This is a Request for Quotations document issued by the Port of Corpus Christi Authority (PCCA) for Project No. 26-324A, Oil Dock 10 Drain Pan Liner. The project scope consists of fabricating and fitting a stainless steel drain pan liner and new drain connection at Oil Dock 10 located at 2799 Suntide Road, in accordance with provided construction drawings. The work is located in a restricted area requiring adherence to access requirements specified in technical specification 01 14 13. A mandatory site visit and project review will be held on Wednesday, October 14, 2026, at 9:00 a.m. at Oil Dock 10, requiring advance registration through ProcureWare and TWIC Site Visit Registration Form submission by Tuesday, October 13, 2026, at 3:30 p.m. Informal quotations must be submitted electronically through the PCCA Procurement website at https://pocca.procureware.com by 3:00 p.m. on Friday, October 16, 2026. No quotes will be accepted in person, by email, or facsimile. This is a lump sum contract with liquidated damages assessed at $2,500 per calendar day for each day the project remains substantially incomplete beyond the required completion time.
The lump sum quote must include all labor, supervision, equipment, materials, insurance, overhead, and profit necessary to successfully complete the project. Selected contractors must obtain all required insurance as detailed in General Conditions 3.36 and Special Conditions 1.07, with certificates of insurance approved by the Texas Insurance Commission and submitted within seven calendar days of the Notice of Award. Contractors must commence work within ten calendar days of the Notice to Proceed and comply with PCCA's ISO 14001 certified Environmental Management System Program Requirements. The contractor will be required to obtain identification cards and vehicle decals for restricted area access, with associated costs to be borne by the contractor. Performance and Payment Bonds may be required depending on contract value. PCCA reserves the right to reject any or all responses and to waive irregularities, selecting the response deemed most advantageous to the agency.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATIONS
for
Oil Dock 10 Drain Pan Liner
Port of Corpus Christi Authority Project No. 26-324A
October 2026
Prepared by:
Port of Corpus Christi Authority
Department of Operations
TABLE OF CONTENTS
for
PCCA Project No. 26-324A
Request for Quotations
CONTRACT DOCUMENTS
Quote Form
General Conditions
Special Conditions
Technical Specifications
Construction Drawings
Agreement
REQUEST FOR QUOTATIONS
PCCA Project No. 26-324A
To Interested Contractors:
The Port of Corpus Christi Authority (PCCA) requests quotations for our Oil Dock 10
Drain Pan Liner project. The project scope generally consists of fabricating and fitting a stainless steel drain pan liner and new drain connection at Oil Dock 10 per the construction drawings. This is a Restricted Area, therefore, Contractor must follow restricted access requirements as stated in technical specification 01 14 13 Access to Port Authority Property.
The PCCA Project Manager will host a site visit and review project requirements with interested Contractors at Oil Dock 10 located at 2799 Suntide Rd., on Wednesday, October 14, 2026, at 9:00 a.m.
This site visit will take place in a TWIC-secured area, and advance registration is required. Contractors planning to attend must register through ProcureWare and complete and submit the TWIC Site Visit Registration Form, available under Bid Events in ProcureWare, no later than Tuesday, October 13, 2026, at 3:30 p.m. to obtain access to the project site.
The Port of Corpus Christi Authority (PCCA) will accept Informal Quotations for Oil
Dock 10 Drain Pan Liner until 3:00 PM on Friday, October 16, 2026, via the PCCA Procurement website https://pocca.procureware.com.
This is a lump sum contract, and prices must include all labor, supervision, equipment, materials, insurance, overhead and profit, etc., to successfully complete the project. Interested
Contractors shall complete and submit their response on the Quote Form included. The Quote
Form must be signed by an authorized representative of the Contractor.
By submitting a Quote, the Contractor acknowledges the following:
A. The lump sum quote must include all labor, supervision, equipment, materials, insurance, overhead, and profit, etc., to successfully complete the project. By submitted a quote, the interested Contractor represents that it has thoroughly examined and become familiar with the work required in this request for quotes and that it is capable of performing quality work to successfully achieve the objectives of the PCCA.
B. The PCCA is a ISO 14001 certified, and the Contractor will be required to adhere to PCCA policies and procedures while working on PCCA property. The PCCA’s
Environmental Management System Program Requirements, outlining the policies and procedures are included in this Quote package.
C. Selected Contractor will not commence work until the contractor has obtained all the insurance requirements as detailed in General Conditions 3.36 and Special
Conditions 1.07 and certificates of such insurance are approved by, and on file with, the Texas Insurance Commission, and must be reasonably acceptable in https://pocca.procureware.com/ their content to PCCA. Contractors will be required to submit a Certificate of Insurance within seven (7) calendar days of the date of the written Notice of Award of Contract.
D. If awarded the contract, the Contractor hereby agrees to commence work under this contract within ten (10) calendar days of the date of the written Notice to Proceed and to complete the project as detailed in Special Conditions. The Contractor specifically acknowledges and agrees to provisions in the General and Special Conditions and the Agreement, under which damages may be assessed for failure to complete the work within the required completion time.
E. Any qualifications or exceptions to the requirements of these Contract Documents may cause the Quote to be rejected.
F. The PCCA reserves the right to reject any or all responses and to waive irregularities contained therein and to accept any response deemed most advantageous to the PCCA.
All quotes must be received through the PCCA’s electronic procurement system website at https://pocca.procureware.com by 3:00 PM on Friday, October 16, 2026. Quotes will not be accepted in person, by e-mail, or by facsimile. Quotes received after the instructed time will not be accepted. If you have any questions, please submit all questions through the electronic procurement system. The PCCA looks forward to receiving your quotation.
QUOTATION FORM
FOR
Oil Dock 10 Drain Pan Liner (26-324A)
Company Name:
Point of Contact Name:
Contact Number:
Email Address:
Scope of Work:
Scope of Work consists of fabricating and fitting a stainless steel drain pan liner and new drain connection at Oil Dock 10.
Liquidated Damages: Liquidated Damages in the amount of $2,500 per calendar day will be assessed against the Contractor for each day beyond the required completion time that the project remains substantially incomplete.
Total Amount – Lump Sum Quote $
Calendar Days to complete the work Days To be provided in 7-day increments, see Special Conditions 1.05.
Number of days after Notice to Proceed until you can start Days
Addendum (if applicable):
Bidder acknowledges receipt of the following addenda: (List Addendum Number(s))
We request quotes be received through the PCCA’s electronic procurement system website at https://pocca.procureware.com by 3:00 PM on Friday, October 16, 2026. Quotes will not be accepted in person, by e-mail, or by facsimile. Quotes received after the instructed time will not be accepted. If you have any questions, please submit all questions through the electronic procurement system.
By signature below, the individual acknowledges they are a signatory official with authority to bind Vendor to a contract, and confirms the correct forms are being submitted with this Quote as identified in the Request for Quotation documents and addenda (if any) as acknowledged.
Submitted by (Print) Title
Signature Date
GENERAL CONDITIONS
Revised March 2024
248742-Revised March 2024
TABLE OF CONTENTS
ARTICLE 1
DEFINITION OF TERMS
1.01 Addenda
1.02 Additive Bid
1.03 Agreement or Contract
1.04 Alternate Bid
1.05 Alternative Item
1.06 Base Bid
1.07 Bid
1.08 Bid Breakdown Sheet
1.09 Calendar Day
1.10 CERCLA
1.11 Change Order
1.12 Claim
1.13 Construction Drawings
1.14 Contract Documents
1.15 Contractor
1.16 Contractor’s Daily Report
1.17 Deductive Bid
1.18 Dispute
1.19 Engineer
1.20 Equal or Approved Equal
1.21 Evaluated Bid
1.22 Extra Work
1.23 Field Order
1.24 Final Acceptance
1.25 Final Statement
1.26 Horizontal Control
1.27 Notice of Award of Contract
1.28 Notice of Intent to Protest
1.29 Notice of Nonconformance
1.30 Notice to Proceed
1.31 Owner
1.32 PCCA
1.33 PCCA Authorized Contract Representative…
1.34 PCCA Construction Representative…
1.35 PCCA Property
1.36 Port Commission
1.37 Principal Officers of Contractor
1.38 Project
1.39 Publications
1.40 RCRA
1.41 Special Conditions
1.42 Statement of Accounts
1.43 Subcontractor
1.44 Substandard Performance
1.45 Substantial Completion
1.46 Technical Specifications
1.47 Unilateral Change Order
1.48 Unit Cost
1.49 Value Engineering Proposal
1.50 Vertical Control
1.51 Work
ARTICLE 2
RESPONSIBILITIES OF ENGINEER
OR CONTRACTOR
2.01 PCCA Construction Representative–Engineer Relationship
2.02 Inspection by PCCA Construction Representative
2.03 Payments for Work
2.04 Dispute Determinations
2.05 Horizontal and Vertical Control
2.06 Contractor’s Duty and Superintendence
2.07 Contractor’s Understanding
2.08 PCCA’s Policies and Procedures
2.09 Character of Workmanship
2.10 Drug–Free Workplace
2.11 Security Access Requirements
2.12 Access and Storage
2.13 Sanitation
2.14 Work and Materials
2.15 Shop Drawings
2.16 Preliminary Approval
2.17 Defects and Their Remedies
2.18 Changes and Alterations
2.19 Barricades and Warnings
2.20 Storm Water Pollution Prevention Plan
2.21 Site Conditions
2.22 Utilities
2.23 Testing, Inspection, and Control
2.24 Contractor’s Daily Reports
2.25 Debris
2.26 Environmental Policy
2.27 Prevailing Wage Rates
ARTICLE 3
GENERAL OBLIGATIONS AND RESPONSIBILITIES
3.01 Bid Exceptions, Deviations, or Qualified Bids
3.02 Conflict of Interest
3.03 Requests for Clarifications
3.04 Correspondence
3.05 Written Notice
3.06 Approved Equal
3.07 Titles or References
3.08 Award of Contract
3.09 Bid Protest Procedure
3.10 Notice to Proceed
3.11 Safety and Environmental Record
3.12 Construction Drawings and Technical Specifications
3.13 Ownership of Construction Drawings and Technical Specifications
3.14 Adequacy of Design
3.15 Value Engineering Proposals
3.16 Right of Entry
3.17 Collateral Contracts
3.18 Discrepancies and Omissions
3.19 Equipment, Materials, and Construction Plant
3.20 Protection Against Accidents
3.21 Performance and Payment Bonds
3.22 Losses from Natural Causes
3.23 Protection of Existing Equipment, Structures, and Utilities
3.24 Protection of Adjoining Properties and Facilities
3.25 Smoking Policy
3.26 Misplaced Material
3.27 Signal Lights
3.28 Channel Traffic
3.29 Physical Data
3.30 Protection against Claims of Subcontractors, Laborers, Materialmen, and Furnishers of Machinery, Equipment, and Supplies
3.31 Protection Against Royalties or Patented Inventions
3.32 Laws and Ordinances
3.33 Taxes
3.34 Assignment and Subletting
3.35 Indemnification and Release
3.36 Insurance
3.36.1 Certificate of Insurance
3.36.2 Waiver of Subrogation
3.36.3 Workers’ Compensation Insurance Coverage
3.37 Schedule
3.38 Damages for Delay
3.39 Liquidated Damages
3.40 Permits
ARTICLE 4
PROSECUTION AND PROGRESS
4.01 Time and Order of Completion
4.02 Extension of Time
4.03 Ozone Action Days
4.04 Hindrances and Delays
4.05 Suspension of Work
4.06 Termination of Agreement
4.07 Differing Site Conditions
ARTICLE 5
MEASUREMENT AND PAYMENT
5.01 Quantities and Measurements
5.02 Estimated Quantities
5.03 Changes in Quantity
5.04 Price of Work
5.05 Progress Payments and Retainage
5.06 Use of Completed Portions
5.07 Notice of Substantial Completion
5.08 Final Acceptance
5.09 Final Payment
5.10 Payments Withheld
5.11 Guarantee
ARTICLE 6
EXTRA WORK AND CLAIMS
6.01 Change Orders
6.02 Minor Changes
6.03 Extra Work
6.04 Time of Filing Construction Claims
ARTICLE 7
MEDIATION/ARBITRATION
7.01 Mediation
7.02 Arbitration
ARTICLE 8
ABANDONMENT
8.01 Abandonment by Contractor
8.02 Abandonment by PCCA
REVISION HISTORY ..................................................................................................... (3 pages)
48742 – Revised March 2024 General Conditions
1/46 | P a g e
ARTICLE 1
DEFINITION OF TERMS
The terms defined in this Article I will apply throughout these General Conditions. All references in the General Conditions to “Section” or “Article” will refer to a section or article of these General Conditions, unless otherwise expressly stated. All references to “herein,”
“hereof,” “hereto,” “hereunder,” or similar terms will be deemed to refer to the entire General
Conditions. The headings of Articles and Sections in these General Conditions are for convenience only and will not affect the interpretation hereof.
1.01 ADDENDA. Any written interpretation or change to the Contract Documents made by
PCCA prior to the opening of Bids.
1.02 ADDITIVE BID. If called for in the Bid, it is the amount stated for any Work to be priced separately from the Base Bid, which Work can be added at the option of PCCA.
1.03 AGREEMENT OR CONTRACT. The written contract for the Project executed after the
Notice of Award of Contract is issued.
1.04 ALTERNATE BID. If called for in the Bid, it is the amount stated for Work to be performed in place of the Base Bid.
1.05 ALTERNATIVE ITEM. Any item the bidder proposes to substitute for a comparable item specified in the Contract Documents.
1.06 BASE BID. The amount stated for performing all of the Work specified in the Contract
Documents that is not specifically identified as an Additive, Deductive, or Alternate Bid item.
1.07 BID. PCCA form on which the bidder sets forth the Base Bid and any Additive or
Deductive Bid Items or Alternate Bid for the Work specified in the Contract Documents, which must be submitted by the date and time stated in the Notice of Solicitation.
1.08 BID BREAKDOWN SHEET. The document that allows PCCA to establish values for the individual items of the Work in order to more easily resolve modifications to the
Contract Documents.
1.09 CALENDAR DAY. Any day of the week or month; no days being excepted. Unless otherwise specified, all PCCA contracts will be done on a calendar-day basis.
Accordingly, where the term “day” is used herein by itself, it means a Calendar Day.
1.10 CERCLA. The Comprehensive Environmental Response, Compensation, and Liability
Act of 1980, 42 USC § 9601 et seq.
1.11 CHANGE ORDER. PCCA form signed by PCCA Construction Representative, Engineer and Contractor that adds to, deletes from, or otherwise changes any part of the
Work or the Project.
48742 – Revised March 2024 General Conditions
2/46 | P a g e
1.12 CLAIM. A written notice received by the PCCA Authorized Contract Representative that a person or entity asserts entitlement to damages arising from the Project.
1.13 CONSTRUCTION DRAWINGS. The drawings to be used for the bidding and construction of the Project.
1.14 CONTRACT DOCUMENTS.
A. The instruments listed in this section and used by PCCA to take Bids for and implement construction of the improvements authorized by the Port Commission, which instruments are incorporated herein by reference:
1. Bid Form
2. Bid Breakdown Sheet
3. General Conditions
4. Special Conditions
5. Construction Drawings (if any)
6. Technical Specifications (if any)
7. Agreement
8. Texas Statutory Performance and Payment Bonds (if any)
9. Certificates of Insurance
10. Contractor’s Statement of Experience
11. Local Preference Program Acknowledgement Form
12. Conflict of Interest Questionnaire
13. Addenda to the Contract Documents (if any)
14. Change Order(s) (if any)
15. Unilateral Change Order(s) (if any)
16. Field Order(s) (if any)
B. The Contract Documents are complementary, and what is called for by any one will be as binding as if called for by all. In case of conflict between any of the
Contract Documents, priority of interpretation will be in the following order (from the highest to the lowest):
1. Unilateral Change Order(s)
2. Change Order(s)
3. Field Order(s)
4. Agreement
5. Bid Form
6. Addenda to Contract Documents
7. Special Conditions
8. Construction Drawings
9. Technical Specifications
10. General Conditions
11. Bid Breakdown Sheet
12. Texas Statutory Performance and Payment Bonds
13. Certificates of Insurance
14. Contractor’s Statement of Experience
15. Local Preference Program Acknowledgement Form
16. Conflict of Interest Questionnaire
48742 – Revised March 2024 General Conditions
3/46 | P a g e
1.15 CONTRACTOR. Contractor is that person or organization identified as such in the
Agreement.
1.16 CONTRACTOR’S DAILY REPORT. A report prepared by Contractor and submitted to
PCCA Construction Representative that provides required information on the progress of the Project.
1.17 DEDUCTIVE BID. If called for in the Bid, it is the amount separately stated for any
Work to be deducted from the Base Bid.
1.18 DISPUTE. Any unresolved issue regarding the Work included in the Contract
Documents after a written decision is made by PCCA Construction Representative.
1.19 ENGINEER. Under the Texas Engineering Practice Act, only duly licensed persons may legally perform, or offer to perform engineering services for the public. Furthermore, public works must be designed and constructed under the direct supervision of a licensed professional engineer. Engineer is identified in the Special Conditions. If Engineer is a
PCCA employee, Engineer may also concurrently serve as Authorized Contract
Representative.
1.20 EQUAL OR APPROVED EQUAL. Any item approved by PCCA Construction
Representative and/or Engineer to be substituted for the item specified in the Contract
Documents.
1.21 EVALUATED BID. The incorporation of the Base Bid plus the unit cost additive or deductive bid items into a theoretical formula that represents a possible project scenario.
This allows the unit price items as well as the Base Bid to be evaluated to determine the most competitive bid submitted.
1.22 EXTRA WORK. All Work that may be required by PCCA Construction Representative to be done by Contractor to accomplish any change, alteration, or addition to the Work shown on the Construction Drawings or reasonably implied by the Technical
Specifications and not covered by Contractor’s Bid, except as provided under Section
2.18, “Changes and Alterations,” herein.
1.23 FIELD ORDER. PCCA form issued by PCCA Construction Representative which indicates any minor change in the Project consistent with the overall intent of the
Contract Documents and which does not involve an increase or decrease in the
Agreement price or schedule.
1.24 FINAL ACCEPTANCE. That point in the Project wherein PCCA Authorized Contract
Representative considers the Project complete and PCCA issues a Certificate of Final
Acceptance.
48742 – Revised March 2024 General Conditions
4/46 | P a g e
1.25 FINAL STATEMENT. A written statement prepared by PCCA Construction
Representative upon completion of the Project that sets forth the value of all Work performed, and materials furnished for the Project under the terms of the Agreement.
1.26 HORIZONTAL CONTROL. A system located in the field that provides a point of horizontal reference for all Work described in the Contract Documents.
1.27 NOTICE OF AWARD OF CONTRACT. A letter issued to Contractor whose Bid has been accepted by the Port Commission.
1.28 NOTICE OF INTENT TO PROTEST. A document prepared by the bidder and delivered to PCCA’s Director of Procurement Services when the bidder chooses to protest the bidding process or contract award.
1.29 NOTICE OF NONCONFORMANCE. A written report issued by PCCA Construction
Representative in the event PCCA Construction Representative or Engineer finds improper work or substandard workmanship in connection with the Project.
1.30 NOTICE TO PROCEED. A letter issued by PCCA Authorized Contract Representative to Contractor once all Contract Documents have been executed and approved by PCCA.
1.31 OWNER. The Owner referred to in these documents is the Port of Corpus Christi
Authority of Nueces County, Texas.
1.32 PCCA. The Port of Corpus Christi Authority of Nueces County, Texas, which may also be referred to as Owner in the Contract Documents.
1.33 PCCA AUTHORIZED CONTRACT REPRESENTATIVE. PCCA representative for the
Contract authorized to issue Notice to Proceed, Notice of Substantial Completion, Notice of Final Acceptance, and who shall assist in resolving disputes that may arise during the construction process. The Authorized Contact Representative is identified in the Special
Conditions.
1.34 PCCA CONSTRUCTION REPRESENTATIVE. PCCA’s duly authorized representative responsible for coordination, oversight and managing the construction process. The
Construction Representative is identified in the Special Conditions.
1.35 PCCA PROPERTY. Any land, structure, equipment, or other improvement owned by
PCCA.
1.36 PORT COMMISSION. The governing board of PCCA.
1.37 PRINCIPAL OFFICERS OF CONTRACTOR. Those persons representing Contractor who have the express or legal authority to contract with PCCA.
1.38 PROJECT. The Work that is described and specified in the Contract Documents.
48742 – Revised March 2024 General Conditions
5/46 | P a g e
1.39 PUBLICATIONS. Any codes, standards, or specifications referred to in the Contract
Documents.
1.40 RCRA. The Resource Conservation and Recovery Act of 1996, 42 USC § 6901 et seq.
1.41 SPECIAL CONDITIONS. The document that details those circumstances individual or particular to a project. If in conflict with the General Conditions, the Special Conditions will govern.
1.42 STATEMENT OF ACCOUNTS. A final written accounting of all costs required to complete the Project after abandonment by Contractor or PCCA.
1.43 SUBCONTRACTOR. Except as separately defined herein relative to Workers’
Compensation insurance coverage, “Subcontractor” means only those persons or entities having a direct contract with Contractor or one who furnishes material worked to a special design according to the Construction Drawings or Technical Specifications of the
Contract Documents but does not include one who merely furnishes material not worked to a special design. A list of all Subcontractors must be submitted with the Bid, and the list must be approved by PCCA Construction Representative prior to starting Work.
Approval of Subcontractors by PCCA Construction Representative does not relieve
Contractor of Contractor’s responsibility for the Work.
1.44 SUBSTANDARD PERFORMANCE. Any Work by Contractor or any Subcontractor or supplier that, in the opinion of PCCA Construction Representative or Engineer, is unacceptable or is not conducive to successful completion of the Project.
1.45 SUBSTANTIAL COMPLETION. That point in the Project wherein PCCA Construction
Representative determines that the Project is suitable for use or occupancy for its intended purpose but may still require minor miscellaneous Work or adjustment.
1.46 TECHNICAL SPECIFICATIONS. The specifications provided by Engineer to be used for the bidding and construction of the Project.
1.47 UNILATERAL CHANGE ORDER. A Change Order issued by PCCA Construction
Representative when agreement cannot be reached with Contractor on the price to be paid or other changes to the Project that are in dispute.
1.48 UNIT COST. Cost for each item of work.
1.49 VALUE ENGINEERING PROPOSAL. A proposal prepared by Contractor and submitted to PCCA regarding a change in the design shown in the Contract Documents.
Value Engineering Proposals that include design revisions shall include design documents that are prepared by a licensed professional engineer.
1.50 VERTICAL CONTROL. A system located in the field that provides a point of vertical reference for all Work described in the Contract Documents.
48742 – Revised March 2024 General Conditions
6/46 | P a g e
1.51 WORK. Any construction, repair, or alteration described in the Contract Documents.
ARTICLE 2
RESPONSIBILITIES OF PCCA, ENGINEER
AND CONTRACTOR
2.01 PCCA CONSTRUCTION REPRESENTATIVE – ENGINEER RELATIONSHIP.
PCCA Construction Representative is an employee of PCCA, and the person Engineer designates as PCCA’s representative during construction. The duties, responsibilities, and authority of PCCA Construction Representative as PCCA’s representative during construction are set forth in the Contract Documents and may not be extended or limited without written consent of PCCA. All of PCCA’s instructions to Contractor will be issued through PCCA Construction Representative.
2.02 FIELD OBSERVATION. PCCA Construction Representative, Engineer, and/or
Engineer’s authorized agent will make periodic visits to the Project site to familiarize themselves with the progress of the executed Work and to determine if such Work generally meets the essential performance and design features and technical and functional engineering requirements of the Contract Documents. PCCA Construction
Representative and/or Engineer, however, are not responsible for making any detailed, exhaustive, comprehensive, or continuous on-site inspection of the quality or quantity of the Work; nor are PCCA Construction Representative or Engineer in any way responsible, directly or indirectly, for Contractor’s construction means, methods, techniques, sequences, quality, procedures, programs, safety precautions, or lack of same, incident to or in connection with the Work. Notwithstanding any other provision of the
Agreement or any other contract document, PCCA Construction Representative and/or
Engineer are not in any way responsible or liable for any acts, errors, omissions, or negligence of Contractor.
2.03 PAYMENTS FOR WORK. In accordance with the Contract Documents, Contractor will submit requests for progress payments to PCCA Construction Representative. Any request for updated project schedule should be submitted within three (3) calendar days from date requested. Failure to submit updated project schedules may cause progress payments to be delayed. PCCA Construction Representative will review Contractor’s requests for progress payments and supporting data, determine the amount owed to
Contractor, and approve, in writing, payment to Contractor of such amount. Such approval of payment to Contractor constitutes a representation to PCCA of PCCA
Construction Representative’s professional judgment that the Work has progressed to the point indicated to the best of PCCA Construction Representative’s knowledge, information, and belief; but such approval of an application for payment to Contractor is not a representation by PCCA Construction Representative that PCCA Construction
Representative has made any examination to determine how or for what purpose
Contractor has used the moneys paid Contractor pursuant to the Agreement.
2.04 DISPUTE DETERMINATIONS. All Claims, Disputes, and other matters in question between Contractor and PCCA relating to the execution or progress of the Work or the interpretation of the Contract Documents will first be decided by PCCA Construction
48742 – Revised March 2024 General Conditions
7/46 | P a g e
Representative; and PCCA Construction Representative's decision will be rendered in writing within a reasonable time after notice to PCCA of any Dispute. Should PCCA
Construction Representative fail to make such decision within a reasonable time, mediation/arbitration pursuant to Article 7, “Mediation/Arbitration,” herein, may be demanded as if PCCA Construction Representative’s decision had been rendered against the party demanding mediation/arbitration.
If PCCA Construction Representative renders any decision that in the opinion of
Contractor is not in accordance with the meaning and intent of the Agreement, Contractor must file with PCCA’s Construction Representative and Authorized Contract
Representative, within thirty (30) days after the date of PCCA’s Construction
Representative’s decision, Contractor’s written objection to the decision and, by such action, reserve the right to submit the Dispute to mediation/arbitration as hereinafter provided in Article 7, “Mediation/Arbitration.” Contractor’s written objection must state all of the grounds upon which the objection is made.
2.05 HORIZONTAL AND VERTICAL CONTROL. Unless otherwise specified, benchmarks for Vertical Control and a baseline for Horizontal Control will be as indicated on the
Construction Drawings or furnished by PCCA Construction Representative. Contractor will use these controls to establish other lines and grades as indicated on the Construction
Drawings. All such Horizontal or Vertical Controls will be preserved by Contractor, and in case of destruction or removal by Contractor or Contractor’s employees, said controls may be replaced by PCCA at Contractor’s expense.
2.06 CONTRACTOR’S DUTY AND SUPERINTENDENCE. Contractor will give adequate attention to the faithful prosecution and completion of the Project and will keep a competent superintendent and any necessary assistants on the Project during its progress.
This superintendent must be present during any Work, whether subcontracted or not. The superintendent will represent Contractor in Contractor’s absence, and all directions given to the superintendent will be as binding as if given to Contractor.
Contractor is an independent contractor, solely responsible for the manner and method of completing Contractor’s Work under the Agreement, with the authority to select the means, method, and manner of performing such Work so long as such methods do not adversely affect the Work or the improvements on the Project, PCCA, and Engineer being interested only in the result obtained and conformity of the improvements on the
Project to the Contract Documents.
All Work performed for Contractor by a Subcontractor or supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or supplier, which specifically binds the Subcontractor or supplier to the applicable terms and conditions of the Contract Documents for the benefit of PCCA. Whenever any such agreement is with a Subcontractor or supplier who is listed as an additional insured on the insurance provided in Section 3.36, “Insurance,” the agreement between Contractor and the
Subcontractor or supplier will contain provisions whereby the Subcontractor or supplier waives all rights against PCCA, Contractor, PCCA Construction Representative, PCCA
Authorized Contract Representative, Engineer, Engineer’s consultants, and all other
48742 – Revised March 2024 General Conditions
8/46 | P a g e individuals or entities identified in these General Conditions to be listed as insureds or additional insureds (and the officers, directors, partners, employees, agents, and other consultants and Subcontractors of each and any of them) for all losses and damages caused by, arising out of, relating to, or resulting from any of the perils or causes of loss covered by such policies and any other insurance applicable to the Work. If the insurers on any such policies require separate waiver forms to be signed by any Subcontractor or supplier, Contractor will obtain the same.
Engineering Construction Drawings and Technical Specifications, as well as any additional information concerning the Work, passing from or through PCCA may not be interpreted as requiring or allowing Contractor to deviate from the Construction
Drawings and Technical Specifications, the intent of such Construction Drawings, Technical Specifications, and any other such instruction being to define with particularity the Work Contractor is to perform. Contractor is responsible, at Contractor’s expense, for design, construction, installation, and use or nonuse of all items and methods incident to performance of the Agreement and for all loss, damage, or injury incident thereto, either to person or property, including without limitation the adequacy of all temporary supports, shoring, bracing, scaffolding, machinery, equipment, safety precautions or devices, and similar items or devices used by Contractor for the Project.
Any review of Work in progress, any visit or observation during construction, or any clarification of Construction Drawings and Technical Specifications by PCCA
Construction Representative or any agent, employee, or representative of Engineer, PCCA Construction Representative or PCCA, whether through personal observation at the Project site or by means of approval of shop drawings for temporary construction or construction processes or by other means or method, is agreed by Contractor to be for the purpose of observing the extent and nature of Work completed or being performed as measured against the Construction Drawings and Technical Specifications constituting the Contract Documents or for the purpose of enabling Contractor to more fully understand the Construction Drawings and Technical Specifications so that the Work will conform thereto. Review by PCCA Construction Representative, Engineer or PCCA in no way relieves Contractor from responsibility for the proper performance of
Contractor’s Work on the Project, including without limitation the propriety of means and methods of Contractor in performing the Work and the adequacy of any designs, Construction Drawings, Technical Specifications, or other facilities for accomplishing such performance. Deviation by Contractor from Construction Drawings and Technical
Specifications that may have been in evidence during any visitation or observation by
PCCA Construction Representative, Engineer or any of Engineer’s representatives, whether called to Contractor’s attention or not, in no way relieves Contractor of
Contractor’s responsibility to complete all Work in accordance with said Construction
Drawings and Technical Specifications.
2.07 CONTRACTOR’S UNDERSTANDING. Subject to General Conditions Section 4.07, Contractor has, by careful examination, become satisfied as to the nature and location of the Work; the conformation of the ground; the character, quality, and quantity of the materials to be encountered; the character of equipment and facilities needed preliminary to and during the prosecution of the Work; the general and location conditions; and all
48742 – Revised March 2024 General Conditions
9/46 | P a g e other matters which can in any way affect the Work under the Agreement. No verbal agreement or conversation with any officer, agent, or employee of PCCA, PCCA
Authorized Contract Representative, PCCA Construction Representative or Engineer, either before or after the execution of the Agreement, affects or modifies any of the terms or obligations contained in the Contract Documents.
2.08 PCCA’S POLICIES AND PROCEDURES. The Contractor is required to follow all of
PCCA’s policies and procedures as described in Specification 00 73 10, “PCCA Policies
& Procedures,” of the Technical Specifications.
2.09 CHARACTER OF WORKMANSHIP. Contractor agrees to employ only orderly and competent workers, skilled in the performance of the type of Work required by the
Agreement, to do the Work, and agrees that whenever PCCA Construction
Representative informs Contractor in writing that any worker on the Project is, in PCCA
Construction Representative’s opinion, not an acceptable worker, such worker will be discharged from the Project and will not again be employed on the Project without PCCA
Construction Representative written consent. This section is applicable to craftsmen, laborers, foremen, superintendents, project managers, and Subcontractors. Contractor is responsible for the workmanship, errors, and omissions of all such persons. All materials and equipment must be installed, and all Work completed in a workmanlike manner by craftsmen skilled in the work they perform.
2.10 DRUG-FREE WORKPLACE. PCCA is a drug-free workplace, and Contractor and
Contractor’s employees as well as Contractor’s Subcontractors and the employees of
Contractor’s Subcontractors must adhere to the requirements of Federal Acquisition
Regulation 52.223-6, “Drug-Free Workplace,” and the Drug-Free Workplace Act of
1988. Any employee of Contractor or Contractor’s Subcontractors may be discharged from the Project if that employee is found to be in violation of these laws or regulations.
The final decision concerning the acceptance or non-acceptance of any employee on the
Project will be determined solely by PCCA Construction Representative.
2.11 SECURITY ACCESS REQUIREMENTS. Due to increased national security concerns and new security regulations, PCCA has revised its Tariff to designate certain areas of the port as “restricted areas” and to address policies and procedures for access to those restricted areas. Contractor should be aware that Contractor will be required to obtain ID cards and vehicle decals for any personnel requiring access to these areas. This procedure will involve criminal background checks as well as costs for the ID cards and decals. These costs will be at Contractor’s expense and should be included in
Contractor’s Bid. For detailed information on the new security requirements, Contractor should review Specification 01 14 13, “Access to Port Authority Property (Tariff Item
669).” Contractor is required to follow all policies and procedures in said Specification
01 14 13.
PCCA reserves the right at any time to increase or decrease its security level as determined by PCCA or mandated by state or federal regulations or authorities, and to deny access to restricted areas to any individual or company based upon the security level in place. Changes in security levels could affect, limit, or stop any or all personnel access
48742 – Revised March 2024 General Conditions
10/46 | P a g e or construction activity at PCCA. If Work is stopped for a period of time totaling five days or less during the course of the contract, then no additional compensation will be due Contractor. If Work is stopped for more than five days, then PCCA and Contractor will enter into good faith negotiations for agreement as to Contractor’s actual costs of the
Work stoppages to be paid by PCCA. In either case, PCCA will grant a day-for-day extension of time for security-induced stoppages as they affect the time of completion required under this contract.
2.12 ACCESS AND STORAGE. PCCA may designate entrance points, parking areas, and work and storage areas to be used by Contractor. The building of structures for housing workers or the erection of tents or other forms of protection will be permitted only at such places as PCCA Construction Representative directs, and the sanitary conditions of the grounds in and about such structures will be at all times maintained in a manner satisfactory to PCCA Construction Representative.
2.13 SANITATION. Contractor will provide sanitary conveniences for use by Contractor’s personnel. Contractor will locate these conveniences in such manner and at locations approved by PCCA Construction Representative. Contractor’s personnel may not use
PCCA’s facilities without the approval of PCCA Construction Representative.
2.14 WORK AND MATERIALS. Contractor will provide and pay for all materials, supplies, machinery, equipment, tools, superintendence, labor, services, insurance, water, light, power, fuel, transportation, and facilities specified or necessary for the execution and completion of the Work. Unless otherwise specified, all materials must be new; and both workmanship and materials must be of good quality. Contractor will, if required, furnish satisfactory evidence as to the kind and quality of materials. Unless otherwise stated in the Contract Documents, words or phrases that have a well-known technical or construction industry trade meaning are used in the Contract Documents in accordance with such recognized meaning. Materials or Work described in words that have a well-known technical or trade meaning will be equal to the standards established by such description.
2.15 SHOP DRAWINGS. Unless otherwise specified, Contractor will submit to PCCA
Construction Representative promptly, and so as not to delay Contractor’s Work or that of any other contractor on the Project, checked copies of all shop and setting drawings and schedules required for the Work, and PCCA Construction Representative and/or
Engineer will review them with reasonable promptness, making desired corrections.
Contractor will promptly make any corrections required and file corrected copies with
PCCA Construction Representative. PCCA Construction Representative/Engineer’s review or approval of such drawings or schedules does not relieve Contractor from responsibility for deviations from Construction Drawings or Technical Specifications unless Contractor has in writing called PCCA Construction Representative’s attention to such deviations at the time of submission, nor will it relieve Contractor from responsibility for errors or omissions of any kind in shop drawings or schedules. It is the
Contractor’s responsibility to review all shop drawings to ascertain their effect on
Contractor’s ability to perform the Work in accordance with the Construction Drawings and Technical Specifications within the time stated in the Contract Documents.
48742 – Revised March 2024 General Conditions
11/46 | P a g e
Review of Construction Drawings or schedules by PCCA Construction Representative or
Engineer is for the sole purpose of determining the sufficiency of the drawings or schedules to achieve finished improvements in conformity with the Construction
Drawings and Technical Specifications, and does not relieve Contractor of Contractor’s duty as an independent contractor; nor does PCCA Construction Representative or
Engineer by such review assume any duty to review or approve the propriety or adequacy of such Construction Drawings or schedules or any means or methods reflected in the same in relation to the safety of either person or property during Contractor’s performance.
2.16 PRELIMINARY APPROVAL. Neither PCCA Construction Representative nor
Engineer have the power to waive the obligations of Contractor under the Agreement.
Failure or omission of PCCA Construction Representative or Engineer to discover, object to, or condemn any defective Work or material does not release Contractor from the obligation to fully and properly perform the Agreement, including without limitation the obligation to at once tear out, remove, and properly replace defective Work or materials at any time prior to Final Acceptance, upon the discovery of said defective Work or materials. PCCA Construction Representative will, however, upon written request of
Contractor, inspect and accept or reject any material furnished; and such acceptance is binding on PCCA unless it can be clearly shown that such material furnished does not meet the Technical Specifications.
Any questioned Work may be ordered taken up or removed for reexamination by PCCA
Construction Representative prior to Final Acceptance. If found not in accordance with the Contract Documents for said Work, all expenses of removing, reexamination, and replacement will be borne by Contractor. Otherwise, such expense will be allowed as
Extra Work and paid for by PCCA, provided that where inspection or approval is specifically required by the Contract Documents prior to performance of certain Work, and should Contractor proceed with such Work without requesting prior inspection or approval, Contractor will pay all expenses of taking up, removing, and replacing this
Work if so directed by PCCA Construction Representative.
2.17 DEFECTS AND THEIR REMEDIES. If the Work or any part thereof or any material brought on the site of the Work for use in the Project, or selected for the same, is deemed by PCCA Construction Representative as unsuitable or not in conformity with the
Construction Drawings and Technical Specifications, Contractor must, at Contractor’s expense, after receipt of a Notice of Nonconformance from PCCA Construction
Representative, forthwith remove such material and rebuild or otherwise remedy such
Work so that it complies with the Agreement.
2.18 CHANGES AND ALTERATIONS. PCCA, in its sole discretion, may make such changes and alterations in the line, grade, form, dimension, plan or material for the Work, or any part thereof, either before or after the beginning of the construction, without affecting the validity of the Agreement between PCCA and Contractor.
48742 – Revised March 2024 General Conditions
12/46 | P a g e
If changes or alterations decrease the amount of Work to be done, Contractor may make a
Claim for damages for the Work that may be eliminated, except as provided in Article 5, “Measurement and Payment.” If the amount of Work is increased and the Work can fairly be classified as such under the Technical Specifications, such increase will be paid for according to the quantity actually done and at the unit price, if any has been established for such Work under the Agreement, except as provided in Article 5, “Measurement and Payment.” Otherwise, such additional Work will be paid for as provided in Article 6, “Extra Work and Claims.” In case PCCA makes changes or alterations that make useless any Work already done or material already furnished or used in said Work, PCCA will compensate Contractor for any such material or labor used and for any actual loss occasioned by such change based upon actual expenses incurred by Contractor.
2.19 BARRICADES AND WARNINGS. Contractor will provide barricades and warning signs and lights to properly mark the Project site. Barricades should be placed so as to prevent access to unfinished areas of Work and to demarcate grade changes and other hazards. Contractor must obtain an approved barricading plan from the City of Corpus
Christi Traffic Division prior to blocking any portion of any city street.
2.20 STORM WATER POLLUTION PREVENTION PLAN. When applicable, Contractor will comply with the written Storm Water Specification included in the Contract
Documents. Contractor will certify Contractor’s compliance by signing the Storm Water
Pollution Prevention Plan certification page which states that Contractor has reviewed and agrees to comply with the terms and conditions of the Texas Pollutant Discharge
Elimination System (TPDES) Construction General Permit (Permit No. TXR150000), which authorizes discharge of storm water from the Project site.
2.21 SITE CONDITIONS. Contractor must become familiar with the working conditions at the Project site. Contractor must also become familiar with utilities and roadway, rail and other approaches to the Project site available to Contractor and with the space available for storage, for working, and for temporary offices, sheds, etc.
2.22 UTILITIES. Contractor will arrange for and secure all temporary connections for water, electricity, telephone, gas, and other services needed by Contractor for the proper prosecution of Contractor’s operations; and any cost for these services will be paid by
Contractor.
Contractor will promptly notify utility and pipeline companies when prosecution of the
Work may affect said companies and will cooperate with said companies in the protection, removal, relocation, and replacement of their property. All damage, injury, or loss to any property caused directly or indirectly, in whole or in part, by Contractor, any subcontractor, supplier, any other person or organization directly or indirectly employed by any of them to perform or furnish any of the Work, or anyone for whose acts any of them may be liable will be remedied by Contractor at Contractor’s expense.
If Contractor encounters uncharted or incorrectly charted utilities or pipelines, Contractor will promptly notify PCCA Construction Representative, who will provide instructions
48742 – Revised March 2024 General Conditions
13/46 | P a g e on how to proceed. Contractor must cooperate with all parties to keep the utility or pipeline in service.
2.23 TESTING, INSPECTION, AND CONTROL. The Special Conditions and Technical
Specifications generally govern the scope and frequency of testing the Work and materials; however, PCCA Construction Representative reserves the right to order additional testing. Testing and inspection of materials may be performed by a commercial testing laboratory selected by PCCA. Except as noted below or in the
Special Conditions, the cost of laboratory tests will be paid by PCCA.
A. Contractor will furnish at Contractor’s expense all materials or specimens for testing ordered by PCCA Construction Representative.
B. Contractor will pay for all tests and re-tests of materials that fail to comply with the Technical Specifications.
C. Contractor will pay for all trip cancellation charges. A deductive change order will be executed between Contractor and PCCA to cover related expenses billed to PCCA.
D. Contractor will furnish at Contractor’s expense all materials and labor required to patch or otherwise repair all Work affected by testing.
It is Contractor’s responsibility to notify and otherwise coordinate with the testing laboratory relative to the material to be tested. Failure of Contractor to have the Work or materials tested may require removal and replacement of the Work or materials at
Contractor’s expense.
2.24 CONTRACTOR’S DAILY REPORTS. On a weekly basis, Contractor will submit to
PCCA Construction Representative daily reports that include the following minimum information:
A. Number of Contractor and Subcontractor employees working on site (itemized by trade).
B. Equipment on site.
C. Ongoing construction activities.
D. Progress made (i.e., quantity of material installed, or Work completed).
E. Delays or problems encountered.
F. Direction received from PCCA Construction Representative.
G. Visitors on site.
H. General comments.
I. Field superintendent’s signature.
J. Construction progress photos or videos.
48742 – Revised March 2024 General Conditions
14/46 | P a g e
The daily reports must be submitted on a weekly basis to avoid miscommunication between PCCA Construction Representative and Contractor. Failure to submit daily reports in a timely manner may delay progress payments to Contractor.
2.25 DEBRIS. From time to time during execution of the Work, Contractor will at
Contractor’s expense remove all surplus materials and debris from the site of the Project and dispose of such materials as directed by PCCA Construction Representative.
Transportation and disposal of all materials and debris will be conducted in accordance with all applicable federal, state, and local laws, ordinances, and regulations. Before
Final Acceptance, Contractor must deliver the Project site in a clean and neat condition satisfactory to PCCA Construction Representative.
2.26 ENVIRONMENTAL POLICY. Contractor and its employees will be aware of and comply with PCCA’s Environmental Policy while conducting any activities on PCCA property. Contractor will utilize best management practices to minimize pollution from activities being conducted and will also adhere to the applicable environmental management programs for the work being conducted.
In its commitment to “Be An Environmental Leader”, the PCCA in collaboration with stakeholders will mitigate environmental impacts, prevent pollution, and undertake environmental stewardship initiatives to uphold the following six (6) key precepts:
▪ Air Quality Uphold, through voluntary actions, the national ambient air quality standards established through the Clean Air Act, as amended in 1990.
▪ Water Quality Maintain or improve the quality of the Coastal Bend bays to be fishable and swimmable in accordance with the Clean Water Act, as amended in
1972.
▪ Soils & Sediment Protect human health, as well as sediment and groundwater quality.
▪ Habitat Promote diverse, healthy native flora and fauna.
▪ Resilience/Climate Adaptation Prioritize sustainability and resilience in the development of Port facilities and Port operations.
▪ Climate Action Support national and global emission reduction and net-zero initiatives under Goal 13 of the Paris Agreement.
The PCCA’s Environmental Policy is a strategic imperative that guides all aspects of development and operations, supporting the Port’s vision To Be the Energy Port of the
Americas and its…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .