01500 Temporary Facilities and Controls.docx
DOCX document 31 KB Posted
- Attached to
- RED HOLE BRIDGE REPAIR Federal contract opportunity
- Solicitation number
- 140L6221Q0018
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Schedule Red Hole Bridge Repairs.xlsx | XLSX spreadsheet | |
| Supplemental Red Hole Bridge Repairs Work Data Sheet.docx | DOCX document | |
| 01009 General Information and Requirements.docx | DOCX document | |
| 01505 Mobilization.docx | DOCX document | |
| RED HOLE BRIDGE DRAWINGS 2020 11 23.pdf | ||
| Sol_140L6221Q0018.pdf | ||
| 4026 21872 01 Red Hole 24 40 11 Poured Joint Sealant.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| DIVISION 1 | SECTION 01500 |
| GENERAL REQUIREMENTS | TEMPORARY FACILITES AND CONTROLS |
| DIVISION 1 | SECTION 01500 |
| GENERAL REQUIREMENTS | TEMPORARY FACILITES AND CONTROLS |
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
PART 1: GENERAL
1.1 SUMMARY
A. Section Includes: Requirements for temporary utilities for construction, sanitary facilities, vehicular access, temporary barriers and controls, and project identification.
1.2 DEFINITIONS
A. Landscape Preservation: The term "injury" includes, without limitation, bruising, scarring, tearing, and breaking private water line, roots, trunks, or branches.
B. Pesticides: Include herbicides, insecticides, fungicides, rodenticides, piscicides, avicides, surface disinfectants, animal repellents, and insect repellents.
| C. | Security: "Restricted Area" means an area where entry will not be allowed unless authorized by the Contracting Officer. |
| 1. | "Security Measures" means those measures contained in regulations or as may be established by the Contracting Officer and carried out by a Federal guard system to provide continuous and effective security of restricted areas. |
1.3 SUBMITTALS
A. Temporary Utilities: Submit three copies of the implementation and termination schedule for each utility; and three reports of tests, inspections, meter readings, and similar procedures performed on temporary utilities.
| B. | Water Management Plan: Submit three copies of a detailed Water Quality Management Plan to the Contracting Officer for review, approval, and use, at least 30 days prior to commencing construction activities that involve less than 5 acres of land in the vicinity of any stream, flowing or dry watercourse, lake, wetland, reservoir, or underground water source. Include in the Water Quality Management Plan the following information: |
| 1. | Name of the person who will be responsible for implementing and carrying out the plan. |
| 2. | Relationship of the methods and descriptions herein to the conditions of required permits specified in article 1.6. |
| 3. | Precautions which will be taken to avoid discharge or accidental spills of pollutants into a river, stream, watercourse, or lake. |
| 4. | Demonstrated compliance with State and local waste disposal, sanitary sewer, or septic regulations. |
| 5. | Methods of handling and treating wastewater, including drawings or maps indicating the locations for evaporation or settling ponds, treatment facilities, best management practices to prevent water pollution, and discharge points. Provide estimates of the amount of wastewater which may be handled and treated at each location. |
| 6. | Methods for preventing or controlling runoff and erosion for all construction sites, both during and after construction, including: |
| a. | Access and haul roads; |
| b. | Stockpile, borrow, and waste areas; |
| c. | Construction plant and equipment yards; |
| d. | All excavated surfaces; |
| e. | Areas containing slurry ponds or water treatment facilities; |
| f. | Buffer zones; and |
| g. | Other impacted areas. |
| 7. | Information on vegetative practices, structural control, silt fences, straw dikes, sediment and operator controls, stormwater controls, and solid waste controls. Stormwater controls shall address appropriate stormwater management measures including velocity dissipators. Solid waste controls shall address controls for building materials and offsite tracking of sediment. |
| C. | Traffic Control Plan: Submit three copies. Include the following topics: |
| 1. | The requirements for specific signs, signals, channelizing and lighting devices, barricades, and flagpersons that are detailed in the current ANSI D6.1. |
| 2. | Provide for an unobstructed passageway for one lines of traffic at all times on smooth and dustless lanes through the construction operations where necessary. |
| 3. | Provide for temporary connections of sufficient width for one lines of traffic between the existing roadway and new temporary construction, where necessary. |
| 4. | Provide for convenient access to private residence and business driveways and buildings along line of work. |
| 5. | Provide for such guards as may be necessary to ensure against accidents and avoid damage or injury to passing traffic in areas where the nature of construction operations in progress and equipment and machinery in use pose a hazard. |
D. Landscape Protection Plan: Submit three (3) copies of description of protective barriers or other methods used to protect vegetation and existing private water lines from damage or injury caused by construction operations seven (7) days before commencing construction activities.
1.4 QUALITY ASSURANCE
| A. | Regulations: Comply with applicable local regulations for haul routes over public highways, roads, or bridges. Comply with industry standards and applicable laws and regulations of authorities having jurisdiction including, but not limited to the following: |
| 1. | Building code requirements. |
| 2. | Health and safety regulations. |
| 3. | Utility company regulations. |
| 4. | Police, fire department, and rescue squad rules. |
| 5. | Environmental protection regulations. |
| 6. | Prevention and control of air pollution. |
| 7. | Prevention and control of water pollution. |
B. Manuals: Comply with latest Manual on Uniform Traffic Control Devices (MUTCD), Part VI.
1.5 EXPLOSIVES
A. Explosives: Shall not be permitted.
1.6 PROJECT CONDITIONS
A. Access Routes: Rightsofway for access to work from existing roads will be established by the Contracting Officer. Use only established roadways, areas, and haul routes, or temporary roadways, areas, or haul routes constructed by the Contractor when and as authorized by the Contracting Officer.
PART 2: PRODUCTS
2.1 UTILITIES
A. General: Electrical power, telephone, heat, and water are not available on the site and will be provided by the Contractor.
B. Electrical: No electrical materials which are part of the permanent electrical system may be used for temporary electrical installations unless approved in writing by the Contracting Officer.
2.2 TOILET UNITS
A. Temporary Toilet Units: Provide self-contained, single-occupant toilet units of the chemical, aerated recirculation, or combustion type. Provide units properly vented and fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material.
2.3 PROJECT IDENTIFICATION
A. Project Site Sign: Within 30 days after Notice to Proceed, furnish and install a project sign which shall be located at the main construction entrance to the site.
B. Construction Signs: Only signs to expedite deliveries, maintain traffic flow, promote safety, and caution against danger shall be erected, as necessary.
PART 3: EXECUTION
3.1 INSTALLATION
| A. | Toilets: Install self-contained toilet units specified in Part 2 of this specification section. Shield toilets to ensure privacy. Use of pit-type privies will not be permitted. |
| 1. | Provide separate facilities for male and female personnel. |
| 2. | Provide toilet tissue, paper towels, paper cups, and similar disposable materials for each facility. Provide covered waste containers for used material. |
3.2 VEHICLE TRAFFIC CONTROL
| A. | Preparation: Provide, erect, and maintain all necessary traffic control devices, including traffic cones, delineators, concrete safety barriers, barricades, suitable and sufficient flasher lights, flagpersons, danger signals, and signs, as specified on approved Traffic Control Plan and as required by the State and local authorities having jurisdiction. Take all necessary precautions for protection of the work and safety of the public on roads affected by the work during the contract period as construction work proceeds. |
| 1. | Do not start any construction work along public or private roads until the proper traffic control devices for warning, channeling, and providing safety for the motorists [as specified on the approved traffic control plan] are in place at the construction site. |
| B. | Application: Maintain flow of public traffic and conduct operations for construction of roadways and bridges so as to offer the least possible obstruction and inconvenience to public traffic. |
| 1. | Protect all roads closed to traffic with effective barricades having acceptable warning and detour signs. Conduct operation in a manner that will not close any thoroughfare or interfere with traffic except with written permission of the Contracting Officer. Illuminate all barricades and obstructions at night, and keep all lights burning from sunset until sunrise. |
| 2. | Erect such additional warning and directional signs in connection with the work as may be required by the Government. Requiring of additional signs by the Government in no way relieves the Contractor from full responsibility for protection of the work and for safety of the public. |
| 3. | Maintain the condition, operation, and effectiveness of all traffic control devices throughout their period of use. Remove all temporary traffic control devices when no longer needed. |
3.3 HAUL ROUTES, ROADWAYS, PARKING AREAS, AND STORAGE/STAGING AREAS
A. Examination: Investigate the condition of available public or private roads for clearances, restrictions, bridgeload limits, bond requirements, and other limitations that affect or may affect access and transportation operations to and from the jobsite.
B. Temporary Parking Areas: Construct temporary parking areas for construction operations personnel. Provide additional offsite parking when site space is not adequate. Locate as approved by the Contracting Officer.
C. Storage/Staging Areas: The Contractor may construct a temporary area for equipment and materials located as approved by the Contracting Officer and within Government property boundaries. Fencing of materials or equipment shall not be required at this site; however, the Contractor shall be responsible for cleanliness and orderliness of the area used and for the security of any material or equipment stored in this area.
D. Maintenance: Maintain haul routes, roadways, parking and storage areas, in a sound, smooth condition. Maintain the roadbed, side slopes, structures, and surfacing of roads and areas until completion and acceptance of all the work under this contract. Maintain the surfacing of gravelsurfaced roads and areas in a smooth condition until completion and acceptance of all work under this contract.
E. Repair: Promptly repair ruts, potholes, low areas with standing water, and other deficiencies to maintain road and parking area surfaces and drainage in original or specified condition.
F. Removal: Remove materials used to construct temporary roadways, areas, and haul routes prior to contract completion. Recycle all salvageable materials as approved by the Contracting Officer.
3.4 LANDSCAPE PRESERVATION
A. Preservation: Preserve the natural landscape and preserve and protect existing vegetation not required or otherwise authorized to be removed. Conduct operations, to prevent unnecessary destruction, scarring, or defacing of the natural surroundings in the vicinity of the work. Move crews and equipment within the rightsofway and over routes provided for access to the work in a manner to prevent damage to grazing land, crops, or property.
B. Protection: Protect vegetation from damage or injury caused by construction operations, personnel, or equipment by the use of protective barriers or other methods approved by the Contracting Officer. Minimize to the greatest extent practicable clearings and cuts through vegetation. Shape irregularly authorized clearings and cuts to soften undesirable aesthetic impacts.
C. Anchorage: Do not use trees for anchorages except in emergency cases or as approved by the Contracting Officer. For such use, wrap the trunk with a sufficient thickness of approved protective material before any rope, cable, or wire is placed.
3.5 MAINTENANCE AND REMOVAL
A. Maintenance: Maintain temporary structures, facilities, and controls as long as needed for safe and proper completion of the work and as directed by the Contracting Officer.
B. Removal: Remove temporary structures, facilities, and controls as rapidly as progress of the work will permit and as approved by the Contracting Officer.
3.6 PROTECTION
A. Barriers: Provide earthen embankments and similar barriers around excavation and subgrade construction, sufficient to prevent flooding by runoff from heavy rains.
3.7 CLEANUP
A. Restoration of Storage Area: Upon completion of the project and after removal of materials and equipment from within the area. Restore areas used by the Contractor for the storage of equipment or material, or other use, to the original or better condition.
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: The work described in this section will not be measured for payment.
4.2 BASIS OF PAYMENT
A. Payment: No direct payment for the work described under this section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.
END OF SECTION