(01) Scope of Work land clearing.docx
DOCX document 249 KB Posted
- Solicitation number
- 70Z02926QNEWO0000003
About this file
This is a Scope of Work for land clearing services at U.S. Coast Guard Station Panama City in Panama City, Florida. The contractor must furnish all labor, tools, and equipment necessary to cut and remove overgrown brush in the vicinity of the station entrance. The total contract performance period is 120 calendar days from notice to proceed, with work performed Monday through Friday from 7:00 a.m. to 4:00 p.m. unless otherwise approved. The contractor is responsible for all site safety, including implementation of a comprehensive safety program, barricades, signs, and compliance with federal, state, and local safety regulations. The work location is U.S. Coast Guard Station Panama City, Building 700, 1700 Navy Blvd, Panama City, Florida 32406, with site visit arrangements available through MK1 Dustin Lay at (850) 238-7687 or Dustin.C.Lay@uscg.mil.
The contractor must comply with all Coast Guard and NSA Panama City safety requirements and coordinate all staging and laydown areas in advance with the Coast Guard. Reasonable amounts of electricity and potable water will be provided at no charge, though the contractor bears all connection and disconnection costs and must provide temporary toilet facilities. The contractor is wholly responsible for locating and verifying underground and concealed utilities using electromagnetic and sonic scanning equipment before commencing work. Daily cleanup is mandatory, and the contractor must remove all construction debris and materials from government property in accordance with RCRA and other environmental regulations, including compliance with the Endangered Species Act, Migratory Bird Treaty Act, and National Historic Preservation Act. Final inspection is requested verbally, and submittals including a project schedule and safety plan must be provided for Coast Guard review within 10 working days of receipt.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF18 REQUEST FOR QUOTES.pdf | ||
| Commercial Supplies Services Clauses Provisions FAC 2023-01.doc | DOC document | |
| Wage rate.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT SPECIFICATIONS
Station Land Clearing
AT
UNITED STATES COAST GUARD
Station Panama City, Panama City, FL
PROJECT NUMBER 31557937
February 2026
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1. GENERAL DESCRIPTION
1.1.1. General Work Requirements
This is the detailed portion of the scope of work. For example:
Furnish all labor, tools, equipment for cutting and removal of overgrown brush on Station property at Station Panama City.
The Base Bid work generally includes, but is not limited to, the following:
A. Contractor shall cut and remove overgrown brush in the vicinity of the entrance to the Station property.
1.1.2. SPECIAL WORK REQUIREMENTS
A. Comply with all safety requirements of the Coast Guard unit and NSA Panama City.
B. Coordinate all staging and laydown areas with the Coast Guard prior to work starting.
1.2. TEMPORARY FACILITIES OR UTILITIES
None required.
1.3. PROJECT PERFORMANCE PERIOD
A. The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.
B. The total contract performance period is 120 calendar days.
1.4. LOCATION
The work is located at:
U.S. Coast Guard Station Panama City Building 700 1700 Navy Blvd Panama City, 32406, Florida Arrangements for visiting the site may be made by contacting:
MK1 Dustin Lay Email: Dustin.C.Lay@uscg.mil Telephone: (850)-238-7687
1.5. DRAWINGS ACCOMPANYING SPECIFICATION
There are no drawings accompanying this specification.
1.6. WORK HOURS
1.6.1. Normal Working Hours
A. Perform all work at the site from Monday through Friday from 7:00am to 4:00 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building operations.
B. Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.
1.7. SPECIFIC ENVIRONMENTAL REQUIREMENTS
There are no specific environmental requirements. Refer to section titled Environmental for general environmental requirements.
1.8. SAFETY PROGRAM
1.8.1. General
The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.
1.9. AVAILABILITY OF UTILITY SERVICES
A. Reasonable amounts of the following utilities will be made available to the Contractor without charge.
(1) Electricity, and
(2) Potable Water.
B. The Contractor shall pay all costs incurred in connecting, converting, and transferring the utilities to the work. The contractor shall be responsible for making connections including providing back flow preventers, transformers and for disconnection. The contractor shall provide temporary toilet facilities for their personnel.
1.10. UNDERGROUND AND CONCEALED UTILITIES
A. Any utility locations provided are diagrammatic, not exact.
B. Physically verify the location and elevation of the existing underground and concealed utilities local to the work area. Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.
1.11. UTILITY OUTAGES
Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).
1.12. CONTRACTOR USE OF PREMISES
The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight.
1.13. CLEANUP
The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.
1.14. ENVIRONMENTAL
1.14.1. Protection of the Environment
The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act (MBTA), National Historic Preservation Act (NHPA), the Resource Conservation and Recovery Act (RCRA), and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).
1.14.2. Generated Waste
A. Any waste generated because of the project shall either be recycled or be disposed of in accordance with RCRA requirements.
B. Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with RCRA and all applicable federal, state, and local laws and ordinances.
C. Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.
1.15. DISPOSITION OF MATERIALS
A. All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.
1.16. STORM PROTECTION
The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property. Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.
1.17. RECEIPT OF MATERIALS
The Contractor is responsible to receive all equipment, materials, and supplies.
1.18. DELIVERY AND STORAGE
The Contractor is responsible for the proper transport and storage of all equipment and materials.
1.19. SECURITY
A. Not needed, work to be completed by GCR via NSA Panama City
1.20. FINAL INSPECTION AND ACCEPTANCE
A. Verbal request for final inspection
1.21. WARRANTIES
A. Not applicable
1.22. TRAINING
A. Not applicable
1.23. SUBMITTALS
A. Submittals will be reviewed by the Coast Guard and returned within 10 working days after receipt, unless otherwise stated.
1.24. SUBMITTAL LIST
A. ROSTER OF PERSONNEL
(1) As required by the paragraph titled Security.
B. PROJECT SCHEDULE
(1) Notify Engineering Petty Officer of project schedule changes and any delays.
C. SAFETY PLAN
(1) At a minimum, describe the general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, or similar conditions of the work. Comply with the paragraph titled Safety Program.
D. PRODUCT DATA
(1) Not applicable
1.24.2. OPERATION AND MAINTENANCE MANUALS
A. Submit electronically and provide the following:
(1) Not applicable
-- End of Section --