01 - 10-Year Capital Planning Study RFP Document.pdf
PDF 291 KB Posted
- Attached to
- 10-Year Capital Needs and Reliability Study
- Solicitation number
- S-R33123-00013779
- Issued by
- Wasco County, Oregon
About this file
This is a Request for Proposal (RFP) issued by Northern Wasco County People's Utility District (NWCPUD) on May 6, 2025, soliciting consulting services for a 10-Year Capital Needs and Reliability Study. The project involves a 69 kV transmission line running from The Dalles to Tygh Valley within Wasco County, Oregon, and covers areas near The Dalles, Dufur, and Tygh Valley. Proposals are due by May 26, 2025, at 5:00 p.m. PST, with an anticipated contract execution date of May 12, 2025, and a potential board approval on June 3, 2025. There is no pre-proposal meeting scheduled, and questions from potential bidders are due by May 19, 2025, with answers provided by May 21, 2025.
The RFP requires consultants to submit a comprehensive proposal including cost proposals, unit rates, relevant experience, key personnel resumes, client references, and contact information. Evaluation criteria focus on the project team's qualifications, consultant experience in similar governmental electric industry projects, and resource availability. The District reserves the right to reject any or all bids and will evaluate proposals based on cost competitiveness, technical capabilities, and references. Consultants must be active and in good standing with the Oregon Construction Contractors Board (CCB) and provide insurance certificates listing NWCPUD as additionally insured. All submitted materials may be subject to public records disclosure in accordance with Oregon Public Records Law.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit C - Personal Service Contract Template.docx | DOCX document | |
| Exhibit D - Cost Proposal - Rates.docx | DOCX document | |
| NOI Letter~1.pdf | ||
| Exhibit B - Proposal Ranking~1.xlsx | XLSX spreadsheet | |
| Exhibit A - Scope of Work.docx | DOCX document | |
| Bid Amendment 001~1.pdf | ||
| Exhibit E - Example Planning Study-3-21-16.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
Issued: 5-6-2025
Qualified organizations are invited to submit an electronic copy of the proposal that meets the requirements described herein no later than May 26, 2025, by 5:00 p.m. PST to the following email address:
purchasing@nwascopud.org
OR
Hardcopy documents can also be submitted to:
CONSULTING SERVICES: 10 YEAR CAPITAL NEEDS AND RELIABILITY STUDY
ATTN: PURCHASING DEPARTMENT
NORTHERN WASCO COUNTY PEOPLE’S UTILITY DISTRICT
2345 RIVER ROAD
THE DALLES, OR 97058
This Request for Proposals (RFP) does not commit Northern Wasco County People’s Utility District, “the District” to award a contract or pay any costs incurred in the preparation of a proposal responsive to this request. The District reserves the right to accept all or part of any proposal or to cancel in part or in its entirety this Request for Proposals. The District further reserves the right to accept the proposal that it considers to be in the best interest of the District.
Summary
Northern Wasco County People's Utility District (hereinafter called "District") issues this Request for
Proposals soliciting 10 YEAR Capital Needs and Reliability Study.
Timeline The following table outlines the expected solicitation and selection timeline:
Milestone Date
RFP ITB Release 5/6/2025
Site Visit or Pre-Bid Meeting N/A
Respondents Questions Due 5/19/2025
Answers to Respondents Questions on or before 5/21/2025
Proposals / Bids due 5/26/2025
Board Approval (If Required) 6/3/2025
Contract Executed 5/12/2025
Project Description and Scope of Work
The work associated with the Project is located in or near the towns of The Dalles, Dufur, and Tygh
Valley, and includes a 69 kV transmission line running from The Dalles to Tygh Valley within Wasco
County, Oregon.
The Scope of Work may include but is not limited to:
Consultant shall provide the services outlined in Exhibit A for providing a 10-year capital planning study.
By submitting a proposal, Consultant agrees to the requirements listed in this RFP including the terms in
Exhibit C.
Proposal Contents Summary
In summary, each proposal must meet all of the following to be considered for acceptance by the
District:
• Provide a copy of Exhibit D for Consultant’s Cost Proposal and Unit Rates.
• Outline the Consultant’s relevant experience in the last two years.
o Consultant may provide a sample report for the District to review to highlight
Consultant’s experience.
• Provide resumes for key personnel.
• Provide a list of previous clients that may be used as references.
• Include the name, address, and telephone number of the primary person from the Consultant who will coordinate the services with the District.
• Provide name and email address of primary contact on this submission.
• See Evaluation Criteria below and include necessary items to determine scoring and evaluation of Consultant.
Evaluation Criteria
Experience and Qualifications
Demonstration of proposed project team members:
• Qualifications to perform work in applicable discipline(s).
• Knowledge of technical criteria and administrative requirements for projects of similar scope.
• Current and projected workload of each proposed project personnel and proportion of time available for this contract.
Consultant Experience
Demonstration of Consultant’s:
• Qualifications to perform work in applicable disciplines.
• Past performance in completing projects of similar size and scope.
• Demonstration of past experience in providing services to governmental agencies in the electric industry by both the Consultant and the project team.
Availability and Commitment of Resources
• Proposed Timeline
• Proposed Staff for project
• Resource Availability
Demonstration of the Consultant’s ability to commit the resources required to complete the project within the established time frames, including responsiveness to specific project technical requirements.
Evaluation Process
District staff will evaluate all the proposals based on the criteria listed above and on cost competitiveness. The District’s staff may also request clarifications or additional information, if needed.
A selection may be based on the cost alone or any combination of the Evaluation Criteria, references and interviews. The District’s Contract Review Board will review staff’s selection and make the determination whether to authorize staff to execute the contract with the selected bidder.
The District reserves the right to reject any or all bids and to waive any informality or technicality in any bid in the interest of the District. All submissions become public records unless labeled ‘confidential’ or a Trade Secret exemption under Oregon’s Public Records Laws, ORS 192.345(2) or ORS 192.355(4).
Disqualification Factors, such as, but not limited to, any of the following, may disqualify bids without further consideration:
• Evidence of collusion, directly or indirectly, among Consultants in regard to the amount, terms or conditions of this invitation to bid;
• Any attempt to improperly influence any member of the evaluation team;
• Existence of any lawsuit, unresolved contractual claim or dispute between Consultant and the
District;
• Evidence of incorrect information submitted as part of the bid;
• Evidence of the Consultant’s inability to successfully complete the responsibilities and obligations described in the invitation to bid; and
• Consultant’s default under any previous agreement with the District.
Submission
Submit questions via email to:
purchasing@nwascopud.org
NWCPUD will not host a pre-proposal meeting.
The District may reject any or all submissions if the District deems doing so would be in the public’s interest.
Once a submittal is selected, the District will determine if they desire to enter into negotiations for a final Contract with the most competitive and qualified bidder. Final project related matters will be negotiated during this period to the satisfaction of the District. Consultant shall provide certificates of insurance listing NWCPUD as additionally insured on liability coverages, except professional liability if included, with respect to activities performed under the contract.
Any entity responding to this solicitation shall do so at its sole expense.
This solicitation is being conducted pursuant to procedures set forth in the District’s Procurement
Policies; the Oregon Revised Statutes, Chapter 279B Public Contracting - Public Procurements; and OAR
137-047. Bidders must be active and in good standing with Oregon CCB to be considered.
Public Records Disclosure
All materials submitted in response to this Request for Proposals (RFP) become the property of the
District and are subject to disclosure in accordance with applicable public records laws, including Oregon
Public Records Law, ORS 192 and ORS 279C.
1. Public Record Status o Proposals, communications, and supporting materials submitted in response to this RFP may be subject to public disclosure upon request.
o The District will not be responsible for determining the applicability of any disclosure exemptions but may rely on the Offeror’s written designation of exempt materials.
2. Confidential or Proprietary Information o If an Offeror believes that any portion of its proposal contains trade secrets, proprietary, or otherwise exempt information under state law, the Offeror must:
Clearly mark each page containing such information as “CONFIDENTIAL.”
Provide a written explanation of the legal basis for the exemption.
o Blanket designations, such as marking an entire proposal as “Confidential” or
“Proprietary,” will not be honored.
3. Handling of Public Records Requests o If the District receives a public records request for any portion of a proposal that has been marked as confidential, the District will:
Notify the Offeror of the request and provide a reasonable time for the Offeror to seek legal protection.
Not be obligated to withhold disclosure if the District determines the records are not exempt under applicable law.
Not be liable for any damages resulting from the release of materials deemed non-exempt.
4. Responsibility of Offeror o Offerors are advised to seek legal counsel regarding the protection of confidential materials before submission.
o The District reserves the right to disclose pricing and contract terms, as these are generally not considered confidential under public records laws.
By submitting a proposal, Offerors waive any claim against the District for the disclosure of any materials not properly marked or supported with a legal basis for exemption.
File details come from the government source that posted it. Updated .