01 SOW VLSB 20-0008 08.26.2025.pdf
PDF 117 KB Posted
- Attached to
- B1510 NDI HVAC Repair
- Solicitation number
- FA480326B0002
About this file
This Statement of Work (SOW) details a design/build HVAC repair project for Building 1510 at Shaw Air Force Base. The project involves demolishing existing HVAC equipment, including an air handler unit, hot water coils, boiler, and domestic water heater, and installing new components based on the existing chiller. The new work includes a 25-ton air handling unit, hot water coils, isolation valves, an air separator, buffer tank, gas-fired boilers for HVAC and domestic hot water, and associated piping and controls.
The project has a comprehensive design phase spanning 112 calendar days, with 35%, 65%, and 95% design submissions required, each with specific review periods. Construction is scheduled for 90 calendar days, beginning after 95% design approval and with all materials on-site. Key requirements include utilizing existing electrical infrastructure, installing DDC controls, ensuring maintenance accessibility, and completing a test and balance of the system in summer and winter conditions. The contractor must coordinate with base personnel, manage utility outages, and follow strict debris disposal and reporting guidelines.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN/BUILD
STATEMENT OF WORK
REPAIR HVAC B1510
08.26.2025 Project: VLSB 20-0008
SCOPE OF WORK:
This Statement of Work (SOW) is for the design, demolition, and installation of HVAC equipment at building 1510. The building is 4,400 square feet and conditioned with a 4-pipe system composed of a one year old chiller, 40 year old air handling unit with straight ducted air, and a 9 year old boiler system supply hot water coils. The air handling unit, hot water coils, and boiler will be the main components replaced.
DEMO:
• The contractor shall demolish the existing air handler unit and any associated isolation valves.
• The contractor shall demolish all hot water coils and any isolation valves located near the coil.
• The contractor shall demolish all ductwork in the mechanical room.
• The contractor shall demolish the existing boiler, associated components, and any isolation valves. The boiler shall be returned to the government.
• The contractor shall demolish the existing domestic water heater, associated components, and any isolation valves.
• The contractor shall demolish the existing controls.
NEW WORK:
The contractor shall design and install the following new components based on the existing chiller:
• 25 ton air handling unit (AHU) that utilizes existing electrical infrastructure.
• Hot water coils in the location of the demolished ones. Hot water coils shall be sized appropriately for the areas they are serving.
• Isolation valves on the supplies and returns of all hot water coils and the AHU.
• Air separator with basket strainer on the inlet side of the chiller pump.
• Buffer tank on chilled water loop.
• Gas fired boiler and accessories to support HVAC system.
• Gas fired water heater and accessories for domestic hot water.
• Isolation valves on the supplies and returns on the HVAC boiler and domestic boiler.
• Chilled and hot water piping needed to connect new equipment.
• Pipe insulation and jacketing shall be installed per Shaw Design Standards.
• Rework ductwork to install AHU and VAV boxes into the HVAC system.
• Upgrade existing HVAC controls and connect to base energy management control shop.
Once the system is complete, a test and balance shall be conducted according to UFGS 23 05 93 Test and Balance, which requires a test conducted in summer conditions and winter conditions.
END OF BASE BID PROPOSAL
NOTE:
New HVAC components electrical characteristics shall match existing if possible. A preconstruction meeting will need to be held before the NTP is given. The contractor will establish a schedule for construction that will show the required work (including phasing) and long lead time items. All long lead-time items shall be on site prior to starting any work.
Long lead items may be purchased with an approved 65% design.
A seer rating of 14 is required for all new equipment.
The facility will be occupied during construction. The contractor shall work around the existing remaining occupants and protect any government property as needed to complete this project. The contractor shall coordinate any outages with the government.
DESIGN:
The Government will require a 35%, 65% and 95% design to be submitted. These should be submitted electronically as .dwg and .pdf. Hard copies of each submittal shall include (1) 24x36 and (1) 3/4 size set. At the completion of the project, the contractor shall provide as-builts in the same formats.
The Design Schedule shall be as follows:
• 35% Design - 3 weeks
• 35% Design - 2 weeks for Government review
• 65% Design - 4 weeks
• 65% Design - 2 weeks for Government review
• 95% Design - 3 weeks
• 95% Design - 2 weeks for Government review
Total Design –112 Calendar days
FOR EACH DESIGN:
• The design shall accurately represent the existing conditions for all trades involved with the exception of finishes.
• All products/materials shall be specified on the submittals.
• No Furniture, Fixtures and Equipment (FF&E) plans shall be required.
• The design shall include the phasing plan.
Design % Minimum submittal requirements 35% Submitted shall include, but not be limited to:
• Initial DD 1354 Form.
• Demolition Plans.
• All interior room layouts.
• Location, size and route for all exterior equipment and utilities (gas, water, sanitary sewer, electrical, telephone). Show exact location of where the utilities will enter the facility.
65% Submitted shall include, but not be limited to:
• All interior finish proposed schedules to include specifications on the finish schedule.
• Major interior construction/finish details.
• All building HVAC equipment layout, location and some details.
Sizing calculations for unit(s) shall also be provided at this time.
• Any special systems, such as ventilation and/or direct digital controls (DDC), shall be submitted complete.
• All building electrical equipment layout location and details.
Service sizing and major electrical equipment shall be shown at this time. Layouts for any new receptacles or updated receptacles.
• Any design, calculations or equipment submittals deemed necessary by the Contractor to allow construction to begin.
• Any items deemed necessary by the Contractor to allow for the continuation of the design.
95% Submittals shall include, but not be limited to:
• All interior, non-load bearing construction including details.
• Complete HVAC design.
• Complete DDC system.
• Any and all remaining design, calculations or submittals that are necessary to provide a complete and constructible design.
CONSTRUCTION:
Construction is 90 calendar days.
Construction will start when the 95% design is approved and all material are on site.
Given the long lead time for some materials, the Contractor may provide submittals to the Government along with the 65% design submittal and may order materials upon the approval of the 65% design and submittals. Contract performance for each phase will start after the issuance of a NTP for that particular phase.
The contractor shall provide material submittals for all new material and equipment that will be used and installed during this project. Material can be ordered once the submittals are approved by the government. Construction will not begin until all long lead materials are on site.
GENERAL CONSTRUCTION NOTES:
Any references to State Government, Federal Government, or Industry standards or specifications made herein shall form a part of this specification to the extent referenced thereto and all materials and workmanship under this contract shall comply with or exceed these standards and references. All referenced standards shall be the latest edition.
All manufactured equipment and products shall be new materials in good condition and installed as per manufacturer's latest printed instructions, unless specified otherwise herein.
The Contractor is responsible for protection of existing facilities equipment from damage during installation and testing operations.
Contractor shall take into account the special treatment of hazardous waste, as well as the environmental implications related to building demolition management (i.e.
fluorescent lighting tubes, t-stats, etc.). Every effort shall be made to recycle eligible materials, and those not suitable, shall be disposed of off base in accordance with all (SCDHEC) South Carolina Department of Health and Environmental Control regulations. Any refrigerant amounts removed or installed shall be documented and the information shall be provided to Shaw AFB.
Any refrigerant amounts removed or installed shall be documented and the information shall be provided to Shaw AFB.
DDC controls shall be utilized on the new equipment. Contractor shall include the capability to shut down the HVAC system from a central point utilizing the DDC system.
The fresh air damper shall also close and positive notification of the closure shall be provided.
• The design shall ensure that maintenance personnel have complete accessibility to all filters, valves, controllers, or any other devices that require maintenance without having to remove more than one cover per unit. Contractor shall also provide a means for removal and replacement of the air conditioning coil in the air handling unit.
• Electrical Service for HVAC Support: Contractor shall install new wiring and electrical equipment per code for the new mechanical equipment based upon the design parameters (loads) of the new HVAC system.
• Any software used to program the system shall be provided to the government and shall become property of the Government.
The contractor shall include make, model number and inherent operational characteristics on the drawings for all of major equipment supplied for the facility. The Contractor shall supply manufacture's cut sheets with the submittal where the component is identified. If any submittal doesn't, in the opinion of the Contracting Officer, meet or exceed the requirements contained within this SOW, in the Shaw AFB Design Standards or in any referenced design guidance or nationally recognized code then it shall be considered to be unacceptable and returned to the Contractor for correction and resubmission. The Contracting Officer has the option, in lieu of disapproval, to provide acceptance of a submittal with required corrections identified if it is determined the submittal is substantially complete and correct.
Ensure that any demolition, utility cut and capping, and debris removal service performed at Shaw AFB, South Carolina in completed in such a manner that will restore a neat and professional appearance of base areas.
The facility/area shall be cleaned in its entirety, including exterior areas, before being returned the government.
Contractor superintendent cannot be quality controller (CQC) and safety (SSHO) at the same time. Meanwhile, contractor superintendent can be the SSHO. This project requires a full-time contractor superintendent and as needed CQC/SSHO.
WARRANTY:
Contractor shall furnish a minimum one year warranty against defects in material and workmanship starting on the beneficial occupancy date.
GENERAL INFORMATION:
The contractor shall provide all management, tools, supplies, equipment, labor, and applicable licenses and permits necessary to complete the requirements within. All work shall be done in strict accordance with this Statement of Work and subject to the terms and conditions of the contract and in accordance with (UFC) Unified Facilities Criteria, Unified Facilities Guide Specifications (UFGS), the International Building Code (IBC), International plumbing code (IPC), South Carolina Department of Health and Environmental Control (SCDHEC), National Electrical Code (NEC), National Electrical Safety Code (NESC), National Fire Protection Association (NFPA), EPA 402-K-01-001 (2008), South Carolina Department of Transportation (SCDOT), South Carolina Department of Health and Environmental Control (SCDHEC) Shaw Air Force Base Design and Construction Standards, Change 2, 21 Aug 2018 and all other applicable codes.
Contractor is responsible for verifying all dimensions, quantities and square footages.
All dimensions, quantities and square footages included are approximations.
Construction and demolition shall be in strict accordance with the Shaw Air Force Base Design and Construction Standards. The information provided in this Statement of Work (SOW), the provided drawings, and the requirements of the Shaw Air Force Base Design and Construction Standards shall be determined to be the minimum standards required in this project.
The contractor shall video all areas in which work shall occur prior to starting work to include interior and exterior of the project site. UFC's take precedence over all standards, codes and Shaw AFB Design Standards and requirements that pertain to the work within this SOW.
During construction, the contractor shall take care not to damage existing structures, etc. that will not be replaced as part of this contract. Contractor shall be responsible for the temporary support of all devices as required to perform work. Any demolition work that needs to be accomplished to complete the contract is the responsibility of the contractor. All material shall be installed per manufacturers' recommendations. All items listed in the SOW are to be supplied and installed by the contractor unless otherwise noted.
A pre-construction meeting will be held at Shaw AFB to include the Contractor and Government representatives. The Government shall set up this meeting, to be held on Shaw AFB, with the Contractor and Government representatives, to discuss all remodel requirements, as well as any other construction issues the Contractor may have. All finishes shall be presented to the government as submittals for selection and approval prior to installation. All material that could be discontinued shall be on-site, i.e. carpet and tile prior to starting project so there will be no difference in color.
All Contractors shall be responsible for submitting a completed DD1354 (AUG 2022 edition, PDF file) upon completion of each phase with each progress payment request (beginning at 50% construction completion). This form shall be marked "Draft" until the Contractor has reached approximately 90% completion, or when it has been determined that funding will not be adjusted due to modifications. The Contractor shall have a reviewed and accepted DD1354 submitted to the contracting officer representative (2) weeks prior to the scheduled final inspection date (i.e. Placed In Service Date). This reviewed and accepted DD1354 shall be marked "Interim" until the final inspection occurs.
PERMITS:
The contractor shall pay for and obtain any required permits. The contractor shall act in accordance with this Statement of Work, SCDHEC, Federal, and Shaw AFB guidelines.
WORKING CONDITIONS:
The Contractor shall take all precautions to insure that his operations are conducted in a manner as to minimally interfere with the normal operations of the base and the safety and convenience of the base personnel. Standard government work hours in this facility are 0700-1700, 5 days a week. On occasion, the user may work nights and weekend.
Contractor may be required to work nights and weekends on work duties that may be disruptive to the mission. All after hours work shall be coordinated thru the contracting officer representative.
The contractor shall coordinate utility outages with the Civil Engineering Squadron (CE) service call and the user.
ASBESTOS/LEAD BASED PAINT:
There is no asbestos present in the areas the work will occur. Refer to attachment 06 “Ltd Asb Survey Report 3-14-25”
DEBRIS HAULING AND DISPOSAL:
Contractor shall use an approved hauling route to prevent interference with base operations. In order to prevent problems with traffic, noise, wear and tear on roads, or other problems having the potential to adversely affect health, safety, or the environment, the government reserves the right to regulate routes, intervals, delivery points, and times for hauling.
All debris hauled by the contractor shall be enclosed to prevent leaking, spilling, or blowing. The Contractor shall ensure all debris or dirt is promptly removed from any transportation route if such debris is spilled, blown, or leaked from hauling equipment and vehicles. The contractor shall remove all dirt and mud caused by tracks of hauling equipment within one hour of notification by the Government. All demolition debris collected by the contractor shall be housed dumpsters and covered at all times and disposed of in an authorized landfill or transfer station. No disposal or burning is allowed on base. The contractor shall provide the government inspector with an electronic copy of each dump receipt on the following work day by 0800 with the daily report.
DAILY REPORTS:
The contractor shall provide the government with an electronic copy of each dump receipt along with the daily report by 0800 the following work day. All daily reports will be submitted in RAKEN format and shall include pictures of work performed for each day. Daily reports shall be submitted in .pdf with report number and date for the file name (ex. 001 may 2 2022).
Contractors pricing shall take into account all updated code requirements.
END OF STATEMENT OF WORK
The following attachments to the TO apply to this SOW:
Attachment 01 DD 1354 draft Attachment 02 Refrigerant Requirements Attachment 03 Contract Environment Provisions Attachment 04 AF Form 66 Attachment 05 Mechanical Drawings Attachment 06 Asbestos Survey
| NOTE: |
| The Design Schedule shall be as follows: |
| FOR EACH DESIGN: |
| GENERAL CONSTRUCTION NOTES: |
| The contractor shall provide the government with an electronic copy of each dump receipt along with the daily report by 0800 the following work day. All daily reports will be submitted in RAKEN format and shall include pictures of work performed for e... |