with any activities within or adjacent to the building, or in any manner create a safety hazard to the users or staff of the facility or park. The contractor shall not use the existing parking lot for parking or staging. All parking and staging areas shall be located on the west side of the building across from the cell tower compound. Parking and staging shall not block access to the adjacent cell tower compound.

G-1

SPECIAL PROVISIONS 01001-2

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01001 - Special Provisions.doc

1.4 ACCESS TO WORK AREA

A. Access to the work area may only be via the existing drive/path on the west side of the building adjacent to the cell tower compound. This access must be used for daily access, removal of all demolition debris and delivery of all materials required to reconstruct the structure. No other access will be permitted unless approved by the Township in writing.

B. No trees/brush or other vegetation may not be removed or trimmed unless written permission is granted by the Township. The contractor shall also be responsible for ensuring that the access route is maintained and free from equipment, materials, ruts, mud and other obstacles that would prevent emergency egress from the building in the case of an emergency.

C. All disturbance created along the access route is the responsibility of the

Contractor. These areas must be restored to their original condition and to the satisfaction of the Township.

D. The Contractor shall take the above into consideration when preparing his bid, and it shall be assumed that he has prepared his bid and entered into contract in full contemplation of these stipulations.

1.5 EMERGENCY ACCESS ROUTE

A. Throughout the entire project, the Contractor must maintain the designated access route as an emergency access route in case of emergency. The route must be maintained no smaller than 6 feet wide from the lower-level doors below the deck, west along the existing path to the driveway adjacent to the cell tower. This entire route must be free and clear at all times, including nights and weekends, from equipment, materials and debris, and must be kept in a mud-free walkable condition.

1.6 PROTECTION OF ACCESS TO DECK DURING CONSTRUCTION

A. The deck is accessed via doors from the second-floor meeting room. The Township will lock these doors and provide signage on the interior side of the doors. The contractor is not permitted to use these doors unless written permission is granted by the Township. Only Township staff will be permitted to unlock the doors for the

Contractor.

B. Should the Contractor need to utilize these doors to accommodate work, the following procedure must be followed:

G-2

01001-3 SPECIAL PROVISIONS

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01001 - Special Provisions.doc

a. The contractor must inform the building manager and the Director of

Recreation when they will need to utilize these doors and the approximate duration needed to perform the work a minimum of three (3) working days in advance. The notification must be via email to both personnel.

b. During the period access is required, the building manager will open only those doors needed for access.

c. The contractor will be responsible for ensuring that barricades are provided on the interior within 5-feet of every door that is unlocked. The barricades must be rigid, stable, and constructed of durable materials suitable for interior use, fully restricting pedestrian access to the deck area under repair. Barricades shall be a minimum of 42 inches in height, highly visible, and securely anchored or self-supporting to prevent displacement or tipping. Barricades shall not obstruct required means of egress and shall comply with applicable

OSHA requirements and all local building and fire codes. Clear signage indicating ‘Area Closed’ shall be provided. Barricades shall be maintained in place and in good condition for the duration of the work and removed only upon completion of repairs and approval by the Owner or Engineer.

d. Once all work is completed that requires access from the existing doors, the

Contractor must notify the building manager and Director of Recreation via email. The contractor shall not leave the building until the building manager and/or staff lock each door.

C. The contractor shall be fully aware of all existing components adjacent to the deck and shall take all necessary precautions during this contract to avoid damage to any component

1.7 PROTECTION OF EXISTING COMPONENTS DURING CONSTRUCTION

A. The contractor shall be responsible for protection of all existing features associated with the deck to remain, and all adjacent features to the deck including but not limited to the building façade, existing posts/foundations; paved patio/walkways;

landscaping, etc. Any damage associated with the construction work shall be repaired by the Contractor as part of the project. No additional payment will be made for repair/replacement of components damaged during construction.

B. The Contractor shall be fully aware of the above stipulations and shall take them into consideration when preparing his bid. It shall be assumed he has prepared his bid and entered into contract in full contemplation of these stipulations.

G-3

SPECIAL PROVISIONS 01001-4

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01001 - Special Provisions.doc

1.8 DEMOLITION PROCESS

A. The demolition of the deck must be fully completed prior to the reconstruction of any portion of the deck unless written permission is provided by the Township.

B. The existing conditions warrant an enhanced level of care be taken during the demolition of the deck. It shall be the Contractor’s responsibility to employ all necessary measures/precautions to protect the existing conditions, including the glass facades. Should any damage occur to any aspect of the building, the

Contractor shall notify the Township immediately and make all necessary repairs as soon as a Township official reviews/documents the damage. Should the damage be beyond immediate repair, the Contractor shall temporarily secure the area and take all necessary steps to ensure the damaged area is fully secured and watertight.

C. Should any damage occur to any aspect of the building, including the glass facades that would jeopardize the safety, security or watertightness of the building, the

Contractor will be required to repair/replace the damaged area(s) to the satisfaction of the Township immediately.

D. Throughout the demolition process, the Contractor shall remove and place into the dumpster all debris on a daily basis. No debris shall be left on the ground surface overnight, and at no time shall any debris, equipment or material block the emergency access route from the lower level of the building as indicated above.

E. Some of the existing components to be replaced may be warrant salvaging. Any components to be salvaged shall be free from rot, mold, insects and other deterioration for the entire length of the member. Should components be salvageable, the Contractor shall remove all fasteners from the entire length of the member and neatly stack the member in an area designated by the Township. Notify the Township so they can review and determine if the material will be salvaged.

1.9 EXISTING COMPONENTS TO BE SALVAGED

A. The following components are to be removed, salvaged and protected for re-installation upon reconstruction of the deck structure:

a. Wood posts and existing metal connectors/bolts.

b. Railings, including posts, spindles and support system.

c. All existing composite deck boards.

The intent is to maintain and/or reuse these components to reconstruct the deck as close as possible to the existing dimensions.

B. Prior to any demolition, the Contractor shall video document all existing components to be reused, including the method of support. The video shall be provided to the

Township prior to commencement of any demolition.

G-4

01001-5 SPECIAL PROVISIONS

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01001 - Special Provisions.doc

C. During the demolition process, the Contractor shall carefully remove these components so as to avoid damage and store them in a location where they will be out of the way of the work, and not susceptible to damage or theft. Removal shall include all components including all associated supports and fasteners.

D. For the railing components, prior to removal, the Contractor shall document the existing locations of all the railings and the order in which the spindles are currently installed so they may be re-installed at the same location and configuration.

E. The existing supporting posts shall remain in place at their current locations unless removal is required to accommodate the work and/or avoid damage. Should the posts be removed, it is the Contractor’s responsibility to document the location and ensure the existing connecting components remain with the post. Any posts that do remain in place shall be properly protected from damage or theft. Should damage or theft occur, the Contractor is responsible to repair or replace the post to the

Township’s satisfaction. If the post cannot be repaired to the Township’s satisfaction, it is the Contractor’s responsibility to provide an identical replacement post.

F. It shall be the Contractor’s responsibility to ensure that the proper level of care is taken to remove all existing components without damaging them. Should any of the components be damaged during the removal process, the Township shall be notified immediately, and the damaged component shall be marked. The component shall not be discarded unless otherwise directed by the Township.

1.10 QUALIFICATIONS

A. Each prospective bidder must demonstrate that they have in the past completed projects of similar scope and magnitude.

B. BIDDERS MAY NOT BE CONSIDERED UNLESS THEY

DEMONSTRATE THAT THEY HAVE SATISFACTORILY COMPLETED

A MINIMUM OF TWO (2) SIMILAR PROJECTS IN EXCESS OF

$100,000 DOLLARS EACH.

C. Each prospective bidder shall be required to submit with their sealed proposal a detailed list of work outlining the projects they have completed within the last five (5) years. This list as a minimum shall include the following:

1. Location of Project.

2. Owner’s Name and Address.

3. Total Contract Amount (including change orders).

4. Dates work was performed.

5. Detailed narrative of work performed.

G-5

SPECIAL PROVISIONS 01001-6

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01001 - Special Provisions.doc

6. Name, address and telephone number of contact person for the awarding agency.

D. Any proposal not accompanied by the above qualifications statement may be deemed non-responsive and may not be considered by the Owner.

E. The Owner has the right to reject any bidders who do not demonstrate the minimum qualifications described above.

F. All contractors shall be fully aware that the Township has “Responsible

Contractor Biding Requirements for projects valued at $250,000 or more.

These requirements are outlined in Chapter 4, Part 10 Fiscal Affairs, Article

XXXI, Procedures, Rules and Regulations, Subsection §4-1008E.(4)

“Responsible Contractor Bidding Requirements”, of the Township Of

Haverford Code. The code can be accessed via the Township’s website @ https://ecode360.com/14964254 In addition, the Ordinance is provided in

Section N.

If the base bid, or base bid plus alternate(s) for this project is $250,000 or greater, your firm must meet the requirements as outlined in the above-referenced section.

1.11 TREE REMOVAL/TRIMMING

A. No trees shall be removed under this contract unless written permission is granted by the Township. Tree branches may be trimmed to avoid damage from equipment. The

Township will determine those branches that can be trimmed, and the extent thereof.

1.12 COMMENCEMENT/COMPLETION OF WORK

A. The intent of this contract is to commence work as soon as the contract has been fully executed and shop drawings submitted/reviewed, with an anticipated

Notice to Proceed to be issued no later than March 2, 2026.

B. The new deck must be fully completed and ready for occupancy no later than

May 2nd, 2026.

C. It shall be assumed each contractor has prepared his bid and entered into contract in full contemplation of the above stipulations.

1.13 ADA ACCESSIBILITY

A. The existing deck accommodates ADA access from the interior of the building.

The new deck must maintain that accessibility.

G-6

01001-7 SPECIAL PROVISIONS

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01001 - Special Provisions.doc

1.14 NUISANCE ORDINANCE

A. Haverford Township allows work between the hours of 8:00 a.m. and 6:00 p.m., Monday through Saturday. No work whatsoever, operation of machinery, or material deliveries may be performed before or after these hours or on a Sunday, unless written permission is provided by the Township.

B. Should the Contractor wish to work on a Saturday, they must request to do so a minimum of 72-hours’ in advance. The request should be made to both the

Director of Recreation and Building Manager. The Township will endeavor to accommodate all requests, but the Contractor shall be aware that there may be scheduled activities at the facility on various weekends that will prohibit such work.

1.15 MAINTENANCE OF SURROUNDING PROPERTY

A. The Contractor shall be required to maintain the existing drives, parking lots, walks and access routes adjacent to the deck and building and within the park area for the duration of the Contract. All areas shall be level and free from any holes, divots, depressions, or other encumbrances that will preclude the normal use of these areas vehicular or pedestrian traffic or in any manner create a safety hazard for the public or users of the park facility.

B. Should the Contractor fail to maintain any area in a reasonable manner, or respond to Township requests for maintenance, the Township may retain the services of qualified professionals to remedy the situation to the extent deemed necessary. All monies for such services will then be deducted from payment to the

Contractor.

1.16 EXISTING UTILITIES

A. The Contractor shall be aware of the existing utilities that have been installed under and through various components of the deck. These utilities consist of a fire suppression system and various lighting and associated electric. These components will be de-energized by the Township. It is the responsibility of the

Contractor to remove them from the structure.

B. For the existing fire suppression system, the Contractor shall salvage the existing piping and connectors and return all components to the Township. For the electrical system, all existing components shall be removed and disposed of unless otherwise indicated by the Township.

C. The Contractor shall be fully aware of the above stipulations and shall take them into consideration when preparing his bid. It shall be assumed he has prepared his bid and entered into contract in full contemplation of these stipulations.

G-7

SPECIAL PROVISIONS 01001-8

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01001 - Special Provisions.doc

1.17 FAILURE TO PERFORM WORK IN ACCORDANCE WITH SPECIFICATIONS

A. If during the duration of this contract, the Contractor fails or refuses to perform work in accordance with the specifications and/or the direction of the Owner or

Engineer, the Owner, may at his discretion, order the Contractor to correct the deficient work and may hold the dollar value of such deficient work from any monies due or become due to the Contractor until the work is corrected to his satisfaction. If such an instance occurs, the Contractor shall have no claim for extra time and/or money as a result of any circumstances related to the deficient work included but not limited to any delays of future work, delivery of materials or interest earned on the monies withheld.

B. The Contractor shall take the above into consideration when preparing his bid, and it shall be assumed that he has prepared his bid and entered into contract in full contemplation of these stipulations.

END OF SECTION

G-8

Job No. HAVTT 221042

01010-1 CONTRACTORS WORK

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01010 - Contractors Work.doc

SECTION 01010

CONTRACTORS WORK

1.1 RESPONSIBILITY OF CONTRACTOR

A. Contractor shall furnish all materials, implements, machinery, equipment, tools, supplies, transportation, labor and supervision required to construct the facilities as shown on contract drawings and specified herein. It shall be the responsibility of the Contractor to proceed with the work in the manner and within such limitations as may be prescribed by the Engineers.

1.2 CONSTRUCTION LIMITS

A. Contractor shall confine his operations strictly within the limits of rights-of-way, indicated by the plans and/or directed by the Engineers, unless written permission is obtained to occupy additional ground. Upon completion of work the Contractor shall cleanup and restore the area of his operations to a condition at least equal to original conditions. Unless specified elsewhere herein, all restoration shall be included in the Contractor's unit and/or lump sum price bid. Damage to property outside of specified construction limits shall be the responsibility of the

Contractor and restoration of same shall be made at the Contractor's expense.

1.3 MEASUREMENT OF WORK AND MATERIALS

A. The Contractor will be paid for the actual quantity of authorized work or material furnished under each item of the contract, at the prices stipulated for each item. If the quantity of any unit price item is decreased the Contractor shall have no claim for damages on the basis of loss of anticipated profits. All quantities of work and materials to be paid will be determined by the Engineers in accordance with working lines specified in the contract documents.

1.4 CONSTRUCTION SEQUENCE

A. Submit for approval prior to construction a detailed schedule outlining all major activities, including the projected dates for work. Upon approval, the Contractor shall adhere to this schedule unless written permission to the contrary is given by the Owner.

G-9

CONTRACTORS WORK 01010-2

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01010 - Contractors Work.doc

1.5 CONTRACTOR'S RESPONSIBILITIES

A. The Contractor shall be responsible for all costs, including temporary power, water, telephone, testing services, road opening permits in local roads, building and electrical permits, construction permits, and licenses.

1.6 PROTECTION OF WORK AND PROPERTY

A. Contractor shall protect and maintain existing structures and access to all existing buildings (unless otherwise specified) in an undisturbed condition during the contract period.

B. Contractor shall provide adequate protection for the public, the Owners, and his employees during the contract period. Provide protective devices and equipment for protection of people and property. Protective measures shall comply with the

Occupational Safety and Health Administration (OSHA) and other codes having jurisdiction.

C. The Contractor shall provide adequate protection against injury or loss arising in connection with this Contract for all his work and the property of the Owner. He shall make good any such damage, injury or loss. He shall adequately protect adjacent property as provided by law and the specifications and drawings. He shall provide facilities for protection required by public authority or local conditions as passageways, guard fences, lights, etc.

D. The Contractor shall furnish, erect, place and maintain traffic control signs and devices (as required) to maintain traffic during hours of construction and at all other times in accordance with the methods indicated on the drawings and:

1 The special provisions of the Contract.

2 PA Code, Title 67, Chapter 212, Publication 213 Work Zone Traffic

Control Guidelines.

3 PA Code, Title 67, Chapter 211, Official Traffic Control Devices.

4 PennDOT Publication No. 35, Approved Construction Materials

(Bulletin 15).

5. PennDOT Publication No. 408, Specifications.

(a) Immediately upon completion of the work, remove devices.

(b) All traffic control devices must be in place before work begins.

(c) Access to all adjacent properties must be maintained at all times.

(d) The work area must be properly barricaded and secured during non-work hours to provide unrestricted full width use for through-traffic lanes.

G-10

01010-3 CONTRACTORS WORK

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01010 - Contractors Work.doc

1.7 CLEAN-UP

A. The Contractor shall remove waste on a daily basis so that at no time shall there be undue accumulation in the work area. Upon completion of the work, the

Contractor shall remove from the project and adjacent property, all surplus and discarded materials, equipment and temporary structures and leave the premises broom clean.

B. A final cleaning inspection shall be made by the Engineer. The Contractor shall perform any additional cleaning as required by the Engineer.

1.8 TIME OF THE ESSENCE

A. Time is of the essence in the performance of the Work required by this Contract.

No extensions of time will be granted for rain days, snow days or cold weather.

1.9 COPIES OF DOCUMENTS

A. Furnished Copies: Contractor will be furnished at not cost to him a maximum of 3 sets of full-size Contract Drawings, (in addition to as-built set) including revised drawings, and a maximum of 3 copies of the Contract Specifications in addition to those used in the execution of the Agreement.

B. Additional Copies: Additional copies of the above documents will be supplied with the Contractor paying for printing, handling and delivery cost upon receipt.

1.10 RELATED DOCUMENTS

A. The Contractor shall adhere to the rules, regulations and requirements of all state, county and local permits and/or approvals issued for this project. Permitting agencies must be notified by the Contractor prior to construction per the requirements of the permits.

1.11 WORK WITHIN PRIVATE PROPERTY RIGHT-OF-WAY

A. The Contractor's construction operations, equipment, materials and any other such items shall not leave the Township property or designated access route without the written permission of the Engineer.

B. The Contractor shall neither damage nor destroy any trees or shrubs. Any trees or shrubs damaged or destroyed shall be replaced in kind by the Contractor at no additional cost to the Owner.

C. Contractor shall restore all disturbed areas as specified herein.

G-11

CONTRACTORS WORK 01010-4

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01010 - Contractors Work.doc

G-12

Job No. HAVTT 221042 PRE-CONSTRUCTION

01015-1 SURVEY

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01015 - Pre-Construction Survey.doc

SECTION 01015

PRE-CONSTRUCTION SURVEY

1.1 PURPOSE

A. The purpose of this survey is to locate and document all existing conditions prior to the commencement of any construction within the area.

1.2 PERSONNEL

A. The Contractor shall provide a competent English speaking person to conduct a detailed survey. This person shall be an officer of the company or a representative of the firm's insurance carrier.

1.3 TIMING

A. The pre-construction survey shall be conducted after issuance of the notice to proceed. The survey shall be conducted no sooner than (four) 4 working days and no later than (two) 2 working days prior to the commencement of work. No mobilization, deliveries or work of ANY NATURE shall be permitted prior to the pre-construction survey.

PART 2 SITE SURVEYS

2.1 EXTERIOR SURVEY

A. The Contractor must obtain the services of a qualified professional to video tape the existing features adjacent to the route of proposed construction activity. The purpose of this video is to establish the pre-construction conditions of the area, so a determination of the required restoration can be made upon completion of the project.

B. The video shall meet the following minimum requirements:

1. Extent:

(a) As a minimum the video shall extend a minimum of 50-feet in all directions from the edge of the deck.

G-13

PRE-CONSTRUCTION Job No. HAVTT 221042

SURVEY 01015-2

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01015 - Pre-Construction Survey.doc

(b) The video shall encompass the indicated access route for a minimum of 25-feet in all directions from the route, including the building façade where the route is adjacent to the building.

(c) The video shall encompass the entire façade of the building both below and above the deck from the ground level to a point a minimum of 10-feet above the deck elevation.

(d) The video shall show in detail the existing ledger board attachment and all posts both attached to the façade and freestanding.

2. The video shall also show the Contractor's proposed staging area and all surrounding features.

3. An audio narrative shall be included, outlining in detail a description of the video being taken. This description shall include the location of the video, house number, proximity, and all other information pertinent to fully describing the object and ascertaining its location and existing condition.

PART 3 EXECUTION

3.1 GENERAL

A. All videotape use shall be submitted in electronic format on a standard DVD. The video shall be a high-quality color format.

B. All film employed for still pictures shall be a high-quality type. All pictures shall be a minimum 4-inch x 6-inch size. Alternately, original digital pictures may be submitted on CD or DVD with all EXIF data intact.

C. All written documentation shall be clear and legible. All designations shall be clearly identified with dimensions to a minimum of two (2) fixed reference points.

Also, a clear and concise description shall be provided for each condition encountered indicating the precise nature, dimensions, location and situation encountered.

D. All documentation shall be clearly identified with the following information:

- Contract Number and Title

- Name of Project

- Date and time the survey was conducted.

E. One (1) copy of all documentation shall be provided to the Engineer for review at least two (2) working days prior to the commencement of construction.

G-14

Job No. HAVTT 221042 PRE-CONSTRUCTION

01015-3 SURVEY

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01015 - Pre-Construction Survey.doc

G-15

Job No. HAVTT 221042 MEASUREMENT

01025-1 AND PAYMENT

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01025 - Measurement Payment.doc

SECTION 01025

MEASUREMENT AND PAYMENT

1.1 SECTION INCLUDES

A. Measurement and payment criteria applicable to the Work performed under a Unit

Price payment method and stipulated Lump Sum method.

B. Defect assessment and non-payment for rejected work.

1.2 AUTHORITY

A. Measurement methods delineated in the individual specification sections, if any, are intended to complement the criteria of this section.

B. The Contractor shall take all measurements and compute quantities. The Engineer will verify measurements and quantities.

1.3 UNIT QUANTITIES SPECIFIED

A. Quantities and measurements indicated in the Form of Proposal are for bidding and contract purposes only. Quantities and measurements supplied or placed in the Work and verified by the Engineer shall determine payment.

B. If the actual Work requires more or fewer quantities than those quantities indicated, provide the required quantities at the unit or lump sum prices contracted.

1.4 MEASUREMENT OF QUANTITIES

A. Measurement by Number: Will be measured by the actual number of completed items installed.

B. Measurement by Volume: Measured by cubic dimension using mean length, width and height or thickness.

C. Measurement by Area: Measured by square dimension using mean length and width or radius.

G-16

MEASUREMENT Job No. HAVTT 221042

AND PAYMENT 01025-2

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01025 - Measurement Payment.doc

D. Linear Measurement: Measured by linear dimension, at the item centerline or mean chord.

E. Stipulated Lump Sum or Unit Price Measurement: Items measured by weight, volume, area, or linear means or combination, as appropriate, as a completed item or unit of the Work.

1.5 PAYMENT

A. Payment Includes: Full compensation for all required supervision, labor, products, tools, equipment, plant, transportation, services and all incidental work; erection, application or installation of an item of the Work; overhead and profit.

B. Final payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities accepted by the Engineer multiplied by the unit price for Work which is incorporated in or made necessary by the Work.

1.6 DEFECT ASSESSMENT

A. Replace the Work, or portions of the Work, not conforming to specified requirements.

1.7 NON-PAYMENT FOR REJECTED PRODUCTS

A. Payment will not be made for any of the following:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products placed beyond the lines and levels of the required Work.

4. Products remaining on hand after completion of the Work.

5. Loading, hauling, and disposing of rejected Products.

PART 2 GENERAL

2.1 GENERAL

A. Payment for materials furnished and work done under this contract will be made as hereinafter stipulated for the amount of materials furnished and work performed under authorization of Engineers, or their authorized representative, and in accordance with their measurements. Contractor shall not be entitled to receive additional compensation for any work or materials except as shall be authorized by written order of the Owner.

G-17

Job No. HAVTT 221042 MEASUREMENT

01025-3 AND PAYMENT

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01025 - Measurement Payment.doc

B. The following items, classifying the various kinds of work, refer to respective items bid in the "Form of Bid."

Item No. 36-1: Payment for “Removal and Reconstruction of Existing Elevated Deck” will be made at the lump sum price bid in "Form of Bid." Lump sum price bid shall include: insurance, bonding, mobilization & demobilization; establishment and maintenance of the indicated emergency access route for the duration of the work; coordination with the Township and recreation facility staff, pre-construction survey; furnishing, installation, maintenance, and removal of the pedestrian control/protection devices indicated; trimming of trees a required to accommodate the work; protection of all existing building components including doors, windows, posts, facades, walks, patios, walls and all exterior fixtures, components and utilities; removal, salvaging, protection and re-installation of those components to be re-installed including the railings, decking and wood posts/existing metal connectors/bolts; removal and salvaging of the existing sprinkler piping; demolition and legal disposal of all other existing components to be removed; temporary support/protection of the existing wood posts to remain;

furnishing/installation of new fasteners associated with attachment of the existing ledger board as indicated on the plans; furnishing and installation of all new wood framing members per the attached drawings; reattachment of new framing members to existing posts/ledger board per the drawings including new connectors and blocking where indicated; reinstallation of the railings with the same configuration as currently exists, including supply of any new material damaged during removal; reinstallation of the existing composite deck boards in the same pattern as existed previously with the same (or approved equal) fastening system; cleanup, restoration of all disturbed areas to the pre-construction condition including and grass, paved areas and patios, and all appurtenant labor, work, supervision, tools, equipment, material, shop drawings and other items incidental thereto, in accordance with the plans, specifications and manufacturer’s instructions and recommendations, in addition to all Local, State and Federal requirements and all generally accepted standards for this work.

G-18

01310-1 CONSTRUCTION SCHEDULES

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01310 - Construction Schedules.doc

SECTION 01310

CONSTRUCTION SCHEDULES

1.1 REQUIREMENTS INCLUDED

A. Promptly after the effective date of the Agreement, prepare and submit to

Engineer estimated construction progress schedules for the Work, with sub-schedules of related activities which are essential to its progress.

B. Submit schedule in accordance with Paragraph 1.4 of Section 01001.

C. Submit revised progress schedules should any significant changes transpire within the schedule and; or at the request of the Engineer or Owner.

D. Schedule and attachments must be prepared on a typewriter or a computer printer.

Handwritten schedules are not acceptable.

1.2 RELATED REQUIREMENTS

A. Section 01010 - Contractors Work

B. Section 01700 - Project Closeout

C. Section 01340 - Shop Drawings, Product Data and Samples

1.3 FORM OF SCHEDULES

A. Prepare schedules in the form of a horizontal bar chart.

1. Provide separate horizontal bar for each trade or operation.

2. Horizontal time scale: Identify the first workday of each week.

3. Scale and spacing: To allow space for notations and future revisions.

4. Minimum sheet size: 8-1/2" x 11".

B. Format of listings: The chronological order of the start of each item of Work.

C. Identification of listings: By major specification section numbers.

G-19

CONSTRUCTION SCHEDULES 01310-2

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01310 - Construction Schedules.doc

1.4 CONTENT OF SCHEDULES

A. Construction Progress Schedule:

1. Show the complete sequence of construction by activity.

2. Show the dates for the beginning, and completion of, each major element of construction.

B. Submittals Schedule for Shop Drawings, Product Data and Samples. Show:

1. The dates for Contractor's submittals.

2. The dates approved submittals will be required from the Engineer.

1.5 PROGRESS REVISIONS

A. Indicate progress of each activity to date of submission.

B. Show changes occurring since previous submission of schedule:

1. Major changes in scope

2. Activities modified since previous submission

3. Revised projections of progress and completion

4. Other identifiable changes

C. Provide a narrative report as needed to define:

1. Problem areas, anticipated delays, and the impact on the schedule.

2. Corrective action recommended and its effect.

3. The effect of changes on schedules of contractor.

1.6 SUBMISSIONS

A. Submit initial schedules within ten days after the effective date of the

Agreements.

1. Engineer will review schedules and return review copy within 10 days after receipt.

2. If required, reissue within 7 days after return of review copy.

B. Submit revised progress schedules with each application for payment.

C. Submit the number of opaque reproductions which the Contractor requires, plus

G-20

01310-3 CONSTRUCTION SCHEDULES

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01310 - Construction Schedules.doc two copies which will be retained by the Engineer.

1.7 DISTRIBUTION

A. Distribute copies of the relevant schedules to:

1. Job site file.

2. Subcontractors.

3. Other concerned parties.

B. Instruct recipients to report promptly to the Contractor, in writing, any problems anticipated by the projections shown in the schedules.

G-21

SHOP DRAWINGS,

Job No. HAVTT 221042 PRODUCT DATA

01340-1 AND SAMPLES

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01340 - Shop Drawings, Product Data & Samples.doc

SECTION 01340

SHOP DRAWINGS, PRODUCT DATA AND SAMPLES

1.1 WORK INCLUDED

A. Submit Shop Drawings, Product Data, and Instruction Manuals required by

Contract Documents.

1.2 RELATED REQUIREMENTS

A. Definitions, and Additional Responsibilities of Parties: Conditions of the

Contract.

1.3 SHOP DRAWINGS

A. Drawings shall be presented in a clear and thorough manner.

1. Details shall be identified by reference to sheet and detail, shown on

Contract Drawings.

1.4 PRODUCT DATA

A. Preparation

1. Clearly mark each copy to identify pertinent products or models.

2. Show performance characteristics and capacities.

3. Show dimensions and clearances required.

1.5 SUBMISSION REQUIREMENTS

A. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor.

B. Number of Submittals Required:

1. Shop Drawings: Submit four (4) copies.

2. Product Data: Submit four (4) copies.

G-22

SHOP DRAWINGS,

PRODUCT DATA Job No. HAVTT 221042

AND SAMPLES 01340-2

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01340 - Shop Drawings, Product Data & Samples.doc

C. Submittals Shall Contain:

1. The date of submission and the dates of any previous submissions.

2. The Project title and contract number.

3. The names of:

a. Contractor.

b. Supplier.

c. Manufacturer.

4. Identification of the product, with the specification section number.

5. Applicable standards, such as ASTM or Federal Specification numbers.

6. Identification of deviations from Contract Documents.

7. Identification of revisions on resubmittals.

8. An 8 in. x 3 in. blank space for Contractor and Engineer stamps.

9. Contractor's stamp, initialed or signed, certifying to review of submittal, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the Work and of Contract Documents.

1.6 RESUBMISSION REQUIREMENTS

A. Make any corrections or changes in the submittals required by the Engineer and resubmit until approved.

B. Shop Drawings and Product Data:

1. Revise initial drawings or data and resubmit as specified for the initial submittal.

2. Indicate any changes which have been made other than those previously noted by the Engineer.

PART 2 PRODUCTS

NOT USED

G-23

01700-1 PROJECT CLOSEOUT

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01700 - Project Closeout.doc

SECTION 01700

PROJECT CLOSEOUT

1.1 RELATED WORK SPECIFIED ELSEWHERE

A. Project Record Documents - Section 01720.

1.2 SUBSTANTIAL COMPLETION

A. When the work is considered substantially complete, submit a written notice that the Work, or a designated portion thereof, is substantially complete. Include a list of all items that require completion or correction.

B. Within a reasonable time after receipt of such notice, an observation will be made to determine the status of completion.

C. If the Work is not considered substantially complete, the Contractor will be notified in writing, giving the reasons therefor.

D. Contractor shall remedy the deficiencies in the work and send a second written notice of substantial completion. This notice shall include a statement of action taken on each item noted a requiring correction or completion to achieve

"Substantial Completion" status.

E. The Work will be observed a second time.

F. When the Engineer concurs that the Work is substantially complete, he will:

1. Issue a letter accompanied by Contractor's list of items to be completed or corrected, as verified and amended by the Engineer.

1.3 FINAL OBSERVATION

A. When the Work is considered complete, submit written certification that:

1. Contract Documents have been reviewed.

2. Work has been observed and has been completed in compliance with

Contract Documents.

G-24

PROJECT CLOSEOUT 01700-2

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01700 - Project Closeout.doc

3. Equipment and systems have been tested in the presence of the Engineer and are operational.

4. Work is ready for final observation.

B. Observation will be made to verify the status of completion with reasonable promptness after receipt of such certification.

C. If the Work is not considered complete, the Contractor will be notified in writing, listing the incomplete or defective work.

D. Contractor shall take immediate steps to remedy the stated deficiencies and, after correcting deficiencies, he shall send a second written certificate that the work is complete. This certification shall itemize each deficiency noted and a statement of action taken to remedy or complete the Work.

E. The work will be observed a second time.

F. When the Work is acceptable under the Contract Documents, the Contractor shall be required to make closeout submittals.

1.4 SECOND OBSERVATION FEES

A. Should the Engineer perform a second observation due to failure of the work to comply with the claims of status of completion made by the Contractor:

1. Engineer will deduct the amount of such compensation from the final payment to the Contractor.

1.5 CLOSEOUT SUBMITTALS

A. Project Record documents as specified under Section 01720.

1.6 FINAL ADJUSTMENT OF ACCOUNTS

A. Submit a final statement of accounting.

B. Statement shall reflect all adjustments to the Contract Sum:

1. The original Contract Sum.

2. Additions and deductions resulting from:

a. Previous Change Orders.

G-25

01700-3 PROJECT CLOSEOUT

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01700 - Project Closeout.doc

b. Allowances.

c. Unit Prices.

d. Deductions for uncorrected Work.

e. Deductions for reinspection payments.

f. Other adjustments.

3. Total Contract Sum, as adjusted.

4. Previous payments.

5. Sum remaining due.

C. The Engineer will prepare a final Change Order, reflecting approved adjustments to the Contract sum which were not previously made by Change Orders.

1.6 FINAL APPLICATION FOR PAYMENT

A. Submit the final Application for Payment in accordance with procedures and requirements stated in the Conditions of the Contracts.

G-26

Job No. HAVTT 221042 PROJECT

01720-1 RECORD DOCUMENTS

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01720 - Project Record Documents.doc

SECTION 01720

PROJECT RECORD DOCUMENTS

1.1 MAINTENANCE OF DOCUMENTS

A. Maintain at job site, one copy of record documents including Drawings, Specification, Amendments, Change Orders and other modifications, Shop

Drawings, product date and samples.

B. In addition, maintain one copy of field orders or written instructions and field test records.

C. Provide files and racks for storage documents.

D. File documents and samples in accordance with Data Filing Format of the

Construction Specifications Institute (C.S.I).

E. Maintain documents in a clean, dry, legible condition and in good order. Do not use record documents for construction purposes.

F. Make Documents and samples available at all times for inspection.

1.2 RECORDING

A. Label each document "Project Record" in neat large letters.

B. Record information concurrently with construction progress.

C. Do not conceal any work until required information is recorded.

D. Drawings - Legibly mark to record actual construction:

1. Depths of various elements of foundation in relation to finish first floor datum.

2. Horizontal and vertical locations of laterals, underground utilities and appurtenances, referenced to permanent surface improvements.

3. Location of internal utilities and appurtenances concealed in the construction, referenced to visible and accessible features of the structure.

4. Field changes of dimension and detail.

5. Changes made by Supplemental Instruction or by Change Order.

6. Details not on original Contract Drawings.

G-27

PROJECT Job No. HAVTT 221042

RECORD DOCUMENTS 01720-2

U:\Accounts\HAVTT\HAVT221042 - Haverford Reserve Community Center\RESOURCES\DRAFT SPECS\01720 - Project Record Documents.doc

E. Specifications and Amendments - Legibly mark each Section to record:

1. Manufacturer, trade name, catalog number, and Supplier of each Product and item of equipment actually installed.

2. Changes made by Supplemental Instructions or by Change Order.

F. Shop Drawings - Maintain as record documents. Legibly annotate any changes made after review.

1.3 SUBMITTALS

A. At completion of the Work, furnish one set of drawings showing all notations specified above. A copy of the Design Professional's drawings may be used for this purpose upon reimbursement of the printing costs to the Design Professional.

In addition, furnish two copies of any shop drawings or product data sheet which required annotation after approval.

B. After inclusion of additional data, if any, furnish:

1. One set of contract drawings as specified under 1.3, A. above.

2. Two sets of all other Project Record Documents.

C. Accompany this final submittal with transmittal letter containing data, project title and number, Contractor's name and address, title and number of each Record

Document, certification that each document as submitted as complete and accurate, signature of Contractor or his authorized representative.

G-28

Copyright 2014 AIA MasterSpec Full Length 06/14

EXTERIOR ROUGH CARPENTRY 061063 - 1

SECTION 061063 - EXTERIOR ROUGH CARPENTRY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Requirement for dimensional lumber to be used for framing associated with the new structure for the deck.

B. Related Requirements:

1. Contract Drawings

1.3 DEFINITIONS

A. Boards: Lumber of less than 2-inches nominal in thickness and 2-inches nominal or greater in width.

B. Dimension Lumber: Lumber of 2-inches nominal or greater but less than 5-inches nominal in least dimension.

C. Timber: Lumber of 5-inches nominal or greater in least dimension.

D. Lumber grading agencies, and the abbreviations used to reference them, include the following:

1. NeLMA: Northeastern Lumber Manufacturers' Association.

2. NLGA: National Lumber Grades Authority.

3. RIS: Redwood Inspection Service.

4. SPIB: The Southern Pine Inspection Bureau.

5. WCLIB: West Coast Lumber Inspection Bureau.

6. WWPA: Western Wood Products Association.

1.4 ACTION SUBMITTALS

A. Product Data: For preservative-treated wood products. Include chemical treatment manufacturer's written instructions for handling, storing, installing, and finishing treated material.

G-29

EXTERIOR ROUGH CARPENTRY 061063 - 2

1.5 INFORMATIONAL SUBMITTALS

A. Material Certificates:

1. For preservative-treated wood products. Indicate type of preservative used and net amount of preservative retained. For products receiving a waterborne treatment, include statement that moisture content of treated materials was reduced to levels specified before shipment to Project site.

B. Certificates of Inspection: Issued by lumber grading agency for exposed wood products not marked with grade stamp.

C. Evaluation Reports: For preservative-treated wood products, from ICC-ES.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Store materials under cover and protected from weather and contact with damp or wet surfaces.

Stack lumber flat with spacers between each bundle to provide air circulation. Provide for air circulation around stacks and under coverings.

PART 2 - PRODUCTS

2.1 LUMBER, GENERAL

A. Comply with DOC PS 20 and with grading rules of lumber grading agencies certified by

ALSC's Board of Review as applicable. If no grading agency is indicated, comply with the applicable rules of any rules-writing agency certified by ALSC's Board of Review.

1. Factory mark each item with grade stamp of grading agency.

2. For items that are exposed to view in the completed Work, mark grade stamp on end or back of each piece. In DOC PS 20, dressed sizes of green lumber are larger than those of dry lumber.

3. Where nominal sizes are indicated, provide actual sizes required by DOC PS 20 for moisture content specified. Where actual sizes are indicated, they are minimum dressed sizes for dry wood products.

4. Provide dressed lumber, S4S, unless otherwise indicated.

B. Maximum Moisture Content:

1. Boards: 15 percent.

2. Dimensional Lumber: 15 percent

3. Timber: 19 percent.

If the moisture content of the lumber at any location exceeds the above, the lumber cannot be used until the moisture content is reduced to the levels indicated.

G-30

EXTERIOR ROUGH CARPENTRY 061063 - 3

2.2 LUMBER

A. Hand select wood for freedom from characteristics, on exposed surfaces and edges, that would impair finish appearance, including decay, honeycomb, knot holes, shake,…